elevator installation processlfportal.eastvaleca.gov/weblink/0/edoc/2343/hydro... · guide to the...

79
Rev. 9/2012 Elevator Installation Process General Contractor Guide © Otis Elevator Company 2012 All rights reserved

Upload: others

Post on 24-Mar-2021

8 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Rev. 9/2012

Elevator Installation

Process

General Contractor

Guide

© Otis Elevator Company 2012 All rights reserved

Page 2: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Introduction

Page 3: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

This book is to be delivered to the General Contractor or Project Manager at the first job site visit. With this book and in conjunction with the sales approvals, the Otis Superintendent will cover important information regarding the preparation of the job site. It is the goal of Otis Elevator to guarantee a safe work environment to all employees. The Otis Superintendent with this book will go over the requirements that are needed for Otis to begin work in a safe and quality environment. Otis is committed to turning over a quality elevator to the final customer. The intent of this book along with the sales approvals is to guarantee communication between the local office and the party with which Otis Elevator has a sales contract. Any suggestion as to how Otis could better communicate in the future will be appreciated. For any suggestions please communicate through the Otis Construction Superintendent.

Otis Elevator Company

Otis Construction Superintendent: _______________________________ ph: __________________

Email: ___________________________________

Otis Construction Coordinator: _________________________________ ph: __________________

Email: ___________________________________

Otis Project Manager / Sales: ___________________________________ ph: __________________

Email: ___________________________________

Otis Office: ph: _________________________________ fax: _______________________________

Otis Office Address: _________________________________________________________________

Page 4: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Elevator Installation Process

Page 5: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

General Contractor’s / Project Manager’s Guide to the Elevator Installation Process

Coordination between the various building trades during the elevator installation process is essential for the smooth installation, completion, and final Code Authority acceptance of the project elevators. The information contained in this reference manual is intended as a tool and an aid to the General Contractor/Project Manager. The purpose is to ensure that “elevator related” work items are identified early in the construction process. This will allow other trades sufficient time to complete their work to permit a timely elevator installation and successful final elevator inspection by the local Code Enforcing Authority. A Contractors Pre-Start Checklist and key items of coordination is enclosed, along with a “Work by Others Reference” section. This information should be shared with the appropriate subcontractors. The checklist items must be completed, and the form signed and returned, before Otis can begin the installation. If drilling is required, the “Outside Drilling Information” form must be completed and a copy sent to Otis and the Drilling contractor. A Contractors Pre-Inspection Checklist of the non-elevator work items is enclosed. This form along with the “Work by Others Reference” section serves as a ready reference. These items, which are often cited as deficiencies during the Code Authority inspection, must to be complete prior to the elevator being inspected and approved for public use. Prior to calling for Code Inspection, all elevator as well as non-elevator work items, outlined in the pre-inspection checklist, must be complete and ready for final inspection. Otis will not be responsible for re-inspection fees or additional labor cost caused by the failure of other trades to perform as required. We would also like to take the opportunity to advise you that it is the policy of Otis Elevator Company that 90% of the contract amount is paid before the equipment is turned over to you. If you foresee any problems with this requirement, please contact the Otis Superintendent.

The enclosed information is provided as a reference based on current Code interpretations and experience. Local Code Authority interpretation of requirements may at times differ and obviously will govern.

Otis Elevator Company

Page 6: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Pre-Start Information

Page 7: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Contractor’s Pre-Start Checklist

Form IPB_03_HYD (Rev. 8/2012)

Job Site Superintendent Otis Project NumberCell Phone Name & AddressJob Site PhoneFaxIn order to help us meet your schedule; the following items must be complete prior to Otis scheduling the job. Initial “checked” items whenthey have been corrected and fax form to the Otis Construction Superintendent. Otis will check the job site and confirm that all items havebeen completed and schedule work accordingly.

GeneralDry material storage and staging close to elevator hoistway. The material is not to be moved until the elevator is installed.

Rollable access (wood, asphalt, concrete, etc.) or uninterrupted use of forklift or crane with supplied operator.

Power for tools

PitPit must be clean and dry with overhead protection (cleaning & pumping of pit by others).

Pit specifications per Otis contract drawing (i.e., width, length and depth).

Metal pit ladder extending from the pit floor upward, not less than 48” above the bottom landing floor level.

HoistwayHoistway clean and dry with overhead protection.

Hoistway rise and rough opening per Otis contract drawing (i.e., width, length and depth). Plumb within 1”.

Overhead clearance per Otis contract drawing.

Blockouts for to-from oil line and wiring (machine room HydroFit) (all cutting and patching by others).

Rail bracket inserts, entrance support, and fastenings per Otis contract drawing. All intermediate steel in place as required.

Rail bracket attachment supports must be exposed and flush with the clear hoistway line and finished floor flush with insidehoistway wall line. Surveyor to coordinate floor lines as required.

Machine Room/Machine SpaceMachine room dry and clean with complete drywall and fire sealant applied. (machine room version only)

Machine room location and size per Otis contract drawing. (machine room version only)

Machine space access door sized and located per Otis contract drawing (3’x7’ door, door frame edge at dimension indicatedon contract layout from inside front of hoistway) (MRL version only)Disconnect mounting panel (shroud) installed in machine space door per Otis drawing instructions (MRL version only)

Lockable fused disconnect switch with 4 wire (separate ground) 3 phase power, correct motor horsepower rating - perpower confirmation and local code.Provide 120v/20A lockable fused disconnect for cab lighting circuit - per power confirmation.

Self-closing, self-locking, fire-rated machine room door, per local code. Swing per Otis contract drawing and local code.

Auxiliary contacts for Emergency Power/ERU operation.

Provide 120v GFCI duplex receptacle and lighting with the light switch located within 18” of the lock side of door.

SafetyOtis / OSHA approved, freestanding, removable barricades on all floors.

Steel safety beam properly supported and secured against movement located over the center of main rails with a minimumload rating of 5000# (or greater) as indicated on the Otis contract drawing.Working area clear of debris, which could cause an accident.

Adequate lighting in front of hoistway, and in machine room.

OSHA approved stairwell access to all floors.

Elevator work Areas 55º min.

Otis Const. Supt.: Office: Mobile: Fax:

Authorized Otis Representative Date: Authorized Representative for GC/Owner Date:

Page 8: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Barricade Form (Rev. 9/2012)

Suggested Barricading Methods

Barricades Must Meet OSHA Minimum Requirements

42” high

Have mid-rail and kick board

Must withstand 200 lbs. of side pressure

Otis Requirements

Installed by others, maintained by Otis

Free-standing, removable barricades

Barricade should span only one rough opening

Typical 2”x4” timber construction (minimum)

#1 #2

#3 #4

Occupied

Building

Page 9: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

(Rev. 8/2006)

Rough Opening Dimensions

Note: If deviation of above is required, seek approval in writing through the Otis Construction Superintendent.

Lintel/Header Beam(By others)

Subfloor to be Formed andPoured to Hoistway Wall(by others)

Subfloor

Rough Opening

Rough opening is 10" larger on each side of frame and 10" larger on top of the frame.

Masonry block hoistways may be saw-toothed at the rough opening.

Fire rating on drywall enclosure (by others). If the header is constructed of wood, it must

be covered inside of the hoistway to provide proper fire rating.

Forms in hoistway must be removed prior to Otis commencing work.

Fixture location on multiple-unit installations are to be coordinated with Superintendent.

If the contractor is planning to leave out the front wall, there must be adequate door frame fastening provided. A horizontal support (lintel) must be provided 12” above the clear opening at each landing. Coordinate with the Superintendent.

10"

10"Clear Opening

10"

Clear Opening

Rough Opening

Lintel/Header Beam(by others)

Notes

10"

Clear Opening

Rough Opening

10" 10"Clear Opening

Rough Opening

Fixtures

Page 10: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Hoistway Entrance Information.doc (Rev. 8/2006)

Hoistway Entrance Information

Drywall Arrangement - D1 - 2 layers of gypsum wallboard on corridor side and 1 layer of 1" (25 mm) shaft wall liner on hoistway side with metal "J-Strut" at interface. Drywall Arrangement - D2 - 2 layers of gypsum wallboard on corridor side and 2 layers of gypsum wallboard on hoistway side around metal or wood studs. Drywall Arrangement - D3 - 1 layer of gypsum wallboard on corridor side and 1 layer of gypsum wallboard on hoistway side around metal or wood.

