eni well test procedures manual

Upload: muhammadihsan

Post on 07-Aug-2018

307 views

Category:

Documents


18 download

TRANSCRIPT

  • 8/20/2019 ENI Well Test Procedures Manual

    1/115

     

    S P E O

    ENI S.p.A. 

    E&P Division 

    ORGANIZINGDEPARTMENT

    TYPE OF ACTIVITY'

    ISSUINGDEPT.

    DOC.TYPE

    REF. N. PAG. 1 

    OF 115 

    STAP P 1 M 7130

    The present document is CONFIDENTIAL and it is the property of EniIt shall not be shown to third parties nor shall it be used for reasons different from those owing to which it was given.

    Eni S.p.A. Exploration & Production division

    Drilling Completion & Production Optimization

    Well Operating Standards

    WELL TEST PROCEDURES MANUAL

    Date of validity: 01-01-2005

    Revision/Reproduction Record:

    2

    1 01-12-2004

    0 General Issue 28-06-1999Rev.No Reason for revision/reproduction Date

    Technical Validation

    P repared P. Magarini  Signature(s): Date:

    02-11-2004

    C ontrolled C Lanzetta Signature(s): Date:

    02-11-2004

     A pproved F Trilli Signature(s): Date:

    02-11-2004

    Endorsement

    V erified C Lanzetta Signature(s): Date:

    30-11-2004

    E ndorsed F. Trilli Signature(s): Date:

    30-11-2004

    I ssued  A. Calderoni Signature(s): Date:

    30-11-2004

  • 8/20/2019 ENI Well Test Procedures Manual

    2/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  2  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    INDEX

    1.  INTRODUCTION .............................................................................................................. 8 

    1.1  PURPOSE OF THE MANUAL .............................................................................. 8 

    1.2  IMPLEMENTATION .............................................................................................. 8 

    1.3  UPDATING, AMENDMENT, CONTROL & DEROGATION................................... 9 

    1.4  OBJECTIVES........................................................................................................ 9 

    1.5  DRILLING INSTALLATIONS................................................................................ 10 

    2.  TYPES OF PRODUCTION TEST..................................................................................... 11 2.1  DRAWDOWN........................................................................................................ 11 

    2.2  MULTI-RATE DRAWDOWN................................................................................. 11 

    2.3  BUILD-UP............................................................................................................. 11 

    2.4  DELIVERABILITY................................................................................................. 11 2.4.1  FLOW-ON-FLOW.................................................................................. 12 2.4.2  ISOCHRONAL ...................................................................................... 12 2.4.3  MODIFIED ISOCHRONAL .................................................................... 12 2.4.4  RESERVOIR LIMIT............................................................................... 12 

    2.5  INTERFERENCE .................................................................................................. 13 

    2.6  INJECTIVITY......................................................................................................... 13 

    3.  GENERAL ROLES AND RESPONSIBILITIES................................................................. 14 

    3.1  RESPONSIBILITIES AND DUTIES....................................................................... 14 3.1.1  COMPANY DRILLING AND COMPLETION SUPERVISOR ................. 14 3.1.2  COMPANY JUNIOR DRILLING AND COMPLETION

    SUPERVISOR....................................................................................... 15 3.1.3  COMPANY DRILLING ENGINEER....................................................... 15 3.1.4  COMPANY PRODUCTION TEST SUPERVISOR ................................. 15 3.1.5  COMPANY WELL SITE GEOLOGIST .................................................. 15 

    3.1.6  CONTRACTOR TOOLPUSHER ........................................................... 16 3.1.7  CONTRACT PRODUCTION TEST CHIEF OPERATOR....................... 16 3.1.8  CONTRACTOR DOWNHOLE TOOL OPERATOR ............................... 16 3.1.9  WIRELINE SUPERVISOR..................................................................... 16 3.1.10  COMPANY STIMULATION ENGINEER................................................ 16 3.1.11  COMPANY RESERVOIR ENGINEER................................................... 16 

    3.2  RESPONSIBILITIES AND DUTIES ON SHORT DURATION TESTS................... 17 3.2.1  COMPANY DRILLING AND COMPLETION SUPERVISOR ................. 17 3.2.2  COMPANY JUNIOR DRILLING AND COMPLETION

    SUPERVISOR....................................................................................... 17 3.2.3  COMPANY WELL SITE GEOLOGIST .................................................. 17 

    3.2.4  CONTRACTOR PERSONNEL .............................................................. 17 

    4.  WELL TESTING PROGRAMME ...................................................................................... 18 

  • 8/20/2019 ENI Well Test Procedures Manual

    3/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  3  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    4.1  CONTENTS........................................................................................................... 18 

    5.  SAFETY BARRIERS........................................................................................................ 19 5.1  WELL TEST FLUID............................................................................................... 19 

    5.2  MECHANICAL BARRIERS - ANNULUS SIDE ..................................................... 20 5.2.1  SSTT ARRANGEMENT ........................................................................ 20 5.2.2  SAFETY VALVE ARRANGEMENT....................................................... 22 

    5.3  MECHANICAL BARRIERS - PRODUCTION SIDE............................................... 23 5.3.1  TESTER VALVE ................................................................................... 23 5.3.2  TUBING RETRIEVABLE SAFETY VALVE (TRSV) OR (SSSV) ........... 24 5.3.3  CASING OVERPRESSURE VALVE ..................................................... 24 

    6.  TEST STRING EQUIPMENT............................................................................................ 25 

    6.1  GENERAL............................................................................................................. 25 

    6.2  COMMON TEST TOOLS DESCRIPTION ............................................................. 30 6.2.1  BEVELLED MULE SHOE ..................................................................... 30 6.2.2  PERFORATED JOINT/PORTED SUB .................................................. 30 6.2.3  GAUGE CASE (BUNDLE CARRIER) ................................................... 30 6.2.4  PIPE TESTER VALVE .......................................................................... 30 6.2.5  RETRIEVABLE TEST PACKER ........................................................... 30 6.2.6  CIRCULATING VALVE (BYPASS VALVE) .......................................... 30 6.2.7  SAFETY JOINT..................................................................................... 31 6.2.8  HYDRAULIC JAR ................................................................................. 31 

    6.2.9  DOWNHOLE TESTER VALVE ............................................................. 31 6.2.10  SINGLE OPERATION REVERSING SUB............................................. 31 6.2.11  MULTIPLE OPERATION CIRCULATING VALVE ................................ 31 6.2.12  DRILL COLLAR.................................................................................... 31 6.2.13  SLIP JOINT........................................................................................... 32 6.2.14  CROSSOVERS ..................................................................................... 32 

    6.3  HIGH PRESSURE WELLS ................................................................................... 32 

    6.4  SUB-SEA TEST TOOLS USED ON SEMI-SUBMERSIBLES ............................... 32 6.4.1  SUB-SEA TEST TREE.......................................................................... 32 6.4.2  FLUTED HANGER................................................................................ 33 6.4.3  SLICK JOINT (POLISHED JOINT) ....................................................... 33 6.4.4  SSTT VALVE ASSEMBLY.................................................................... 34 6.4.5  LATCH ASSEMBLY.............................................................................. 34 6.4.6  BLEED OFF VALVE AND RETAINER VALVE..................................... 34 

    6.5  FISHING TOOL..................................................................................................... 35 

    6.6  LUBRICATOR VALVE.......................................................................................... 35 

    6.7  TOOLS FOR DYNAMIC POSITIONING RIG......................................................... 36 6.7.1  SHEAR JOINT ...................................................................................... 36 6.7.2  ELECTRO-HYDRAULIC CONTROL SYSTEM ..................................... 36 6.7.3  REAL-TIME SURFACE READ-OUT OF SUB SEA PRESSURE

     AND TEMPERATURE........................................................................... 37 

    7.  SURFACE EQUIPMENT .................................................................................................. 38 

  • 8/20/2019 ENI Well Test Procedures Manual

    4/115

  • 8/20/2019 ENI Well Test Procedures Manual

    5/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  5  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    9.2  WIRELINE CONVEYED PERFORATING ............................................................. 59 

    9.3  PROCEDURES FOR PERFORATING.................................................................. 59 

    10.  PREPARING THE WELL FOR TESTING......................................................................... 61 

    10.1  PREPARATORY OPERATIONS FOR TESTING.................................................. 61 10.1.1  GUIDELINES FOR TESTING 7INS LINER LAP ................................... 61 10.1.2  GUIDELINES FOR TESTING 95/8INS LINER LAP ................................ 61 10.1.3  GENERAL TECHNICAL PREPARATIONS .......................................... 61 

