enhancing the performance of large diameter piles by
TRANSCRIPT
~ ~ ~
Enhancing the pe~iorI IIanceof large diarIIeter pilesby groutingby D.A. BRUCE>, BSc, PhD, CEng, MICE, MIWES, MASCE, MHKIE, FGS
IntroductionQUERULOUS EYEBROWS were raised in the1975 Offshore Technology Conference in
Dallas, Texas, when Gouvenot and Gabaixpresented the conclusions of their testprogramme on the effects of postgrouting onlarge diameter pile performance:—an increase in ultimate load of up to three
times in sands and clays,—similar increases in creep load,—highly repeatable performance under
cyclic loading with almost no permanentset, and
—direct relationship between ultimate loadand volume of cement grout injected.Since then, grouting techniques have been
employed confidently throughout the world,as a routine construction process. Byexploiting the higher values of skin frictionand end-bearing resulting, engineers havebeen able to reduce pile dimensions safely.There are thus relative savings in plant andlabour costs, as well as reductions in materialrequirements —a key logistical factorespecially in developing countries.
Equally, where the satisfactoryperformance of conventional piling has beenthreatened, either due to faulty orinappropriate installation techniques (e.g.Logic, 1984), or due to interference by laterconstruction activities (e.g. Karol, 1983),grouting as a remedial process has gainedwidespread application.
This review is a synthesis of data publishedprimarily in the last decade on pile grouting.Case histories are presented in three basiccategories:(l) Enhancement by devices placed within
the pile (i.e. attached to thereinforcement prior to installation).
(ii) Enhancement by toe/ground grouting(i.e. after concreting), and
(iii) Enhancement by ground consolidation(either before or after construction).
Throughout, the term "grouted pile" refersto a pile which has been treated in one ofthese categories. It is not used in distinctionto the term "concrete pile" for example.
Enhancement by devicesplaced within the pile
Such devices have been developed toimprove both shaft friction and end-bearing.The use for the former has been encouragedby the success of such as Osterm eyer (1 974)and Jones Ef Turner (1980) with respect toalbeit smaller diameter anchorage and
minipile systems. On the other hand, theneed to improve end-bearing performance,primarilyto minimisethe settlement requiredto fully mobilise it, has triggered intensivepractical research.
Bearing in mind that shaft friction is fullymobilised at displacements of 0.5-1.00/o D,but that end-bearing is maximised only atdisplacements of 10-15%D, it is clear thatthe service settlement criteria will usuallygovern the design basis, and that thefrictional component is likely to be fullymobilised.
Indeed, Lizzi (1981) noted that there iseven a tendency to over-design pile lengthsto thereby ensure adequate capacity in shaftfriction alone, reflecting fears thatdisturbance of the pile toe zone by pressurerelief or by upf low of ground water duringconstruction may seriously reduce the end-
10 200 I
10
O 15-c
erR i(
301
Section AA
Plan at pile base
Fig. 1 (rl'ghtJ."Preloading cell"grouting device,Parana RiverIBolognesi e Moretto
1 973)
Fig. 2 (top, rl'ghtj.Estimated settlementof hotel tower as afunction ofpile toedepth, CalrO (Piccione
eral, 1984)
Hook64msquare IIsteelplates
Groutho I es
spacers
1
TABLE I: TYPICAL BASE GROUTING VOLUMES(Bolognesi B Maretto, 1973)
Typical grout takesAverage Grout take
dPile diameter, number kg of portlanm of stages cement
1.00 (SS.RC) 2 5001.20 (SS.RC) 3 7001.80 (RCS.RC.LG)" 3 35002.00 (WS.BA) 5 60002.00 (SS.BA) Still experimentalSS: Steel Shell.RCS: Reinforced concrete shell.WS: Without Shell.RC: Reverse circulation.BA; Bucket augaring with drilling mud.LG: Lateral grouting to increase skin friction
of pile shaft.
Piles in the nver course
a0I
Depth: m
60 60
~Pilef'5< reinforcement
~ g
Plug
Neoprene sleeve100mm dia.
Smm dia.perforationson inside of tube
Grouting tube50mm dia.
dia. groutpipe
Lt-30mm dia. corepile reinforcement
25mm dia,
Rubber orneoprenesheet
>Contracts Director, GKN Colcrete, Wetherby, West Yorks.
'This is the first section of a two-part article. The second,to be published in our next issue, will cover enhancementby toe/ground contact grouting, enhancement by groundtreatment, summary and conclusions as well as all thereferences.
