energy gateway south transmission projecta123.g.akamai.net/7/123/11558/abc123/forestservic... ·...
TRANSCRIPT
NOVEMBER 2016
U.S. Department of Interior Bureau of Land Management Wyoming State Office
Energy Gateway South Transmission Project
Plan of DevelopmentVolume I
Colorado UtahWyoming
PREPARED BY:
THIS PAGE INTENTIONALLY LEFT BLANK
ENERGY GATEWAY SOUTH TRANSMISSION PROJECT
PLAN OF DEVELOPMENTVOLUME I
Case Files Wyoming: WYW-174597
Colorado: COC-72907
Utah: UTU-87237
Prepared by:
U.S. Department of the Interior
Bureau of Land Management
Wyoming State Office
November 2016
THIS PAGE INTENTIONALLY LEFT BLANK
ENERGY GATEWAY SOUTH TRANSMISSION PROJECT
Plan of Development
Because there will be an extended period oftime between execution of the Records of Decision (ROD) and the completion of the design and engineering and commencement of construction of the Energy Gateway South Transmission Project (Project), the Plan of Development (POD) is being developed in two phases. This phase of the POD is required by the BLM to contain sufficient information for the BLM and the other federal land-management agencies to sign their respective RODs at the culmination of the NEP A process. This draft of the POD contains data and information (including the framework for mitigation) documented in the Final Environmental Impact Statement (EIS), which is based on a description of a typical 500-kilovolt (kV) transmission line along the location of the right-of-way centerline since the design and engineering of the Project is not available during preparation ofthe EIS. Also, as an appendix, tbis phase of the POD contains a complete and agency-approved POD for geotechnical investigation that will commence once the RODs are executed and the right-of-way is granted, the special-use authorization is issued, and the encroachment permit and grant of easement are issued (Appendix G- Geotechnical Investigation Plan of Development).
The approval of tbis phase of the POD is required as evidence that tbis phase of the POD contains sufficient information to support the respective RODs of the federal land-management agencies cooperating in tbis Project and for implementation of the Geotechnical Investigations that are required prior to development of the second phase of the POD for construction.
CONCURRENCE
Approved by: .& ~, Sharon Seppi Managing Director, Construction PacifiCorp
Date:_I_I/__;,_~__;_//.J...._~ _ ___ _
THIS PAGE INTENTIONALLY LEFT BLANK
Energy Gateway South Transmission Project i Plan of Development Table of Contents November 2016
TABLE OF CONTENTS
VOLUME I – Plan of Development
Section 1 – Introduction ............................................................................................................................. 1-1 1.1 Introduction ............................................................................................................................ 1-1 1.2 Purpose and Need of the Plan of Development ...................................................................... 1-3 1.3 Project Overview .................................................................................................................... 1-3 1.4 Organization of the Plan of Development .............................................................................. 1-4
1.4.1 Volume I .................................................................................................................... 1-4 1.4.1.1 Sections 1 through 5.................................................................................. 1-7 1.4.1.2 Appendices ................................................................................................ 1-7
1.4.2 Volume II: Map Sets ................................................................................................. 1-9 1.4.2.1 Map Set 1 – Project and Environmental Features (1 inch = 2,000
feet [1:24,000]) ......................................................................................... 1-9 1.4.2.2 Map Set 2 – Key Mitigation and Reclamation Practices (1 inch =
400 feet [1:4,800]) .................................................................................... 1-9 1.5 Relationship with Other Environmental Documents .............................................................. 1-9 1.6 Federal, State, and Local Permits ......................................................................................... 1-10
Section 2 – Roles and Responsibilities ...................................................................................................... 2-1 2.1 Roles and Responsibilities ...................................................................................................... 2-1
2.1.1 Company ................................................................................................................... 2-1 2.1.2 Bureau of Land Management, U.S. Forest Service, and Bureau of Indian
Affairs/Ute Indian Tribe ............................................................................................ 2-1 2.1.3 Compliance Inspection Contractor ............................................................................ 2-2 2.1.4 Construction Contractor(s) ........................................................................................ 2-2