Notes: 1. All frames are bolted. Frame heads project 1/4" (6 mm) beyond front face of side jamb. All jamb faces (head and sides) are 2". 2. Embossed handicapped plates measuring 4" x 4" (102 mm x 102 mm) are applied to both jambs of each entrance at appropriate

height, characters are 2" (51 mm) high and raised with adjacent Braille. 3. Opening type and size are per cab selection. Entrances arranged for flush sill support per layout "Detail A". 4. Arrangements D1, D2, M1, M2, and M3 have a one and a half (1½) hour fire protection rating. Arrangement D3 has a one (1) hour

fire protection rating. 5. Sight guards are black with any metal finish door. Powder painted doors have matching powder painted sight guard.

Warning - Interface of the two-hour wall with the Otis frame by the drywall constructor must be per Otis requirements in order to maintain the fire rating of the entrance assembly, only the exact arrangements depicted above can be provided.

(2) Layers 5/8" Sheetrock

W ood orMetal Stud

3 1/2" Min. 7 1/2" Max.

X

5/8" (2) Layers 5/8" Sheetrock

W 6" Min. 10" Max.

(2) Layers 1/2" Sheetrock

W ood or Metal Stud

3 1/2" Min. 7 1/2" Max. X

5/8(2) Layers 1/2" Sheetrock

W 5 1/2" 9 1/2"

(1) Layer 1/2" Sheetrock

W ood or M eta l Stud

3 1/2" M in. 7 1/2" M ax. X

5/8" (1) Layer 1/2" Sheetrock

W 4 1/2" M in. 8 1/2" M ax.

(1) Layer 5/8" Sheetrock

Wood or Metal Stud

3 1/2" Min. 7 1/2" Max. X

5/8" (1) Layer 5/8" Sheetrock

W 4 3/4" Min. 8 3/4" Max.

1" Shaft W all Liner Metal "J" Strut

(2) Layers 1/2" or 5/8" Sheetrock

W 3 1/2" Min. 7 1/4" Max.

X

5/8"

F

4.81" Min.20.00" Max. X

W

X

W

GYPSUM WALLBOARD(OPTIONAL)

5/8"

METAL ORWOOD FURRING(OPTIONAL)

3.45" Min.18.18" Max.

X

W

1/2"

3.45" Min.18.18" Max.

PLASTER FINISH

Masonry Arrangement - M2 Unfinished masonry wall or masonry with furred drywall

Masonry Arrangement - M1 Recessed frame in masonry wall

Masonry Arrangement - M3 Masonry with plaster finish

F = Total side jamb depth

W = Total wall thickness at entrance (actual; not nominal)

X = Standard side jamb extension beyond back of wall (1-3/16” (30.2mm) typical; 1-1/8” (28.6mm) with two speed doors)

Page 11: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Rev. 9/2012

HydroFit MRL Access Door Location & Size

The location of the HydroFit MRL access door in critical to ensure proper componentclearances and elevator operation. The elevator layouts include details on positioning thisdoor, specifically the door jamb, and these requirements need to be clearly understood.

The requirements reference the position of the inside edge of the door jamb, not the roughopening. The rough opening requirements will depend on the door frame construction and wallinterface and should be accounted for so that the final door jamb position is as indicated on thelayout.

Page 12: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Rev. 9/2012

Requirements:

1. The access door size is 914mm (3’-0”) wide x 2134mm (7’-0”) tall.2. Standard self closing and self locking metal door with a group 2 locking device

per agreed upon location and Otis layout. Self closing mechanism cannotprotrude into the machine space at any time. Door knob shall have a blank plateon the hoistway side of the door.

3. The door must be located on an interior wall of the building. It cannot be openedto the outside of a building.

4. The dimension locating this access door from the front hoistway wall only has a+/- 6mm (1/4”) tolerance. – SEE DETAIL ON NEXT PAGE

2100/2500lb passenger duty examples shown below

Left-hand Controller

Right-hand Controller

2’-

7”

3’-

0”

Doo

r

2’-

7”

3’-

0”

Doo

r

waldschg
Highlight
Page 13: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Rev. 9/2012

MRL Access Door Location Detail

Note: Left-hand controller arrangement shown above; right-hand arrangement opposite

36

”D

OO

R(9

13

mm

)X

(SE

ET

AB

LE

)

“X” DIMENSION TABLE

TYPE DUTY

DOOR DIMENSION“X” FROM INSIDE

FRONT HOISTWAYWALL

PASSENGER

2100 31 ± ¼”(787 ± 6mm)2500

3000 33 ± ¼”(838 ± 6mm)3500

HOSPITAL/SERVICE4500 16 ± ¼”

(406 ± 6mm)5000

waldschg
TextBox
The MRL access door location (dim 'X') is critical to ensure proper running clearances with the elevator and components mounted in that access door opening (i.e., controller and disconnect shroud)
waldschg
Oval
Page 14: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of HydroFit Machine Roomless Access Door Size and Position Customer:

OTIS ELEVATOR COMPANY

Project: Contact:

Phone: Fax:

NOTE: Installation will not be started until the owner or the owner's representative signs and returns this form to Otis Elevator

Company. This form must be completed, signed and returned by _____ to meet the scheduled completion date of _ _ ___ .

You are requested to verify (or correct) this information and confirm its accuracy by your signature in the space provided. Should a

change in the information provided subsequently occur, immediate notification of the change is necessary.

A. Machine Roomless Access Door Dimensions

Access door must be 36” (3’), 914 mm wide by 84” (7’), 2134 mm tall.

B. Machine Roomless Access Door Position

For 2100 and 2500 passenger duty elevators the inside edge of the access door jamb (show below) must be between 30-3/4

inches and 31-1/4 inches (781 and 793 mm) from the front hoistway wall.

For 3000 and 3500 passenger duty elevators the inside edge of the access door jamb (show below) must be between 32-3/4

inches and 33-1/4 inches (832 and 844 mm) from the front hoistway wall.

For service/hospital duty elevators (4500, 5000, and 5000AIA LB) the inside edge of the access door jamb (show below)

must be between 15-3/4 inches and 16-1/4 inches (400 and 412 mm) from the front hoistway wall.

The above access door dimensions and position are confirmed:

SIGNED BY: __________________________________ DATE: ________________

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 15: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

SHEET NO. KIT DESCRIPTION REMARKS

2

---

MRL PASSENGER DUTY WORKING SPACE SAFETY ZONE

3 MRL HOSPITAL DUTY WORKING SPACE SAFETY ZONE

4 MRL ACCESS DOOR SURFACE MOUNT

SUPPLIED BY OTHERS5 MRL ACCESS DOOR FLUSH MOUNT

6 MRL ACCESS DOOR RECESSED MOUNT

OTIS HYDROFITTM

MRL ACCESS DOOR REQUIREMENTS

DOOR REQUIREMENTS PROVIDE A ROUGH OPENING FOR AND INSTALL A 3' X 7' STANDARD FIRE RATED INTERIOR DOOR ON ONESIDE OF THE HOISTWAY, AS SHOWN ON THE OTIS LAYOUT. WHEN DETERMINING THE LOCATION OF THEMACHINE SPACE DOOR, THE DIMENSION ON THE OTIS LAYOUT IS FROM INSIDE DOOR EDGE OF THE JAMBAND NOT THE DOOR STOP EDGE. PLEASE BE ADVISED THAT THIS DOOR LOCATION IS VERY CRITICAL.FOLLOW DOOR MANUFACTURING INSTRUCTIONS FOR THE DIFFERENT TYPES OF HOISTWAY WALL MATERIALAND MAKE THE APPROPRIATE ADJUSTMENTS SO THAT THIS DOOR WILL BE PLACED IN THE PROPER LOCATION. THE DOOR FRAME MUST BE SECURLY MOUNTED TO THE WALL TO SUSTAIN A CANTILEVERED / HORIZONTALFORCE EXERTED BY ELECTRICAL DISCONNECT(S), ELECTRICAL CONDUIT AND WIRING UP TO AN APPROXIMATE325 lb. LOAD. THE DOOR IN SOME CONFIGURATION HAS A MINIMUM OPENING OF 180 . MRL ACCESS DOORS MUST MEET CODE COMPLIANT FIRE RESISTIVE CONSTRUCTION. THE DOOR SHOULD BE SELFCLOSING (LOCAL BUILDING CODE DEPENDANT) AND BE SELF LOCKING WITH A GROUP 2 LOCKING DEVICE. INADDITION, ENSURE THAT ALL AIR GAPS AROUND THE DOOR ARE SEALED (i.e. THRESHOLD, WEATHER STRIPPING,ETC.). SELF CLOSING MECHANISMS CANNOT PROTRUDE INTO MACHINE SPACE AT ANY TIME. THE MACHINESPACE DOOR KNOB SHALL HAVE A BLANK PLATE ON THE HOISTWAY SIDE OF THE DOOR.