Fig. 3 (centre, right).Details of basegrouting device,Thailand
Uniformsl zegravel
Basket
14mm dia.
May 1986 9
bearing potential.Such disturbance to the underbase
material is almost impossible to eliminatecompletely. However, the effects may rangefrom not being of "practical importance" insoft rocks or clays (Sliwinski Ef Philpot,1980), to the other extreme: Sliwinski EfFleming (1984) concluded that "if a pile isfounded in cohesionless soils which are likelyto be disturbed, with a loss of the originalcompaction, consideration should be givento reducing or ignoring the end-bearing,unless pressure grouting is used to restoreit."
In addition to problems caused by baseinstability, end-bearing can be furthercompromised by accumulations of sedimentpreventing the "clean butt joint" of concreteand bearing material referred to by SliwinskiEf Philpot (1980), and by poor concretingprocedures. Endo (1977) notes that suchaccumulations may be up to 400mm thick atthe pile centre, and twice that at theperimeter.
According to Sliwinski Ef Fleming (1984)pregrouting of pile bases via grouting cellswas first reported in 1961 at the MaracaiboBridge site, whilst the similar system laterused for bridge foundations on the ParanaRiver has been described in detail byBolognesi Ef Moretto (1973). This projectinvolved several hundred piles up to 75mlong and 2m in diameter, each of which was"preloaded" through a basal-cell (Fig. 1).Each pressure cell had 40 holes, protected bya rubber membrane with an equal number ofoffset holes, thereby acting as a one-wayinjection valve. One grout line from thesurface extended to each quadrant of thecell. Suspended below, and fixed to the pilereinforcement, was a basket of coarse gravelsewing as a "grout and pressure distributionchamber". A neat grout mix of w/c ratio 0.66(by weight) was used in several phases ofinjection typically 12 hours apart. The targetvolume for each phase was 500-1 500kg,depending on pile diameter, and groutingwas repeated until either the target pressureof 100 bars was held for 5 minutes or a pileuplift of 20mm was recorded. Table I
summarises the typical grout takes. Theauthors noted that the technique not onlyimproved the characteristics of the soilbelow the toe, but it also served to appraisethe development of skin friction along theshaft.
More recently, Piccione et al (1984)
Fig. 4 fright/. The"preload" cell(Lizzi, 1981)
Beforeconcreting
Afterconcreting
After injectionof the
preloed bulb
~Borehole
~Reinforcement
~Injection pi pes
Double skinnedimpermeeble cover
Holes
Injection pipes
.3 w=. "'.w..3E.Perforeted ~ +~J ~ e (
pletes
MAINTAINED LOAD TESTPILE No.1 DIA. 600mm DEPTH 42m BUCKET EXCAV.PILE No.2 " 1000 " 42PILE No.3 " 1000 " 42PILE No.4 " 1000 " 43 5 BENTONITE CIRCPILE No.5 " 1000 " 43PILE Nos " 1000 " 46m BUCKET EXCAV.
WITH GROUTED TOE
SOIL DATA
GL LOOSE SAND~;~, & SILT
NORMALLY
E 20. CONSOLIDATEDSILTY CLAY=—:CLAY & SAND LAYERS
O 40. s>;~,.'EDIUMai~ DENSE SAND
EE 50-Z0I-O(uu. 100-O
150-
LOAD(kN)
5000 10 000
Fig. 5. ReSultS Of eXperimental pile teStS, Italy (Sliwinski 9 Fleming, 1984)
15 000
0IZ
described a similar application at the ElGazira Sheraton Hotel in Cairo. 76 piles1 800mm dia. for the critical lower structurewere cast into very dense fluviatile sands(N h 50). Individual working loads of 850tonnes were required for the 27m long piles,cased to 10m and drilled with bentonite flushtherebelow. Fig. 2 compares the total(calculated) settlement with and without thecell. (The calculated ultimate end-bearingresistance was 1 710 tonnes (BerezantzeVSformula)) and side friction was 226 tonnes(Kerisel's formula). Given the shorter pilelength and different soil conditions from thePara na contract, maximum g routingpressures were limited to 12 bars, in theorysufficient to fully mobilise the shaft friction.Typically grout takes were 500-1 500kg,with the lower value yielding the volumenecessary to fill the gravel pack voids.
Individual cell injections took between 2and 5 hours to complete. All piles provedcompletely satisfactory in service.
