elmp iii white paper i - cdn.misoenergy.org
TRANSCRIPT
ELMP III White Paper I R&D report and Design
Recommendation on Short-Term Enhancements
January 31, 2019
ELMP III- Part I Short-Term Items
1
Purpose Statement
This white paper summarizes the 2019 ELMP III Research and Development study and Design recommendations
on short-term enhancements. Medium to long term enhancements are expected in a future report.
Executive Summary
Following the implementation of ELMP Phase I and ELMP Phase II in MISO’s Day-Ahead and Real-Time markets
on March 01, 2015 and May 01, 2017 respectively, MISO continues to evaluate and enhance ELMP along with its
overall price formation effort. Enhancements are explored under ELMP III including short-term, medium-term and
long-term efforts. While the medium-term effort of Enhanced Combined Cycle pricing and long-term efforts of
multi-interval pricing and future scenarios are on-going, studies of short-term enhancements show plausible
benefits and design recommendations are developed.
The short-term enhancements arise from multiple sources including the original plan to improve the approximation
to Convex Hull Pricing or full ELMP, recommendations by the Independent Market Monitor (IMM) and production
experiences. A recent development of convex envelope formulation in academia allows better approximation of
full ELMP and this report studies its practical application to MISO system. The IMM strongly supports ELMP and
recommends extended eligibility of Fast Start Resources in ELMP price setting by including Day-Ahead
committed Fast Start Resources and Ramp Relaxation. Regulation Enhancement has been implemented in the
Day-Ahead market based on production experiences to address inaccurate regulation price spikes and is now
studied for the Real-Time market.
The three enhancements were prototyped in the ELMP engine and were simulated against production system.
The convex envelope resulted in modest pricing impacts, and prices could be higher, lower or most of the time
equal to production ELMP II results. Overall uplifts trended down. Simulation results of including Day-Ahead
committed Fast Start Resources were consistent with the evaluation by the IMM and prices could increase by up
to about $2/MWh depending on the operating day. Day-Ahead and Real-Time price convergence was improved
over production ELMP. After in-depth investigation of the ramp relaxation issue, solution options were developed
but more studies are needed for improved ELMP ramp modeling to avoid unintended consequences. The
simulation study showed potential to largely automate the Real-Time regulation management process and free up
operations from manual actions. The production cost savings obtained from the enhanced regulation
management logic could range from half to multi-million dollars annually.
Based on the studies, design recommendations are summarized below:
ELMP III- Part I Short-Term Items
2
Time Issue Recommendation
Short-Term Convex Envelope Implementation after Market System Enhancement
(Tighter formulation resulted in modest price changes and
uplift reduction; low to medium implementation complexity)
IMM-1: Include DA
committed Fast Start
Resources
Implementation in near-term
(Pricing increased up to $2/MWh, reflecting usage of fast
start resources in DA; low implementation cost)
IMM-2: Relax ramp-down
limits of Fast Start
Resources
Further Study
(Need further evaluation of identified solution options to
avoid unintended consequence or discrepancy with ex
ante)
Real-Time Regulation
Clearing Enhancement
Implementation in near-term
Simulation showed favorable production costs savings
among other benefits; low implementation cost
Medium-Term ELMP enhancement for
Enhanced Combined Cycle
On-going research
Long-Term Multi-Interval Pricing and
Future Scenarios
Coordinating with Renewable Integration and Future
Resource projects
ELMP III- Part I Short-Term Items
3
Table of Contents
1. Introduction ....................................................................................................................... 4
2. Convex Envelope .............................................................................................................. 6
3. IMM Recommendations .................................................................................................... 9
3.1 Include Day-Ahead Committed Fast Start Resources ............................................................................. 10
3.2 Relax the ramp-down limitation for peaking resources ........................................................................... 15
4. Regulation Enhancement ............................................................................................... 20
5. On-going research and future scenarios ...................................................................... 28
6. Conclusion ...................................................................................................................... 30
ELMP III- Part I Short-Term Items
4
1. Introduction Price Formation is critical to an efficient wholesale electricity market that supports reliable operation and
efficient investment1. Unit commitment requires discrete decisions and units that are dispatched at their
operating limits or costs associated with the commitment decisions cannot set prices. This inability to
participate in pricing can lead to significant uplift payments. MISO developed the Extended Locational
Marginal Pricing (ELMP) to allow these units to set prices including the commitment costs based on a
mathematical concept of convex hull. ELMP was cited by FERC as a model for Fast Start Pricing in RTO
markets.
Considering the computational challenges and the existing market structure, MISO implemented ELMP in
a staged approach. The initial implementation employed a partial commitment variable to allow Fast Start
Resources such as gas turbines to set prices. ELMP Phase II expanded the definition of Fast Start
Resources2 up to resources that can start within 60 minutes. Nevertheless, challenges remain to
continuously improve ELMP modeling, including IMM recommended enhancements. For example,
resources may still not be able to set prices if ramp constrained even if their Economic Minimum Dispatch
Limits (EconMin) are relaxed to zero. Day-Ahead committed resources are not included as Fast Start
Resources in Real-Time. The currently implemented approximation of the full ELMP needs to be further
tightened to capture more benefits of the convex hull pricing theory. New pricing needs arise as MISO
gains production experience with ELMP and as the generation fleet evolves with more renewables and
future resources.
How can ELMP be improved to address these challenges and what are the benefits or liabilities of each
change? ELMP Phase III research and analysis efforts are investigating these enhancements in short-
term, medium-term and long-term initiatives. In the short-term, three items were explored, Convex
Envelope – a tighter formulation toward full ELMP, the IMM recommendation of including Day-Ahead
committed Fast Start Resources and Ramp Relaxation, and Real-Time Regulation Enhancement.
Recently, a convex primal formulation was developed that tightens, or under certain conditions exactly
reproduces, the partial commitment variable-based approximation to full ELMP3. This model was proved
to be equivalent to the SOS2 piece-wise linear cost function formulation that MISO prototyped in 20164
1 FERC AD14-14, “Price formation in energy and ancillary services markets operated by regional transmission organizations and independent system operators,” Washington, DC, USA, Tech. Rep., 2015. [Online]. Available: http://www.ferc.gov/whats-new/comm-meet/2015/111915/E-2.pdf 2 Online Fast Start Resource: An online Generation Resource that is started, synchronized and injects Energy, or a Demand Response Resource that reduces its Energy consumption, within sixty (60) minutes of being notified and that has a minimum run time of one hour or less and that will participate in setting price as described in the process in Schedule 29A of the Tariff. 3 “A convex primal formulation for convex hull pricing," Ross Baldick and Bowen Hua, IEEE Transactions on Power Systems, 32(5):3814-3823, September 2017. http://users.ece.utexas.edu/~baldick/papers/convex_hull_2017.pdf 4 FERC Technical Conference “Improving Market Clearing Software Performance to Meet Existing and Future Challenges – MISO’s Perspective,” Y. Chen, J. Bladen, A. Hoyt, D. Savageau, R. Merring, June 2016 https://www.ferc.gov/CalendarFiles/20160804133957-3%20-%20MISO%20FERC_M1_Chen_062016.pdf
ELMP III- Part I Short-Term Items
5
and implemented in 2017. This formulation improved Day-Ahead unit commitment performance by
20~30% and contributed to the reduction of MISO Day-Ahead market clearing time from 4 to 3 hours5.
