engineering and construction contract ciob nottingham 03... · engineering and construction...
TRANSCRIPT
![Page 1: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/1.jpg)
Engineering and
Construction Contract
© Blake Newport Associates Ltd. 2007
![Page 2: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/2.jpg)
Engineering and
Construction Contract
NEC3 Engineering and Construction Contract
Simon McGrail Head of Construction and Dispute Resolution, South
![Page 3: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/3.jpg)
Engineering and
Construction Contract
OBJECTIVES
• Understand rationale of NEC3; Ethos and Practical Use
• Focus on the commercial importance and application of Contract
Data, Priced Activity Schedules and Assessing Compensation
Events
![Page 4: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/4.jpg)
Engineering and
Construction Contract
AGENDA
• Introduction and Philosophy of NEC3
• Overview of NEC Standard Clauses and Structure
• Cost Components and Fees
• Activity Schedule
• Compensation Events
![Page 5: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/5.jpg)
Engineering and
Construction Contract
Philosophy
• Flexibility
- primary options give choice of pricing mechanism (lump sum to cost plus)
- secondary options allow specific employer policies to be addressed
• Clarity
- conditions expressed more simply and clearly; non-legalistic language
• Stimulus to Good Management
- emphasis on communications, co-operation and programming – from outset.
![Page 6: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/6.jpg)
Engineering and
Construction Contract
Standard Forms
• Engineering and Construction Contract (ECC)
• Engineering and Construction Subcontract (ECS)
• Engineering and Construction Short Contract
• Engineering and Construction Short Sub-contract
• Professional Services Contract
• Adjudicator’s Contract
• Term Service Contract
• Framework Contract.
![Page 7: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/7.jpg)
Engineering and
Construction Contract
Option Structure
• 6 Main Options (pricing mechanism)
• 9 Core Clauses
• 18 Secondary Clauses (includes ‘Z’ clauses and Dispute Resolution
options).
![Page 8: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/8.jpg)
Engineering and
Construction Contract
Main Options
• A – Lump Sum with Activity Schedule
• B – Lump Sum with Bill of Quantities
• C – Target Cost with Activity Schedules
• D – Target Cost with Bill of Quantities
• E – Cost Reimbursable Contract
• F – Management Contract
![Page 9: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/9.jpg)
Engineering and
Construction Contract
Core Clauses
1. General
2. Contractor’s main responsibilities
3. Time
4. Testing and Defects
5. Payment
6. Compensation events
7. Title
8. Risks and insurance
9. Termination
![Page 10: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/10.jpg)
Engineering and
Construction Contract
Secondary Options
Various secondary option clauses (X, Y and Z prefixes)
Selected as appropriate – include payment and risk-related options:
• X2: changes in the law
• X5: sectional completion
• X6: bonus for early completion
• X7: delay damages
• X14: advance payment to Contractor
• X15: limitation of Contractor’s design liability
• X16: retention
• X17: low performance damages
• Y(UK)2: HGCRA 1996 / LDEDCA 2009
• Z: amendments to contract.
![Page 11: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/11.jpg)
Engineering and
Construction Contract
Schedules of Cost Components
• Provide division between reimbursable items of cost, and items deemed to
be included in the Fee
• Two types of schedule:
Schedule of Cost Components (SCC); used only with Options C, D and
E for payment of Defined Cost and assessment of compensation events
Shorter Schedule of Cost Components (SSCS); used always with
Options A and B for assessment of compensation events, and also under
Options C & D if the PM and Contractor agree.
![Page 12: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/12.jpg)
Engineering and
Construction Contract
Schedules of Cost Components
• Does not constitute a schedule of costs, simply a list of categories of costs that the Contractor can recover directly
• All other costs are deemed to be included in the Fee
![Page 13: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/13.jpg)
Engineering and
Construction Contract
Schedules of Cost Components
Defines components of the cost of:
• People
• Equipment (non-permanent)
• Plant & Materials (permanent)
• Charges
• Manufacture & Fabrication
• Design
• Insurance
![Page 14: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/14.jpg)
Engineering and
Construction Contract
Schedules of Cost Components
• In Contract Data part 2, the Contractor must ensure all offices such as satellite
and head offices are included as Working Areas to ensure staff working in those
areas are covered by the Defined Costs
• If not, the Contractor has been deemed to allow for the recovery of their costs in
the fee (i.e. Contracts Manager).
