emc project no.: 18-2019 may 21, 2018creekonthebluemile.com/images/feasibility-study.pdf ·...
TRANSCRIPT
FEASIBILITY STUDY FOR
CREEK ON THE BLUE MILE
STATESBORO, BULLOCH COUNTY, GEORGIA
PREPARED FOR:
BLUE MILE FOUNDATION &
DOWNTOWN STATESBORO DEVELOPMENT AUTHORITY 102 SOUTH MAIN STREET
STATESBORO, GEORGIA 30458
EMC PROJECT NO.: 18-2019
MAY 21, 2018
ENVIRONMENTAL MARINE CIVIL SURVEY
1211 Merchant Way, Suite 201 Statesboro, GA 30458 (912) 764-7022 (912) 764-2884-f www.emc-eng.com
Albany Atlanta Augusta Brunswick Columbus Savannah Statesboro Valdosta
Feasibil ity Study Table of Contents Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
TABLE OF CONTENTS
Executive Summary ....................................................................................................................................... 1 Project Overview ........................................................................................................................................... 2 Existing Conditions ........................................................................................................................................ 4
Project Area............................................................................................................................................... 4 Little Lotts Creek ....................................................................................................................................... 5 Little Lotts Creek Cross Section ................................................................................................................. 6 Little Lotts Creek Roadway Crossings ....................................................................................................... 7
South College Street Crossing ............................................................................................................... 7 Norfolk Southern Railway Crossing ....................................................................................................... 8 South Main Street (US Hwy 301) Crossing ............................................................................................ 9 Fair Road (State Hwy 67) Crossing ...................................................................................................... 10 Zetterower Avenue Crossing ............................................................................................................... 11
Flood Concerns ........................................................................................................................................ 12 Technical Considerations ............................................................................................................................ 13
Modification of Little Lotts Creek ........................................................................................................... 13 Reservoir/Regional Detention Pond ....................................................................................................... 14 Existing Utilities ....................................................................................................................................... 15 Roadway Crossings .................................................................................................................................. 15 Flood Plain ............................................................................................................................................... 17
Permitting Requirements ............................................................................................................................ 18 Project Construction Results ....................................................................................................................... 20
Recreational Reservoir / Regional Stormwater Detention ..................................................................... 20 South College Street Crossing ................................................................................................................. 22 Norfolk Southern Railroad Crossing ........................................................................................................ 22 Between South College and South Main ................................................................................................ 23 South Main Street Crossing and Blue Mile Streetscape Connectivity .................................................... 24 Between South Main and Fair Road ....................................................................................................... 25 Fair Road Crossing ................................................................................................................................... 26 Between Fair Road and Zetterower Avenue ........................................................................................... 27 Zetterower Avenue Crossing and Outfall ................................................................................................ 28
Schedule ...................................................................................................................................................... 29 Findings and Recommendations ................................................................................................................. 30
Feasibil ity Study Page | 1 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
EXECUTIVE SUMMARY
The Creek on the Blue Mile is best described as a revitalization project within a portion of Downtown
Statesboro. The project will involve creating a recreational reservoir and creek side pedestrian
promenade which will provide unique residential, commercial, cultural and recreational opportunities,
while enhancing the quality of life for the community.
Goals of the project include addressing and mitigating current flooding concerns within this portion of
the City, provide a regional stormwater detention facility, create developable land to be utilized for
commercial, residential and community use, and to reinforce the ongoing revitalization effort within the
area.
Technical considerations shall be identified and solved in the early stages of the project to determine
the physical goals of the project can actually be met. These considerations include physical,
environmental concerns relating to wetland mitigation and permitting requirements in relation to the
modification of Little Lotts Creek, construction of a regional detention pond, solving potential utility
conflicts, modifying roadway crossings, and addressing flood plain issues.
Once all technical considerations have been addressed, land is acquired, construction plans and
specifications are developed, permits for construction are obtained from the authorities having
jurisdiction, a contractor will be selected and the project can be constructed as envisioned. The end
result of the project will feature a recreational reservoir located west of South College Street with
various amenities, a pedestrian promenade along Little Lotts Creek between South College Street and
Zetterower Avenue with commercial, residential and community uses. The project will also feature a
reconfigured City park between Fair Road and Zetterower Avenue including recreation, entertainment,
educational and aesthetic features.