Section 3 – Project Description .................................................................................................................. 3-1 3.1 Introduction ............................................................................................................................ 3-1 3.2 Proposed Facilities ................................................................................................................. 3-1
3.2.1 Transmission Segment Descriptions ......................................................................... 3-1 3.2.2 Typical Design Characteristics .................................................................................. 3-3 3.2.3 Transmission Structures ............................................................................................ 3-5 3.2.4 Structure Foundations................................................................................................ 3-9 3.2.5 Transmission Line Hardware .................................................................................. 3-11 3.2.6 Communications Systems ....................................................................................... 3-12 3.2.7 Substations and Series Compensation Stations ....................................................... 3-14
3.2.7.1 Substation and Series Compensation Stations Overview ............................ 3-14 3.2.7.2 Series Compensation Station Components .................................................. 3-15
3.2.8 Preliminary Access Road Information .................................................................... 3-16 3.3 Land Requirements and Construction Disturbance .............................................................. 3-19
3.3.1 Right-of-Way Acquisition ....................................................................................... 3-20 3.3.2 Temporary and Permanent (Long-term) Construction Disturbance ........................ 3-21
Section 4 – Environmental Setting, Issues, and Mitigation Measures ....................................................... 4-1 4.1 Introduction ............................................................................................................................ 4-1 4.2 Summary of Environmental Setting ....................................................................................... 4-1 4.3 Summary of Environmental Issues by Environmental Resource ........................................... 4-5
Climate and Air Quality ............................................................................................ 4-5 4.3.1
Earth Resources ......................................................................................................... 4-5 4.3.2
Energy Gateway South Transmission Project ii Plan of Development Table of Contents November 2016
4.3.2.1 Geologic Hazards ...................................................................................... 4-5 4.3.2.2 Soil Resources ........................................................................................... 4-6 4.3.2.3 Mineral Resources .................................................................................... 4-6
Paleontological Resources ......................................................................................... 4-6 4.3.3
Water Resources ........................................................................................................ 4-6 4.3.4
Vegetation ................................................................................................................. 4-7 4.3.5
Special-status Plants .................................................................................................. 4-7 4.3.6
Wildlife ...................................................................................................................... 4-7 4.3.7
4.3.7.1 Raptors ...................................................................................................... 4-7 4.3.7.2 Mammals .................................................................................................. 4-8 4.3.7.3 Big Game .................................................................................................. 4-8 4.3.7.4 Reptiles ..................................................................................................... 4-8
Special-status Wildlife .............................................................................................. 4-9 4.3.8
4.3.8.1 Special-status Passerine and Waterfowl Birds .......................................... 4-9 4.3.8.2 Special-status Raptors and Migratory Birds ............................................. 4-9 4.3.8.3 Yellow-Billed Cuckoo .............................................................................. 4-9 4.3.8.4 Greater Sage-grouse .................................................................................. 4-9 4.3.8.5 Mammals ................................................................................................ 4-10 4.3.8.6 Reptiles ................................................................................................... 4-10