CRITICAL NOTE: DOOR MUST NOT BE LOCATED ON AN OUTSIDE WALL.

NOTE: SEE AAA29517B_FMI FOR SHROUD INSTRUCTION

7' DOOR

OPENING

Page 16: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

1219

[4']

1092[3' - 6"]

1092[3' - 6"]

1219

[4']

CAR OFFSET = LH

DOOR HAND SHOWN IS RECOMMENDED, BUT IF DOORHAND RESTRICTS WORKING SPACE DUE TO WALLS OROTHER BUILDING STRUCTURES, THEN DOOR HANDMUST BE OPPOSITE

MINIMUM DOOR OPENING

DOOR HAND SHOWN IS RECOMMENDED, IF DOOR CANNOT OPEN 180 DEGREES OR DOOR RESTRICTS WORKINGSPACE DUE TO WALLS OR OTHER BUILDING STRUCTURES,THEN DOOR HAND MUST BE OPPOSITE

CAR OFFSET = RH

MINIMUM 180 DOOR OPENING

!! CRITICAL: WORKING SPACE REQUIREMENTS

HYDROFITTM MRL ACCESS DOOR HAND GUIDELINES

PASSENGER DUTY(2100, 2500, 3000, 3500)

WORKING SPACE DEFINITION: THIS SPACE & DOOR HAND IS DEFINED BYTHE MAINLINE DISCONNECT ON/OFF LEVER

Page 17: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

1219

[4']

1092[3' - 6"]

1092[3' - 6"]

1219

[4']

!! CRITICAL: WORKING SPACE REQUIREMENTS

HYDROFITTM MRL ACCESS DOOR HAND GUIDELINES

HOSPITAL DUTY(4500, 5000)

DOOR HAND SHOWN IS RECOMMENDED, IF DOOR CANNOT OPEN 180 DEGREES OR DOOR RESTRICTS WORKINGSPACE DUE TO WALLS OR OTHER BUILDING STRUCTURES,THEN DOOR HAND MUST BE OPPOSITE

CAR OFFSET = LH

MINIMUM 180 DOOR OPENING

WORKING SPACE DEFINITION: THIS SPACE & DOOR HAND IS DEFINED BYTHE MAINLINE DISCONNECT ON/OFF LEVER

CAR OFFSET = RH

DOOR HAND SHOWN IS RECOMMENDED, BUT IF DOORHAND RESTRICTS WORKING SPACE DUE TO WALLS OROTHER BUILDING STRUCTURES, THEN DOOR HANDMUST BE OPPOSITE

MINIMUM DOOR OPENING

Page 18: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

"X" DIMENSION TABLE

SERVICE TYPE DUTYDOOR DIMENSION "X"FROM INSIDE FRONT

HOISTWAY WALL

P

2100 787 6 mm[2' - 7" 1/4 in]2500

3000 838 6 mm[2' - 9" 1/4 in]3500

H4500 406 6 mm

[1' - 4" 1/4 in]5000

SURFACE MOUNT ACCESS DOOR JAMB

JAMB MUST BE TIGHTAGAINST HOISTWAY WALL

JAMB RECOMMENDED TO BE MOUNTED ON THE INSIDEHOISTWAY WALL FOR PROPER RUNNING CLEARANCESWITH THE ELEVATOR AND ITS COMPONENTS(i.e. CONTROLLER AND SHROUD).

FRONT HOISTWAY WALL

CLEAR HOISTWAY

914 DOOR

[3' - 0"]

X(SEE TABLE)

Page 19: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

"X" DIMENSION TABLE

SERVICE TYPE DUTYDOOR DIMENSION "X"FROM INSIDE FRONT

HOISTWAY WALL

P

2100 787 6 mm[2' - 7" 1/4 in]2500

3000 838 6 mm[2' - 9" 1/4 in]3500

H4500 406 6 mm

[1' - 4" 1/4 in]5000

FLUSH MOUNT ACCESS DOOR JAMB

JAMB FLUSH TOHOISTWAY WALL

ACCEPTABLE INSTALLATION ARRANGEMENT TO DOOR JAMB.ADDITIONAL MATERIAL MAY BE NEEDED TO PROPERLYSECURE THE SHROUD IN ITS POSITION. JAMB SHOUD BE MOUNTED SO THAT THE JAMB AND THEELEVATOR COMPONENTS (i.e. CONTROLLER AND SHROUD)ACHIEVE THE PROPER RUNNING CLEARANCES.

FRONT HOISTWAY WALL

CLEAR HOISTWAY

914 DOOR

[3' - 0"]

X(SEE TABLE)

Page 20: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

"X" DIMENSION TABLE

SERVICE TYPE DUTYDOOR DIMENSION "X"FROM INSIDE FRONT

HOISTWAY WALL

P

2100 787 6 mm[2' - 7" 1/4 in]2500

3000 838 6 mm[2' - 9" 1/4 in]3500

H4500 406 6 mm

[1' - 4" 1/4 in]5000

RECESSED MOUNT ACCESS DOOR

IF THIS CONFIGUATION IS PROVIDED, ADDITIONAL MATERIAL(BY OTHERS; ANGLE IRON, UNISTRUT, FALSE DOORJAMB) MUST BE OBTAINED TO PROPERLY SECURE SHROUDAND CONTROLLER TO HOISTWAY WALL (SEE AAA29517B_FMI). THE ADDITIONAL MATERIAL SELECTED MUST BE INSTALLEDIN A MANNER SO THAT THE ELEVATOR COMPONENTS(i.e. CONTROLLER AND SHROUD) ACHIEVE THE PROPERRUNNING CLEARANCES.

FRONT HOISTWAY WALL

CLEAR HOISTWAY

914 DOOR

[3' - 0"]

X(SEE TABLE)

Page 21: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

HydroFit MRL Access Door Shroud

Purpose & Design: The HydroFit machine room less (MRL) arrangement requires the use of a shroud that serves three purposes:

1. It provides a mounting location for the mainline and cab lighting disconnects 2. It defines the space that is allowed for the disconnects to avoid any potential

interference with the elevator components. 3. It acts as a barrier to prevent access to the hoistway in the upper portion of the

MRL access door.

The shroud design is not “handed”; it will work with either left or right MRL machine space locations. The shroud is simply flipped accordingly to orient the deeper section toward the rear of the hoistway for passenger duties or to orient the deeper section to the front of the hoistway for hospital (service) duties. The cover plate on the bottom of the shroud is then removed. Installation: The shroud ships with hardware and brackets for mounting it in the machine space door jamb, adjustable unistrut sections for mounting the mainline disconnects to the shroud, and both top and bottom covers (note: once installed the cover on the bottom is removed).

Shroud shown with

disconnects installed

Page 22: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Note: The small brackets may need to be removed and reattached depending on the which side of the hoistway the MRL access door is and what “hand” of the shroud is needed…the deeper section of the shroud is oriented toward the rear of the hoistway for passenger duties (2100, 2500, 3000, 3500) or toward the front of the hoistway for hospital (service) duties (4500, 5000, 5000AIA). EXAMPLE: For a 2500lb duty passenger car, orient the deep portion of shroud to rear of hoistway; shallow portion toward the front of hoistway

Mounting brackets can be used to hang shroud from top of door jamb; the brackets also

set the correct depth of the shroud in the jamb

Unistrut provides adjustment for mounting

a range of disconnect cabinet sizes

Brackets to set (locate) shroud from

top of door jamb

Front of Hoistway

Attach mounting brackets to top of shroud w/ screws

provided

If top of jamb is >2” the supplied brackets may

not work as intended

Small cover plates used to fill slots

when smaller disconnects are

mounted

Unistrut can be removed if

necessary for deeper disconnects

Page 23: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

The shroud fits inside jamb and is butted up against the top inside of the jamb; ensure

that it is plumb and parallel to the jamb; attach to jamb with screws provided.

Hoistway side

Inside top of door jamb

Make sure the shroud butts up against the top of the door jamb

Depending on door stop width, the shroud may not butt up against the door stop – use mounting brackets to set correct depth in jamb

Door stop

Shroud ships with top and bottom cover so that it is not handed – only the top cover is needed once it is installed, the bottom can be removed

Cutouts will need to be made in the top cover to accommodate disconnect feeder conduit

Top cover not shown

Disconnects should not extend below the lower notch in

the shroud

Note: there may be a gap between the shroud and the door stop

Page 24: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Note: There should be a small notch (approximately 7/8” gap) between the door jamb

and top-most and bottom-most edges of the shroud. This gap at the bottom allows

clearance for the top mounting bracket for the controller.