The convex envelope formulation allows ELMP to be solved by using existing commercial solver within
polynomial solution time. The resulting price can be higher or lower than the current ELMP. The higher
price can help to reduce make-whole payments and the lower price can help to avoid lost opportunity
costs. The ELMP III study evaluated this enhancement against MISO’s current version to understand the
pricing and uplift impact and to assess the feasibility of implementation. Prototyping the enhancement on
the ELMP production engine and simulation on actual Operating Days produced the pricing and uplift
outcomes as expected.
IMM recommendations are focused on expanding the eligibility of Fast Start Resources. In the initial
implementation of ELMP, Day-Ahead committed resources were not included as Fast Start Resources in
Real-Time pricing due to cost causation considerations and the rare commitment of Fast Start Resources
in Day-Ahead under previous market conditions and the more restrictive definition of Fast Start
Resources. As market conditions have changed and the Fast Start Resources definition has been
revised, more Fast Start Resources are being committed in the Day-Ahead market. The ELMP III study,
based on sampled production days, shows that the pricing impact could be significant, up to double
relative to the existing ELMP II. The enhancement also produced better Day-Ahead and Real-Time price
convergence. Other aspects such as start-up cost allocation were also examined to evaluate the
appropriateness of including Day-Ahead committed Fast Start resources in Real-Time price setting.
Ramp relaxation is a more complicated issue and requires appropriate modeling to avoid unnecessary
divergence between ex ante and ex post solutions. As observed by both MISO and the IMM, some Fast
Start Resources constrained by ramp may still not be able to set prices even if EconMin is relaxed to
zero. Ramp relaxation could be needed in a manner that is similar to the unit commitment problem where
a large ramp limit is used to allow the unit to ramp from above or equal to EconMin to zero during shut-
down intervals (equivalently, an online Fast Start Resource is partially committed toward zero).
Nevertheless, this should be differentiated from the inter-temporal ramp during non-shutdown intervals.
Otherwise, an inappropriate relaxation could violate ramp rate constraints and lead to unintended
incentives for resources to deviate from their ex ante dispatch schedule given the ex post prices. Such
relaxation may also fail to accurately reflect system ramping needs and distort inter-temporal pricing
which is becoming increasingly important for the non-fuel based and energy limited new resources such
as storage. Solution options are developed either by using the partial commitment variable or by using
Ex Ante information. Further study of multi-interval pricing and production cases are needed to
appropriately model the ramp down constraints under single-interval pricing scheme.
The Regulation Enhancement was developed to address a production experience with ELMP II after it
was implemented on May 01, 2017. Regulation price spikes were then infrequently observed in the Day-
5 FERC Technical Conference “Experience and Future R&D on Improving MISO DA Market Clearing Software Performance,” Y. Chen, D. Savageau, F. Wang, R. Merring, J. Li, J. Harrison, and J. Bladen, June 2017 https://www.ferc.gov/CalendarFiles/20170623123549-M1_Chen.pdf?csrt=18151806463483539378
ELMP III- Part I Short-Term Items
6
Ahead market, and a restrictive regulation clearing logic was identified that led to the spikes. When Fast
Start Resources were dispatched down in ex post and left with less room to provide regulation (down), it
became costly to make up the RegMW within a restricted pool of “REG-Commit” units, and RegMCP was
driven high. An enhancement was developed and implemented in December 2017 for the Day-Ahead
market by designating units that have non-stranded capacity as “REG-Commit.” ELMP III develops an
enhancement for the Real-Time market based on the Day-Ahead experience and also has an important
application of enhancing or automating the operation process of regulation management.
The medium-term enhancement for pricing of Enhanced Combined Cycle model and the long-term
enhancement of multi-interval pricing and future scenarios are on-going and will be reported in a future
white paper.
2. Convex Envelope The Bid-based Security Constrained Unit Commitment and Economic Dispatch (UCED) problem involves
discrete unit commitment decisions. Traditional Locational Marginal Pricing (LMP) is not able to reflect
the lumpy costs associated with commitment decisions and uplift payments have to be used to support
the commitment and dispatch. Full ELMP, or Convex Hull Pricing, reflects both the commitment and
dispatch costs, and minimizes overall uplift payments. It was developed from the convex hull (the closest
convex approximation from below) of the total cost function. Such prices can be obtained as the optimal
multipliers of the Lagrangian dual of the UCED problem, but can be computationally expensive and no
commercial solver is currently available.
Other convex approximations exist. The current ELMP implementation at MISO is an approximation by
relaxing the integer commitment variables to be continuously adjustable from 0 to 1, and can be solved by
using existing software in the primal space. Recently, a convex primal formulation of Convex Hull Pricing
was developed by describing for each generating unit the convex hull of its feasible set and the convex
envelope of its cost function. This model was proved to be equivalent to the SOS2 piece-wise linear cost
function formulation that MISO implemented in 2017. The formulation improved Day-Ahead unit
commitment performance by 20~30% and contributed to the reduction of Day-Ahead clearing time from 4
to 3 hours. With convex envelope of cost functions and convex hull of constraints on individual
generators, the formulation maintains polynomial solution time by using commercial Linear Programming
solvers. Although some constraints like ramp rate constraints still may not be described in exact convex
hull, the convex envelope model provides tighter approximation to convex hull pricing and is expected to
further reduce uplift payments.
ELMP III- Part I Short-Term Items
7
Figure 2-1 Convex Envelope (red) obtains tighter approximation or exact convex hull of the cost function (blue) as compared to
today’s ELMP implementation (green)
The convex envelope formulation for the piece-wise linear cost function is achieved by a simple
modification to the current ELMP implementation and involves modest implementation efforts.