Most recently, the engineers of a major
10 Ground Engineering
Fig. 6 (rightj. Details and results fromCementation experimental grouting cell(Sliwinski & Fleming, 1984)
1. U-tube fabrication from32 mm dia. pipe
2. 8 mm dia. perforations3. Rubber sleeves4. 8 mm thick plate 405 mm dia.
in 457 mm dia. cased hole
I
.)
l
U-shapad grouting cell in position atbottom of hole
p0EE+c
A'5
—10
—15
—20
Load, kN500 I 000
50 mm
toe pilaeee
)()lade groundash fillbricks andclay fill
:= Boulder clay:=- and silty clay
Clayey silt'5 Black sand
is Silty sand N = 22
Founding level
Borehole strata
Load, kN
0 2 000 4 000 6 000 8 000 10 000 12 000ps
Soil condi tions
1//F;II
:== Firm clay
—10::.:".:Silt and sand30—';.'.':;SPT —15
Sandmedium
2p.;. dense40—.
" fine to,; . medium
:.;-.'PT5025. '..FL25
~ '
'SANO
REINFORCING BAR GROUTING PIPESSKIN
UTI NG
GROUT PIPETO THE BASE
EE Sp
c
+
as 60
~ Grouted base and skirt—Conventional (bentonite flush)
IN
GROUT PIPE,TO 1HE BASE
REI NFORCI NG
CAGE
Fig. 7 (abovej. Comparative perlbrmance of two 1 500mm diameterbored piles, on the same site, one grouted, one conventional(Sliwinski & Fleming, 1984)
Fig. 8 (rightj. Arrangement for toe and shaft grouting (stocker, 1983)
Fig. 9 (below, rightj. performance of bored piles of 570mm diameterwith and without postgrouting in sand with medium to high relativedenSity (Stocker, 1983)
GROUTSAREAS
ASE
TOP PLATEFIXEO TOTHE CAGE
t BOTTOSS THINPLATE
GROUTI NG CELL
cable-stayed bridge in Thailand havereverted to a system similar to that of Fig. 1
but without the suspended cage, (Fig. 3).Here 172 bored piles of 2 000mm dia. Up to35m long are being installed under the piersfor the bridge, and are founded in verycompact fine to medium silty sand. Test pilesof smaller diameter have proved thatdisplacements of over 120mm are necessaryto mobilise adequate end-bearingresistance, as a consequence of thehydrogeological and constructionalcircumstances. (No shaft friction isconsidered through the overlying soft clays).Grouting of the pile toes has therefore beenspecified to improve service performance.
0EE
10
cE'0a
Ul
Load, kN
5X 1000 1500 20X 2500 XX 3500
raulrs)
e base-alonq
he stall
Grouting is conducted in three separatestages (to 20, 40 and 60 bars, verified bygrouting trials), and in such a way as to avoidhydrofracture of the ground and so damageto that or adjacent piles. Injections are madewhen the pile concrete is "relatively weak",(i.e. less than 2 days). Strict controls havebeen placed on the timing (more than onestage) and the spacing () 4D) of adjacenttreatments, whilst the maximum pile uplift islimited to Smm.
Similar devices have also been developedby Lizzi (1981) (Fig. 4), whilst Sliwinski EtFleming (1984) cite test data from"experienced specialist contractors in Italy"(Fig. 5) and from their own company's
May 1986 11
Em
t00c0
300LL
200
100
mm
0
I
settlement = 10 mm
VovxoB
XXXX (
XXX
XX
XXX
000
~ AB()t)
4.