Dimensions for allowable space for main line (3-phase) disconnect

7/8”

7/8”

21”

29”

Deep section - up to 11” deep w/o

unistrut - handle in furthest extended

position (On or Off)

13-3/4”

Shallow section 7-1/8” deep

Page 25: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Example of installed shroud and disconnects (2500 lb passenger duty, car offset = left):

Electrical feeders into top cover of shroud Disconnects mounted on shroud

Wiring from disconnects to top of controller

If disconnect is mounted directly to shroud panel (i.e., unistrut is not used) make sure only the bolt

heads are on the hoistway side of the shroud

Page 26: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Examples of shroud installations on 2500lb passenger duty units:

Front of hoistway (car offset = left)

Front of hoistway (car offset = right)

Page 27: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

SHEET NO. KIT DESCRIPTION REMARKS

2PASSENGER DUTY SHROUD ORIENTATION

3

4HOSPITAL DUTY SHROUD ORIENTATION

5

6 MRL ACCESS DOOR SHROUD ASSEMBLY

7

ABA384AVP400

MRL ACCESS DOOR SHROUD SURFACE MOUNT

INSTALLED BY OTHERS8 MRL ACCESS DOOR SHROUD FLUSH MOUNT

9 MRL ACCESS DOOR SHROUD RECESSED MOUNT

10 MRL ACCESS DOOR SHROUD COMPONENT PLACEMENT

OTIS HYDROFITTM

MRL SHROUD

NOTE: FOR FUTHER DETAIL ASK YOUR LOCAL OTIS REPRESENTATIVE FOR THE MANUFACTURING DRAWING OF THE SHROUD (ABA384AVP)

Page 28: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

112

[4.409]

169.5

[6.673]

ABA384AVP1ITEM DESCRIPTION PICTURE QTY

A MOUNTING PANEL (ABA384AVP2) 1

B GUARD (ABA384AVP4) 4

C HANGER (ABA384AVP3) 2

D UNI-STRUT (AAA347BLG25) 2

E COVER TOP (ABA384AVP6) 1

F COVER BOTTOM (ABA384AVP6) 1

G M12 X 25 HEX HEAD SCREW 4

HM12 HEX NUT WITH SERRATED

FLANGE4

J M12 PLAIN WASHER 4

KM6 X 12 HEX HEAD THREAD

ROLLING SCREW10

LM4 X 8 HEX HEAD THREAD

ROLLING SCREW6

TOOLING LEGENDBOLT/NUT SIZE WRENCH/SOCKET REQUIRED

M4

M6

M12

NOTE: 1. THE SHROUD SHOULD BE ASSEMBLED FROM THE SUPPLIER. IN THE EVENT IT NEEDS TO BE ASSEMBLED AS SHOWN. DEPENDING ON CONFUGRATION BOTTOM TO BE REMOVED OR NOT ASSEMBLED. 2. HANGING HOOKS MAY NEED TO BE PUT OPPISITE SIDE OR NOT USED AT ALL DEPENDING ON ACCESS DORR FRAME LOCATION IN ROUGH OPENING.

MRL ACCESS DOOR SHROUD ASSEMBLY

B. SLOT GUARDS ARE USED TO COVER SLOTS FOR SAFETY WHEN SMALL DISCONNECTS ARE MOUNTED. C. HANGER TO BE USED TO MOUNT SHROUD TO DOOR JAMB. IF DOOR JAMB IS RECESSED AWAY FROM HOISTWAY, HANGERS WILL HELP LINE UP SHROUD. IF DOOR FRAME IS MORE THAN 2 INCHES WIDE HANGER WILL NEED TO BE REMOVED. D. UNI-STRUT IS TO HELP IN MOUNTING SMALLER DISCONNECTS. IF DISCONNECT IS TO DEEP, REMOVE UNI-STRUT. E & F. DEPENDING ON THE ORIENTATION E OR F COULD BE A TOP OR BOTTOM. ALWAYS REMOVE BOTTOM.

TOP

BOTTOM(SEE NOTE 1)

(LEFT HAND CAR OFFSET SHOWN)

Page 29: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

PASSENGER DUTY (2100, 2500, 3000, 3500)CAR OFFSET LEFT HAND, DOOR RIGHT HAND OPENING

ORIENTATION GUIDE

CAR OFFSET

CAR OFFSET: LOOKINGINTO THE HOISTWAYFROM FRONT ENTRANCE

DOOR HAND: LOOKINGOUT OF THE HOISTWAYDIRECTION CAR DOORMOVES IN

DOORDIRECTION

Page 30: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

CAR OFFSET

CAR OFFSET: LOOKINGINTO THE HOISTWAYFROM FRONT ENTRANCE

DOOR HAND: LOOKINGOUT OF THE HOISTWAYDIRECTION CAR DOORMOVES IN

DOORDIRECTION

PASSENGER DUTY (2100, 2500, 3000, 3500)CAR OFFSET RIGHT HAND, DOOR LEFT HAND OPENING

ORIENTATION GUIDE

Page 31: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

HOSPITAL DUTY (4500, 5000)CAR OFFSET LEFT HAND, DOOR RIGHT HAND OPENING

ORIENTATION GUIDE

CAR OFFSET

CAR OFFSET: LOOKINGINTO THE HOISTWAYFROM FRONT ENTRANCE

DOOR HAND: LOOKINGOUT OF THE HOISTWAYDIRECTION CAR DOORMOVES IN

DOORDIRECTION

Page 32: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

CAR OFFSET

CAR OFFSET: LOOKINGINTO THE HOISTWAYFROM FRONT ENTRANCE

DOOR HAND: LOOKINGOUT OF THE HOISTWAYDIRECTION CAR DOORMOVES IN

DOORDIRECTION

HOSPITAL DUTY (4500, 5000)CAR OFFSET RIGHT HAND, DOOR LEFT HAND OPENING

ORIENTATION GUIDE

Page 33: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

A

A

B

B

224[8.819]SHROUDDEPTH MAX

1344.5

[52.933]

CLEARENCE FOR

CONTROLLER

AAA21242E402ITEM DESCRIPTION PICTURE QTY

AM6.3 X 32 HEX WASHER HEAD

SELF-DRILLING SCREW10

TOOLING LEGENDBOLT/NUT SIZE WRENCH/SOCKET REQUIRED

M6

MRL ACCESS DOOR SHROUD SURFACE MOUNT

A-A

C

C0.320

B-B

D

D0.240

HANGER REST ON DOORFRAME TO POSITIONSHROUD VIRTICALLY

Page 34: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

A

A

B

B

224[8.819]SHROUDDEPTH MAX

1344.5

[52.933]

CLEARENCE FOR

CONTROLLER

AAA21242E402ITEM DESCRIPTION PICTURE QTY

AM6.3 X 32 HEX WASHER HEAD

SELF-DRILLING SCREW10

TOOLING LEGENDBOLT/NUT SIZE WRENCH/SOCKET REQUIRED

M6

MRL ACCESS DOOR SHROUD FLUSH MOUNT

A-A

C

C0.320

FLUSH MOUNT APPLICATIONREQUIRES A BLOCKING PIECETO FILL THE GAP BETWEENDOOR FRAME & HANGER BRACKETTHE ENTIRE LENGTH OF DOORJAMB TO MOUNT THE SHROUD& CONTROLLER

B-B

D

D0.240

FLUSH MOUNT APPLICATIONHANGER MAY NOT BE ABLETO BE USED

Page 35: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

A

A

B

B

224[8.819]SHROUDDEPTH MAX

1344.5

[52.933]

CLEARENCE FOR

CONTROLLER

AAA21242E402ITEM DESCRIPTION PICTURE QTY

AM6.3 X 32 HEX WASHER HEAD

SELF-DRILLING SCREW10

TOOLING LEGENDBOLT/NUT SIZE WRENCH/SOCKET REQUIRED

M6

MRL ACCESS DOOR SHROUD RECESSED MOUNT

A-A

C

C0.320

RECESSED MOUNT APPLICATIONREQUIRES ADDITIONAL MATERIAL(BY OTHERS; A BLOCKING PIECE)TO FILL THE GAP BETWEENDOOR FRAME & HANGER BRACKETTHE ENTIRE LENGTH OF DOORJAMB TO MOUNT THE SHROUD& CONTROLLER

B-B

D

D0.240

RECESSED MOUNT APPLICATIONHANGER MAY NOT BE ABLETO BE USED

Page 36: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

A

2 3 5 6

B

C

D

E

1

1 2 3 4

A1

5 6 7

D

E

B

C

A

4 7

ALL DIMENSIONS METRICDRAFTED IN ACCORDANCE

WITH OTIS DOCUMENT 52847

FORM PA1102 Rev.1998-03-01

DWG

DRAWN

CHK

APPD

AUTH SHEET

SHEETS

ORIGINAL DATE

CHANGESTHIS WORK AND THE INFORMATION IT CONTAINS ARE THEPROPERTY OF OTIS ELEVATOR COMPANY ("OTIS"). IT ISDELIVERED TO OTHERS ON THE EXPRESS CONDITION THATIT WILL BE USED ONLY FOR, OR ON BEHALF OF, OTIS;THAT NEITHER IT NOR THE INFORMATION IT CONTAINSWILL BE REPRODUCED OR DISCLOSED, IN WHOLE OR INPART, WITHOUT THE PRIOR WRITTEN CONSENT OF OTIS;AND THAT ON DEMAND IT AND ANY COPIES WILL BEPROMPTLY RETURNED TO OTIS. UNPUBLISHED WORK OTIS ELEVATOR COMPANYALL RIGHTS RESERVED.