Migratory Birds ....................................................................................................... 4-11 4.3.9
Fish and Aquatic Resources .................................................................................... 4-11 4.3.10
Land Use ................................................................................................................. 4-11 4.3.11
Parks, Preservation, and Recreation ........................................................................ 4-12 4.3.12
Transportation and Access ...................................................................................... 4-12 4.3.13
Congressional Designations .................................................................................... 4-12 4.3.14
Special Designations and Other Management Areas .............................................. 4-12 4.3.15
Non-wilderness Study Area Lands with Wilderness Characteristics ...................... 4-13 4.3.16
Inventoried Roadless Areas and Unroaded/Undeveloped Areas ............................. 4-13 4.3.17
Visual Resources ..................................................................................................... 4-13 4.3.18
National Trails System ............................................................................................ 4-14 4.3.19
Cultural Resources .................................................................................................. 4-14 4.3.20
Fire Ecology and Management ................................................................................ 4-14 4.3.21
Public Health and Safety ......................................................................................... 4-14 4.3.22
4.4 Overview of Mitigation Measures ........................................................................................ 4-14 4.5 Overview of Mitigation Measures Discussed in Appendices ............................................... 4-16 4.6 Selective Mitigation by Milepost ......................................................................................... 4-17
Section 5 – Literature Cited ....................................................................................................................... 5-1
Appendix A – Construction Considerations
A1 Flagging, Fencing, and Signage Plan
A2 Traffic and Transportation Management Plan
A3 Project Construction
A4 Environmental and Safety Training Plan
A5 Environmental Compliance Management Plan
A6 Operation and Maintenance Plan
Appendix B – Environmental Protection Plans
B1 Biological Resources Conservation Plan
Attachment A – Biological Resources Survey Requirements
Attachment B – Biological Resources Monitoring Plan Framework
Energy Gateway South Transmission Project iii Plan of Development Table of Contents November 2016
Attachment C –Wildlife Variance Management Plan Framework
Attachment D – Migratory Bird Nest Management, Monitoring, and Nesting Plan Framework
Attachment E – Clay Phacelia and Deseret Milkvetch Suitable Habitat Parameters
Attachment F – Uinta Basin Hookless Cactus Survey Protocol
Attachment G – Seasonal and Spatial Restrictions for Biological Resources
B2 Noxious Weed Management Plan
B3 Water Resources Protection Plan
B4 Vegetation Management Plan
B5 Historic Properties Treatment Plan
B6 Paleontological Resources Treatment Plan
B7 Erosion, Dust Control, and Air Quality Plan
B8 Fire Protection Plan
Appendix C – Environmental Protection Plan Frameworks
C1 Reclamation, Revegetation, and Monitoring Plan Framework
C2 Stormwater Pollution Prevention Plan Framework
C3 Spill Prevention, Containment, and Countermeasures Plan Framework
C4 Hazardous Materials Management Plan Framework
C5 Emergency Preparedness and Response Plan Framework
C6 Blasting Plan Framework
C7 Water Use Plan Framework
Appendix D – Resource Survey Protocols
D1 Cultural Resources Survey Protocol
D2 Draft Paleontological Resources Survey Plan
Appendix E Land Description of the Project Across Federal Lands
Appendix F – Company Transmission Construction Standards
Appendix G – Geotechnical Investigation Plan of Development
VOLUME II – Map Sets 1 and 2
Map Set 1 – Project and Environmental Features (1 inch = 2,000 feet [1:24,000])
Map Set 2 – Key Mitigation and Reclamation Practices (1 inch = 400 feet [1:4,800])
LIST OF FIGURES
Figure 1-1 Project Study Area ........................................................................................................... 1-5 Figure 3-1 Project Layout Diagram ................................................................................................... 3-2 Figure 3-2 Proposed Tangent Single-circuit 500-kilovolt Lattice Steel Structure (Delta
Configuration) .................................................................................................................. 3-6 Figure 3-3 Alternative Proposed Single-circuit 500-kilovolt Lattice Steel Structure