Although the Creek on the Blue Mile project has many potential obstacles, it has even greater
opportunities and end benefits. Thorough planning and design efforts are paramount to the success of
this project. Based on the information obtained from the various resources cited and the information
presented herein; EMC Engineering Services, Inc. recommends the continuation of this project.
Feasibil ity Study Page | 2 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
PROJECT OVERVIEW
On February 25, 2018 the Blue Mile Foundation and Downtown Statesboro Development Authority
partnered with EMC Engineering Services, Inc. to begin a feasibility study to redevelop a portion of Little
Lotts Creek within Downtown Statesboro into an urban, pedestrian-oriented green-way.
Due to the project’s proximity and connectivity with the Statesboro Blue Mile, this project was
affectionately named “The Creek on the Blue Mile”. The Statesboro Blue Mile is a grass-roots
revitalization effort aimed to upgrade and enhance the South Main Street corridor, and encourage
commercial and residential redevelopment into a pedestrian friendly, mixed-use area. Earning national
recognition by placing second in the Country through the America’s Best Communities completion; the
Blue Mile project has begun a revitalization drive within the community. The Creek on the Blue Mile
supports this initiative.
The mission of the Creek on the Blue Mile project is to modify the existing flood plain that exists along
little lots creek tributary in order to create a creek-side park through Downtown Statesboro, which
provides unique residential, commercial, cultural and recreational opportunities, while enhancing the
quality of life for the community. This mission serves to accomplish the following specific goals of the
project:
Reduce localized flooding impacts from major storm events to the surrounding properties
Create developable/usable land located outside the flood plain to reduce insurance and other
costs to developers/users
Provide stormwater detention storage for a portion of the City drainage basin
Attract new private development interests to support the continued growth of the downtown
area
Create a safe pedestrian corridor with connectivity to other existing pedestrian corridors such as
the Blind Willie McTell Trail, and Blue Mile Streetscape Phase I (currently in the design portion of
the project)
Integrate Little Lotts Creek into the community to ensure preservation and enhancement of
Statesboro’s natural attributes
Reinforce Statesboro’s image as a visually attractive City
Stimulate choices for compatible development of new land uses
This project envisions revitalizing approximately 36-acres within the downtown Statesboro area. The
project also aims to provide connectivity with the Georgia Southern University campus. Georgia
Southern University is the State’s largest and most comprehensive center of higher education south of
Atlanta and serves more than 27,000 students. Successful implementation of this project will attract not
only local residents and college students, but will also drive those located within the county and region
due to the unique atmosphere that will be created, none of which currently exist within the area.
The project is best described as a rehabilitation of one of the major storm water drainage canals that is
maintained by City. The beginning of project corridor is west of S. College Street and the terminus is
Feasibil ity Study Page | 3 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
east of Zetterower Avenue along the alignment of the existing canal. The primary objective of the
project is to reduce the impacts of major storm events that impact the project corridor with localized
flooding. The results of the primary objective will present a secondary result; the development of a
creek side park. The Creek at the Blue Mile will be unique in Southeast Georgia and will provide direct
connectivity to Downtown Statesboro and Georgia Southern University via its connectivity with the Blue
Mile Streetscape project.
Feasibil ity Study Page | 4 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
EXISTING CONDITIONS
PROJECT AREA
The project encompasses the area adjacent to Little Lotts Creek, between South College Street and
Zetterower Avenue, in Statesboro Bulloch County Georgia. Properties within the project corridor consist
of various usage types such as commercial, residential, and undeveloped properties. The project
corridor crosses several thoroughfares including South College Street, Norfolk Southern Railroad, South
Main Street (US Hwy 301), Fair Road (State Hwy 67) and Zetterower Avenue.
Figure 1: Project Area Highlighted in Red (Approximately 36-Acres)
Feasibil ity Study Page | 5 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
LITTLE LOTTS CREEK
Little Lotts Creek is a stream that collects storm water from a major portion of the City of Statesboro
water shed area, and conveys it south and into Lotts Creek. According to the United States Geological
Survey (USGS), Little Lotts Creek begins at the outfall of an un-named pond located along Miller Street
on the northwestern side of the City (immediately west of Joiner-Anderson Funeral Home). The creek
flows southeastward toward downtown and turns south after crossing under West Main Street. The
creek joins with an un-named tributary and then turns southeastward again at the western most portion
of the project area and runs along a City utility easement. From here the creek flows eastward through
the project area, crossing under South College Street, the Norfolk Southern railway, South Main Street,
Fair Road and Zetterower Avenue. After leaving the project area the creek continues to flow southeast
toward Veterans Memorial Parkway and then turns southward and flows into Bird Bond. From here the
creek conveys water south and eventually discharges into Lotts Creek.
