enablesintelligentcompletions … forenhancedoilrecoveryin openholeandmultilateralwells november2007...
TRANSCRIPT
Swellpacker™ Technology
Enables Intelligent Completions
for Enhanced Oil Recovery in
Openhole and Multilateral Wells
Novembe r 2 0 0 7
HALLIBURTON
EASYWELL
RedTe ch™ PAPERPart of the RedTech Learning Series
Multilateral and intelligent wells are evolving as key completion technologies to enhance and to
maximize hydrocarbon recovery. Such technologies require zonal isolation. Conventional
cementing techniques employ complex mechanical systems and packers to achieve isolation while
at the same time permitting potential failure points in the well design. A major Operator in the
Middle East capitalized on a successful multilateral and intelligent-well completion campaign by
partnering with Halliburton to implement an innovative and successful openhole completion
process for lateral isolation using the Swellpacker™ cable system.
Industry Challenge
Until recently, conventional completion techniques have employed cementing the mainbore
and/or using mechanical equipment such as packers to achieve zonal isolation. However, these
approaches involve complex operations and reduce the inner diameter (ID) of the casing string.
Furthermore, feed-through of hydraulic, electrical, or fiber-optic cable requires splicing the cable
lines, introducing a potential failure point in the well design. An innovative approach to intelligent
well completion for spliceless zonal isolation that simplifies openhole completions and addresses
the root causes of failure is an alternative that also reduces rig time, enhances production and
increases reliability.
Halliburton Solution
The Swellpacker cable system deploys a swelling
elastomer bonded onto a base pipe. The packer
element is manufactured with a channel to match
the cable size to be run. During operations, a
feed-through system opens the rubber elastomer,
allowing the control lines to lay down in the
channel without requiring a connection or a splice
of the cable at the packer. Once in the hole, the
elastomer swells in the presence of hydrocarbon,
remediating the splice in the elastomer while
providing an effective downhole seal between the
base pipe and the irregularities of an open hole to
maintain zonal isolation in even the most complex
EASYWELL
1
HALXXXX
2
environments. Line installation, requiring up to 8-12 hours
per packer with conventional packers, is reduced to 10
minutes per packer with the Swellpacker cable system.
Furthermore, no moving parts or service technicians are
involved and any number of Swellpacker cable systems can
be integrated into the completion string and run in a single
trip.
Operator Results
A major Middle East Operator had successfully employed
horizontal and multilateral wells with greater than 8 km of
reservoir contact to maximize hydrocarbon recovery from
its reservoirs. In recent years, completion designs included
the integration of both intelligent and passive inflow control
completion systems, further enhancing the value of
maximum reservoir contact (MRC) wells by providing
inflow control, downhole monitoring capabilities and more
detailed inflow profiles.
The Operator’s first intelligent well completions were drilled
as 7-in fullbore wells using standard 3½-in internal control
valves (ICVs) and mechanical packers. This completion
approach proved to be very successful and is utilized in
numerous fields as required. With the goal of saving costs
associated with casing, the Operator partnered with
Halliburton and WellDynamics to develop a successful
openhole version of this completion process using
Swellpacker cable systems for lateral isolation while enabling
an efficient and more reliable deployment of the
communication lines of an intelligent completion by
eliminating the requirement for cable splices, control line
cuts and cable stripping.
Laboratory testing. Before installing the first openhole
intelligent well completion using the Swellpacker cable
system, an extensive battery of laboratory tests were
performed with crude oil samples in a range of viscosities
from different oil fields to verify the Swellpacker cable
system’s swelling and sealing ability. Testing was carried out
at a major Gulf R&D center. The three main objectives of
testing were to verify the Swellpacker system performance
with respect to:
• Swelling capacity in a variety of crude oils
• Sealing capacity (ability to withstand differential
pressure) after swelling
• Expansion rate (time to complete seal and hold
differential pressure).
Scaled versions of the Swellpacker system (using a scale of
1:5) were employed to simplify handling in the laboratory.
Both separator crude oils and bottomhole samples were
studied. Reservoir pressure and temperature were applied to
the test autoclave during the swelling period to simulate
downhole conditions. Pressure was increased at
predetermined intervals of 50 psi until leakage occurred.
Conducting a number of differential pressure tests in a
given interval made it possible to determine the swelling
time for different hole dimensions and crude oils. Viscosity
is one of the major factors influencing the swelling process.
Results from the 1:5 scaled tests appear in Fig. 1, which also
details swelling profiles against time for Swellpacker system
sizes of the following dimensions:
• 3.5-in basepipe, 5.8-in OD Swellpacker system for
6-1/8-in hole ID
• 4.5-in basepipe, 5.8-in OD Swellpacker system for
6-1/8-in hole ID
• 7-in basepipe, 8.2-in OD Swellpacker system for
8.5-in hole ID.
In conclusion, laboratory testing verified (1) swelling and
sealing for a range of crude oil samples, (2) maximum
3
differential pressure exceeding the required differential
pressure and (3) expected sealing time. These positive
results confirmed that the Swellpacker cable system could
provide the annular seal required for the planned openhole
intelligent well completions.
Intelligent well completions. The Operator’s intelligent
well completion design consisted of four subassemblies:
1. Swellpacker system and ICV for the mainbore
2. Swellpacker system and ICV for Lateral 1
3. Swellpacker system and ICV for Lateral 2
4. Pressure/temperature sensor and production packerin the 7-in liner.
The installation of the intelligent well completion assembly
gave the Operator a three-zone intelligent well completion
with each valve controlling inflow from each of the three
sections.