(Horizontal Configuration) .............................................................................................. 3-6 Figure 3-4 Proposed Tangent Single-circuit 500-kilovolt H-frame Structure ................................... 3-7 Figure 3-5 Proposed Tangent Single-circuit 500-kilovolt Guyed V .................................................. 3-7 Figure 3-6 Proposed Tangent Single-circuit 500-kilovolt Guyed Delta ............................................ 3-8 Figure 3-7 Proposed Tangent Single-circuit 345-kilovolt H-frame Structure ................................... 3-8 Figure 3-8 Proposed Single-circuit 345-kilovolt Mono-pole Tangent Structure (for angles
0° to 5°) ............................................................................................................................ 3-9
Energy Gateway South Transmission Project iv Plan of Development Table of Contents November 2016
Figure 3-9 Proposed Double-circuit 345-kilovolt Mono-pole Tangent Structure (for angles
0° to 5°) ............................................................................................................................ 3-9 Figure 3-10 Typical Regeneration Site Layout ................................................................................. 3-13 Figure 3-11 Typical 500-kilovolt Substation ..................................................................................... 3-15 Figure 3-12 Typical Right-of-Way .................................................................................................... 3-19
LIST OF TABLES
Table 1-1 Land Ownership/Jurisdiction – Miles Crossed by the Project ......................................... 1-4 Table 1-2 Summary of Potential Major Federal, Tribal, State, and Local Permits or Licenses
Required and Other Environmental Review Requirements for Project Construction
and Operation ................................................................................................................. 1-10 Table 3-1 Typical Design Characteristics of the 500-kilovolt and 345-kilovolt Transmission
Lines ................................................................................................................................ 3-3 Table 3-2 Typical 500-kilovolt Structure Type Foundation........................................................... 3-10 Table 3-3 Typical 345-kilovolt Structure Type Foundations ......................................................... 3-10 Table 3-4 Right-of-way Disturbance Acreages Across Administrative Jurisdictions for the
Project ............................................................................................................................ 3-20 Table 4-1 Design Features of the Project for Environmental Protection ....................................... 4-18 Table 4-2 Selective Mitigation Measures ....................................................................................... 4-31 Table 4-3 Selective Mitigation Measures by Link and Milepost ................................................... 4-39
Energy Gateway South Transmission Project v Plan of Development List of Acronyms November 2016
LIST OF ACRONYMS
A AC Alternating current
ACEC Area of Critical Environmental Concern
ACSR Aluminum-conductor steel-reinforced
ARPA Archaeological Resources Protection Act
ATV All-terrain vehicles
B BIA Bureau of Indian Affairs
BLM Bureau of Land Management
C CCR Code of Colorado Regulations
CFR Code of Federal Regulations
CIC Compliance Inspection Contractor
Company PacifiCorp, doing business as Rocky Mountain Power
C.R.S. Colorado Revised Statutes
CWA Clean Water Act
E ECMP Environmental Compliance Management Plan
EIS Environmental Impact Statement
EPA Environmental Protection Agency
ESA Endangered Species Act
F FAA Federal Aviation Administration
FFSL Utah Division of Forestry, Fire and State Lands
FLPMA Federal Land Policy and Management Act
FWS U.S. Fish and Wildlife Service
G GIS Geographic Information System
H HPTP Historic Properties Treatment Plan
K Kcmil Thousand circular mil
kV Kilovolt
Energy Gateway South Transmission Project vi Plan of Development List of Acronyms November 2016
M MW Megawatts
N NEPA National Environmental Policy Act
NERC National Electric Reliability Council
NHPA National Historic Preservation Act
NTP Notice to Proceed
O OPGW Optical Ground Wire
P PFYC Potential Fossil Yield Classification
P.L. Public Law
POD Plan of Development
Project Energy Gateway South Transmission Project
PRPA Paleontological Resources Preservation Act
PRTP Paleontological Resources Treatment Plan
PSC Public Service Commission
R RMP Resource Management Plan
ROD Record of Decision
S SHPO State Historic Preservation Office
SITLA School and Institutional Trust Lands Administration
SPCC Spill Prevention, Containment, and Countermeasures
SWPPP Stormwater Pollution Prevention Plan
U UAC Utah Administrative Code
UDEQ Utah Department of Environmental Quality
UDWR Utah Division of Wildlife Resources
USACE U.S. Army Corps of Engineers
U.S.C. United States Code
USFS U.S. Forest Service
W WDEQ Wyoming Department of Environmental Quality
WECC Western Electricity Coordinating Council
WSA Wilderness Study Area
WWPC Wyoming Weed and Pest Control