WARNING

C

MRL ACCESS DOOR SHROUD COMPONENT PLACEMENT

GFCI RECEPTACLESUPPLIED BY OTHERS

SMOKE SENSORSUPPLIED BY OTHERS

LIGHT DISCONNECTSUPPLIED BY OTHERS

MAIN LINE DISCONNECTSUPPLIED BY OTHERS

CAR OFFSET LEFT HAND

CUTOUTS WILL NEED TO BEMADE IN THE TOP COVERFOR ELECTRICAL FEEDS

GFCI RECEPTACLESUPPLIED BY OTHERS

SMOKE SENSORSUPPLIED BY OTHERS

LIGHT DISCONNECTSUPPLIED BY OTHERS

MAIN LINE DISCONNECTSUPPLIED BY OTHERS

CUTOUTS WILL NEED TO BEMADE IN THE TOP COVERFOR ELECTRICAL FEEDS

33.5

[1.319]

BOTTOM LINE

NOTHING BELLOW

THIS POINT

33.5

[1.319]

BOTTOM LINE

NOTHING BELLOW

THIS POINT

Page 37: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

(Rev. 8/2012)

HydroFit Elevator Machine Rooms

Standard Machine Rooms

Standard Machine Room (Left)

Note: Standard Machine Room (Right) – opposite of above

Page 38: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

(Rev. 8/2012)

Standard Machine Room (Rear w/ Car Offset = Left)

Note: Standard Machine Room Rear (w/ Car Offset = Right) – opposite of above

Page 39: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

(Rev. 8/2012)

Non-Standard or Remote Machine Rooms

Notes:

1. Machine room sizes reflect the typical worst case conditions and Otis' largest tank size. 2. All machine room sizes and clearances are ANSI & NEC Compliant. Consult your local code for

greater clearances required in your area. 3. It is recommended that a minimum clearance of 4" be maintained between the tank and the machine

room wall.

11'-6" (3505mm) - 2 Car Group 17'-0" (5182mm) - 3 Car Group 22'-0" (6708mm) - 4 Car Group

8'-6" (2591mm)

Tank

Controller

Tank

Controller

1'-6" (458mm) CLEAR

3'-6" (1067mm) CLEAR

4'-0" (1220 mm)

CLEAR

1'-6" (458mm) CLEAR

MAIN LINES (NOT BY OTIS)

MAIN LINES & LIGHT SW.

(NOT BY OTIS)

NOTES: 1. Machine room sizes reflect the typical worst case conditions and Otis' largest tank size. 2. All Machine room sizes and clearances are ANSI & NEC Compliant. Consult your local code for greater clearances required in your area. 3. It is recommended that a minimum clearance of 4" be maintained between the tank and the machine room wall. 4. The preferred machine room location is adjacent to the hoistway at the lowest landing, however, remote machine rooms are acceptable.

3'-0" (915mm) CLEAR

OPENING

3'-6" (1067mm)

CLEAR

LOCATION SHOWN

IS FOR DIMENSION

REFERENCE ONLY.

5'-9" (1753)mm)

Tank

Controller

3'-6" (1067mm) CLEAR

1'-6" (458mm) CLEAR

MAIN LINE &LIGHT SW.

(NOT BY OTIS)

NOTES:

1. Machine room size reflects the typical worst case condition and Otis' largest tank size.

2. All Machine room sizes and clearances are ANSI & NEC Compliant. Consult your local code forgreaterclearances required in your area.

3. It is recommended that a minimum clearance of 4" be maintained between the tank and the machine room wall.

4. The preferred machine room location is adjacent to the hoistway at the lowest landing, however, remotemachinerooms are acceptable.

3'-0" (915mm)CLEAR

OPENING

3'-6"(1067mm)

CLEAR

7'-4"(2236)

Simplex Duplex

Page 40: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Key Item of Coordination

Rev.8/2012

Typical Elevator Pit Ladder

Consult the Otis Construction Superintendent if any unusual space conditions exist.

Clear distance from the centerline of the rungs, cleats or steps to the nearest permanent object in the back of the ladder will be 4.5” or 7”, determined by local code requirements. A pit wall pocket may be required to maintain this distance. Consult the “Pit Plan View” on the contract specific layout for the pocket detail.

The rungs, cleats, or steps shall be a minimum of 16”

wide.

The ladder must extend not less than 48” above the sill of the access door.

The rungs, cleats, or steps shall be spaced

12 in. on center.

Refer to the elevator drawings for pit depth and any pit wall pocket requirements. Layout the pit ladder components (rungs, handrail, etc.) accordingly.

Page 41: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Preparatory Work By Others

Page 42: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Page 1 of 5 Revision: 03/16/2012

PREPARATORY WORK BY OTHERS The following items must be performed or provided at no cost to Otis Elevator Company (“Otis”) by the Owner or General Contractor or their agents in accordance with governing codes. The price and installation schedule of Otis is based on these jobsite conditions existing at the beginning and during installation of the elevator equipment. Failure to provide the items specified in this list will result in additional work performed by Otis beyond the scope of our contract causing installation delays. A change order will be submitted by Otis for materials and / or labor expended. All work to be performed per the latest revision of the applicable national code and / or local code.

General Prep / Work

1. Provide any cutouts to accommodate elevator equipment (troughing, venting, and hall fixtures) along with patching and painting of walls, floors, or partitions together with finish painting of entrance doors and frames, if required.

2. Provide tractor trailer access to the building for unloading of material and an onsite storage area for elevator equipment as follows: dry and enclosed, provides roll-able access to the elevator hoistway at the ground level, located within 100 feet (30.5 meters) of the hoistway, and is larger than 25 x 20 feet (7620 mm X 6096 mm) per elevator. Any warranties provided by Otis for elevator equipment are null and void if equipment is stored in a manner other than a dry enclosed building structure.

3. Provide sufficient onsite refuse containers for the proper disposal of elevator packaging material. Should sufficient refuse containers not be provided, disposal of packaging material shall become the responsibility of the owner.

Hoistway and Pit Prep / Work

4. Prior to the start of installation, provide a dry, properly framed, enclosed and vented hoistway in accordance with all applicable codes.

5. Provide a clear plumb hoistway with variations from the size shown on the Otis layout not to exceed -0 inch / +1 inch (25 mm).

6. Install per Machine Room / Machine Space Prep / Work and Electrical Requirements.

Provide a rough opening for and install a 3’ X 7’ standard fire rated interior door on one side of the hoistway, as shown on the Otis layout. When determining the location of the machine space door,the dimension on the Otis layout is from the inside door edge of the jamb and not the door stop edge. Please be advised that this door location is very critical. Follow door manufacturing instructions for the different types of hoistway wall material and make the appropriate adjustments so that this door will be placed in the proper location.

The door frame must be securely mounted to the wall to sustain a cantilevered / horizontal force exerted by the electrical disconnect(s), electrical conduit, and wiring up to an approximate 150 lb. load. Install per Machine Room / Machine Space Prep / Work and Electrical Requirements. The door should be able to open fully (180°).

7. Furnish adequate rail bracket supports and bracket spacing as required by governing code from pit floor to top of hoistway. For steel or wood frame construction, adequate backing for a rail bracket to be installed not less than 10’-3” (3124 mm) or more than 11’-3” (3429 mm) from the top landing. Furnish separator beams where required. Rail bracket attachment supports must be exposed and flush with the clear hoistway line.

If the floor to floor height exceeds the maximum bracket spacing allowed by the elevator code, Otis requires some form of steel support to properly attach our guide rail brackets. The maximum allowed bracket spacing is indicated in the rail force and bracket detail table on the Otis layout. Any rail bracket mounting surfaces that are not in line with the finished hoistway dimension (i.e. the clear hoistway line) may need to be extended to meet the required distance. Otis agrees to provide guidance on this matter at the appropriate time.