Suppose that generator i offers piece-wise linear cost function for time period t with breakpoint �̅�𝑖,𝑛,𝑡 for
each piece or offer block n = 1, …, N (blue line in Figure 2-1):
𝐶𝑖,𝑡(𝑝𝑖,𝑡) = 𝑐𝑖,1,𝑡𝑝𝑖,1,𝑡 + 𝑐𝑖,2,𝑡𝑝𝑖,2,𝑡 + ⋯ + 𝑐𝑖,𝑛,𝑡𝑝𝑖,𝑛,𝑡 + ⋯ + 𝑐𝑖,𝑁,𝑡𝑝𝑖,𝑁,𝑡
𝑝𝑖,𝑡 = 𝑝𝑖,1,𝑡 + 𝑝𝑖,2,𝑡 + ⋯ + 𝑝𝑖,𝑛,𝑡 + ⋯ + 𝑝𝑖,𝑁,𝑡
0 ≤ 𝑝𝑖,1,𝑡 ≤ �̅�𝑖,𝑛,𝑡, n = 1, …, N
𝑃𝑖,𝑡𝑚𝑖𝑛 ≤ 𝑝𝑖,𝑡 ≤ 𝑃𝑖,𝑡
𝑚𝑎𝑥
The current ELMP formulation applies partial commitment variable Oni,t, 0 Oni,t 1, to allow EconMin
(𝑃𝑖,𝑡𝑚𝑖𝑛) to be relaxed to zero and the fixed commitment related costs to be averaged over EconMax (𝑃𝑖,𝑡
𝑚𝑎𝑥)
(green line in Figure 2-1):
𝑂𝑛𝑖,𝑡𝑃𝑖,𝑡𝑚𝑖𝑛 ≤ 𝑝𝑖,𝑡 ≤ 𝑂𝑛𝑖,𝑡𝑃𝑖,𝑡
𝑚𝑎𝑥
𝑂𝑏𝑗𝐶𝑜𝑠𝑡 = 𝐶𝑖,𝑡(𝑝𝑖,𝑡) + 𝑂𝑛𝑖,𝑡𝑆𝑖,𝑡𝐹𝑖𝑥𝑒𝑑𝐶𝑜𝑠𝑡
The convex envelope of the piece-wise linear cost function can be obtained by further applying the
commitment variable Oni,t to each offer block (red line in Figure 2-1):
0 ≤ 𝑝𝑖,1,𝑡 ≤ 𝑶𝒏𝒊,𝒕�̅�𝑖,𝑛,𝑡, n = 1, …, N
As can be seen in Figure 2-1, the convex envelope of the piece-wise linear cost function is tighter than
the convex approximation under existing ELMP implementation. It averages the fixed cost over the
quantity corresponding to the tangent point between the original cost curve and the convex envelope
ELMP III- Part I Short-Term Items
8
instead of averaging over EconMax. The resulting price (slope of the cost curve) thus can be higher
(below the tangent point) or lower (above the tangent point) than the current ELMP. The higher price can
help to reduce make-whole payments and the lower price can help to avoid lost opportunity costs.
Overall, uplift payments are expected to reduce as compared to the current ELMP implementation. It
should also be noted that the convex envelope formulation results in the same prices as current ELMP
under three situations:
1) Block-loaded units;
2) Single-block offer curve;
3) The tangent point coincides with EconMax.
To evaluate the actual pricing impact of the convex envelope formulation on a large-scale system, we
prototyped the enhancement on the ELMP engine and simulated the enhancement against production
cases. Four production days (1152 Real-Time ELMP cases) were sampled from May 2018:
1) 05/06/2018: A modest day when ELMP II production results were the same as ex ante LMP prices
2) 05/15/2018: Max gen alert, reg deficit; ELMP II average $2.00 higher than LMP
3) 05/28/2018: MISO hit 100F record; ELMP II averaged $0.05 higher than LMP
4) 05/31/2018: Large ELMP II impact observed and averaged $5.60 higher than LMP
As expected, simulation results show that ex post prices under the convex envelope formulation can be
higher or lower than those under ELMP II. The average daily price difference varies from $0/MWh up to a
$0.08/MWh reduction. A close review of cases with price differences showed that when prices decrease,
there were usually Fast Start Resources partially committed above the tangent point (Oni,t = 1) and when
prices increase there were usually Fast Start Resources partially committed below the tangent point (Oni,t
< 1).
ELMP III- Part I Short-Term Items
9
Figure 2-2 Price difference between Convex Envelope and production ELMP II over the 5 minute intervals of sampled days
As shown in Figure 2-2, the overall price impact of convex envelope is modest. The convex envelope
formulation may result in the same prices as the current ELMP under situations as noted earlier. In
addition, the price impact can also be related to the eligibility rule of Fast Start Resources and the impact
can increase as we expand the eligibility as will be discussed in Section 3.
Given the prices resulted from the convex envelope formulation as compared to ELMP II production
results, uplift payments are evaluated as the difference between optimal profit and actual profit:
{Ex Post price*Ex Post MWenergy,reg,spin,sup,ramp – Offer Cost(Ex Post MW, Ex Post Oni,t)} –
{Ex Post price*Ex Ante MWenergy,reg,spin,sup,ramp – Offer Cost(Ex Ante MW, Ex Ante Oni,t)}
As such, the uplift defined here includes both make-whole payments and lost opportunity costs, although
in production lost opportunity costs are not explicitly compensated at MISO.
Considering the complexity to replicate the two-settlement system in production, several simplifications
are made to validate whether uplift payments are trending in the expected direction while the specific
value may not be accurate due to the simplifications:
1) Use Ex Post MW to approximate profit max MW
2) Use RT price and MW for settlement, not netting with DA
3) Skip some detailed settlement rules such as reserve substitution
Uplift payments are thus calculated for each of the four sample days and compared between convex
envelope and ELMP II as shown in Table 2-1.
Day 5/6/2018 5/15/2018 5/28/2018 5/31/2018
Uplift reduction 0 -$814 -$116 -$1,112
Table 2-1 Uplift reduction under the convex envelope formulation as compared to ELMP II production
As expected, uplift payments trended down under the convex envelope formulation.
3. IMM Recommendations In the State of Market Report 2017, the IMM assessed that ELMP still has not been effective in allowing
online peaking resources to set prices when they are the marginal source of supply in MISO, attributing to
1) Eligibility rules only allow 26 percent of the online peaking resources to potentially set prices; and 2)
Modeling assumptions governing the ability of peaking resources to ramp down and other resources to
ramp up in the ELMP model.
ELMP III- Part I Short-Term Items
10
To address these inefficiencies, the IMM updated its recommendation 2015-1 as:
1) Expanding the price-setting eligibility to include Fast Start peaking resources committed in the Day-
Ahead market;
2) Relaxing the ramp-down limitation for Fast Start peaking resources in the ELMP model; and
3) Establishing constraints to ensure the quantity of capacity (energy plus reserves) does not increase or
decrease in the ELMP model from the physical dispatch in the UDS.
The first two recommendations will be explicitly discussed below, whereas recommendation 3) is not an
issue for the current ELMP implementation and is more of an unintended consequence of inappropriate
ramp relaxation in recommendation 2).
3.1 Include Day-Ahead Committed Fast Start Resources
Currently Fast Start Resources committed in the Day-Ahead market are not eligible to participate in the
ELMP price setting algorithm in the Real-Time market. Different design goals were considered in the
original design, including:
1) RT ELMPs should equal DA ELMPs if nothing changes between DA and RT. To meet this goal, the
start-up and no-load costs of resources committed in the DA market must be considered when setting RT
ELMPs.