    10.2  BRINE PREPARATION ........................................................................................ 62 10.2.1  ONSHORE PREPARATION OF BRINE................................................ 62 10.2.2  TRANSPORTATION AND TRANSFER OF FLUIDS............................. 62 10.2.3  RECOMMENDATIONS ......................................................................... 62 

    10.2.4  RIG SITE PREPARATIONS.................................................................. 63 10.2.5  WELL AND SURFACE SYSTEM DISPLACEMENT TO BRINE ........... 64 10.2.6  DISPLACEMENT PROCEDURE........................................................... 65 10.2.7  ON-LOCATION FILTRATION AND MAINTENANCE OF BRINE.......... 65 

    10.3  DOWNHOLE EQUIPMENT PREPARATION ........................................................ 66 10.3.1  TEST TOOLS........................................................................................ 66 

    10.4  TUBING PREPARATION...................................................................................... 66 10.4.1  TUBING CONNECTIONS ..................................................................... 66 10.4.2  TUBING GRADE................................................................................... 67 10.4.3  MATERIAL ............................................................................................ 67 10.4.4  WEIGHT PER FOOT............................................................................. 67 

    10.4.5  DRIFT.................................................................................................... 68 10.4.6  CAPACITY............................................................................................ 68 10.4.7  DISPLACEMENT .................................................................................. 68 10.4.8  TORQUE............................................................................................... 68 10.4.9  INSPECTION ........................................................................................ 68 10.4.10  TUBING MOVEMENT........................................................................... 69 

    10.5  LANDING STRING SPACE-OUT.......................................................................... 70 10.5.1  LANDING STRING SPACE-OUT PROCEDURE .................................. 73 

    10.6  GENERAL WELL TEST PREPARATION............................................................. 73 10.6.1  CREW ARRIVAL ON LOCATION ......................................................... 73 10.6.2  INVENTORY OF EQUIPMENT ONSITE................................................ 73 

    10.6.3  PRELIMINARY INSPECTIONS............................................................. 74 

    10.7  PRE TEST EQUIPMENT CHECKS....................................................................... 75 

    10.8  PRESSURE TESTING EQUIPMENT .................................................................... 76 10.8.1  SURFACE TEST TREE......................................................................... 77 

    11.  TEST STRING INSTALLATION ....................................................................................... 80 

    11.1  GENERAL............................................................................................................. 80 

    11.2  TUBING HANDLING............................................................................................. 81 

    11.3  RUNNING AND PULLING .................................................................................... 81 

    11.4  PACKER AND TEST STRING RUNNING PROCEDURE ..................................... 82 

    11.5  RUNNING THE TEST STRING WITH A RETRIEVABLE PACKER...................... 82 

  • 8/20/2019 ENI Well Test Procedures Manual

    6/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  6  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    11.6  RUNNING A TEST STRING WITH A PERMANENT PACKER............................. 83 

    12.  WELL TEST PROCEDURES ........................................................................................... 85 12.1   ANNULUS CONTROL AND PRESSURE MONITORING ..................................... 85 

    12.2  TEST EXECUTION ............................................................................................... 85 

    13.  WELL TEST DATA REQUIREMENTS ............................................................................. 87 

    13.1  PRE-TEST PREPARATION.................................................................................. 87 

    13.2  METERING REQUIREMENTS.............................................................................. 87 

    13.3  DATA REPORTING.............................................................................................. 88 

    13.4  WELL TEST DATA ACQUSITION PROCEDURE................................................. 89 

    14.  SAMPLING....................................................................................................................... 90 

    14.1  CONDITIONING THE WELL ................................................................................. 90 

    14.2  DOWNHOLE SAMPLING ..................................................................................... 90 

    14.3  SURFACE SAMPLING ......................................................................................... 91 14.3.1  GENERAL ............................................................................................. 91 14.3.2  SAMPLE QUANTITIES......................................................................... 92 14.3.3  SAMPLING POINTS ............................................................................. 92 14.3.4  SURFACE GAS SAMPLING................................................................. 93 

    14.4  SURFACE OIL SAMPLING .................................................................................. 94 

    14.5  SAMPLE TRANSFER AND HANDLING............................................................... 95 

    14.6  SAFETY................................................................................................................ 96 14.6.1  BOTTOM-HOLE SAMPLING PREPARATIONS ................................... 96 14.6.2  RIGGING UP SAMPLERS TO WIRELINE ............................................ 97 14.6.3  RIGGING DOWN SAMPLERS FROM WIRELINE ................................ 97 14.6.4  BOTTOMHOLE SAMPLE TRANSFER AND VALIDATIONS................ 97 14.6.5  SEPARATOR/WELLHEAD SAMPLING ............................................... 98 14.6.6  SAMPLE STORAGE............................................................................. 98 

    15.  WIRELINE OPERATIONS................................................................................................ 99 

    16.  HYDRATE PREVENTION ................................................................................................ 100 

    17.  NITROGEN OPERATIONS .............................................................................................. 101 

    18.  COILED TUBING OPERATIONS ..................................................................................... 102 

    19.  WELL KILLING ABANDONMENT ................................................................................... 103 

    19.1  WELL KILLING..................................................................................................... 103 

    19.2  WELL KILLING ABANDONMENT........................................................................ 103 

  • 8/20/2019 ENI Well Test Procedures Manual

    7/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  7  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    20.  HANDLING OF HEAVYWATER BRINE........................................................................... 104 

     APPENDIX A - REPORT FORMS ............................................................................................. 105  A.1.  DAILY REPORT (ARPO 02) ................................................................................. 105 

     A.2.  WELL TEST REPORT “ GENERAL DATA” (ARPO 10/A).................................... 106 

     A.3.  WELL TEST REPORT “DST DATA” (ARPO 10/B) .............................................. 107 

     A.4.  WELL TEST REPORT “ RECORD DATA” (ARPO 10/C)...................................... 108 

     A.5.  WASTE REPORT (ARPO 6) ................................................................................. 109 

     A.6.  WELL PROBLEM REPORT (ARPO 13) ............................................................... 110 

     A.7.  MALFUNCTION & FAILURE REPORT (FB-1) ..................................................... 111 

     A.8.  CONTRACTOR EVALUATION (FB-2).................................................................. 112 

     APPENDIX B – ABBREVIATIONS............................................................................................ 113 

     APPENDIX C – BIBLIOGRAPHY.............................................................................................. 115 

  • 8/20/2019 ENI Well Test Procedures Manual

    8/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  8  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    1. INTRODUCTION

    The main objective of drilling a well is to test and evaluate the target formation. The usualmethod of investigating the reservoir is to conduct a well test and there are two methodswhich are available:

    •  Drill Stem Test (DST). The scope is to define the quality of the formationfluid.

    This is a short term test which uses a combination of drillpipe/tubing anddownhole tools to evaluate the reservoir. The formation fluid may notreach or only just reach the surface during the flowing period.

    •  Production Test. The scope is to define both the quality and quantity of the

    formation fluid. The formation fluid, in this case, is flowed to surface.

    Many designs of well test strings are possible depending on the requirements of the testand the nature of the well and the type of flow test to be conducted.

    In fact, the production test can be performed either through a temporary completion stringmade up of DST down hole tools or through the final permanent completion string.

    Basically, a completion string consists of a tailpipe, packer, safety system, downhole testtools and a tubing or drill pipe work string; by introducing a low density fluid into the workstring, formation fluids can flow to the surface testing equipment which controls the flowrate, separates the different phases and measures the flow rates and pressures.

     A short description of the types of tests that can be conducted and the generic test stringconfigurations for the various drilling installations, as well as the various downhole toolsavailable, surface equipment, pre-test procedures and test procedures are included in thissection.

    Specific wire line and coiled tubing services for well test operations are also described.

    1.1 PURPOSE OF THE MANUAL

    The purpose of the manual is to guide technicians and engineers, involved in Drilling &Completion activities, through the requirements, methodologies and rules that enable tooperate uniformly and in compliance with the Company Principles. This, however, still

    enables the Company capability to operate according to laws or particular environmentalsituations.

    The final aim is to improve performance and efficiency in terms of safety, quality andcosts, while providing all personnel involved in Drilling & Completion activities withcommon guidelines in all areas worldwide where Eni E&P operates.

    1.2 IMPLEMENTATION

    The guideline and policies specified herein are applicable to all Eni E&P Drilling andCompletion engineering activities.

     All engineers engaged in Eni E&P casing design activities are expected to makethemselves familiar with the contents of this manual and be responsible for compliance toits policies and procedures.