If rail bracket embedded plates or inserts are provided by Otis, they shall be installed by others in accordance with Otis’ documentation and instruction.

If vertical tube steel is utilized as rail support, (2) vertical tubes spaced at 20.4” (518 mm) on center are required for car rail brackets with “A” dimension ≥ 5.76” (146 mm). For Machine Space applications, horizontal rail bracket supports must be provided. Note: Vertical supports will interfere with the machine space access door.

Page 43: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Page 2 of 5 Revision: 03/16/2012

8. Furnish a dry pit reinforced to sustain vertical forces on car rails and impact loads on cylinder head(s) and buffer(s). The pit must be dry and clean. The elevator pit must have a floor drain or sump pump to prevent the accumulation of water. Location to be coordinated with Otis to avoid all elevator components and access areas. In areas requiring Firefighter’s Emergency Operation, a sump pump / drain shall be provided that shall have the capacity to remove a minimum of 11.4 m³ / h (3,000 gal / h) per elevator (2.2.2.5, ASME A17.1-2007 / CSA B44-07). Otis recommends that the owner verify the system complies with all applicable laws and local codes.

9. Provide and install a fixed vertical iron ladder in each pit as required by governing code and located per Otis layouts, or as coordinated with Otis personnel. Ladder width and projection from wall per local code. If pit depth is greater than 9’-10” (3000 mm) [13’-9” (4191 mm) with no floor below bottom landing], a pit access door is required.

10. A.) Protection from Falls:

As required by the Occupational Safety and Health Administration (OSHA) 1926.502 (B) (1-3), a freestanding removable barricade at each hoistway opening at each floor. Barricades shall be 42” (1067 mm) high, with mid-rail and kick board, and withstand 200 lbs. (90.7 kg) of vertical and horizontal pressure.

B.) Protection from Falling Objects:

As required by the Occupational Safety and Health Administration (OSHA) 1926.502(j), hoistway protection from falling debris and other trades materials by either:

1.) Full entrance screening / mesh in front of all elevator entrances. 2.) Secured / controlled access to all elevator lobbies (lock and key) with posted Notice “Only

Elevator Personnel Beyond This Protection.” Notes:

- Items A.) and B.) can be integrated systems. - Hoistway barricades and screening shall be constructed, maintained, and removed by others.

11. The front entrance wall at the main landing, is not to be constructed until after all elevator equipment is installed in the hoistway (the entire front wall – CLEAR HOISTWAY WIDTH – must be open for installation). Remaining front entrance walls are not to be constructed until after door frames and sills are in place.

The rough openings, per sizes shown on the Otis layout, are required. Prior to the completion and turnover of the elevator(s), all entrance walls must be installed and rough openings filled in complete to maintain fire rated hoistway requirements.

12. Provide adequate support at all fastening points of each entrance. Provide plumb vertical surfaces for entrances and sill supports, one above the other, and square with the hoistway. For 4’-0” (1219 mm) and 4’-6” (1372 mm) two speed door arrangements, an additional hoistway attachment point is required for an auxiliary support bracket under the sill assembly in the center of the clear door opening. Finish floor and grout, if required, between door frames to sill line. A horizontal support is to be provided 1 foot (305 mm) above the clear opening at the top landing to support the door frame assembly. If floor heights exceed 12’-0” (3658 mm), a horizontal support is to be provided 1 foot (305 mm) above the clear opening. If transoms are required, the support would be 1 foot (305 mm) above the transom height.

13. Provide and install a steel safety beam per elevator, from side wall to side wall at the top of the hoistway, capable of withstanding a maximum net live load of 5000 lb. (2268 kg). Otis requires 2” (51 mm) clear above the beam. Beam must be removed before car is placed in operation if it infringes on required clearance.

14. Glass used in hoistway construction must block 98% or more of incident full spectrum ultraviolet radiation for the full height of the hoistway.

15. If an emergency door in a blind hoistway is required, provide an outward swinging single section type door with door closer and a self closing barrier per ASME A17.1-2007, section 2.11.1.2. Contact your local Otis personnel for a detailed drawing (AAA26900D_FMI), showing Otis specific requirements.

Page 44: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Page 3 of 5 Revision: 03/16/2012

Machine Room / Machine Space Prep / Work

16. When a machine room is used, provide a suitable dry machine room with access and ventilation in accordance with all applicable codes and regulations. The machine room is to be maintained at a temperature between 60°F (15.5°C) and 100°F (38°C). When a machine space is used, the machine space will be in the hoistway behind the metal door installed per Hoistway and Pit Prep / Work above with ventilation in accordance with all applicable codes and regulations. The machine space is to be maintained at a temperature between 32°F (0°C) and 104°F (40°C). Relative humidity not to exceed 95% non-condensing. Local codes may require tighter temperature ranges. The temperature and humidity range shall be permanently posted in the machine room / machine space. Please check with your local code authority for the exact requirements in your area.

17. Machine room and Machine space doors to meet code compliant fire resistive construction. When a machine room is used, provide a self closing and self locking door with a group 2 locking device. When a machine space is used, provide a standard 3’ x 7’ self closing and self locking metal door with a group 2 locking device in the hoistway per Otis layout. In addition, ensure that all air gaps around the machine room / machine space door are sealed (i.e. threshold, weather stripping, etc.). Self closing mechanism cannot protrude into the machine space at any time. The machine space door knob shall have a blank plate on the hoistway side of the door.

18. When a machine space is used, Otis will provide a metal shroud and metal shroud cover to be mounted on the hoistway side of the machine space door frame per Otis layout. The metal shroud will accommodate the mounting of the main electrical feeder system, fused disconnect switch or circuit breaker for car lighting, and the convenience outlet. Conduit knockouts through the metal shroud cover will be required as needed to access the disconnect switches or circuit breakers, and convenience outlet. See Electrical Requirements.

[Note: Consult with the Otis Representative at your location concerning the metal shroud mentioned above for machine space applications.]

19. [Refers to elevators with remote machine rooms requiring buried piping and wire way] Provide trenching and backfilling as necessary to accommodate remote machine room conditions.

Fire Prevention Prep / Work

20. Provide hoistway walls designed and constructed in accordance with the required fire rating (including those places where elevator fixture boxes and rail bracket fastenings penetrate into the hoistway walls).

21. In the United States, provide smoke detectors, located as required, with wiring from the sensing devices to the controller(s) designated by Otis.

a. For each group of elevators, provide a normally closed contact representing the smoke detector at the designated return landing.

b. For each group of elevators, provide a normally closed contact representing all smoke detectors located in lobbies, hoistways, or machine rooms / machine space, but not the smoke detector at the designated return landing (see above) or the smoke detectors as described in i. and ii. below:

i. If a smoke detector is located in the hoistway at or below the lower of the two recall landings, it shall be wired to activate the same normally closed contact as the smoke detector located in the lobby at the lower of the two recall landings.

ii. If machine rooms / machine space is located at the designated return landing, the smoke detectors located therein shall be wired to activate the same normally closed contact as the smoke detector at the designated landing.

c. Requirements for intermittently illuminating the fire hat visual signal in the car operating panel, either i. or ii. apply.

i. For a single unit or for a group of elevators having one common machine room / machine space and one common hoistway, provide one additional normally closed contact representing the machine room / machine space and hoistway smoke detectors.

ii. If the group contains more than one hoistway and hoistway smoke detectors are installed, or if the group has more than one machine room / machine space, provide one normally closed contact for each elevator. The contact is to represent the smoke detector in the machine room / machine space for that particular elevator, and any smoke detectors in the hoistway containing that particular elevator.

Page 45: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Page 4 of 5 Revision: 03/16/2012

22. In Canada, provide smoke detectors, located as required, with wiring from the sensing devices to the controller(s) designated return landing.

a. For each group of elevators, provide a normally closed contact representing the smoke detector at the designated return landing and, if provided, from the sensing device in the pit.

b. For each group of elevators, provide a normally closed contact representing all smoke detectors located in elevator lobbies, but not the smoke detector at the designated return landing (see above) and, if provided, from the sensing device in the top of the hoistway.

c. For each group of elevators, provide a normally closed contact representing the smoke detector in the elevator machine room / machine space(s).

d. If the machine room / machine space is located at the designated return landing, the smoke detectors located therein shall be wired to activate the same normally closed contact as the smoke detector at the designated landings. When a machine room is used, for each group of elevators, provide in addition to the above, a normally closed contact representing the sensing devices in the machine room and, if provided, in the pit or at the top of the hoistway (for the Fire Hat in the Elevator).

