energynetworks.org 1 presented by andrew neves, chair cmg cmg and workstream update
TRANSCRIPT
energynetworks.org 1
PRESENTED BY Andrew Neves, Chair CMG
CMG and Workstream Update
3 June 2010 energynetworks.org 2
EDCM Overview
• Two workstreams (WSA & WSB) set up to deliver EDCM charging methodologies as outlined in Ofgem’s July 2009 decision document (ref: 90/09)
• Open to all stakeholders• Current representation from all DNOs,
suppliers, IDNOs (where relevant) and Ofgem
• Submission deadline -1 September 2010
3 June 2010 energynetworks.org 3
WSA Update
Progress so far:
• ‘Working Draft’ LRIC / FCP Methodology Statements and Implementation and Guidance Notes were produced in March:
• documenting the common understanding, of the individual EDCM methodologies outlined in Ofgem July 2009 decision document (ref: 90/09)
• sent to Ofgem for review
• published on the ENA’s Structure of Charges website
3 June 2010 energynetworks.org 3
WSA Update (cont.)
• Ofgem subsequently indicated that further development is required to address its concerns on some aspects of the LRIC and FCP methodologies
• In response, WSA has developed a number of improvements to the EDCM methodologies for inclusion in the forthcoming consultation
WSA Update (cont.)
LRIC Improvements• Revised modelling of generation in the minimum
demand scenario
• ‘Sense checking’ of powerflows derived from application of security factors
FCP Improvements• Revised generation analysis – increases the number
of locations that a Test Size Generator is applied (increasing the extent of network ‘tested’)
• ‘Sense checking’ of TSG sizes
energynetworks.org 53 June 2010
WSB Update
Progress so far• Recent consultation on EDCM/CDCM boundary received
10 responses (including all DNOs), which have now been summarised
• Response to CDCM condition on generation-dominated areas being developed
• Draft EDCM models based on current proposals provided to Ofgem for feedback and further development
energynetworks.org 63 June 2010
WSB Update (cont.)
Current proposals for tariff elements:
1. Demand (import tariffs)•Charge 1 from FCP/LRIC (p/kVA/day)• Transmission exit (p/kVA/day)• Sole user asset charge (p/day)• Scaling (p/kVA/day) (might be negative)
energynetworks.org 73 June 2010
WSB Update (cont.)
2. Generation (export tariffs)•Charge 1 from FCP/LRIC (p/kWh) credit for non-
intermittent generation•Charge 2 from FCP/LRIC (p/kVA/day)• Transmission exit (p/kVA/day) charge or credit
energynetworks.org 83 June 2010
WSB Update (cont.)
3. Network interconnections• LDNOs: portfolio with CDCM-like and EDCM-like
parts•Offshore: portfolio ?•DNO-to-DNO: treat as demand?
energynetworks.org 93 June 2010
Next steps
• Agree key outstanding issues and seek positive opinion from Ofgem for consultation paper
• Revised WSA documentation to be produced to accompany the consultation
• Continued development of LRIC/FCP as issues identified through implementation/ consultation phase
• DNOs populate EDCM pricing model to produce illustrative tariffs for consultation paper
• Issue EDCM consultation on 18 June 2010• Complete work on CDCM generation-dominated areas
energynetworks.org 103 June 2010
Revised EDCM timeline
energynetworks.org 113 June 2010