  • 8/20/2019 ENI Well Test Procedures Manual

    9/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  9  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    1.3 UPDATING, AMENDMENT, CONTROL & DEROGATION

    This manual is a ‘live’ controlled document and, as such, it will only be amended and

    improved by the Company, in accordance with the development of Eni E&P operationalexperience. Accordingly, it will be the responsibility of everyone concerned in the use andapplication of this manual to review the policies and related procedures on an ongoingbasis.

    Derogations from the manual shall be approved solely in writing by the Company WellOperations Manager after the Company Manager and the Corporate Drilling & ProductionOptimisation Services Department in Eni E&P Division Head Office have been advised inwriting.

    The Corporate Drilling & Production Optimization Services Standards Department willconsider such approved derogations for future amendments and improvements of theCorporate manual, when the updating of the document will be advisable.

    Feedback for manual amendment is also gained from the return of completed ‘Feedbackand Reporting Forms’ from well operations refer to Appendix A, page 105. 

    1.4 OBJECTIVES

    The test objectives must be agreed by those who will use the results and those who willconduct the test before the test programme is prepared. The Petroleum Engineer shoulddiscuss with the geologists and reservoir engineers about the information required andmake them aware of the costs and risks involved with each method. They should selectthe easiest means of obtaining data, such as coring, if possible. Such inter-disciplinarydiscussions should be formalised by holding a meeting (or meetings) to insure theseobjectives are agreed and fixed.

    The objectives of an exploration well test are to:

    •  Conduct the testing in a safe and efficient manner.

    •  Determine the nature of the formation fluids.

    •  Measure reservoir pressure and temperature.

    •  Interpret reservoir permeability-height product (kh) and skin value.

    •  Obtain representative formation fluid samples for laboratory analysis.

    •  Define well productivity and/or injectivity.

    •  Investigate formation characteristics.

    •  Evaluate boundary effects.

  • 8/20/2019 ENI Well Test Procedures Manual

    10/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  10  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    1.5 DRILLING INSTALLATIONS

    Well tests are conducted both onshore and offshore in either deep or shallow waters. The

    drilling units from which testing can be carried out include:

    Land Rigs,Swamp BargesJack-Up Rigs

    The preferred method for testing on a land rig installationnecessitates the use of a permanent/retrievable type productionpacker, seal assembly and a conventional flowhead or test treewith the test string hung of in the slips. In wells where thesurface pressure will be more than 10,000psi the BOPs will beremoved and testing carried out with a tubing hanger/tubingspool and a Xmas tree arrangement. This requires all thenecessary precautions of isolation to be taken prior to nipplingdown the BOPs

    Semi-Submersible

    The preferred method for testing from a Semi-submersible is byusing a drill stem test retrievable packer. However wheredevelopment wells are being tested, the test will be conductedutilising a production packer and sealbore assembly so that thewell may be temporarily suspended at the end of the test. Whentesting from a Semi-submersible the use of a Sub-Sea Test Treeassembly is mandatory.

    It consists of hanger and slick joint which positions thevalve/latch section at the correct height in the BOP stack andaround which the pipe rams can close to seal of the annulus.The valve section contains two fail-safe valves, usually a ball

    and flapper valve types.

     At the top of the SSTT is the hydraulic latch section, whichcontains the operating mandrels to open the valves and thelatching mechanism to release this part of the tree from the valvesection in the event that disconnection is necessary.

    Drill Ship Same as Semi-Submersible above.

  • 8/20/2019 ENI Well Test Procedures Manual

    11/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  11  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    2. TYPES OF PRODUCTION TEST

    2.1 DRAWDOWN

     A drawdown test entails flowing the well and analysing the pressure response as thereservoir pressure is reduced below its original pressure. This is termed drawdown. It isnot usual to conduct solely a drawdown test on an exploration well as it is impossible tomaintain a constant production rate throughout the test period as the well must first clean-up. During a test where reservoir fluids do not flow to surface, analysis is still possible.This was the original definition of a drill stem test or DST. However, it is not normalnowadays to plan a test on this basis.

    2.2 MULTI-RATE DRAWDOWN

     A multi-rate drawdown test may be run when flowrates are unstable or there aremechanical difficulties with the surface equipment. This is usually more applicable to gaswells but can be analysed using the Odeh-Jones plot for liquids or the Thomas-Essi plotfor gas.

    It is normal to conduct a build-up test after a drawdown test.

    The drawdown data should also be analysed using type curves, in conjunction with thebuild up test.

    2.3 BUILD-UP

     A build-up test requires the reservoir to be flowed to cause a drawdown then the well isclosed in to allow the pressure to increase back to, or near to, the original pressure, whichis termed the pressure build-up or PBU. This is the normal type of test conducted on oilwell and can be analysed using the classic Horner Plot or superposition.

    From these the permeability-height product, kh, and the near wellbore skin can beanalysed.

    On low production rate gas wells, where there is a flow rate dependant skin, a simple formof test to evaluate the rate dependant skin coefficient, D, is to conduct a second flow andPBU at a different rate to the first flow and PBU. This is the simplest form of deliverability

    test described below.

    2.4 DELIVERABILITY

     A deliverability test is conducted to determine the well’s Inflow Performance Relation, IPR,and in the case of gas wells the Absolute Open Flow Potential, AOFP, and the ratedependant skin coefficient, D.

    The AOFP is the theoretical fluid rate at which the well would produce if the reservoir sandface was reduced to atmospheric pressure.

    This calculated rate is only of importance in certain countries where government bodies

    set the maximum rate at which the well may be produced as a proportion of this flow rate.

  • 8/20/2019 ENI Well Test Procedures Manual

    12/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  12  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    There are three types of deliverability test:

    •  Flow on Flow Test.

    •  Isochronal Test.

    •  The Modified Isochronal Test.

    2.4.1 FLOW-ON-FLOW

    Conducting a flow-on-flow test entails flowing the well until the flowing pressure stabilisesand then repeating this at several different rates. Usually the rate is increased at each stepensuring that stabilised flow is achievable. The durations of each flow period are equal.This type of test is applicable to high rate gas well testing and is followed by a singlepressure build up period.

    2.4.2 ISOCHRONAL

     An Isochronal test consist of a similar series of flow rates as the flow-on-flow test, eachrate of equal duration and separated by a pressure build-up long enough to reach thestabilised reservoir pressure. The final flow period is extended to achieve a stabilisedflowing pressure for defining the IPR.

    2.4.3 MODIFIED ISOCHRONAL

    The modified isochronal test is used on tight reservoirs where it takes a long time for theshut-in pressure to stabilise. The flow and shut-in periods are of the same length, except

    the final flow period which is extended similar to the isochronal test. The flow rate again isincreased at each step.

    2.4.4 RESERVOIR LIMIT

     A reservoir limit test is an extended drawdown test which is conducted on closed reservoirsystems to determine their volume. It is only applicable where there is no regional aquifersupport. The well is produced at a constant rate until an observed pressure drop, linearwith time, is achieved. Surface readout pressure gauges should be used in this test.

    It is common practice to follow the extended drawdown with a pressure build-up. Thedifference between the initial reservoir pressure, and the pressure to which it returns, is

    the depletion. The reservoir volume may be estimated directly from the depletion, also thevolume of produced fluid and the effective isothermal compressibility of the system. Thevolume produced must be sufficient, based on the maximum reservoir size, to provide ameasurable pressure difference on the pressure gauges; these must therefore be of thehigh accuracy electronic type gauges with negligible drift.

  • 8/20/2019 ENI Well Test Procedures Manual

    13/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  13  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    2.5 INTERFERENCE

     An interference test is conducted to investigate the average reservoir properties and

    connectivity between two or more wells. It may also be conducted on a single well todetermine the vertical permeability between separate reservoir zones.

     A well-to-well interference test is not carried out offshore at the exploration or appraisalstage as it is more applicable to developed fields. Pulse testing, where the flowrate at oneof the wells is varied in a series of steps, is sometimes used to overcome the backgroundreservoir pressure behaviour when it is a problem.

    2.6 INJECTIVITY

    In these tests a fluid, usually seawater offshore is injected to establish the formation’sinjection potential and also its fracture pressure, which can be determined by conducting astep rate test. Very high surface injection pressures may be required in order to fracturethe formation.

    The water can be filtered and treated with scale inhibitor, biocide and oxygen scavenger, ifrequired. Once a well is fractured, which may also be caused by the thermal shock of thecold injection water reaching the sandface, a short term injection test will generally notprovide a good measure of the long term injectivity performance.

     After the injectivity test, the pressure fall off is measured. The analysis of this test is similarto a pressure build-up, but is complicated by the cold water bank.

  • 8/20/2019 ENI Well Test Procedures Manual

    14/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  14  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    3. GENERAL ROLES AND RESPONSIBILITIES

    Well testing is potentially hazardous and requires good planning and co-operation/co-ordination between all the parties involved.