Little Lotts Creek is considered a State Water and is under the jurisdiction of the US Army Corps of
Engineers. The Georgia Environmental Protection Division also requires a 25-ft stream buffer along the
waterway. The section of Little Lotts Creek between South Main Street (US Hwy 301) and Fair Road
(State Hwy 67) is armored (concrete-lined); therefore there is no 25-ft stream buffer requirement in this
area.
Figure 2: USGS Map - Creek through Project Area Highlighted in Red
Feasibil ity Study Page | 6 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
LITTLE LOTTS CREEK CROSS SECTION
Little Lotts Creek top of bank within the project corridor ranges in width from approximately 24 feet to
45 feet; with an average water width range of 5 feet to 15 feet. The concrete-lined portion of the creek
consists of a bank width of approximately 24 feet, 2.5:1 side slopes, and a 6 foot to 12 foot wide flat
bottom. The longitudinal slope of the creek within the project area varies but is an average of 0.20
percent from the beginning of the project at South College Street to the project terminus at Zetterower
Avenue. The images below represent two cross sections of the existing creek. The first image is a
representation of the creek at a cross section taken between the Midtown Market detention pond
(parcel owned by Mid-Town Holdings, LLC), and the residential property currently owned by Joseph
Robert Charron. The second image is a representation of the creek at a cross section taken between the
RJ’s Grill parking lot (parcel owned by Underwood Stacy, LLC) and the vacant commercial lot (parcel
owned by Marybeth Wildes Sapp).
Figure 3: Little Lotts Creek Existing Cross Sections
Feasibil ity Study Page | 7 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
LITTLE LOTTS CREEK ROADWAY CROSSINGS
Little Lotts Creek crosses five (5) roadways within the limits of the project area. These crossings are
described as follows:
SOUTH COLLEGE STREET CROSSING
Little Lotts Creek crosses South College Street via an 80-in and a 72-in reinforced concrete pipe. These
pipes are owned and maintained by the City of Statesboro. These culverts are inspected every three
years. The last inspection was 2017. The City of Statesboro Stormwater Division advises that there is
scheduled work to install a headwall on the upstream end of the culvert. There are no structural defects.
The pipe culvert condition is satisfactory. There are no scheduled plans to replace the structures.
Figure 4: Upstream Side of South College Street Culvert Crossing
Feasibil ity Study Page | 8 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
NORFOLK SOUTHERN RAILWAY CROSSING
Little Lotts Creek crosses the Norfolk Southern Railroad via two 6-ft x 6-ft vaulted box culverts. These
culverts are owned by Norfolk Southern Railroad and leased to and maintained by Georgia Southern
Railroad. The southern culvert barrel is elevated higher than the northern barrel. According to
representatives at Georgia Southern Railroad this are no scheduled plans to replace the culverts.
Figure 5: Upstream Side of Railroad Crossing
Feasibil ity Study Page | 9 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
SOUTH MAIN STREET (US HWY 301) CROSSING
Little Lotts Creek crosses South Main Street via five (5) 72-in box culverts. These culverts are owned and
maintained by the Georgia Department of Transportation. These culverts are considered bridge culverts
and are inspected every two years. The last inspection was on April 11, 2018. This culvert was
constructed in 1934. The current condition of this culvert is satisfactory. There are no scheduled plans to
replace of this culvert.
Figure 6: Upstream Side of South Main Crossing
Feasibil ity Study Page | 10 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
FAIR ROAD (STATE HWY 67) CROSSING
Little Lotts Creek crosses Fair Road via three (3) 96-in box culverts. These culverts are owned and
maintained by the Georgia Department of Transportation. These culverts are considered bridge culverts
and are inspected every two years. The last inspection was performed on March 21, 2018. This culvert
was constructed in 1935 and reconstructed in 1946. The current condition of this culvert is satisfactory.
There are no scheduled plans to replace of this culvert.
Figure 7: Upstream Side of Fair Road Crossing
Feasibil ity Study Page | 11 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
ZETTEROWER AVENUE CROSSING
Little Lotts Creek crosses Zetterower Avenue via three (3) 9-ft box culverts. These culverts are owned
and maintained by the City of Statesboro. These culverts are inspected every three years. The last
inspection was 2017. There is no major maintenance scheduled for this culvert. This culvert is in
satisfactory condition. There are no structural defects. There are no scheduled plans to replace this
culvert.