2) RT ELMPs are set based upon only avoidable RT costs. Only start-up and no-load costs for resources
committed after Day-Ahead would be considered in setting RT ELMP, and virtual transactions in DA are
expected to drive DA ELMP toward RT ELMP
Nevertheless, these two goals are not compatible. Under MISO’s existing market construct, Day-Ahead
commitment decisions are binding in Real-Time, and the commitment related costs are thus sunk costs.
Even if a resource did not show up in Real-Time, it still had to buy-back its Day-Ahead position. More
importantly, when ELMP was originally designed, Fast Start Resources (start-up and notification time
within 10 minutes under ELMP I) were rarely committed in the Day-Ahead market and the pricing impact
was minimal. Therefore, Day-Ahead committed Fast Start Resources were not included in the Real-Time
ELMP pricing.
ELMP III- Part I Short-Term Items
11
As the generation fleet continues to evolve including low gas prices and following the expansion of Fast
Start Resources definition (start-up and notification time within 60 minutes under ELMP II), more units
meeting the definition of Fast Start Resources are being committed in Day-Ahead, and the pricing impact
of including these units in Real-Time ELMP setting becomes potentially significant.
For example, in May 2014, there were few Fast Start Resources (10 minute notification) committed in the
Day-Ahead market. In 2017, the expanded definition of Fast Start Resources (60 minute notification),
resulted in more commitments in the Day-Ahead market but the number was still modest and
commitments of more than ten Fast Start Resources in one day were infrequent. More recently in May of
2018, significant commitment of Fast Start Resources was observed in the Day-Ahead market as shown
in Figure 3-1.
Figure 3-1 Number of 60 minutes Fast Start Resources committed in Day-Ahead for each day of May
To evaluate the pricing impact, we prototyped the change to include Day-Ahead Committed Fast Start
Resources and studied the change against Real-Time ELMP cases of the same four production days as
before (1152 five-minute cases).
Day Highlights Daily Average ELMP II-LMP
05/06/2018 modest day $0
05/15/2018 max gen alert; reg deficit $2.00
05/28/2018 miso hit 100F record $0.05
05/31/2018 largest ELMP impact $5.60
Table 3-1 Four production days selected for study
0
10
20
30
40
50
1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031
Daily Count of Fast Start Day-Ahead Commitments(May 2014 and May 2018)
2014 2018 day
ELMP III- Part I Short-Term Items
12
By including Day-Ahead committed Fast Start Resources, prices increased over ELMP II, and this impact
was more significant than that assessed in 20166 as a result of the increased usage of Fast Start
Resources in Day-Ahead as summarized in Table 3-2 - Table 3-4, and detailed in Figure 3-2 - Figure 3-3.
5/6/2018 5/15/2018 5/28/2018 5/31/2018
ELMP II $0.00 $2.00 $0.05 $5.60
DA Units $0.00 $3.74 $2.07 $7.79
Table 3-2 Average price increase from Ex Ante by including Day-Ahead committed Fast Start Resources
# of FSR 5/6/2018 5/15/2018 5/28/2018 5/31/2018
ELMP II 0 4 0.3 6
DA Units 2 14 10 18
Table 3-3 Average number of Fast Start Resources participated in ELMP pricing
% of Inv 5/6/2018 5/15/2018 5/28/2018 5/31/2018
ELMP II 0% 62% 15% 37%
DA unit 0 62% 49% 66%
Table 3-4 Percentage of intervals where Fast Start Resources participated in ELMP pricing
6 “ELMP Phase II,” Market Subcommittee, August 2016, https://cdn.misoenergy.org/20160802%20MSC%20Item%2005b%20ELMP%20Phase%20II74705.pdf
ELMP III- Part I Short-Term Items
13
Figure 3-2 Real-Time prices by including Day-Ahead committed Fast Start Resources as compared to ELMP phase II
Figure 3-3 Number of Fast Start Resources participated in ELMP pricing under Phase II and including Day-Ahead units
In the above charts, an interesting observation is that on 5/28/2018 when MISO hit 100F, only a modest
ELMP impact was observed in production. That was because on that day Fast Start Resources were
mostly committed in the Day-Ahead market but did not participate in the Real-Time pricing. By including
these units, Real-Time prices increased more than $2/MWh on average, resulting in better convergence
with Day-Ahead prices as shown in Figure 3-4.
0
10
20
30
40
50
60
70
80
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
DA RT-ELMP II RT-DA unit
$/M
Wh
Hour
ELMP III- Part I Short-Term Items
14
Figure 3-4 Day-Ahead and Real-Time hourly average prices for 05/28/2018
The study results suggested that it is beneficial to include Day-Ahead committed Fast Start Resources in
Real-Time ELMP price setting, given the increased usage of Fast Start Resources in Day-Ahead. During
the prototyping process, we were also able to assess the implementation efforts. The inclusion of Day-
Ahead committed Fast Start Resources requires modifying the definition of two parameters and therefore
the implementation efforts would be modest. Nevertheless, the testing can still be extensive given the
complexity of the pricing engine and interdependencies of other areas.
One important area identified during the review of impacted areas is the allocation of startup cost.
Currently, startup cost is allocated to the first min run hour. When Day-Ahead commitment is eligible, the
first min run hour can be shifted:
1) Situation one: RT extend DA commitment
2) Situation two: RT advance DA commitment
3) Situation three: RT bridge DA commitment
A key question is whether the current allocation needs to be changed. A detailed review confirms that the
current allocation method applies when we include Day-Ahead committed Fast Start Resources to reflect
cost causation, although allocated hour may not be the same as Day-Ahead given the commitment shift.
Specifically in situation one, under ELMP II no startup cost will be allocated for the RT commitment since
it is outside of the first min run hour. When Day-Ahead commitment becomes eligible, startup cost will be
allocated to the first Day-Ahead committed hour similar to the allocation in Day-Ahead market. In
situation two, Real-Time market will allocate startup cost to the first committed hour in Real-Time, and the
Day-Ahead market allocates startup cost to the first committed hour although this hour can be different
from that in Real-Time. Similarly, in situation three, Real-Time market will allocate cost to the first Day-
Ahead committed hour, but will not allocate cost again for the second commitment block since the Real-
Time commitment bridged the two Day-Ahead commitment blocks.
Based on the study results, we recommend near-term implementation of including Day-Ahead committed
Fast Start Resources in ELMP pricing setting. We further point out several on-going or potential future
initiatives that could be related to this change:
1) Startup cost allocation and multi-interval pricing: During the convex hull pricing study, startup costs
exhibited a tendency to be allocated to intervals when the resource was most needed. Under the
narrative definition of Fast Start Resources, these units tended to be started when most needed and stay
DA RT
DA RT
DA RT DA
ELMP III- Part I Short-Term Items
15
online for at least minimum run time. With the expansion of the price-setting eligibility or Fast Start
Resource definition, intervals when the resources was most needed may not be the first intervals over
minimum run time and there could be a potential to improve the startup cost allocation method base on
the multi-interval pricing study. The allocation can be important to provide more accurate prices for
different time periods, signalizing when resources are most needed and facilitating the optimal usage of
energy limited resources such as storage.