    The most important aspect when planning a well test is the safety risk assessmentprocess. To this end, strict areas of responsibilities and duties shall be defined andenforced, detailed below.

    3.1 RESPONSIBILITIES AND DUTIES

    The following Company’s/Contractor’s personnel shall be present on the rig:

    •  Company Drilling and Completion Supervisor.

    •  Company Junior Drilling and Completion Supervisor.

    •  Company Drilling Engineer.

    •  Company Production Test Supervisor.

    •  Company Well Site Geologist.

    •  Contractor Toolpusher.

    •  Contract Production Test Chief Operator.

    •  Contractor Downhole Tool Operator.

    •  Wireline Supervisor (slickline & electric line).

      Tubing Power Tong Operator.•  Torque Monitoring System Engineer.

    Depending on the type of test, the following personnel may also be required on the rigduring the Well test:

    •  Company Stimulation Engineer.

    •  Company Reservoir Engineer.

    3.1.1 COMPANY DRILLING AND COMPLETION SUPERVISOR

    The Company Drilling and Completion Supervisor retains overall responsibility on the rigduring testing operations. He is assisted by the Company Production Test Supervisor,Drilling Engineer, Well Site Geologist and Company Junior Drilling and Completionsupervisor. When one of the above listed technicians is not present, the Company Drillingand Completion Supervisor, in agreement with Drilling and Completion Manager andDrilling Superintendent, can perform the test, after re-allocation of the duties andresponsibilities according to the Well Test specifications. If deemed necessary he shallrequest that the rig be inspected by a Company safety expert prior to starting the well test.

  • 8/20/2019 ENI Well Test Procedures Manual

    15/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  15  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    3.1.2 COMPANY JUNIOR DRILLING AND COMPLETION SUPERVISOR

    The Company Junior Drilling and Completion Supervisor will assist the Company Drilling

    and Completion Supervisor in well preparation and in the test string tripping operation. Hewill co-operate with the Company Production Test Supervisor to verify the availability ofdownhole drilling equipment, to carry out equipment inspections and tests and tosupervise the Downhole Tool Operator and the Contractor Production Chief Operator. Inco-operation with the Drilling Engineer, he will prepare daily reports on equipment used.In the absence of the Company Junior Drilling and Completion Supervisor, his function willbe performed by the Company Drilling and Completion Supervisor.

    3.1.3 COMPANY DRILLING ENGINEER

    The Drilling Engineer will assist the Company Drilling and Completion Supervisor in thewell preparation and in the test string tripping operation. He will co-operate with theCompany Production Test supervisor to supervise the downhole tool Operator and theContractor Production Chief Operator. He shall be responsible for supplying equipment heis concerned with (downhole tools) and for preliminary inspections. He shall provideContractor personnel with the necessary data, and prepare accurate daily reports onequipment used in co-operation with the Company Junior Drilling and CompletionSupervisor.

    3.1.4 COMPANY PRODUCTION TEST SUPERVISOR

    The Company Production Test Supervisor is responsible for the co-ordination andconducting of the test. This includes well opening, flow or injection testing, separation and

    measuring, flaring, wireline, well shut in operations and all preliminary test operationsrequired on specific production equipment. In conjunction with the Reservoir Engineer, heshall make recommendations on test programme alterations whenever test behaviour isnot as expected. The final decision to make any programme alterations will be taken byhead office.

    The Company Production Test Supervisor will discuss and agree the execution of eachphase of the test with the Company Drilling and Completion Supervisor. He will theninform rig floor and test personnel of the actions to be performed during the forthcomingphase of the test. He will be responsible for co-ordination the preparation of all reports andtelexes, including the final well test report.

    He is responsible for arranging the supply of all equipment necessary for the test i.e.

    surface and downhole testing tools, supervising preliminary inspections as perprocedures. He will supervise contract wireline and production test equipment operator, aswell as the downhole tool operator and surface equipment operators. He will beresponsible in conjunction with the Company Well site Geologist for the supervision ofperforating and cased hole logging operations, as per the test programme.

    The Company Production Test Supervisor is responsible for the preparation of all reports,including the final field report previously mentioned.

    3.1.5 COMPANY WELL SITE GEOLOGIST

    The Well Site Geologist is responsible for the supervision of perforating operations (for

    well testing) cased hole logging when the Company Production Test Supervisor is notpresent on the rig. If required he will co-operate with the Company Production TestSupervisor for the test interpretation and preparation of field reports.

  • 8/20/2019 ENI Well Test Procedures Manual

    16/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  16  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    3.1.6 CONTRACTOR TOOLPUSHER

    The Toolpusher is responsible for the safety of the rig and all personnel. He shall ensure

    that safety regulations and procedures in place are followed rigorously. The Toolpushershall consistently report to the Company Drilling and Completion supervisor on the statusof drilling contractors’ material and equipment.

    3.1.7 CONTRACT PRODUCTION TEST CHIEF OPERATOR

    The Production Test Chief Operator shall always be present to co-ordinate and assist thewell testing operator and crew. He will be responsible for the test crew to the CompanyProduction Test Supervisor and will draw up a chronological report of the test.

    3.1.8 CONTRACTOR DOWNHOLE TOOL OPERATOR

    The downhole tool operator will remain on duty, or be available, on the rig floor from thetime the assembling of the BHA is started until it is retrieved. He is solely responsible fordownhole tool manipulation and annulus pressure control during tests.

    On Semi-Submersibles the SSTT operator will be available near the control panel on therig floor from the time when the SSTT is picked up until it is laid down again at the end ofthe test. During preliminary inspections of equipment, simulated test (dummy tests), toolstripping in and out of the hole and during the operations relating to the well flowing (fromopening to closure of tester), he will report to the Company Production Test Supervisor.

    3.1.9 WIRELINE SUPERVISOR

    The Wireline Supervisor will ensure all equipment is present and in good working order.He will report directly with the Company Production Test Supervisor.

    3.1.10 COMPANY STIMULATION ENGINEER

    If present on the rig, the Stimulation Engineer will assist the Company Production TestSupervisor during any stimulation operations. He will provide the Company ProductionTest Supervisor with a detailed programme for conducting stimulation operations,including the deck layout for equipment positioning, chemical formulations, pumping ratesand data collection. He will monitor the contractors during the stimulation to ensure theoperation is performed safely and satisfactorily.

    The Stimulation Engineer will also provide the Company Production Test Supervisor with areport at the end of the stimulation operation.

    3.1.11 COMPANY RESERVOIR ENGINEER

    If present on the rig, the Reservoir Engineer shall assist the Company Production TestSupervisor during the formation testing operation. His main responsibility is to ensure thatthe required well test data is collected in accordance to the programme and for the qualityof the data for analysis. He will provide a quick look field analysis of each test period andon this basis he will advise on any necessary modifications to the testing programme.

  • 8/20/2019 ENI Well Test Procedures Manual

    17/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  17  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    3.2 RESPONSIBILITIES AND DUTIES ON SHORT DURATION TESTS

     As a general rule the only Company personnel present on the rig shall be the Company

    Drilling and Completion Supervisor, the Company Junior Drilling and CompletionSupervisor and the well site Geologist. The Company Well Operations Manager/Superintendent shall evaluate, in each individual case, the opportunity of providing aCompany Drilling Engineer. The responsibilities and duties of the Company Drilling andCompletion Supervisor and Well Site Geologist will be as follows.

    3.2.1 COMPANY DRILLING AND COMPLETION SUPERVISOR

    The Company Drilling and Completion Supervisor retains overall responsibility on the rigduring testing operations assisted by the Company Junior Drilling and CompletionSupervisor and the well site Geologist. He is responsible for the co-ordination of testing

    operations, well preparation for tests, shut-in of the well, formation clean out, measuring,flaring and wireline operations. The Company Drilling and Completion Supervisor isresponsible for the availability and inspection of the testing equipment. He shall supervisethe contractor Production Chief Operator, Wireline Operator and Production Test Crew, aswell as the Downhole Tool Operator and Surface Tool Operator.

    3.2.2 COMPANY JUNIOR DRILLING AND COMPLETION SUPERVISOR

    The Company Junior Drilling and Completion Supervisor shall assist the Company Drillingand Completion Supervisor to accomplish his duties. He shall also prepare accurate dailyreports on equipment used.

    3.2.3 COMPANY WELL SITE GEOLOGIST

    The Well Site Geologist is responsible for the supervision of perforating operations and forcased hole logging operations. He is responsible for the final decision making to modifythe testing programme, whenever test behaviour would be different than expected. Heshall draw up daily and final reports on the tests and is responsible for the firstinterpretation of the test.