Figure 8: Upstream Side of Zetterower Avenue Crossing
Feasibil ity Study Page | 12 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
FLOOD CONCERNS
According to the Federal Emergency Management Agency’s Flood Insurance Rate Maps, portions of the
project area are located within flood zones. Flood zone information has been referenced from FEMA
Map 13031C0208D (effective 08/05/10), 13031C0209D (effective 05/05/10), 13031C0216D (effective
08/05/10), and 13031C0217D (effective 08/05/10). FEMA Zones found within the project area are
defined as follows:
Zone X (unshaded on map): Areas with minimal flood hazards.
Zone A (shaded brown on map): Areas located within the 100-year flood zone (1-percent-
annual-chance-flood) with flood elevations not determined.
Zone AE (shaded blue on map): Areas located within the 100-year flood zone (1-percent-annual-
chance-flood) with a known flood elevation determined.
Floodway (shaded red/blue stripes on map): Channel of a watercourse and the adjacent land
areas that are reserved in order to discharge the base flood without cumulatively increasing the
water surface elevation more than a designated height. Development within this area shall be
regulated to insure there are no increases in upstream flood elevations.
Portions of the project area located west of South College Street are located in Flood Zone AE and Flood
Zone A. Portions of the remainder of the project area are located in a Floodway, Flood Zone AE and
Flood Zone A.
Figure 9: FEMA Flood Map
Properties located along Little Lotts Creek within the project area have a history of flooding. The City of
Statesboro has recognized flooding concerns in and around Little Lotts Creek and has included the
concern within the City’s masterplan to correct in the future.
Feasibil ity Study Page | 13 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
TECHNICAL CONSIDERATIONS
In order to adequately identify potential project restraints and technical considerations, several sources
were included during the preliminary assessment of this study. These sources include the City of
Statesboro, Georgia Department of Transportation, Resources and Land Consultants (Environmental
Engineer Consultant), and EMC Engineering Services (Civil Engineer Consultant). The results of
preliminary meetings and finding are presented below, broken out over each component of the project.
Figure 10: Proposed Reservoir and Creek Route
MODIFICATION OF LITTLE LOTTS CREEK
A portion of Little Lotts Creek shall be modified to meet the goals of this project, including removing
adjacent creek properties from the flood plain, and creating a park-like pedestrian corridor with
commercial and residential spaces along the creek channel. Creek modifications to achieve these goals
will include 1) the diversion of the creek into a reservoir/regional detention pond west of South College
Street, 2) rerouting the creek along a portion of the project corridor to provide more usable area for
commercial development, 3) modifying a portion of the creek from a natural channel slope to a
decorative concrete/masonry wall with river rock/gravel bottom, and 4) lowering the bottom elevation
of the creek to provide more stormwater storage, a greater elevation difference between the creek and
proposed commercial development, and also allowing the creek to detain water for visual appearances.
These proposed changes must be carefully analyzed and planned through a Drainage Study. The Study
will take into consideration stormwater flows entering the creek, required storage capacity within the
creek, water elevations during flooding events, longitudinal creek slope modifications, and the elevation
of the existing water table as it relates to modifying the bottom of the creek bed. Creek channel design
must be studied and designed in conjunction with the regional detention pond to provide one
hydrological system.
Feasibil ity Study Page | 14 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Figure 11: Typical Retail/Residential Section Rendering
RESERVOIR/REGIONAL DETENTION POND
The undeveloped land located west of South College Street is proposed to house a recreational
reservoir, which will also serve as a regional stormwater detention facility. This 165-acre parcel consists
of wetlands, woodlands and cleared lands currently utilized for agricultural purposes. This parcel is the
ideal location for the reservoir/regional detention facility as it is undeveloped, located directly adjacent
to Little Lotts Creek and is located up gradient from the Creek on the Blue Mile corridor.
The reservoir shall serve to perform three functions necessary for the project: 1) provide the necessary
stormwater storage to mitigate the size of the downstream flood plain, 2) provide a source of water to
continuously supply The Creek on the Blue Mile corridor through times of low rainfall, and 3) provide an
urban recreational area for the City. To accomplish these tasks, a drainage study must be conducted.
The study will analyze the entire drainage basin located up gradient from the terminus of the project at
Zetterower Avenue. Existing GIS information, as well as survey data shall be utilized to create
stormwater models to calculate stormwater flows within the watershed, the needed storage volume
and the appropriate outfall controls. This information will be utilized to determine the ideal location
and required size/dimensions of the reservoir.