2) Day-Ahead commitment of Fast Start Resources: Traditionally, power systems were operated to
decide the commitment well ahead of time and then balance inelastic demand by altering the output of
conventional generation such as nuclear and coal units. Now with increasing net load variations and
uncertainties introduced by renewables, demand responses, etc., it could be the time to revisit whether
we want to bind the commitment decisions in Day-Ahead, especially for those fast start resources, or
want to make them more financial decisions and have the flexibility to re-optimize them in Real-Time
based on the latest system conditions. NYISO and PJM have similar efforts where the commitment of
fast start resources in Day-Ahead may not bind until further committed in Real-Time.
3) Short-Term Reserve: Besides the flexibility to revisit Day-Ahead fast start resource commitment,
another possibility is to reserve the capacity of fast start resources so that they can quickly come online
when needed. The Short-Term Reserve product could allow offline fast start resources to participate and
get compensated for their availability to respond fast when needed.
3.2 Relax the ramp-down limitation for peaking resources
Under the Fast Start Pricing scheme, the general concept is to allow Fast Start Resources to be partially
committed (or other variations of relaxing the minimum generation limit to zero) instead of an on/off
decision, so that they can set prices in the ex post process. Nevertheless, it has been observed that
some Fast Start Resources may still not be able to set prices if constrained by ramp. The ramp modeling
under ELMP thus needs to be improved for Fast Start Resources to more effectively set prices. To
improve the ELMP ramp modeling, it is very important to examine the unit commitment problem and
differentiate between two sets of ramp rate constraints:
1) Inter-temporal Ramp
2) Startup/Shut down Ramp
Typically, a unit is ramp constrained across intervals when it is online for dispatch.
−𝑅𝑎𝑚𝑝𝑖,𝑡 ≤ 𝐺𝑒𝑛𝑖,𝑡 − 𝐺𝑒𝑛𝑖,𝑡−1 ≤ 𝑅𝑎𝑚𝑝𝑖,𝑡 (1)
Nevertheless, during startup or shutdown periods, a different ramp limit is used to allow the unit to ramp
from 0 to EconMin or EconMin to 0, where in-between the unit is in the starting or shut down process and
is not for the RTO’s dispatch. Specifically, when an online Fast Start Resource is partially committed
toward zero, it is essentially a shutdown and the ramp constraint for shut down is:
−𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡 ≤ 𝐺𝑒𝑛𝑖,𝑡 − 𝐺𝑒𝑛𝑖,𝑡−1 (2),
ELMP III- Part I Short-Term Items
16
or combining (1) and (2), the ramp down constraint can be uniformly formulated as
𝐺𝑒𝑛𝑖,𝑡−1 − 𝐺𝑒𝑛𝑖,𝑡 ≤ 𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡 × 𝑂𝑛𝑖,𝑡−1 − (𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡 − 𝑅𝑎𝑚𝑝𝑖,𝑡) × 𝑂𝑛𝑖,𝑡 (3)
The lumpiness or non-convexity thus arises associated with the shutdown intervals, and the Fast Start
Resource would not be able to set price if constrained by the normal ramp limit from being further
dispatched down below EconMin. Fast Start Resources are usually flexible with high ramp rates. With
the previous 10 minute definition of Fast Start Resources, about three quarters of Fast Start Resources
can ramp from EconMin to zero within 5 minutes. Nevertheless, with the expansion of the definition to 60
minutes, about 40% of Fast Start Resources will have the issue of being ramp constrained from EconMin
to zero in Real-Time 5 minutes pricing.
Example 1 Fast Start Resource is ramp constrained and cannot set prices
Consider a one-period three-unit problem, where units 2 and 3 are Fast Start Resources.
Time t
load 108MW
Table 3-5 Load of Example 1
Unit min max ramp cost IntMW
unit1 0 100 100 $10/MWh 100MW
unit2 12 20 10 $20/MWh 20MW
unit3 0 20 100 $30/MWh 5MW
Table 3-6 Generation offer of Example 1
The market clearing results for ex ante and ex post under the current model, as well as ex post with
relaxation of ramp down limits are obtained below.
Ex Ante $10/MWh Ex Post -Current $10/MWh
Ex Post -RelaxRamp $20/MWh
unit1 96MW unit1 98MW unit1 100MW
unit2 12MW unit2 10MW unit2 8MW
unit3 0MW unit3 0MW unit3 0MW
Table 3-7 Market clearing results for Example 1
As can be seen, unit 2 is dispatched at EconMin and cannot set prices under ex ante. It cannot set prices
under the current ex post model either since it is ramp constrained even if its EconMin is relaxed to zero.
By further relaxing the ramp limit (using a larger limit to account for the partial shutdown), it sets prices.
Nevertheless, the shutdown ramp should be differentiated from the inter-temporal ramp when a resource
is ramp constrained while being dispatched above EconMin.
Example 2 Ramp constraint binding in a two-period problem with no lumpiness
ELMP III- Part I Short-Term Items
17
Consider an example with load and generation offers specified below, where EconMin is set to zero so
that there is no lumpiness at all in this example.
Time t1 t2
load 136MW 125MW
Table 3-8 Load of Example 2
min max ramp cost
unit1 0 100 100 $10/MWh
unit2 0 20 100 $20/MWh
unit3 0 20 5 $30/MWh
Table 3-9 Generation offer of Example 2
The market clearing results are obtained below.
t1 t2
Ex Ante $40/MWh $20/MWh
unit1 100MW 100MW
unit2 20MW 14MW
unit3 16MW 11MW
Ex Post-Current $40/MWh $20/MWh
unit1 100MW 100MW
unit2 20MW 14MW
unit3 16MW 11MW
Ex Post-RelaxRamp $30/MWh $30/MWh
unit1 100MW 100MW
unit2 20MW 20MW
unit3 16MW 5MW
Table 3-10 Market clearing results for Example 2
In Example 2, unit 3 was dispatched to meet a system peak at t1, and is ramp constrained at t2 before it
can be dispatched down to zero. The resource is not setting prices at t2, but its inter-temporal cost effect
is reflected in the price it sets at t1. That is, if we increase the load by 1MW at t1, unit 3 will generate
17MW at t1. Because of the ramp constraint, it can only ramp down to 12MW at t2 and unit 2 will back
down 1MW to balance with load at t2. As a result, the marginal cost to serve an incremental MW at t1 is
set by unit 3 at $40/MWh (= $30/MWh + $30/MWh - $20/MWh). Similarly, if we increase the load by 1MW
at t2, unit 2 will produce the incremental MW and is the marginal unit that sets the price at $20/MWh.
Because there is no lumpiness, the market clearing results under ex ante and the current ex post model
are the same. Nevertheless, if we relax the ramp-down limit in this case, unit 3 will set price for both
intervals t1 and t2 at $30/MWh. Such flat prices fail to reflect the different system needs at t1 and t2, and
could not provide the incentive for resources to follow dispatch. As shown in Table 3-10, the dispatch
ELMP III- Part I Short-Term Items
18
results diverges from those under ex ante. Given the price at $30/MWh at t2, unit 2 would like to produce
at full capacity of 20MW, and has incentive to deviate from the RTO dispatch of 14MW.