23. In the United States, if sprinklers are installed in the hoistway or machine room / machine space(s), a means to automatically disconnect the mainline power supply to the affected elevator and any other power supplies used to move the elevator, upon or prior to the application of water is required (unless prohibited by local code). Smoke detectors shall not be used to activate sprinklers in hoistways or machine rooms / machine spaces or to disconnect the mainline power supply.

24. Provide a Class “ABC” fire extinguisher, minimum 10 lbs., in the machine room or in a location convenient to the machine space.

Electrical Requirements

25. All 125 volt, 15 or 20 ampere single phase receptacles installed in pits, machinery spaces, and elevator car tops shall be of ground fault circuit interrupter (GCFI) type. All 125 volt, 15 or 20 ampere single phase receptacles installed in machine rooms / machine spaces shall have GFCI protection. A dedicated single phase receptacle supplying a permanently installed pit sump pump shall not require GFCI protection. (NEC 620-85 or CEC Rule 38-085).

26. Furnish a dedicated, balanced, 3 phase, 3 wire electrical feeder system with a separate solidly grounded equipment grounding conductor terminating in the machine room / machine space. Size of the feeders and grounding conductor to suit elevator power characteristics. Feeder conductors and grounding conductor must be copper. A fused disconnect switch or circuit breaker capable of being locked in the open position for each elevator per the National Electrical Code (ANSI/NFPA 70) or Canadian Electrical Code (C22.1) with feeder or branch wiring to the controller (NEC 620-51, 620-61(D), and 620-62 or CEC Rule 38-013(2)(a)) must be provided. Fuses are to be current limiting class RK1 or equivalent. Circuit breakers are to have current limiting characteristics equivalent to class RK1 fuses. Fuses or circuit breakers are to be time delay to cover the full load up accelerating current as listed in the Otis Confirmation of Power Supply form.

[Note: If the 3 phase power to the control system is simulated (not from the utility), by use of a phase converter system, the phase converter must have all three phases balanced. Digital phase converter is required.]

Furnish a separate 120 volt, 15 ampere single phase branch circuit and SPST fused disconnect switch or circuit breaker capable of being locked in the open position to supply the car lights, receptacles, auxiliary lighting power source, and ventilation on each car in compliance with the National Electrical Code must be provided.

When a machine room is used and where practical, disconnects shall be located adjacent to the door of the machine room enclosure. When a machine space is used, disconnects or circuit breakers shall be located behind the door of the machine space per Otis layout.

Branch circuit wiring to each controller (NEC 620-53 or CEC Rule 38-053) must be provided.

For machine room applications, a convenience outlet and a suitable light, of not less than 200 Lux (19FC) as measured at floor level must be provided in the machine room with a light switch located within 18” (456 mm) of lock jamb side of machine room door.

For machine space applications a convenience outlet located inside the machine space door and a suitable light located outside the machine space door on the lock jamb side, of not less than 200 Lux (19FC) as measured at

Page 46: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Page 5 of 5 Revision: 03/16/2012

floor level must be provided per Otis layout. The machine space light circuit shall be a dedicated circuit separate from other lighting circuits. (NEC 620-23 or CEC Rule 38-023)

A convenience outlet and light fixture of not less than 100 Lux (10FC) as measured at the pit floor level must be in the pit with a light switch located adjacent to the pit access door (NEC 620-24 or CEC Rule 38-024). The light bulb(s) shall be externally guarded to prevent contact and accidental breakage.

[Note: Consult with the Otis Construction Superintendent at your location concerning the following paragraph.]

To meet the date upon which the elevators are to be turned over, the permanent 3 phase feeder system and protective devices must be installed and power available prior to the start of elevator installation.

27. Provide 120 volt, 20 ampere power for light, tools, hoist, etc. to the hoistway during installation. Source must be within 75 feet (22.86 M) of the hoistway.

28. Provide one (1) dedicated outside telephone line per elevator car to the elevator machine room / machine space(s), and terminated at the controller designated by the Otis construction superintendent. Reference the A17.1 / CSA-B44 code and the Otis Confirmation of Power Supply for specific requirements.

29. [Optional for Elevators with an intra building Intercom] Provide a separate 120 volt, 15 ampere, single phase power supply with fused SPST disconnect switch or circuit breaker located as required for intercommunicating system power supply. Circuit to be arranged for feeding from the building emergency lighting supply if provided. Conduit and wiring for remotely located intercommunicating stations must be provided.

30. [Optional for Elevators with a Battery Powered Emergency Return Unit (ERU)] Provide the disconnecting means required by the National Electrical Code (NEC) or Canadian Electrical Code (CEC) with an auxiliary contact and wiring to the controller. The auxiliary contact is to be positively open when the main disconnecting means is open. The auxiliary contact shall cause the ERU power source to be disconnected from its load when the disconnecting means is in the open position. Size of main contacts to suit elevator power characteristics.

[Additional ERU Requirement] In the United States, heat sensors used to automatically disconnect the mainline power supply prior to the application of water from sprinklers shall be provided with a normally closed contact with wiring from the sensing device to a controller designated by Otis. The normally closed contact shall be closed when the heat sensor is not activated and shall be open when the heat sensor is activated.

31. [Optional for Installations with Emergency (Standby) Power] Provide the emergency (standby) power unit and means for starting it, and deliver to the elevator via disconnect switches in the machine room / machine space, sufficient power to operate one or more elevators at a time at full rated speed and rated load.

An automatic Power Transfer Switch is required for each power feeder to monitor both Normal and Emergency (Standby) Power conditions and to perform the transfer from one to the other. Switch to have two sets of normally closed dry contacts, one to be open when the switch is in the Emergency (Standby) Power position, the other to open upon initiation of power transfer and to close when transfer is complete. Switch to have an inhibit function which will delay transfer to Normal and / or Emergency (Standby) Power by an adjustable period of 0 - 300 seconds. Switch shall have a Phase Monitor feature, which prohibits the transfer of power between "live" sources unless the sources are in phase with each other. If a Shunt Trip device is provided, an additional Normally Closed contact is required from the Emergency (Standby) Power source.

Emergency (standby) power system shall be connected to the 125 volt power circuit as noted in A.3 of the Confirmation of Power Supply for the branch circuit supplying the car lights, car top receptacle, auxiliary car lighting power source and car ventilation.

You agree to indemnify and save Otis harmless against any and all liability and costs arising out of your failure to carry out any of the foregoing requirements.

Page 47: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Pre-Inspection Information

Page 48: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Contractor’s Pre-Inspection Checklist

Form 4330_HYD (rev 08/2012)

Job Name: ________________________ Contract # _________________ Date:

In order to help us meet your schedule; the following items NOT marked "Complete" must be completed prior to Otis scheduling the elevator inspection. Please initial the non-completed items when they have been completed, and fax the form to the Otis Construction Superintendent.

Before the above referenced elevator(s) can be complete and ready for inspection by the state or local inspector, all requirements of the ASME/ANSI A17.1 (CAN/CSA B44) elevator code and local building codes must be met. This includes completion of work that must be performed by other trades. NOTE: The list below is general and may not include all state and local codes.

Item Complete Int. Item

1 Pit shall be so designed as to prevent entry of ground water into the pit. Drains and sump pumps, where provided, shall comply with the applicable plumbing code, and they shall be provided with a positive means to prevent water, gases, and odors from entering the hoistway. Sumps and sump pumps in pits, where provided, shall be covered. The cover shall be secured and level with the pit floor.

2 Metal pit ladder is to extend from the pit floor upward, not less than 48” above the bottom landing floor level, per Otis shop drawings and/or Otis instructions.

3 Hall fixtures blocked in or mounted complete. All patching and fire sealing complete.

4 Door frames to be sealed to meet code. Patch any holes in the elevator hoistway and machine room.

5 Grout under and in front all sills. Elevator lobby flooring shall be flush with the elevator entrance sill at each landing

6 Lockable 120V disconnects per power confirmation.

7 Top of hoistway and machine room shall have a fire rating in accordance with local elevator codes.

8 Walls and ceiling shall be finished for mounting of hall fixtures and smoke detectors.

9 Lockable fused disconnect switch in machine room with feeder wires to elevator controller, all piped in accordance with N.E.C. or C.E.C. (Canadian Electrical Code), and grounded. Switch must be in sight of elevator machine and shall be the type that cannot be engaged with door open. Disconnect should be equipped with microswitch when ERU units are being furnished.

10 Smoke detectors maybe required in each elevator lobby, hoistway, and machine room. Check w/ local code authority. Furnish normally closed fire system contacts to the elevator controller as per power confirmation.

11 Pit light and ground fault receptacle (with cover and guard) mounted 12" off pit floor on rear wall and switch to be located adjacent to pit ladder piped in accordance with local code. (If front and rear opening, contact Otis representative).