Wetlands are located along the eastern border of the property, within the proposed area of the
reservoir. Wetland areas are regulated by the US Army Corps of Engineers and special permitting is
required to disturb these natural habitats. As wetland permitting and mitigation requirements have
significant cost and time factors, there are two possible options in constructing a reservoir within this
wetland area. Option 01 is to mitigate and remove all wetland areas within the reservoir, creating an
open reservoir. This option would produce the smallest possible reservoir footprint as more per-foot
Feasibil ity Study Page | 15 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
vertical storage can be achieved within the reservoir area by excavation of the wetlands and other
areas. However mitigation and permitting time and costs could be significant. Option 02 is to retain as
much wetland area as possible. This option would involve building an earthen dam around the eastern
border of the wetland area and excavating a portion of the uplands located west of the wetlands to
provide the needed storage. Option 02 would create a partially open/partially wetland/wooded
reservoir. If this option is chosen, the wetlands would create a unique natural environment within the
reservoir area, where raised pathways could be built within the wetlands and utilized for
recreational/educational purposes. The footprint of the reservoir would most likely be larger utilizing
Option 02 than Option 01 as less per-foot vertical storage would be available with Option 02.
The reservoirs outfall control structure would ensure stormwater released during a major storm event
would not cause flooding to any of the adjacent properties, but must also release enough water during
times of drought to ensure the creek retains water. This structure will most likely have a mechanical
control device to ensure these dual functions will be achieved. The drainage study and hydrologic
design would determine the minimum required size of the reservoir, outfall structure type, elevations
and release mechanisms.
The goals of the project cannot be met without the construction of this detention facility, therefore
property acquisition of the land needed to house the reservoir is paramount. Project planners and
developers should ascertain if this area can be acquired prior to the project proceeding any further.
EXISTING UTILITIES
Various utilities currently cross Little Lotts Creek within the project corridor. Since the creek bed
elevation is proposed to be lowered, there is the potential of utility conflicts. Utilities such as water,
communication, gas, sanitary force main, etc. can be easily modified with modifications to the creek
bed. Existing gravity sewer located along the main roadways may conflict with the proposed lowered
creek bed elevation. These conflicts will be identified and alleviated through survey and design during
the project design stage. Options include utilizing pump stations or lowering existing gravity runs, if
possible.
ROADWAY CROSSINGS
The pedestrian corridor is proposed to cross five (5) roadways as described in the sections above. The
desirable crossing path shall be below roadway travel lanes to keep pedestrian traffic from interacting
with vehicular traffic as much as possible. To provide pedestrian access under these roadways, all
crossings shall be improved to allow for at least 8-ft of vertical height for pedestrians. Several crossing
options are available for achieve the desired crossing type. The intersecting roadway height can be
increased and cross Little Lotts Creek by either a standard spanning concrete beam bridge (shown in the
example below), via large culverts, or a combination of both. Technical considerations for these
crossings include allowing at least 8-ft in height for pedestrian access under a bridge, impacts to
adjacent properties access located along the raised portion of roadways, costs of the bridge as it relates
to bridge type, and permitting implementation.
Feasibil ity Study Page | 16 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Figure 12: Example of Pedestrian Crossing under a Roadway
Two of the roadway crossings are roadways owned and maintained by the Georgia Department of
Transportation (US Hwy 301 and State Hwy 67). The design and construction of crossings along these
two roadways shall be coordinated and permitted through the GDOT Bridge Design and Maintenance
Office. GDOT requires all pedestrian walkways under a bridge to be above the 50-year flood elevation.
One of the roadway crossings is a short line railroad track, immediately east of South College Street,
owned by Norfolk Southern Railroad and leased to and maintained by Georgia Southern Railroad. No
vertical changes to the track are proposed; however the design and construction of the crossing shall be
coordinated and permitted through Norfolk Southern.
Feasibil ity Study Page | 17 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
FLOOD PLAIN
Part of the overall project will be to address the flooding within the project area along Little Lotts Creek.
Alleviating the flooding in the project area will provide opportunities for redevelopment of the area.
Improvements to the creek and tributary channels as well as culverts under road and railroad crossings
will be needed to alleviate the flooding. In the 2013 Drainage Inventory that was performed for the City
of Statesboro, several infrastructure projects within the Creek on the Blue Mile project area have been
identified. The projects include project 6 (S. College Street Infrastructure), 14 (Brannen Street at Lotts
Creek Tributary), and 48 (South College Street Drainage Canal).