os
x ((gxX XX
1000- I 670 — 570—16001 900 900
o red p tes P os t - 9rou tedBore d P iles
Small- DiameterPi(e s Anchors
200- 1100- 120- 160-300 I 200 170 I 120
600
E400-z
- 3000V
200
set ttement = )Q mm
00
x x
~ OOOO00
OOOO~0000oo @
1000-1 600- 1300 1700-180011000
I900
R3st-groutedBored- Pr(es
200- I 100- 90-300 I 200 180
Std(-Diameter Arrhors wrhout
Piles est-grctiting
Oo0
(XOO(t(0
90—180
Anchas withFbs)- groating
600
EK 300
o 200
LJL
t)0C
Vt
~ OISIII p4
4
1000- 570-1500 900
Bored - Piles
570-900
Post - groutedBored Piles
settlement = 20mmov0
Y
4
Fig. 10 (above, leftj. Skin friction ofcastin-situbored piles (at a settlement of 10mmj andanChOrSin nOn-COheSiVe SOilS (Stocker,1983)Fig. 11 (leftj. Skin friction of castin-situ boredpiles with and without post-grouting at asettlement of 20mm in non-cohesive soils(Stocker, 1983)Fig. 12 (top, rightj. Skin friction of castin-situbored piles (at a settlement of 10mmj andanchorsin cohesive soils (stocker. 1983)Fig. 13(rightj. Skin friction ofcast-in-situ boredpiles with and without post-grouting at asettlement of 20mm in cohesive soils(Stocker, 1983)Fig. 14 (below, leftj. Base pressure of boredpiles with and without post-groutingin non-cohesive soil at settlements of 10, 20 and30mm (Soil type: 1-sand, medium density, 2= sand, high density, 3 =gravel, medium tohigh density) (stocker, 1983)Fig. 15 (below, ri ghtj. Base pressure of boredpiles with and without post-grouting incohesive soils at settlements of 10, 20 and30mm (Stocker, 1983)
300EK
200
lJ
100C
s/1 0
Dd0~0D
Sto
1300-1
600-1800 I 1000
Bored Piles
700-1300
Post - groutedBored Piles
settlement = 20 mm
setllemeht =10mm. settlement = 20mm settlement=30 mm
3000— settlement = 10mm settlement =20 mm settlement o30mm
3000—
-2000(-
Q.1000
0o3
I)o
~ +
~ 000
0~ 0
+ ~ 0
IkVF(e 12 3 2 3 1 2 3 2 3 12 3 2
Boed Rl 9 tro ed PkL0 Bor d P )esBooed P I
" 'o d~R)es 'orecr R(as
~E
z~2 000
0
u1000—Q
i(XO+ OX+
tr+Q ~
Bx QP(~
XX
+xxxx
+OO+
Poet -Brouiad ~ p ()00'.-9rc(uted ~~ pkPoet.-groukd
Bored P)es (Bored P(l(ts Borerd P()rts
experimentation "some years ago" (Fig. 6).The same authors also quoted results from "acompany working in the Middle East" (Fig. 7)featuring systems designed to incorporateimprovement in shaft friction as well.However, on this particular topic, the mostcomprehensive and quantitative contributionappears to have been made by Stocker(1 983).
He described the tube 8 manchette/flatjack combination of Fig. 8, andrecommended that to improve shaft friction,injection after 1 or 2 days, at pressures up to50 bars, be conducted, repeatedly ifnecessary. For improvement in end-bearing,grouting at the same interval to 60 bars wasexecuted. He emphasised that the head dis-placement during toe grouting operationsmust be carefully monitored and limited to
3mm: higher displacements could decreasethe frictional resistance subsequentlymobilised. He also reminded that the amountby which the bearing capacity can beincreased depends on the type of soil and itsvirgin density. Typical data are shown in Fig.9, whilst the results of Stocker'sexperimental data may be summarised asfollows:
Effect on shaft frictionNon cohesive soil
Figs. 10 and 11 show results atsettlements of 10 and 20mm respectively.(The elastic deformations were notconsidered). These results show increasingfriction with decreasing diameter, ascribedto the effects of dilation and constructionmethod. Stocker did emphasise, however,
that the post-grouting of the large diameterpiles was by high pressure at different levels,whilst minipiles and anchors were grouted atlow pressure (5-6 bars) over their wholelength, during installation.Cohesive soils
Figs. 12 and 13 show results atsettlements of 10 and 20mm respectively. Adistinct relation between diameter andfrictional resistance is apparent, with a majorimprovement made by post grouting(supported by data of Ostermeyer (1974)and Whitaker Et Cooke (1966)).
Effect on end-bearingNon cohesive soil
Fig. 14. Although theoretical studies(Meissner, 1982) have shown a clearrelationship between end-bearing capacity
12 Ground Engineering
00
Load, kN Fig. 16 (eft). Pile load test results, Pile Test 1,
SOO 1 OOO 1 SOO 2 OOO 2 SOO 3 OOO 3 SOO 4 OOO 4 SOO S OOO S SOO 6OOO Pier E-55, Jeddah issuer AG)I I I I I
2.0-
4.0-
6.0
8.0-
c 100-
<yi 12.0Pile diameterPile lengthGrouted lengthWorking loadTest loadSettlement under working loadSettlement under test loadPermanent settlement
I
770mm22.5m3.5m2 500 I<N
5 OOO kN3 51mm10 01mm2.47mm
I I
and pile diameter, this was not conclusivelyconfirmed by Stocker's tests. A "veryessential" increase of the base pressure was,however, attainable.Cohesive soil
Fig. 15.These data are for piles from 620to 1 800mm in diameter. From limitedresults it would appear that post-groutingincreases the bearing capacity significantly(but less than in non cohesive soils) withinthe range of working loads considered.