This unintended consequence could become even more severe in the co-optimization of energy with
reserves. In example 2 under the ramp relaxed ex post case, unit 3 was unrealistically dispatched down
at t2 and unit 2 is largely dispatch up to balance the load. If unit 2 was providing reserve in ex ante, then
it will not have room to provide reserve anymore in the ex post case, resulting in decreased capacity in to
provide reserve as the IMM pointed out in its recommendation 3).
Currently, several RTOs including MISO use a single-interval pricing model, which further complicates the
problem since the inter-temporal pricing impact may not be captured by the single-interval model.
Nevertheless, the nature of inter-temporal ramping in constraint (1) is different from the lumpiness issue in
constraint (3), and the ELMP ramp modeling needs to be carefully developed to avoid any unintended
consequences. As shown in Example 2, inappropriate relaxation of ramp-down limits may result in
unnecessary divergence between ex ante and ex post. The divergence could further lead to unintended
incentive for resources to deviate from their ex ante dispatch schedule given the ex post prices. The
inappropriate relaxation may also distort inter-temporal pricing and fail to accurately reflect system
ramping needs, whereas the price accuracy across different time periods will be critical given the
increasing penetration of resources such as storage that arbitrage the temporal price differences.
Solution options are explored to address the shutdown ramp issue without inadvertently affecting the
inter-temporal ramp.
Option 1: Utilizing Partial Commitment Variable7
ELMP allows Fast Start Resources to relax their dispatch minimums to zero by allowing the partial
commitment of such resources for pricing purposes. That is, instead of an on (1) or off (0) commitment
decision in reality, ELMP allows a Fast Start Resource to be partially committed between 0 and 1. When
a Fast Start Resource is partially committed down from Oni,t-1 to Oni,t, it can be interpreted as that the
resource is shut down by a fraction of (Oni,t-1 - Oni,t), and has a fraction of Oni,t remaining committed.
Therefore, the shutdown ramp limit can be used for the shutdown fraction, and the normal limit can be
used for the remaining fraction. That is, by re-writing ramp down constraint (3), it can be obtained that
𝐺𝑒𝑛𝑖,𝑡−1 − 𝐺𝑒𝑛𝑖,𝑡 ≤ 𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡 × (𝑂𝑛𝑖,𝑡−1 − 𝑂𝑛𝑖,𝑡) + 𝑅𝑎𝑚𝑝𝑖,𝑡 × 𝑂𝑛𝑖,𝑡 (4)
Compared to the ramp down constraint (1) that is used in the current ELMP model, the ramp limit can be
relaxed to larger value that accounts for the shutdown. For example, a Fast Start Resource can generate
between 100MW to 200MW and its Ramp Rate is 10MW/min. Under the existing ramp model (1), it can
only ramp down 50MW over a 5 minutes interval and will be ramp constrained even though EconMin is
relaxed to 0. By using (4), the ex post pricing can further dispatch the unit down by pushing the partial
commitment variable Oni,t toward 0 so that the ramp limit is pushed toward the larger value of
7 Dr. Gribik’s manuscript
ELMP III- Part I Short-Term Items
19
𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡. The costs associated with the dispatch and partial commitment will be able to eligible
to participate in price setting. In addition, if the resource is ramping normally between two consecutive
online intervals, i.e., Oni,t toward 1, the ramp limit will be pushed toward 𝑅𝑎𝑚𝑝𝑖,𝑡.
The shutdown ramp is usually a larger limit than normal ramp to ensure that the unit can be dispatched
down from anywhere to zero in shutdown periods. In the current unit commitment problem, it is set at
EconMax. However, real time dispatch intervals are much shorter. Assuming a large shutdown ramp may
cause significant divergence between ex-ante and ex-post even under the scenario when fixed cost is
near zero. Other possibilities include 𝐺𝑒𝑛𝑖,𝑡−1 or max {EconMin, 𝑅𝑎𝑚𝑝𝑖,𝑡}. Further studies are needed to
determine the appropriate value for shutdown ramp.
Another challenge is related to the single-interval pricing model. To calculate price at t in Real-Time,
𝐺𝑒𝑛𝑖,𝑡−1 in (4) will be a known parameter based on the latest resource output. If the resource is partially
committed or dispatched down in ex post pricing to 𝐺𝑒𝑛𝑖,𝑡, in the next interval t+1 the unit will be ramping
from 𝐺𝑒𝑛𝑖,𝑡 which can be different from 𝐺𝑒𝑛𝑖,𝑡. For example, a unit that has low incremental energy cost
and high no-load cost may be dispatched at EconMax. The ex post pricing would try to dispatch the unit
down toward zero at t, but in the next interval it will have to ramp from EconMax again. This can affect a
unit being dispatched down to zero in ex post pricing if the down ramping process takes more than one
interval. A large 𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡 can force the unit ramp to zero in one interval but may result in
significant deviation if it takes several intervals to ramp the unit to zero in ex ante. Further studies are
needed to understand the pricing impact in coordination with the value selection of 𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡.
Option 2: Utilizing information from ex ante
This option is to leverage the information from ex ante to detect the issue when the ramp-down limit
should be relaxed. For example,
1) If the dispatch ex ante is close to EconMin, then the ramp-down limit may be relaxed to shutdown ramp
to allow the unit to be dispatched down to zero when EconMin is relaxed to zero in ex post.
Nevertheless, this approach may be limited in its effectiveness if a resource is shut down from a dispatch
level above EconMin. For example, resources with high start-up and no-load costs may be dispatched
well above EconMin in Ex Ante where commitment costs are not considered, but could be dispatched
toward zero when those costs are considered in Ex Post pricing.
2) If the ramp rate constraint is binding in ex ante, it indicates an inter-temporal ramping situation and
ramp rate may not be relaxed in ex post.
MISO continues to study this problem in collaboration with its IMM and research partners. The multi-
interval pricing research could provide guidelines on the appropriate ramp modeling for current single-
interval ELMP implementation. Simulation against production cases would also be performed in selecting
the parameters discussed above such as 𝑆ℎ𝑢𝑡𝐷𝑜𝑤𝑛𝑅𝑎𝑚𝑝𝑖,𝑡.
ELMP III- Part I Short-Term Items
20
4. Regulation Enhancement Following the implementation of ELMP II on May 01, 2017, Day-Ahead Ex Ante/Ex Post energy price
differences remain negligible but large RegMCP differences were infrequently observed. A restrictive
regulation clearing logic was identified that led to these regulation price spikes. More specifically, a unit
can have different operational limits depending on whether it clears regulation or not (reg capacity econ
capacity). In the Day-Ahead Market clearing process, SCUC optimize unit commitment schedule and
specifies whether a unit is committed for regulation or not (about 30 units among over 500 all committed
units). SCED regulation clearing had been limited to “REG-Commit” resources by SCUC to not impact
available capacity. With costs more fully considered in SCED-Pricing, Fast Start Resources could be
dispatched down, leaving less room to provide regulation (down). Within the very restricted “REG-
Commit” pool, it is costly to make up the RegMW and RegMCP is thus driven high.