    3.2.4 CONTRACTOR PERSONNEL

    For the allocation of responsibilities and duties of contractor’s Personnel (Toolpusher,

    Production Chief Operator, Downhole Tool Operator), refer to long test responsibilities.

  • 8/20/2019 ENI Well Test Procedures Manual

    18/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  18  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    4. WELL TESTING PROGRAMME

    When the rig reaches the Target Depth and all the available data are analyzed, theCompany Reservoir/Exploration Departments shall provide the Company Drilling &Completion and Operative Geology departments with the information required for planningthe well test (type, pressure, temperature of formation fluids, intervals to be tested, flowingor sampling test, duration of test, type of completion fluid, type and density of fluid againstwhich the well will be opened, type of perforating gun and number of shots per foot, use ofcoiled tubing stimulation, etc.).

    The Company Drilling & Completion department shall then prepare a detailed testingprogramme verifying that the testing equipment conforms to these procedures and also tomake sure that the testing equipment is available at the rig in due time.

    Company and contractor personnel on the rig shall confirm equipment availability andprogramme feasibility, verifying that the test programme is compatible with general andspecific rules related to the drilling unit.

    Governmental bodies of several countries lay down rules and regulations covering theentire drilling activity. In such cases, prior to the start of testing operations a summaryprogramme shall be submitted for approval to national agencies, indicating well number,location, objectives, duration of test and test procedures.

    Since it is not practical to include all issued laws within the company general statement theCompany Drilling & Production Optimisation Service department and rig personnel shallverify the consistency of the present procedures to suit local laws, making any

    modifications that would be required. However, at all times, the most restrictiveinterpretation shall apply.

    4.1 CONTENTS

    The programme shall be drawn up in order to acquire all necessary information taking intoaccount two essential factors:

    a) The risk to which the rig and personnel are exposed during testing.

    b) The cost of the operation.

    c) A detailed testing programme shall include the following points:

    •  A general statement indicating the well status, targets to be reached,testing procedures as well as detailed safety rules that shall be applied,should they differ from those detailed in the current procedures.

    •  Detailed and specific instructions covering well preparation, completionand casing perforating system, detailed testing programme field analysison test data and samples, mud programme and closure of the testedinterval.

  • 8/20/2019 ENI Well Test Procedures Manual

    19/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  19  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    5. SAFETY BARRIERS

    Barriers are the safety system incorporated into the structure of the well and the test stringdesign to prevent uncontrolled flow of formation fluids and keep well pressures off thecasing.

    It is common oilfield practice to ensure there are at least two tested barriers in place oravailable to be closed at all times. A failure in any barrier system which means the wellsituation does meet with these criteria, then the test will be terminated and the barrierreplaced, even if it entails killing of the well to pull the test string.

    To ensure overall well safety, there must be sufficient barriers on both the annulus sideand the production or tubing side. Some barriers may actually contain more than one

    closure mechanism but are still classified as a single barrier such as the two-closuremechanism in a SSTT, etc.

    Barriers are often classified as primary, secondary and tertiary.

    This section describes the barrier systems which must be provided on well testingoperations.

    5.1 WELL TEST FLUID

    The fluid which is circulated into the wellbore after drilling operations is termed the welltest fluid and conducts the same function as a completion fluid and may be one and thesame if the well is to be completed after well testing. It provides one of the functions of adrilling fluid, with regards to well control, in that it density is designed to provide ahydrostatic overbalance on the formation which prevents the formation fluids entering thewellbore during the times it is exposed to the test fluid during operations. The times thatthe formation may be exposed to the test fluid hydrostatic pressure are when:

    •  A casing leak develops.

    •  The well is perforated before running the test string.

    •  There is a test string leak during testing.

    •  A circulating device accidentally opens during testing.

    •  Well kill operations are conducted after the test.

    The test fluid density will be determined from log information and calculated to provide ahydrostatic pressure, generally between 100-200psi, greater than the formation pressure. As the test fluid is usually clear brine for damage prevention reasons, high overbalancepressures may cause severe losses and alternatively, if the overbalance pressure is toolow, any fluid loss out of the wellbore may quickly eliminated the margin of overbalance.When using low overbalance clear fluids, it is important to calculate the temperatureincrease in the well during flow periods as this decreases the density.

     An overbalance fluid is often described as the primary barrier during well operations.

     A modern test method used on wells which have high pressures demanding high densitytest fluids which are unstable an extremely costly, is to design the well test with an

    underbalanced fluid which is much more stable and cheaper. In this case there will be onebarrier less than overbalance testing. This is not a problem providing the casing isdesigned for the static surface pressures of the formation fluids and that all othermechanical barriers are available and have been tested.

  • 8/20/2019 ENI Well Test Procedures Manual

    20/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  20  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    5.2 MECHANICAL BARRIERS - ANNULUS SIDE

    On the annulus side, the mechanical barriers are:

    •  Packer/tubing envelope.

    •  Casing/BOP pipe ram/side outlet valves envelope.

    Therefore, under normal circumstances there are three barriers on the annulus side withthe overbalance test fluid. If one of these barriers (or element of the barrier) failed thenthere would still be two barriers remaining.

     An alternate is when the BOPs are removed and a tubing hanger spool is used with aXmas tree. In this instance the barrier envelope on the casing side would becasing/hanger spool/side outlet valves.

    The arrangement of the BOP pipe ram closure varies with whether there is a surface orsubsea BOP stack. When testing from a floater, a SSTT is utilised to allow the rig tosuspend operations and leave the well location for any reason. On a jack-up, a safetyvalve is installed below the mud line as additional safety in the event there is any damagecaused to the installation (usually approx. 100m below the rig floor). Both systems use aslick joint spaced across the lower pipe rams to allow the rams to be closed on a smoothOD.

    5.2.1 SSTT ARRANGEMENT

     A typical SSTT arrangement is shown in Figure 5-1- SSTT Arrangement. The positioningof the SSTT in the stack is important to allow the blind rams to be closed above the top of

    the SSTT valve section providing additional safety and keeping the latch free from anyaccumulation of debris which can effect re-latching.

    Note: The shear rams are not capable of cutt ing the SSTT assembly unless asafety shear joint is installed in the SSTT across the shear ramposition.

  • 8/20/2019 ENI Well Test Procedures Manual

    21/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  21  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Figure 5-1- SSTT Arrangement

  • 8/20/2019 ENI Well Test Procedures Manual

    22/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  22  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    5.2.2 SAFETY VALVE ARRANGEMENT

    On jack-ups where smaller production casing is installed, the safety valve may be too

    large in OD (7-8ins) to fit inside the casing. In this instance a spacer spool may be addedbetween the stack and the wellhead to accommodate the safety valve. This is less safethan having the valve positioned at the mud line as desired (refer to Figure 5-2).

    PIPE RAMS

    SHEAR RAMS

    5” PIPE RAMS

    5” SLICK JOINT

      8” O.D.SAFETY VALVE

    9 5/8” CASING

    TUBING

    TUBING SPOOL

      ALL WELLS  WITH 9 5/8”PROD. CASING

    TUBING

    13 3/8” or 11” 5000 - 10000 - 15000 psi W.P. BOP STACKS

    TUBING SPOOL

    TUBING SPOOL TUBING SPOOL

    TUBING SPOOL

      5.25” O.D.SAFETY VALVE

      8” O.D.SAFETY VALVE

      8” O.D.SAFETY VALVE

      8” O.D.SAFETY VALVE

    7” CASING 7” CASING 7” CASING

    7” CASING

    5” SLICK JOINT

    5” SLICK JOINT

    5” SLICK JOINT 5” SLICK JOINT

      JACK UP, FIXED PLATFORMS and ON-SHORE RIGS WITH 7” PRODUCTION CASING  ALL WELLS  WITH 7”PROD. CASING

    PIPE RAMS

    SPACER SPOOL0.6 to 1.0 metre long

    SPACER SPOOL0.6 to 1.0 metre long

    SPACER SPOOLminimum 1 metre longfor fixed platforms

     Figure 5-2 - Safety Valve Arrangement

  • 8/20/2019 ENI Well Test Procedures Manual

    23/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  23  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    5.3 MECHANICAL BARRIERS - PRODUCTION SIDE

    On the production side there are a number of barriers or valves, which may be closed to

    shut-off well flow. However some are solely operational devices. The barriers used in wellcontrol are:

    Semi-submersible string - Latched

    •  Tester valve

    •  SSTT

    •  Surface test tree.

    Semi-submersible string - Unlatched

    •  Tester valve•  SSTT.

    Jack-Up

    •  Tester valve

    •  Safety valve

    •  Surface test tree.