To illustrate the practical application of themethod, Stocker's company have reportedon a project executed in Jeddah between1981 and 1983 wherein 1 072 piles of770mm dia. (working load 250tonnes) and1 213 of 900mm dia. (working load375tonnes) were installed. These piles
sxecs
Geologicaldescnption
Classificanon 5
Fine sand~ Sand and ~~ silly layers~
Fine sand
Static penetrometer
Point resistance Ckp (bars)
10 20 50 100 200 500
Dynamic penetrometer
Point resistance Rp (bars) u5 10 20 50 100 200 500
Menard pressuremeter
Limit pressure pt (bars)
5 10 15 20
10 ~ Silt
Fine sand
Silt
20Fine sand
ss
c00'
PR1
Silt
Medium sand30
~coarse ~sand
Ypresclay
—SP1 ———-SR2
—DP.1 ————DP. 2
40—GOUDA penetrometer
Capacity . 10 tonnesConical pointCross section 10 cmsCone angle
60'ERMES penetrometerBentonite in)ectionExpendable coneDiameter 70 mmCone angle
45'asing~
27in dia.
Grout
v—31 5m
E<o
Clay
E E
Depth, m
02.4.68.
10.12.1416.18.2022.24.2628.
Fine sand
Silt
Fine sand
S i It
Medium sand3032343638-40
-- ~- Coarse sand
Ypres clay
Fine sandSand and silty layers
Fine sand
Si It
)i)
E
1)e-31 .smil
. Clay
Fig. 17 (aboveJ. Summary ofsiteinvestigationdata, N. FranCe (Gouvenot & Gabaix, 1975)
support 300 piers carrying an elevatedsection of the Jeddah-Mecca Expressway.The soil consisted of loose silty sand andbroken coral (—5 to —28m) overlying hardcoral limestone. The piles ranged from 8 to30m in length. Grouting was executed at thebase, and along the shafts (in the densesand). Fig. 16 shows the excellent testloading results of a 22.5m long pile, 770mmin diameter, tested to twice working load (i.e.500tonnes).
Fig. 18 (ieftj. Location of test piles, N. France(Gouvenot a Gabaix, 1975)
May 1986 13
TABLE Ilt SUMMARY OF GROUTING OPERATIONS (Gouvanot e Gabaix, 1975)
Injection I, Injection l, Total
Pilenumber
A,A,AsB,BsBs
groutedsoil
SandClaySandClaySandClay
G routedlength
in
metres
1 2.507.809.507.40
1 3.407.40
Quantityinjected
in
tonnes
1 7.7
31.51 9.7
1 8.8
Mean groutpressure
at the endof grouting
in bars
25-30
12-3020-30
20-50
Quantityinjected
per metreof groutedlength in t
1.4
3.32.65
2.55
Quantityinjected
in
tonnes
32.126.457.65.4
25.611.25
Mean groutpressure
at the endof grouting
in bars
30-4020-5050-8050-801 5-3050-100
Quantityinjected
per metreof groutedlength in t
2.553.41.250.731.91.7
Quantityinjected
in
tonnes
49.826.4539.125.125.630.05
Quantityinjected
per metreof groutedlength in t
3.953.44.13.381.94.23
TABLE III: SUMMARY OF LOAD TEST RESULTS (Gouvanot a Gabaix, 1975)
EoPileNos. Q, Q,
200A, (ex) 120
Qt
Qr
1.6
E,
Qt Qr
350(ex) 220
Qt
Qr
1.6
E,
Qt
520(ex) 330
Qt
Qr
1.6
Compression
QtQt Qr
Qr
Pull-out
Qt Q,QtQr
A,
70 400 420As (r) 55 1.3 (ex) > 300 (ex) > 400
Poorly 260defined> 300
Poorlydefined > 300> 300
180 370 440B, (r) 120 1.5 (r) 240 1.5 (ex) 270 1.5
B,
G routingdestroyed byloads on 8,
450 300 1.5 160 140 1.14
180 440Bs (r) 120 1.5 (ex)
490290 1.5 (ex) > 400
ex —Load found by extrapolationr —Effective load without extrapolation
Qt —Ultimate bearing capacityQr —Creep load
All loads in tonnes
Injection point blocked bytop sleeve of packer
va inflated with waterks injection point
Inner tube of packerassambly 160 mm dia.