The existing regulation clearing logic has been conservative, since capacity from resources with reg limits
= econ limits is not impacted by regulation selection. If these resources are made eligible for SCED to
clear regulation, the Day-Ahead market will continue to identify the best way to meet capacity obligations,
and SCED can clear regulation from these additional units if needed or continue not to clear regulation
from these units. An enhancement was implemented in Dec 2017 to designate units as “REG-Commit”
for potential regulation clearing if they are: 1) committed; 2) reg-qualified; 3) reg limits = econ limits. The
enhancement, implemented in both ex ante and ex post engines, effectively addressed the RegMCP
price spikes and resulted in modest production cost savings.
In the Real-Time market, regulation management tools are already available to designate units as “REG-
Commit” for potential regulation clearing as system conditions change in Real-Time. In addition, the
regulation clearing logic is more complicated in Real-Time. To name a few, a unit offers three ramp rates
in Real-Time, up ramp rate, down ramp rate and bi-directional ramp rate, and has to use bi-directional
ramp rate ( up/down ramp rate) if it is designated as “REG-Commit” to potentially clear regulation.
Another complication involves the 5 minutes Real-Time interval versus an hourly regulation selection
process.
Recently, operations had interests to automate the regulation management tool to address inefficiencies
and operation risks associated with the manual process, and if possible to enhance the Real-Time
regulation clearing process given the anticipated benefits based on experience with the Day-Ahead
enhancement. One example of the inefficiency as identified by the IMM involves units that are
designated as “REG-Commit” during high load hours but with stranded capacity (reg limits < econ limits).
A unit was noticed that cleared full economic capacity in Day-Ahead but was designated as “REG-
Commit” in Real-Time and lost more than 100MW capacity (EconMax – RegMax). Nevertheless, the unit
was a more economic resource for energy and spin and did not actually clear regulation. As a result, no
regulation was obtained from this unit but the lost capacity could result in extra GT commits and some
isolated ramp-related price spikes for the system. The unit itself also incurred significant DAMAP
payments to buy-back its Day-Ahead position. Other examples of inefficiencies include the need for
ELMP III- Part I Short-Term Items
21
operations to spare time every hour for manually put units on “REG-Commit,” and any failure to do so
may introduce operational risks of regulation scarcity.
Considering the Day-Ahead enhanced regulation clearing logic and the Real-Time complications, the
enhanced regulation clearing logic is developed for Real-Time as:
Figure 4-1 Real-Time enhanced regulation clearing logic
To evaluate the possibility of automation and/or enhancement, the existing Real-Time regulation clearing
process was reviewed. Currently, FRAC regulation committed units are automatically passed to Real-
Time for regulation clearing in UDS, and Day-Ahead regulation committed units are manually added back.
As needed by the latest Real-Time conditions, operators manually designate more units as “REG-
Commit” for potential regulation clearing as recommended by the Real-Time regulation management tool.
Figure 4-2 Existing Regulation Real-Time Clearing process
In production, about 20~40 units are “REG-Commit” in Day-Ahead and a few more in FRAC, and the DA
and FRAC “REG-Commit” units can be different as shown in Figure 4-3.
ELMP III- Part I Short-Term Items
22
Figure 4-3 “REG-Commit” units in Day-Ahead and FARC over four sample production days
More units added as “REG-Commit” in Real-Time to ensure there are sufficient regulation supply. In
addition, most of units manually added in Real-Time already have the same reg limits and econ limits
(non-stranded capacity) and the same bi-directional ramp and up/down ramp rates (non-stranded
flexibility).
Figure 4-4 “REG-Commit” units in Real-Time, most of which as non-stranded capacity and flexibility
ELMP III- Part I Short-Term Items
23
We simulated the enhanced Real-Time regulation clearing logic against production cases to compare the
market clearing results. The same four production days as before were used, and two studies were
performed:
1) Simulate the enhanced logic against production cases, i.e., units designated as “REG-Commit” include
both those existing ones added by the existing manual regulation management (blue bar in Figure 4-4)
and those added by the enhanced logic on top of that (red bar Figure 4-4)
2) Remove operation manual regulation commitment from production cases and apply the enhanced logic
The enhanced logic is deemed effective if it improves regulation clearing relative to production solutions
based on the metrics listed in Table 4-1 and is able to capture units committed in the existing manual
regulation management tool.
Table 4-1 Market Clearing Result Measurement Metrics
Simulation results of study 1) that applies the enhanced logic to production cases are summarized in
Table 4-2 and detailed in the charts in Figure 4-5 - Figure 4-8.
Reg-Committed units 11~75 units were added on reg; generally on an hourly basis but could be
intra-hour if units offer or operating status changes within hour (like today)
Reg clearing results Reg clearing typically concentrated on a few of units add on reg, but there
could be large MW cleared on more units (1~27) at reg tight periods
Production cost Production cost reduced with more significant values at reg tight intervals;
averaged reduction of $1.8k~$20k per day
Energy/Reg price impacts
Reg price trended down with average reduction of (-$0.49/MWh)~(-
$3.55/MWh); energy price may increase or decrease through co-
optimization with averaged change of $0.02/MWh~(-$1.09/MWh)
Reg scarcity impacts The scarcity case in the sampled days was resolved with the expanded
pool of units on reg
Table 4-2 Simulation results of Study 1) Simulate the enhanced logic against production cases
ELMP III- Part I Short-Term Items
24
Figure 4-5 Units that are designated as “REG-Commit” by the enhanced logic on top of production
ELMP III- Part I Short-Term Items
25
Figure 4-6 Regulation actually cleared on the “REG-Commit” units added by the enhanced logic
Figure 4-7 Production cost savings per 5 minutes Real-Time interval by the enhanced logic
Figure 4-8 System-wide energy and regulation price changes by the enhanced logic
As can be seen, significant benefits are obtained by designating more units as “REG-Commit” for
potential regulation clearing, while maintaining the overall capacity and flexibility. Among these benefits,
production cost was reduced by up to $0.24 million per day. Moreover, while the pool of “REG-Commit”
units to potentially clear regulation is expanded, actual regulation clearing is still concentrated on the most
ELMP III- Part I Short-Term Items
26
economic ones as determined by SCED among the pool of “REG-Commit” units. This is important result
to validate the enhanced logic. Otherwise if actual regulation clearing is spread all over the expanded
pool with small amount of cleared MW, deployment could be a challenge. Since the enhanced logic is
based on offer parameters and operating status that are mostly at an hourly granularity, the regulation
commitment is also verified to be generally on an hourly basis, although intra-hour change is still possible
due to unit offer or operating status changes similarly like today. Close review of the regulation cleared
results also shows that no regulation is cleared on units that are off-control. As such, the enhanced logic
in Figure 4-1 was found to be feasible for Real-Time regulation clearing with favorable benefits.