![Page 15: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/15.jpg)
Engineering and
Construction Contract
Contract Data
• Part One - provided by Employer
• Part Two - provided by Contractor
![Page 16: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/16.jpg)
Engineering and
Construction Contract
Fees
• Contractor provides fee percentages under Contract Data Part 2
– Direct Costs
– Subcontracted Costs
![Page 17: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/17.jpg)
Engineering and
Construction Contract
Fees
• Typically, the Fee includes:
– Profit / Head Office Overheads
– Insurance Premiums
– Corporation Tax
– Advertising and Recruitment Costs
– Sureties and Guarantees
– Indirect Payments.
![Page 18: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/18.jpg)
Engineering and
Construction Contract
Fees
• Additional percentages are required within the SCC section of the Contract Data
– people overheads
– Adjustment of published equipment rates
– design overheads
– Working Areas overheads
– manufacturing and fabrication
![Page 19: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/19.jpg)
Engineering and
Construction Contract
Activity Schedule
Pertinent to Options A and C
• Activity Schedule is a list of activities prepared by the Contractor which he
expects to carry out in providing the works.
• When it has been priced by the Contractor, the lump sum for each activity is
the price to be paid by the Employer for that activity.
• The total of the prices is the Contractors price for providing the whole of the
works, including for all matters which are at the contractors risk.
![Page 20: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/20.jpg)
Engineering and
Construction Contract
Activity Schedule
• Clause 31.4 provides that the start and finish of each activity on the Activity
Schedule are shown on each programme submitted.
• The activity schedule therefore allows the prices for activities to be identified
and the programme the duration of the activities.
• Together the programme and the Activity Schedule allow the projected cash
flow for the contract to be identified.
• Under Option A and C additional Clauses 54.2 and Clause 54.3 require the
Activity Schedule and the Accepted Programme to be modified to remain
compatible.
![Page 21: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/21.jpg)
Engineering and
Construction Contract
Activity 1
Activity 2
Month 1 Month 2 Month 3 Month 4
Poor Spread of Cash flow – Activities not Completed until Months 3 & 4
Activity Schedule
![Page 22: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/22.jpg)
Engineering and
Construction Contract
Activity 1
Activity 2
Activity 3
Activity 4
Month 1 Month 2 Month 3 Month 4
Effective Spread of Cash flow – Activities Completed in Each Month
Activity Schedule
![Page 23: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/23.jpg)
Engineering and
Construction Contract
Compensation Events
• Variations, claims and modifications are managed as ‘compensation events’
in NEC contracts.
• Importantly, notification of events and assessment of cost and time
consequences is done at the time the event arises.
• This enables the project manager to take immediate decisions on how to
deal with the event rather than trying to work out what cost and extension of
time should be awarded for historic events.
![Page 24: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/24.jpg)
Engineering and
Construction Contract
Compensation Events
• Assessment of compensation events comprises the forecast change in cost
and delay to completion.
• Both are assessed on the basis of the supplier’s current intentions as shown
on an updated programme and not from a historic tender document.
• The project manager is entitled to seek quotations for compensation events
for different methods of dealing with the event, allowing the project manager
to identify the effect on the contractor’s operations of different solutions to
the problem faced.
• This provides the information needed to allow a decision to be taken on the
solution which best achieves the purchasers' objectives.
![Page 25: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/25.jpg)
Engineering and
Construction Contract
CE Procedures and Timescales
Potential
Compensation
Event
Contractor notifies
PM
PM instructs
Contractor to
give
quotation(s)
Contractor submits
quotation(s)
Contractor to
submit revised
quotation
PM’s response
PM to make
own
assessment Decision not
to proceed
Acceptance
Contractor
informed of
PM’s
assessment
8 weeks 1 week
3 weeks
3 weeks
2 weeks
2 weeks
![Page 26: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/26.jpg)
Engineering and
Construction Contract
QUESTIONS
![Page 27: Engineering and Construction Contract CIOB Nottingham 03... · Engineering and Construction Contract OBJECTIVES • Understand rationale of NEC3; Ethos and Practical Use • Focus](https://reader033.vdocuments.us/reader033/viewer/2022051507/5a7299647f8b9aa7538db64d/html5/thumbnails/27.jpg)
Engineering and
Construction Contract
© Blake Newport Associates Ltd. 2007