Pile 508 mm dia.
Fig. 19 (left/. Post grouting device for pipepiles, N. France IGouvanot & Gabaix, 1975)
cv- o
at%BI'RSZK'Mv ~~ Qmt
ssxssv. ~rm~=;-==--- -x==-~u
h msrout
Lower sleeveinflated with water
Injectionpoint open1 000 mm
In)acoon point blockedby lower sleeve
Log time, min
3 4 5 10 20 50 100I I I I 401
I )20
200
1 2Load on the pile cap, tonnas
0 200 4000 ~
EE, Q . Esi8
Es
S 30I (a)Z
0
67.8"9
101112 ~240
I280
I320t
2 3 4 5 10 20 50 100min
16
E 21E 22c~ 28
29m 30
(c)0 32
1
3(b)
00
Eto .~E
200 400t
The work of Gouvenot Er Gabaix (1975)concentrated solely on the improvement ofskin friction as a means of reducing offshorepile geometries. These tests followedGouvenot's (1973) experiments with soilanchors where a 2-5 times enhancement offrictional resistance was attained. A six pilefield test programme (Figs. 17 and 18) wasconducted in fine-medium silty sands andFlanders clay. Over the uncased pile lengths,subsequently pressure-g routed, thediameter was 660mm, formed by rotarydrilling with water and/or bentonite in thesands, and by auger and bucket in the clay.
Pile reinforcement consisted of a 508mmo.d. steel pipe of 11mm wall thickness, intowhich was attached an inner tube assemblyof 160mm i.d. (Fig. 19), permittingsubsequent pressure grouting at discrete 1mintervals, through non-return valves.
The initial phase of pile grouting (i.e. atgravity pressure, while installing) wasreferred to as lo, whilst later pressure grout-ing operations were referenced l, and I,.After each of these three phases, load testingwas conducted (i.e. E,, E, and E, data).Grouting results are summarised in Table II.
Fig. 20 (leftJ. Performance of Test Pile A 1 insand, N. France (Gouvanot & Gabaix, 1975)
14 Ground Engineering
The substantial improvements in
performance after each of the phases ofpressure grouting are shown clearly in Figs.20 (sand) and 21 (clay), whilst the results ofthe whole programme are summarised in
Table III. As indicated in the introduction tothis review, the authors were able to makeseveral clear and important conclusions,principally:(1) Q,, the ultimate bearing capacity, is very
sensitive to the effects of grouting —by afactor of 2 to 3.
(2) Q„, the creep load, varies similarly, withthe Q,:Qr ratio (1.3to 1.6) independentof the grouting influence.
(3) The piles remained very stable undercyclic loading: after several cycles nopermanent displacement remained.
(4) The increase in Q, is directly proportionalto
(V+ V)(V.+ V,)
for both clay and sand (Fig. 22) assumingcontrolled pressure and volume (i.e. noclaquage),where V = volume of grout injected
Vp = volume of pileV,= volume of grout used for
initial gravity grouting.
(to be concludedj
Load on pile cap, tonnes
200 400 6000
ja,
I
I40.I
Ec(I
E0E
1
2'
60
a6e'a
+
eZc
v- 0O sc
COfh
0 .=to 4
IA
80
X Et
(a)
1004
Ee ~ Et
0 200 400 600
Fig. 2 1.Performance of Test Pile B1in clay, N.France (Gouvenot a Gabaix, 1975)
05c)
a4
E,AE2A2 (sand
Theoretical
I
I I
EtB2(clay)e +
E2Bl (clay)
El B1
(clay)
Et A t (sand)
0 1 2 3 4 5 6
V = Pile volumeP
V = Volume injected under pressureIl = Volume filled without pressure
Fig. 22. Inferred relationship between groutvolumes and enhancement of pilepafformal)CB (Gouvenot 8 Gabaix, 1975)
Q< = Ultimate bearing capacity of the pile
Q = Effective grouted diametersA = Coefficient characteristic of the pile's geometry
(grouted length)
QLlQLo =
Ultimate bearing capacity after pressure grouting
Bearing capacity before grouting
FACING THE FUTUREWITH 100 YEARS QF EXPERIENCE.
SJg
CK'M',LIUS COMPANY LTD.Head Office and Works: Long March, Daventry, Northants NN11 4DX
Telephone: Daventry 703431 (STD Code 0327) Telex: 31600
May 1986 15