    Land well

    •  Tester valve

    •  Safety valve

    •  Surface test tree.

    5.3.1 TESTER VALVE

    The tester valve is an annulus pressure operated fail safe safety valve. It remains open bymaintaining a minimum pressure on the annulus with the cement pump. Bleeding off thepressure or a leak on the annulus side closes the valve.

    The tester may have an alternate lock open cycle device and it is extremely important that

    this type of valve is set in the position where the loss of pressure closes the valve. It isunsafe to leave the tester valve in the open cycle position as in an emergency situationthere may not be sufficient time to cycle the valve closed.

    The tester valve may be considered as the primary barrier during the production phase.

  • 8/20/2019 ENI Well Test Procedures Manual

    24/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  24  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    5.3.2 TUBING RETRIEVABLE SAFETY VALVE (TRSV) OR (SSSV)

    This is a valve normally installed about 100m below the wellhead or below the mud line in

    permanent on-shore and off-shore completions respectively.This type of valve can also be installed inside the BOP for well testing as an additionaldownhole barrier on land wells or on jack-up rigs, see Figure 5-2  for the variousconfigurations of BOP stacks combinations relating to the production casing size.

    Due to the valve OD (7-8ins) available today in the market, its use with 7” productioncasing is only possible by installing a spacer spool between the tubing spool and the piperams closed on a slick joint directly connected to the upper side of the valve itself. A spaceof at least two metres between pipe rams and top of tubing spool is required.

    The valve OD must be larger than the slick joint to provide a shoulder to prevent upwardstring movement.

     A small size test string with a 5.25ins OD safety valve can be used with 7ins casing, asindicated.

    In all cases the valve is operated by hydraulic pressure through a control line and is failsafe when this pressure is bled off. The slick joint body has an internal hydraulic passagefor the control line.

    The safety valve can be considered the secondary barrier during production.

    5.3.3 CASING OVERPRESSURE VALVE

     A test string design which includes an overpressure rupture disk, or any other system

    sensible to casing overpressure, should have an additional single shot downhole safetyvalve to shut off flow when annulus pressure increases in an uncontrolled manner.

    This additional safety feature is recommended only in particular situations where there arevery high pressures and/or production casing is not suitable for sudden highoverpressures due to the test string leaking.

    This valve is usually used with the single shot circulating valve which is casing pressureoperated and positioned above the safety valve, hence will open at the same time thesafety valve closes. This allows the flow line to bleed off the overpressure.

  • 8/20/2019 ENI Well Test Procedures Manual

    25/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  25  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6. TEST STRING EQUIPMENT

    6.1 GENERAL

    The well testing objectives, test location and relevant planning will dictate which is themost suitable test string configuration to be used. Some generic test strings used fortesting from various installations are shown over leaf:

    For well tests performed inside a 7ins production liner, use full opening test tools with a2.25ins ID. In larger production casing sizes the same tools will be used with a largerpacker. In 5-51/2ins some problems can be envisaged: availability, reliability and reducedID limitations to run W/L. tools, etc. smaller test tools will be required, but similarly, thetools should be full opening to allow production logging across perforated intervals. For abarefoot test, conventional test tools will usually be used with a packer set inside the95/8ins casing.

    If conditions allow, the bottom of the test string should be 100ft above the top perforationto allow production logging, reperforating and/or acid treatment of the interval.

    In the following description are included tools that are required both in production testsand conventional tests. The list of tools is not exhaustive, and other tools may be included.However, the test string should be kept as simple as possible to reduce the risk ofmechanical failure. The tools should be dressed with elastomers suitable for the operatingenvironment, considering packer fluids, prognosed production fluids, temperature and thestimulation programme, if applicable.

    The tools must be rated for the requested working pressure (in order to withstand themaximum forecast bottom-hole/well head pressure with a suitable safety factor).

    In a well testing through a completion string, prior to flowing, the annulus will bepressurised to 500 psi and this pressure will be held, monitored and recorded throughoutthe entire test.

  • 8/20/2019 ENI Well Test Procedures Manual

    26/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  26  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Figure 6-1 - Typical Jack Up/Land Test String - Packer With TCP Guns On Packer

  • 8/20/2019 ENI Well Test Procedures Manual

    27/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  27  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Figure 6-2 - Typical Test String - Production Packer With TCP Guns Stabbed Through

  • 8/20/2019 ENI Well Test Procedures Manual

    28/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  28  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Figure 6-3 - Typical Jack Up/Land Test String - Retrievable Packer

  • 8/20/2019 ENI Well Test Procedures Manual

    29/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  29  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Figure 6-4 - Typical Semi-Submersible Test String - Retrievable Packer

  • 8/20/2019 ENI Well Test Procedures Manual

    30/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  30  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6.2 COMMON TEST TOOLS DESCRIPTION

    6.2.1 BEVELLED MULE SHOE

    If the test is being conducted in a liner the mule shoe makes it easier to enter the liner top.The bevelled mule shoe also facilities pulling wireline tools back into the test string.

    If testing with a permanent packer, the mule shoe allows entry into the packer bore.

    6.2.2 PERFORATED JOINT/PORTED SUB

    The perforated joint or ported sub allows wellbore fluids to enter the test string if the tubingconveyed perforating system is used. This item may also be used if wireline retrievablegauges are run below the packer.

    6.2.3 GAUGE CASE (BUNDLE CARRIER)

    The carrier allows pressure and temperature recorders to be run below or above thepacker and sense either annulus or tubing pressures or temperatures.

    6.2.4 PIPE TESTER VALVE

     A pipe tester valve is used in conjunction with a tester valve which can be run in the openposition in order to allow the string to self fill as it is installed. The valve usually has aflapper type closure mechanism which opens to allow fluid bypass but closes whenapplying tubing pressure for testing purposes. The valve is locked open on the first

    application of annulus pressure, which is during the first cycling of the tester valve.

    6.2.5 RETRIEVABLE TEST PACKER

    The packer isolates the interval to be tested from the fluid in the annulus. It should be setby turning to the right and includes a hydraulic hold-down mechanism to prevent the toolfrom being pumped up the hole under the influence of differential pressure from below thepacker.

    6.2.6 CIRCULATING VALVE (BYPASS VALVE)

    This tool is run in conjunction with retrievable packers to allow fluid bypass while runningin and pulling out of hole, hence reducing the risk of excessive pressure surges orswabbing. It can also be used to equalise differential pressures across packers at the endof the test. It is automatically closed when sufficient weight is set down on the packer.

    This valve should ideally contain a time delay on closing, to prevent pressuring up of theclosed sump below the packer during packer setting. This feature is important whenrunning tubing conveyed perforating guns which are actuated by pressure. If the valvedoes not have a delay on closing, a large incremental pressure, rather than the staticbottom hole pressure, should be chosen for firing the guns.

  • 8/20/2019 ENI Well Test Procedures Manual

    31/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  31  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6.2.7 SAFETY JOINT

    Installed above a retrievable packer, it allows the test string above this tool to be

    recovered in the event the packer becomes stuck in the hole. It operates by manipulatingthe string (usually a combination of reciprocation and rotation) to unscrew and the upperpart of the string retrieved. The DST tools can then be laid out and the upper part of thesafety joint run back in the hole with fishing jar to allow more powerful jarring action.

    6.2.8 HYDRAULIC JAR

    The jar is run to aid in freeing the packer if it becomes stuck. The jar allows an overpull tobe taken on the string which is then suddenly released, delivering an impact to the stucktools.

    6.2.9 DOWNHOLE TESTER VALVE

    The downhole tester valve provides a seal from pressure from above and below. Thevalve is operated by pressuring up on the annulus. The downhole test valve allowsdownhole shut in of the well so that after-flow effects are minimised, providing betterpressure data. It also has a secondary function as a safety valve.

    6.2.10 SINGLE OPERATION REVERSING SUB

    Produced fluids may be reversed out of the test string and the well killed using this tool. Itis actuated by applying a pre-set annulus pressure which shears a disc or pins allowing amandrel to move and expose the circulating ports. Once the tool has been operated it

    cannot be reset, and therefore must only be used at the end of the test.

    This reversing sub can also be used in combination with a test valve module if a furthersafety valve is required. One example of this is a system where the reversing sub iscombined with two ball valves to make a single shot sampler/safety valve.

    6.2.11 MULTIPLE OPERATION CIRCULATING VALVE

    This tool enables the circulation of fluids closer to the tester valve whenever necessary asit can be opened or closed on demand and is generally used to install an underbalancefluid for brining in the well.

    This tool is available in either annulus or tubing pressure operated versions. The tubingoperated versions require several pressure cycles before the valve is shifted into thecirculating position. This enables the tubing to be pressure tested several times whilerunning in hole. Eni E&P preference is the annulus operated version.