Other improvements will include the construction of a 21 acre pond in an existing low area to the west
of South College Street adjacent to Little Lotts Creek. The pond would be utilized to regulate
stormwater flows from Little Lotts Creek upstream of the project area. Another project that will need to
be investigated further due to the implementation of improvements upstream is project 53 (Gentilly
Canal Regional Detention) in the 2013 City of Statesboro drainage inventory.
The flood control portion of the project that would consist of improvements to Little Lotts Creek and its
tributaries is feasible. A drainage study which will require modeling of the creek and its tributaries will
be needed in order to determine the specific details of the required improvements. The flood control
project would need to be implemented first prior to construction of the linear trail and other
redevelopment in the project area. Other items that will be required for the flood control project
include:
Preparation of construction plans and contract documents for the proposed improvements.
Analysis of impacts along Little Lotts Creek downstream of the project area to verify that there
will be no adverse impacts to properties if upstream drainage improvements are made.
Obtain a Letter of Map Revision from FEMA to revise the Flood Insurance Rate Maps upon
implementation of the new drainage improvements.
Wetland delineations.
Obtain permitting from the Army Corps of Engineers which will require an individual permit to
improve the creek and tributaries.
Obtain a Buffer Variance from Georgia EPD to improve the creek and tributaries.
Obtain permitting from the railroad to install new drainage infrastructure at rail crossings.
Design and permit the dam for the 21 acre pond in accordance with the Georgia Safe Dams Act.
Obtain permitting from GDOT to install new drainage infrastructure at state route road
crossings.
Feasibil ity Study Page | 18 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
PERMITTING REQUIREMENTS
The project area described is under the jurisdiction of the following regulatory authorities.
City of Statesboro: All work shall be permitted through the City of Statesboro through the City’s
formal review and approval processes. The City of Statesboro Engineering Department shall be
directly involved in any design and modifications to Little Lotts Creek and in the creation of a
regional detention pond. Permitting of the commercial portion of the project shall follow the
City’s review process including a Right Start Meeting, submittals of Construction Documents and
Permit Applications, revisions/negotiations/correspondence, and approvals through a process
that typically takes 40-days.
Federal Emergency Management: In order to remove a portion of the project area out of the
FEMA Flood Zone (remove the need for flood insurance), a Letter of Map Revision (LOMR)
would need to be prepared and submitted to FEMA. This consists of modeling the as-built
drainage improvements and presenting the as-built water levels in the creek, compared to the
water levels under the pre-developed condition to FEMA. Upon FEMA review, a letter would be
issued indicating that the flood maps will be revised to show changes to the flood plain,
floodways, or flood elevations. This work requires completion of FEMA document Mt-2 with the
required supporting documentation (model results, etc.). To expedite this process, a
Conditional Letter of Map Revision (CLOMR) can be prepared once the initial modeling has been
completed. Upon FEMA review, a letter would be issued indicating if the project is built as
proposed, it would meet minimum NFIP standards. This type of map revision would also require
the completion of a FEMA Document Mt-2.
Georgia Department of Transportation: All work within the Georgia DOT Right-Of-Way (US Hwy
301 and State Hwy 67) shall be permitted through the DOT. Any modifications to crossing
structures shall be coordinated and permitted through the Bridge Design and Maintenance
Office. Any other work conducted within the Right-Of-Way shall be permitted with Right of Way
Encroachment Permit.
Georgia Environmental Protection Division: All work located within the 25-ft stream buffer must
be permitted through the Georgia EPD via a Stream Buffer Variance. Permitting will include the
submittal of a Buffer Variance Application with Exhibits, revisions/negotiations/correspondence,
and approvals. The EPD has a 60-day window to either provide written comments or issue a
variance once the complete buffer variance application has been submitted. Upon the issuing of
a variance, the public shall be notified of the proposed buffer disturbance and shall have 30 days
from the date of publication to comment on the proposed buffer disturbance. After that period
the variance will be issued and work may begin. Approved buffer impacts shall be completed
within five years of the date issued. The cost of buffer impacts is currently $350 per linear foot
of stream impact.