Study 2) essentially mimics the scenario where we automate the regulation management process by
removing operation manual regulation commitment from production cases. Results show that the
enhanced logic can capture most of units that are currently being manually committed via the regulation
management tool, and would not strand or reduce resource capacity and flexibility as compared to Day-
Ahead. As shown in Figure 4-9, more units are designated as “REG-Commit” for potential regulation
clearing when applying the enhanced logic as compared to the existing manual regulation management in
production. In addition, the enhanced logic can capture most of units (green triangle) that are currently
manually designated as “REG-Commit” by the regulation management tool and would not include those
units (the portion of red bar above the green triangle) with stranded capacity or flexibility. For high load
periods when existing manual regulation management was conscious of not stranding capacity or
flexibility, the enhanced logic can capture almost all units that were manually added in production.
Examination of regulation capacity (min {(RegMax - RegMin)/2, RampRate*5min}) shows a similar pattern
as the observation above with the number of units on regulation.
ELMP III- Part I Short-Term Items
27
Figure 4-9 Units designated as “REG-Commit” by the enhance logic as compared to the manual process in production
Compared to the benefits observed in Study 1), simulation results of study 2) can be less (when missing
the economic regulation units in production), equal or more (when remove the uneconomic regulation
units in production). Compared to production, the results of study 2) are overall improved. Note that
energy price can be reduced in study 2) since units are from reg if their capacities were stranded
(RegMax < EconMax).
Reg-Committed units 2~63 units more units were on reg than production; 0~17 units were
removed from production reg due to stranded capacity or flexibility
Reg clearing results
Among the more units on reg, about 3 or 4 units on average actually
cleared reg; among the remove units about 2 or 3 units on average were
not able to clear reg anymore
Production cost Production cost reduced $2k~$16k per day than production
Energy/Reg price impacts
Price trended down but may also increase with average reg price change
of $0.48/MWh~(-$3.49/MWh) and energy price change of (-
$0.16/MWh)~(-$1.84/MWh)
Reg scarcity impacts The scarcity case in the sampled days was relieved
Table 4-3 Simulation results of Study 2) Remove operation manual regulation commitment from production cases and apply
the enhanced logic
The simulation results indicate significant efficiency gains, and support the recommendation for
enhancement and automation. The Real-Time regulation clearing enhancement is then designed for
each of processes including regulation commitment, regulation clearing, and communication of regulation
clearing results:
Figure 4-10 Design of Real-Time regulation clearing enhancement
This Real-Time Regulation Clearing Enhancement is a significant step in the overall Regulation
Enhancement Roadmap as shown in Figure 4-11.
ELMP III- Part I Short-Term Items
28
Figure 4-11 Overall Regulation Enhancement Roadmap
Efficiency Grade Description
Reg Capacity New logic added more capacity/units than current RT reg tool
DA/RT convergence Units with stranded capacity/flexibility will not be put on reg
(IMM)
Reliability and
Economic Efficiency
Simulation shows no spread reg clearing; production cost
reduced from production
Operation Process
Improvement
Could largely free up operation from the manual regulation
management every hour; may still need operation surveillance
Optimality Capture majority of economic reg units; can be further improved
by LAC optimization
Table 4-4 Evaluation of the proposed Real-Time Reg Enhancement relative to the overall Roadmap
5. On-going research and future scenarios In the medium-term, ELMP III is exploring appropriate pricing for the Enhanced Combined Cycle (ECC)
model. MISO developed the ECC model to more accurately reflect combined cycle resource operational
characteristics utilizing Configurations, Components, and Transitions.8 With the existing ELMP logic,
ECC resources are not able to include transition costs in their price setting and cannot set prices if not
dispatchable such as transitioning into the Duct Burner (DB) configuration as shown in Figure 5-1.
Incorporation of the transition-related costs in price setting is explored under ELMP III by investigating
appropriate convexification of transition related decisions.
8 Enhanced Combined Cycle Task Team, https://www.misoenergy.org/stakeholder-engagement/committees/enhanced-combined-cycle-task-team-ecctt/
ELMP III- Part I Short-Term Items
29
Figure 5-1 ECC Resource Costs Related to Transitions to DB Configurations
In the long-term, high penetration of renewables and emerging future resources post new challenges for
price formation. For example, under the future scenarios as shown in Figure 5-2, net load could ramp up
fast during sunset hours, and it will be important for resources that are committed to meet the needs to
set prices. In addition, while energy pricing may be driven down by the near-zero marginal cost
renewables, other resources might be hold online to provide reliability or flexibility services and it is
important to send the corresponding price signal to the market place.
Figure 5-2 Net load curve with high penetration of renewables
With the integration of future resources such as Storages and Distributed Energy Resources, temporal
and locational price accuracy will become critical for the efficient utilization of these resources and the
overall system reliability. For example, Storage resources are featured by their fast ramping flexibility, but
are meanwhile energy limited and their offers could be driven by the anticipated temporal price
ELMP III- Part I Short-Term Items
30
differences. Different aggregation schemes are being explored for Distributed Energy Resources and
aggregation across multiple injection nodes needs to be carefully design to ensure the accuracy of local
price formation. As a result, it is important to use these resources at the right time and location, and
accurate price signals can incentivize efficient charging or discharging of these resources or appropriate
locational response. Currently, the RTO employs a single-interval dispatch and pricing model, which can
be hard to co-optimize with future intervals and inform the future prices. Multi-interval pricing is thus
studied under ELMP III. Real-Time application can be challenging where prices are calculated on a
moving window basis and the advisory prices at the future intervals may not materialize when they
become binding.9
6. Conclusion The ELMP III research and development studies show benefits of the continued price enhancements, and
the prototyping experiences help to understand the implementation complexity. Based on the study, the
IMM recommendation of including Day-Ahead Fast Start Resources in Real-Time ELMP setting and the
Real-Time Regulation Enhancement are recommended for near-term implementation considering the
significant benefits and the modest implementation efforts. Convex Envelope formulation and the IMM
recommendation of ramp relaxation are recommended to be prioritized in the implementation queue after
the new Market System is in place. Additional study and validation against production cases may also be
needed for the ramp relaxation. Medium-term and long-term efforts are under investigation and are
expected in a future report.
Endnotes
MISO acknowledges the effective collaboration with the IMM, its research partners of Prof. Ross Baldick and Bowen Hua from the University of Texas, Austin. We specially appreciate the discussions with Dr. Paul Gribik.
9 FERC Technical Conference, “Price Formation with Evolving Resource Mix,” C. Wang, D. Chatterjee, J. Li and M. Robinson, June 2017. https://www.ferc.gov/CalendarFiles/20170623124149-20170620%20MISO%20Price%20Formation_FERC%20Tech%20Conf.pdf?csrt=18151806463483539378