    6.2.12 DRILL COLLAR

    Drill collars are required to provide a weight to set the packer. Normally two stands of43/4ins drill collars (46.8lbs/ft) should be sufficient weight on the packer, but should beregarded as the minimum.

  • 8/20/2019 ENI Well Test Procedures Manual

    32/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  32  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6.2.13 SLIP JOINT

    These allow the tubing string to expand and contract in the longitudinal axis due to

    changes in temperature and pressure. They are non-rotating to allow torque for settingpackers or operating the safety joint.

    6.2.14 CROSSOVERS

    Crossovers warrant special attention. They are of the utmost importance as they connectpieces of equipment of the test string which have different threads. If crossovers have tobe manufactured, they need to be tested and fully certified. In addition, they must bechecked with each mating item of equipment before use.

    6.3 HIGH PRESSURE WELLS

    If the SBHP >10.000psi a completion type test string and production Xmas tree iscompulsory to test the well.

    6.4 SUB-SEA TEST TOOLS USED ON SEMI-SUBMERSIBLES

    6.4.1 SUB-SEA TEST TREE

    The SSTT is a fail-safe sea floor master valve which provides two functions: the shut off ofpressure in the test string and the disconnection of the landing string from the test stringdue to an emergency situation or for bad weather. The SSTT is constructed in two parts:the valve assembly, consisting of two fail safe closed valves, and the latch assembly. Thelatch contains the control ports for the hydraulic actuation of the valves and the latch head.

    The control umbilical is connected to the top of the latch which can, under mostcircumstances be reconnected, regaining control without killing the well. The valves holdpressure from below, but open when a differential pressure is applied from above, allowingsafe killing of the well without hydraulic control if unlatched.

    The Sub Sea Test Tree (SSTT) system comprising from bottom upwards:

    •  Adjustable fluted hanger to land in the wear bushing of the sub sea wellhead,

    •  Valve assembly to be located below the lower BOP pipe rams oralternatively split one valve below the lower BOP pipe rams and onevalve between the two lower BOP pipe rams,

    •  Slick joint to be located across the two lower BOP pipe rams,

    •  Latch assembly to be located between the upper pipe ram and the lowershear ram,

    •  Shear joint to be located across the two upper BOP shear rams,

    •  Bleed-Off-Valve and Retainer valve to be located above the upper shearram,

    •  Sub sea electro-hydraulic control pod to be located above the riser flex joint,

    •  Electro-hydraulic control umbilical with chemical injection line and

    •  Surface control panel

  • 8/20/2019 ENI Well Test Procedures Manual

    33/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  33  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    It shall together with the BOP comprise the main barriers during testing and provide themeans to, with the greatest possible emphasis on safety, fast and efficiently secure thewell and disconnect from the well.

    The SSTT system shall be able to effectively close, seal and disconnect in less than 15seconds.

    The SSTT system shall go to fail safe position following an emergency shear of the shear joint, i.e. the SSTT valves and Retainer Valve shall go to closed positions.

    The SSTT system shall be able to disconnect under tension and min. 4° angle. A 4° angleof the SSTT may not be applicable in the BOP due to tight tolerances between the SSTTelements and the BOP. However max. angle versus friction must be considered case bycase, as the SSTT disconnect angle have a dramatical effect on the “DP rigs” operatingenvelope).

    6.4.2 FLUTED HANGER

    The fluted hanger lands off and sits in the wear bushing of the wellhead and is adjustableto allow the SSTT assembly to be correctly positioned in the BOP stack so that when theSSTT is disconnected the shear rams can close above the disconnect point.

    The fluted hanger shall:

    •  Be equipped with a locking device to ensure that position stays asadjusted,

    •  Fit the 7”, 7 5/8”, 95/8” or 10

    3/4” wear bushings of the 183/4” ID subsea

    well head,

    •  Be able to transfer the weight of the complete test string to the subseawell head.

    6.4.3 SLICK JOINT (POLISHED JOINT)

    The slick joint (usually 5ins OD) is installed above the fluted hanger between the valveassembly and the latch assembly and has a smooth (slick) outside diameter around whichthe BOP pipe rams can close and sustain annulus pressure for DST tool operation or, if inan emergency disconnection, contain annulus pressure. The slick joint should bepositioned to allow the two bottom sets of pipe rams to be closed on it and also allow theblind rams to close above the disconnect point of the SSTT.

    The slick joint shall:

    •  Be designed and positioned such that the two BOP lower pipe rams canclose and seal on the slick joint.

    •  Have an upset below the pipe ram that will normally be closed during thetest, tentatively the upper pipe ram, to limit possible upwards movement ofthe SSTT assembly. This is to ensure that the shear joint will alwaysremain in position across the BOP shear rams.

    Tentative dimension shall be:

    •  5" or 5 1/2” OD

    •  External Collapse Pressure rating: 690 bar (10.000 psi)

  • 8/20/2019 ENI Well Test Procedures Manual

    34/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  34  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6.4.4 SSTT VALVE ASSEMBLY

    The SSTT valve assembly shall:

    •  Be positioned below the lower two BOP pipe rams or alternatively splitone valve below the lower BOP pipe rams and one valve between thetwo lower BOP pipe rams,

    •  Have two normally (fail safe) closed, hydraulically operated, surfacecontrolled valves,

    •  Have pump through capability from above with hydraulic pressure bledoff,

    •  Be capable of failsafe cutting of 7/32" wireline and pressure assistedcutting of 11/2” OD, 0,156” wall thickness coiled tubing and sealafterwards,

      Be designed not to damage valves or operating mechanism if attemptingto open valves with excessive differential pressure across valves,

    •  Have chemical injection facilities optionally between or below the valveswith dual check valves at the injection point. The chemical for injectionshall be methanol. Required methanol injection rate capacity shall be up to5 litres/minute (a 1/4” chemical injection line will be sufficient).

    External Collapse Pressure rating: 690 bar (10.000 psi).

    6.4.5 LATCH ASSEMBLY

    It is positioned between the BOP upper pipe ram and the lower shear ram, such thatremnants of the shear joint has an adequate stick-up for retrieval/fishing after emergencycutting of the shear joint.

    The latch assembly shall has:

    •  A primary electro-hydraulically, surface controlled, unlatch system that isable to disconnect under up to 50.000 lbs. tension, 345 bar (5.000 psi)internal pressure and min. 4°angle,

    •  A mechanical or pressure actuated, preferably not by string rotation,secondary unlatch system,

    •  A surface controlled hydraulically operated relatch system with positiveindication on surface whether latching parts are in correct position or not,

    •  A physical function to prevent accidental unlatch while running in the hole.

    6.4.6 BLEED OFF VALVE AND RETAINER VALVE

    The Bleed off Valve (BOV) and Retainer Valve (RV) shall be installed immediately abovethe latch assembly or shear joint (if present).

    It is hydraulic operated and must be a fail-open or fail-in-position valve. When closed, itwill contain pressure from both above and below.

  • 8/20/2019 ENI Well Test Procedures Manual

    35/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  35  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    It shall be able to contain high pressure hydrocarbons in the string and prevent theirrelease into the marine riser in the event of an emergency disconnect of the SSTT (i.e.prevent U-tubing of gas into the marine riser that can result in riser collapse); it shall:

    •  Be fail safe closed and fail safe cut up to 7/32” wireline such that aboverequirement is fulfilled also in the event of emergency cutting of the shear joint,

    •  Be hydraulically operated in conjunction with the latch assembly suchthat the RV must be closed and the BOV must have opened prior tounlatching,

    •  Provide a bleed-off function between the SSTT and RV to preventexplosive decompression of gas that can “shoot” the landing string up inthe derrick,

    •  Have pump through capability if failed in the closed position,

    •  Provide pressure testing facilities of the landing string when re-runningsame after unlatching,

    •  Be able to optionally close BOV and open RV to spot glycol at latch noseprior to relatching, or relatch with closed RV and BOV open (to avoidcompressing fluids when latching. BOV to be closed after latching.).

    6.5 FISHING TOOL

    The dedicated fishing equipment, for use after an eventual emergency shear of the shear joint, shall have the following capabilities:

    •  Fit and interface the specific BOP, SSTT and remaining part of the shear joint (Ref. latch requirements: The latch shall be positioned between the

    BOP upper pipe ram and the lower shear ram, such that remnants of theshear joint has an adequate stick-up for retrieval/fishing after emergencycutting of the shear joint.)

    •  Transmit high torque values (15.000 lbs./ft) to release secondary releasemechanism if applicable.