Georgia Soil and Water Conservation Commission: A Erosion Sedimentation and Pollution
Control Plan shall be created and permitted through GSWCC for any land disturbance greater
than 1.0-acres. The permitting process includes the creation of a 3-Phase Erosion
Sedimentation and Pollution Control Plan in accordance with the Manual for Erosion and
Feasibil ity Study Page | 19 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Sediment Control in Georgia (2016 Edition), and submission to GSWCC and the Local Issuing
Authority for review and final acceptance of the plan.
Norfolk Southern Railroad: Any work conducted within the Norfolk Southern Right-Of-Way,
and/or any modifications to any structures owned by Norfolk Southern shall be permitted
through the railroad’s Industrial Development office.
United States Army Corps of Engineers: Any impacts to wetlands or State Waters shall be
permitted through the USACE. This includes Wetland Jurisdictional Determination and an
Individual Permit. The proposed relocation and improvements to Little Lotts Creek is a standard
permitting process estimated to take between 12 to 18-months. The permitting of a
reservoir/regional stormwater detention basin will most likely be a more-involved process due
to the size and potential wetland impacts. The permitting process will involve demonstrating
the need for regional detention, consideration of alternative sites that could satisfy stormwater
needs and require fewer impacts, and minimize impacts to the greatest extent practical. A full
watershed assessment shall also be conducted and submitted to the USACE. The permitting
process for this shall take at least 18-months.
Feasibil ity Study Page | 20 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
PROJECT CONSTRUCTION RESULTS
Upon meeting all the goals and restrictions described above, the Creek on the Blue Mile shall have the
following physical outcomes.
Figure 13: Overall Conceptual Plan
RECREATIONAL RESERVOIR / REGIONAL STORMWATER DETENTION
The recreational reservoir will be located adjacent to the western end of the pedestrian promenade and
provide a permanent water source for the enhanced creek. It is intended to have a natural look and will
be informal in shape conforming to the natural contours of the land. A public picnic area will be
provided with limited parking, a shelter, tables, and a fishing pier. It is envisioned that non-motorized
boats will be allowed in the reservoir for fishing and recreational use. A perimeter multipurpose trail
will encircle the reservoir that will include benches and reservoir overlooks. The entire site will be
enhanced with a variety of native plantings and as much of the surrounding woodlands and vegetation
will be preserved as possible.
Feasibil ity Study Page | 21 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Figure 14: Recreational Reservoir / Stormwater Detention Plan Rendering
Feasibil ity Study Page | 22 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
SOUTH COLLEGE STREET CROSSING
The pedestrian promenade will begin just to the west of S College Street. At this location the existing
creek will cascade over a decorative waterfall approximately 5ft down to the level of the newly
enhanced creek. A decorative and welcoming pedestrian entry will include an accessible ramp that will
allow visitors to safely transcend to the lower level while experiencing the sight and sound of the
waterfall. The existing pair of storm pipes beneath the street will be replaced with a large enhanced
culvert that will be wide enough to accommodate the 18ft wide creek channel and a 10ft pedestrian
walkway along the north side. The new culvert will provide 8ft of clearance height for pedestrians.
NORFOLK SOUTHERN RAILROAD CROSSING
The enhanced creek and walkway will continue east beneath the railroad through another enlarged
culvert. It is planned that one of the 2 existing culverts will be retained and provide a tunnel like feature
for children (and adults) to explore. At the outfall of the crossing the will be a deck over the creek that
will allow for pedestrians to access both sides of the promenade. An access ramp will also be provided
up to S College Street for neighborhood connectivity.
Figure 15: Norfolk Southern Railroad Crossing Rendering
Feasibil ity Study Page | 23 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
BETWEEN SOUTH COLLEGE AND SOUTH MAIN
This area of the promenade will be approximately 550 feet in length and will feature a mix of residential,
new and existing commercial retail buildings, and a refurbished boutique hotel with a conference center
addition. A landscaped open space centrally located will provide a focal point for pedestrians to enjoy.
It will include a small plaza with seating beneath a shade arbor that steps down to a widened creek area
with a decorative fountain and pedestrian crossings.
Figure 16: Promenade between South College and South Main Plan Rendering
Feasibil ity Study Page | 24 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Figure 17: Plaza between South College and South Main Rendering
SOUTH MAIN STREET CROSSING AND BLUE MILE STREETSCAPE CONNECTIVITY
The promenade and creek will continue beneath South Main Street through another enhanced culvert.
Sidewalks along the creek front retail buildings will connect with those along the Blue Mile. This will
allow for pedestrians to also use the new at-grade crossing at this location provided by the Blue Mile
Streetscape project. The road will be elevated approximately 2 feet at this location.