The original well was drilled conventionally, and the
laterals were then added which resulted in placing the
completion off-bottom. It is believed that the completion
fell into the first low-side lateral, thereby setting the
uppermost Swellpacker systems in the 7-in liner. As a
result, the uppermost ICV was not used. The second ICV
controlled the two bottom laterals and the mainbore in
commingled flow, while the third ICV controlled the first
low-side lateral.
A review of the production and pressure data from this
well indicated the Swellpacker cable systems provided
lateral isolation. Furthermore, test results indicated that,
when all laterals are open to production, total flow rate was
7.6 MBOD.When only the second ICV was open, the
mainbore and Lateral 2 contributed a total rate of 7.4
MBOD. The similarity in flow rates arises because the
Final Installation Schematic
Saudi Aramco Intelligent Completion
4
mainbore and Lateral 2 are in a rock facies with better
permeability when compared to Lateral 1; therefore the
mainbore and Lateral 2 dominate the flow when all the
three laterals are open to production.
Test data also indicated that when Lateral 1 is opened to
flow while the second ICV is closed, production from
Lateral 1 is 5 MBOD, suggesting that Lateral 1 has the
potential to produce when the other two laterals are closed.
Testing was conducted when all downhole chokes were fully
opened and the surface choke was set at 25% open.
Currently, the well is producing at a rate of 6 MBOD with
1% water cut at an average pressure drawdown of 60 psi,
compared to a pre-workover rate of 1 MBOD and 15%
water cut.
A second well was drilled and completed using the same
Swellpacker cable systems and openhole ICV concept. This
time the completion was run in a dual lateral to avoid the
problem of running the liner into the lower lateral drilled
on the low side. This completion ran as planned and is
being evaluated.
Operator Benefits
The Swellpacker cable system offers multiple advantages
over conventional completion techniques. It has a
straightforward design and is able to reliably conform to
irregular wellbores. It can be tailored to swelling size and
time requirements. It can serve in openhole completions,
eliminating the need for a completion liner to achieve zonal
isolation and saving rig time and cost. The 7-in liner can be
replaced by a 6-1/8-in openhole section while still allowing
the Operator to install 3½-in ICVs; this slimming of the
wellbore continues all the way to surface, delivering
significant savings in time and cost. Lastly, a feed-through
system allows control lines and fiber-optic cables to be run
through without requiring a connection or a splice at the
packer.
Ultimately and economically, openhole intelligent well
completions using the Swellpacker system enable the inflow
from different reservoir sections to be remotely monitored
and controlled from the surface without well intervention.
Following the success of these first two intelligent well
completions, the Operator has selected Swellpacker
technology to deliver openhole annular isolation in its ICD
(passive ICV) completions for long horizontal completions.
The Swellpacker system makes it possible to place additional
annular barriers (one every 100 ft of horizontal section) and
to provide better compartmentalization and therefore better
inflow conformance, resulting in increased well recoveries
and delayed water breakthrough.
Future trilateral wells will be planned as new wells where
this new-generation openhole intelligent well design can
provide further opportunities to optimize well costs without
sacrificing inflow control.
Swellpacker Technology
The Swellpacker cable system is an annular isolation cable
feed-through packer for both open hole and cased hole
completions. This technology employs standard oilfield
tubulars with rubber layers chemically bonded along their
length. The rubber element swells upon exposure to
hydrocarbons to form an effective annular seal and a seal
around the control lines through a process known as
diffusion, which occurs as hydrocarbon molecules are
absorbed by the rubber molecules and cause them to
stretch. The oil enters the rubber, which swells the packer
and ensures that it will remain swollen, unlike water
swelling systems which can shrink due to the effect of the
osmosis process being reversible. Mere trace amounts of
hydrocarbons are sufficient to initiate the thermodynamic
absorption process.
Sales of Halliburton products and services will be in accord solelywith the terms and conditions contained in the contract betweenHalliburton and the customer that is applicable to the sale.
Biblio # 11/07© 2007 Halliburton. All Rights Reserved.
HALLIBURTONwww.halliburton.com/easywell
or email us at [email protected]
The wellbore fluid’s viscosity and temperature are key
variables in determining the time required for the
Swellpacker system to absorb hydrocarbon and ultimately to
set. Swelling of the packer is consistent along its length.
Although hydrocarbons will not degrade the rubber, they
will alter its mechanical properties, such as hardness and
tensile strength, depending on the rubber’s volume increase.
Swellpacker elements are chemically bonded to a tubing or
casing joint with element lengths tailored to accommodate
the desired differential pressure. Slip-on sleeve designs are
also available, normally in 12-in and 3-ft lengths, but for
low-pressure applications.
The Swellpacker system is suitable to run “as is” in a water-
environment well that will ultimately produce oil and set the
packer. However, packer construction for an oil-based mud
system normally uses a multilayered design that delays the
onset of swelling while the packer is deployed into the well.
This Halliburton white paper is a summary of IADC/SPE
100824 “Swell Packers: Enabling Openhole Intelligent and
Multilateral Well Completions for Enhanced Oil Recovery”
by Drew Hembling, Salam Salamy and Abdullah Qatani,
Saudi Aramco; Neale Carter, Easywell (now with Sensornet
Ltd.); and Suresh Jacob, WellDynamics, paper presented at
the 2006 IADC/SPE Asia Pacific Drilling Technology
Conference and Exhibition, Bangkok, Thailand, 13–15
November.
Table 2 Pressure Text Results
Table 3 Swelling Profile vs Time