    •  Be designed to be released without use of rotation.

    6.6 LUBRICATOR VALVE

    The lubricator valve is run 3 joints of tubing below the surface test tree and such that bothvalves will be below the drilling riser telescoping joint's inner barrel. This valve eliminatesthe need to have a long lubricator to accommodate wireline tools above the surface testtree swab valve. It also acts as a safety device when, in the event of a gas escape atsurface, it can prevent the full unloading of the contents in the landing string after closingof the SSTT. The lubricator valve is operated by remote hydraulic control from surfacethrough a second umbilical line and should be either a fail closed or a fail-in-position valve.When closed it will contain pressure from both above and below. It has: pump throughcapability if failed in the closed position, facilities for chemical (glycol or methanol) injectionbelow the valves, hoses for hydraulic control and chemical injection of the type where allhoses are incorporated in one bundle.

    Note: For standard operations only the upper valve will be closed. The lowerone will remain open and serve as back up for the upper one.

  • 8/20/2019 ENI Well Test Procedures Manual

    36/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  36  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    6.7 TOOLS FOR DYNAMIC POSITIONING RIG

     As exploration moves into deeper and remote Subsea locations, the use of dynamic

    positioning vessels require much faster SSTT unlatching than that available with thenormal hydraulic system on an SSTT. The slow actuation is due to hydraulic lag timewhen bleeding off the control line against friction and the hydrostatic head of the controlfluid. To allow the faster SSTT unlatching, the following tools will be foreseen in the teststring assembly.

    If a programme required deepwater test tools, the tool operating procedures would beincluded in the test programme.

    6.7.1 SHEAR JOINT

    If the well testing is carried out using Dynamic Positioning rig, the shear joint shall be used

    to allow an emergency disconnection.

    It is positioned above the latch assembly, across the two BOP shear rams such that bothshear rams can close and cut same in the latched position.

    The shear joint shall be:

    •  Designed to withstand the tension, compression and bending forces likelyto be encountered during the test,

    •  Traceable. Verification that the actual BOP will be able to shear the shear joint with external hydraulic control/injection lines and internal 7/32”electric wireline shall have been performed on the actual or identical BOP.The required shear pressure shall be documented.

    6.7.2 ELECTRO-HYDRAULIC CONTROL SYSTEM

    The Hydraulic deep water actuator  is a fast response controller for the deepwater SSTTand retainer valve and controls all their functions using hydraulic power from accumulatorson the tree controlled electrically from the surface control unit.

    The fluid is vented into the annulus or an atmospheric tank to reduce the lag time andreducing closure time to seconds.

    It includes one local (on the control unit) and two remote (in the drillers and DP operatorscontrol rooms) one-button ESD (Emergency Shut Down) functions:

    •  ESD 1 Close SSTT valves.•  ESD 2 Close SSTT valves, close RV, open BOV and unlatch.

    It gives clear warning, by both flashing light and audible alarm, whenever ESD 2 has beenactivated.

    Clearly indicate:

    •  Normal status of each function with green indicating lights

    •  Abnormal status of each function with red indicating lights.

    It shall be powered through an uninterrupted power supply system to ensure SSTT systemoperability also during rig power black-out periods, and has the real time pressure read-out of the sub sea accumulator pressure.

  • 8/20/2019 ENI Well Test Procedures Manual

    37/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  37  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    The electro-hydraulic pod/control system shall be provided with:

    •  Clamps to support the umbilical to the landing string, hold its position

    over the thermal tubing couplings, and protect the umbilical from thelateral movements of the marine riser.

    •  “Unique” connections on the sub sea umbilical and surface jumper hoseto prevent accidental miscoupling,

    •  A hose bundle protective shield for rotary table.

    The sub sea umbilical provided shall permit up to 5 litre/minute methanol injection at 690bar sub sea injection pressure.

    Red alert on the rig and SSTT control panels shall not be interfaced as trouble pronesystems should not form part of a well control system. Simple BOP and SSTT control

    systems shall be independent - linked by procedures.

    6.7.3 REAL-TIME SURFACE READ-OUT OF SUB SEA PRESSURE AND TEMPERATURE

    To enable the proper measurements against hydrate problems to be taken at all timesreal-time surface read-out of sub sea pressure and temperature shall be provided.

  • 8/20/2019 ENI Well Test Procedures Manual

    38/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  38  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    7. SURFACE EQUIPMENT

    This sub-section describes the components of the surface equipment and the criteria forits use; typical lay-outs of the surface equipment for light oil, heavy oil and gas productiontests are respectively shown in Figure 7-1, Figure 7-2 and Figure 7-3. 

     A test pressure programme for the surface layout equipment must be prepared by thecontractor.

    7.1 TEST PACKAGE

    7.1.1 FLOWHEAD OR SURFACE TEST TREE

    Modern flowheads are of solid block construction (a single steel block) as opposed to theearlier modular units which were assembled from various separate components.Irrespective of the type used, both should contain:

    •  Upper Master Valve for emergency use only.

    •  Lower Master Valve situated below the swivel for emergency use only.

    •  Kill Wing Valve on the kill wing outlet connected to the cement pump orthe rig manifold.

    •  Flow Wing Valve on the flow wing outlet, connected to the chokemanifold, which is the ESD actuated valve.

    •  Swab Valve for isolation of the vertical wireline or coil tubing access.

    •  Handling Sub which is the lubricator connection for wireline or coiledtubing and is also used for lifting the tree.

    •  Pressure Swivel which allows string rotation with the flow and kill linesconnected.

    With the rig at its operating draft, the flowhead should be positioned so that it is at adistance above the drill floor which is greater than the maximum amount of heaveanticipated, plus an allowance for tidal movement, for example 5 ft and an additional 5ft fora safety margin.

    Flexible flow lines are used to connect the flowhead kill wing and flow wing outlets

    respectively to the rig manifold and the test choke manifold. A permanently installed testline is sometimes available which runs from the drill floor to the choke manifold location.

    7.1.2 FLEXIBLE FLOW LINES AND PIPING

    Flexible flow lines must be installed on the flowhead correctly so as to avoid damage.They must be connected so that they hang vertically from the flowhead wing outlets. Thehoses should never be hung across a windwall or from a horizontal connection unlessthere is a pre-formed support to ensure they are not bent any tighter than their minimumradius of 5ft.

    Hoses are preferred to chiksan connections because of their flexibility, ease of hook up

    and time saving. They are also less likely to leak since they have fewer connections. Onfloaters, they connect the stationary flowhead to the moving rig and its permanentpipework.

  • 8/20/2019 ENI Well Test Procedures Manual

    39/115

     

    S P E O 

    ENI S.p.A. 

    E&P Division 

    IDENTIFICATION CODE PAG  39  OF  115 

    REVISION

    STAP-P-1-M-7130 0 1

    Piping must have hammer connections with sealing devices and pressure ratingcompatible with the application.

    The hammer connection shall be welded on pipe for upstream application; it should bewelded on pipe for down stream application.

    The connection for up stream application on HP-HT wells shall be flange type.

     Additional protection can be provided by installing relief valves in the lines. It is nowcommon practice to have a relief valve on the line between the heater and the separator toaccommodate for any blockage downstream which may cause an over-pressure in theline. If there is a potential risk from plugging of the burner nozzles by sand production,then consideration should be given to installing additional relief valves downstream of theseparator to protect this lower pressure rated pipework.

     All surface lines from the wellhead to the flare manifold and vessels must be pressure

    tested using water; all pressures will be recorded on a Martin Decker type chart recorder. All surface lines will be anchored to the platform deck or to the ground.

    Note: Ensure that the flexible flow lines are suitable for use with corrosivebrines.

    7.1.3 DATA/INJECTION HEADER

    This item is usually situated immediately upstream of the choke. The data/injection headeris merely a section of pipe with several ports or connections to enable:

    •  Chemical injection•  Wellhead pressure recording

    •  Temperature recording

    •  Wellhead pressure recording with a dead weight tester

    •  Wellhead sampling

    •  Sand erosion monitoring

    •  Bubble hose.

    Each port shall be equipped with a block and bleed valve.

    Most of the pressure and temperatures take off points will be duplicated for Data Acquisition System sensors.

    7.1.4 CHOKE MANIFOLD

    The choke manifold is a system of valves and chokes for controlling the flow from the welland usually has two flow paths, one with facilities to install and change chokes of fixedsizes and the other with an adjustable choke. Some choke manifolds may also incorporatea bypass line.

    Each flow path shall have a minimum of two closing valves which are used to direct theflow through either of the chokes or the bypass and to provide isolation from pressurewhen changing the fixed choke.

     A well shall be brought in using the adjustable choke and this choke sh