Feasibil ity Study Page | 25 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
BETWEEN SOUTH MAIN AND FAIR ROAD
This area of the promenade will be approximately 400 feet in length and will feature a new mixed-use
retail shopping area. A mix of retail and restaurants will occur primarily on the bottom level with
residential living above. The promenade will feature many outdoor sitting areas, shade trees, fountain
features, aquatic plants, lighting, and other amenities. An extension of the promenade at grade will
provide pedestrian access to parking areas and other commercial properties to the south. A driveway
and parking will also be provided on the north side of this section that will connect S Main Street with
Fair Road.
Figure 18: Promenade between South Main and Fair Plan Rendering
Feasibil ity Study Page | 26 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
Figure 19: Typical Retail/Residential Section Rendering
FAIR ROAD CROSSING
The re-aligned creek and pedestrian walkway will continue beneath Fair Road though an enhanced
culvert. Ramps will be provided to allow pedestrian access from the street down to the promenade.
The road crossing at this location will be raised approximately 3.5 feet.
Feasibil ity Study Page | 27 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
BETWEEN FAIR ROAD AND ZETTEROWER AVENUE
This large open space will consist of public enhancements to include recreation, entertainment,
educational, and aesthetic features. The northern end will include the existing recreation department
offices, a refurbished playground, a pavilion with restrooms, and a large amphitheater. The stage and
support building will be located on a landscape island formed by the creek and promenade. The central
portion of the site includes a parking lot with optional parking deck off of Fair Road and an open air
farmers market with access from Zetterower Avenue. The southern end of the park consists of an
interactive fountain/ smaller gathering area, a demonstration garden, an arboretum, and a major entry
gateway feature. The gateway includes a potential elevated walkway connecting to the campus of
Georgia Southern University.
Figure 20: Park between Fair Road and Zetterower Avenue Rendering
Feasibil ity Study Page | 28 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
ZETTEROWER AVENUE CROSSING AND OUTFALL
The pedestrian promenade will terminate at Zetterower Avenue, but will provided connectivity to
existing sidewalks or walkways. The Zetterower Avenue drainage culverts will be deepened and
modified to accommodate the new creek elevation. Creek improvements, including
widening/deepening will continue eastward behind College Plaza Shopping Center and end at South East
Wood Products. A multi-level weir will regulate the outfall of the creek back to natural grade. The weir
will have the ability to lower the creek level by as much as 2 feet in advance of a major rain event.
Feasibil ity Study Page | 29 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
SCHEDULE
Project Phase Work Type Description Time
Pre-Design Drainage Study Limited topographic survey of key points within the drainage study area. Hydrology/Hydraulic study of the affected drainage basin.
4-months
Topographic Survey
Topographic and boundary survey of the reservoir area and project corridor adequate to prepare construction documents
1-month
Design Development
Site Engineering Preparation of construction documents for the construction of a reservoir and project corridor
4-months
Permitting City of Statesboro FEMA LOMA Ga EPD GSWCC USACE
Submittals, correspondence / revisions / negotiations with regulatory authorities adequate to approve construction documents
18-months
Construction Bidding Bidding and negotiations with contractor
2-months
Site Work Construction of all proposed work on construction documents
12-months
Feasibil ity Study Page | 30 Creek on the Blue Mile, Statesboro Georgia EMC Project No. 18-2019
FINDINGS AND RECOMMENDATIONS
The Creek on the Blue Mile is a major revitalization project. The project has many potential obstacles,
but even greater opportunities and end benefits. Thorough planning and design efforts are paramount
to the success of this project.
The recommended next steps are listed as follows:
Preparation of an Opinion of Probable Costs for the land acquisition, hydrologic/hydraulic study,
design, permitting, and proposed infrastructure improvements
Public affirmation of the project by elected officials and acceptance by the all stakeholders
Ensure property needed for this project can be secured for development into a
reservoir/regional detention facility
Conduct a hydrologic/hydraulic drainage study to ensure the goals of this project can physically
be achieved
Conduct a thorough cost-benefit analysis
Prepare construction documents and specifications
Bid the project to ensure preliminary Opinions of Probable Costs are accurate
Award the contract to the lowest qualified contractor
Build the detention pond, bridges, creek alignment
Based on the information obtained from the various resources cited and the information presented
herein; EMC Engineering Services, Inc. recommends the continuation of this project.