12 Telephone in elevator cab connected to a 24-hour maintained location. (It should be wired and, upon entry into the machine room, piped to the elevator controller).

13 Elevator floor covering complete.

14 Elevator interior complete.

15 Only elevator equipment is allowed in an elevator machine room and hoistway (no access panels). No pipes or conduit are allowed in the hoistway or control room unless they are required for the elevator. If a sprinkler system is required contact local code authority.

16 Machine room/machine space doors - shall be self-closing and self-locking and rated per machine room construction.

17 Machine room to be vented, to maintain temperature between 60°F (15.5°C) and 100°F (38°C); or, for MRL machine space between 32°F (0°C) and 104°F (40°C). Ventilation can be natural or mechanical.

18 Machine space/machine rooms must have ground fault receptacle and permanent lighting, and must be equipped with a fire extinguisher. For machine space (MRL access door), receptacle and lighting switch may be outside access door but immediately adjacent to lock side door jamb; fire extinguisher must be located in close proximity to access door.

19 Hoistway walls shall be flush on hoistway sides. Any ledges over 4” shall be provided with a beveled angle of not less than 75º.

20 Spaces containing machines, control equipment, sheaves and other machinery shall be enclosed with fire-resistive enclosures. Enclosures and access doors thereto shall have a fire-resistance rating at least equal to that required for the hoistway enclosure.

21

Per out agreement, it is Otis’ responsibility to arrange for this inspection and to pay the required fee. We ask you to ensure that all “work by others” has been completed prior to our agreed-upon date for inspection.

If the elevator installation does not pass inspection due to uncompleted work by others, we would expect all additional costs associated with a re-inspection to be the responsibility of others. The total charge for the re-inspection will be a minimum of $ 500.00.

Otis Construction Superintendent Name: Fax:

_______________________________________________ _______________________________________________

Form Prepared By / Date General Contractor / Date

Page 49: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Work By Others Reference

Page 50: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

1

Work by Others Reference

General

Provide suitable on-site storage area for all elevator equipment, with rollable access to the elevator hoistway at ground level or uninterrupted use of a forklift or crane with supplied operator. A suitable storage area is defined as follows: Dry and enclosed under a dried in-building structure, is within 100 ft. of the hoistway, is larger than 25 x 20 feet per elevator.

We require suitable tractor-trailer access to the building for unloading of material. In addition, we need rollable access from unloading point to and from storage, and storage to hoistway area.

.

Hoistway

RAILS

Rail brackets

Platform

Structural cab panels

Tank and controller

(close to MRL door location or in Machine

Room)

TC and hoistway wiring kits

Raceway

Entrances

Cab finishes

Tools

CYLINDERS

Piping kit

Oil

Page 51: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

2

Hoistway and Pit

Hoistway Requirements

NOTE:

Sketch is not to scale and is exaggerated for demonstration purposes.

95”

5”

100”

100”

Effective hoistway dimension when the

hoistway is not plumb

The hoistway tolerance is +1”, -0” for the entire elevation of the hoistway.

The hoistway must be finished on the non-opening sides including drywall taping.

The hoistway must be plumb or alterations will be required beyond the scope of the Otis Contract. If the hoistway is not plumb it effectively decreases the hoistway dimension in the direction it is leaning.

The elevator rise (first finished floor to top finished floor) + pit depth must be match the dimensions on the Otis Contract Layout.

97.5”

2.5”

Page 52: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

3

Rail Bracket Attachment Points

Rail bracket support provided by a weldplate in a drywall hoistway.

Rail bracket support provided by inserts in CMU.

Page 53: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

4

Rail bracket support provided by attaching directly to concrete hoistway wall.

Rail bracket support provided by tube steel sections (see detail next page for larger brackets).

Page 54: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

5

Rail bracket support provided by building structural steel sections.

Page 55: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

6

Tube Steel requirements for rail bracket mounting

Passenger Arrangements

Hospital Arrangements

30” (762mm)

17” (432mm)

30” (762mm)

17”

(432

mm

)

4”

(10

2m

m)

Max

. W

idth

28

-7/8

” (7

33m

m)

2”

(51

mm

)

15” (381mm)

15”

(381

mm

) X

” (s

ee t

able

)

X” Dimension

Opening

Arrangement 4500lb

duty

5000lb

duty

5000AIA

duty

Front only 65-3/8”

(1661mm)

68”

(1727mm)

71-5/8”

(1819mm)

Front & rear 76”

(1930mm)

78-9/16”

(1996mm)

82-3/16”

(2088mm)

1/2” (12.7mm) Thick Plate

(Not by Otis)

1/2” (12.7mm) Thick Plate

(Not by Otis)

6”

(15

2m

m)

6”

(15

2m

m)

Page 56: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

7

Pit Requirements

Pit light and GFCI convenience outlet (with cover and guard) mounted 12" off pit floor on rear wall and switch to be located adjacent to pit ladder piped in accordance with local code. If front and rear opening contact Otis representative for location. Metal pit ladder is to extend from the pit floor upward, not less than 48” above the bottom landing floor level, per Otis shop drawings and/or Otis instructions.

Pit light and outlet The pit must be clean and dry

Typical pit

ladder

Pit light switch

Furnish a dry pit reinforced to sustain vertical forces on car rails and impact loads on cylinder head(s) and buffer(s). The pit must be dry and clean. The elevator pit may not have a floor drain/sump pump connected directly to a storm drain or sewer. Otis recommends that the owner verify the system complies with all applicable laws. See “Preparatory Work by Others”, for more information.

Page 57: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

8

Hoistway Overhead Beam Provide and install a safety beam capable of withstanding a maximum net live load of 5000 lb. (2268 kg). Otis requires 2” clear above the beam. Beam must be removed before car is placed in operation if it infringes on required clearance.

Page 58: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

9

Hoistway Barricades

Otis/OSHA compliant barricades in place. Freestanding and removable barricades at each hoistway opening at each floor. Barricades shall be 42” high, have mid-rail and kick board, and withstand 200lbs. of side pressure. Erected, maintained and removed by others.

Page 59: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

10

Hoistway Entrance Support The hoistway walls are to include adequate fastening for hoistway entrance assemblies. One front entrance wall, at the main landing, is not to be constructed until after all elevator material is located in the hoistway. Remaining front entrance walls are not to be constructed until after door frames and sills are in place. If front walls are poured concrete weight bearing walls, rough openings are to be provided to accept entrance frames and filled in after frames are set. Rough opening size per Otis layouts. Provide plumb vertical surfaces for entrance-sill supports, one above the other, and square with the hoistway. For 4’-0” (1220 mm) and 4’-6” (1372 mm) two-speed door arrangements on 4500 lb. (2041 kg) and 5000 lb. (2270 kg) cars a hoistway attachment point is required for an auxiliary support bracket under the sill assembly in the center of the clear door opening. Finished floor and grout, if required, between doorframes to sill line. A horizontal support is to be provided 12” (305 mm) above the clear opening at each landing to support the doorframe assembly.

Masonry rough opening with block poured solid as an entrance header support

Drywall hoistway with steel tube as an entrance header support

Page 60: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

11

Hoistway Ledges (Bevels) and Patching Hoistway walls shall be flush on hoistway sides. Any ledges over 4” shall be provided with a beveled angle of not less than 75º.

Spaces containing machines, control equipment, sheaves and other machinery shall be enclosed with fire-resistive enclosures. Enclosures and access doors thereto shall have a fire-resistance rating at least equal to that required for the hoistway enclosure.

Furnish hoistway walls designed and constructed in accordance with the required fire rating (including those places where elevator fixture boxes and rail-bracket fastenings penetrate the hoistway walls).

Page 61: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

12

Door frames to be sealed to meet code. Patch any holes in the elevator hoistway and machine room. Grout under and in front all sills. Top of hoistway and machine room shall have a fire rating in accordance with local elevator codes.

Hoistway Venting Provide hoistway ventilation in accordance with all applicable codes and regulations.

Overhead hoistway vent Side wall hoistway vents

Page 62: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

13

Machine Space & MRL Access Door

Provide a rough opening for and install a 3’ X 7’ standard fire rated interior door (referred to as machine space door) on one side of the hoistway, as shown on the Otis layout. When determining the location of the machine space door,the dimension on the Otis layout is from the inside door edge of the jamb and not the door stop edge. Please be advised that this door location is very critical. Follow door manufacturing instructions for the different types of hoistway wall material and make the appropriate adjustments so that this door will be placed in the proper location. The 3’ x 7’ machine space door must be a self closing and self locking metal door with a group 2 locking device in the hoistway per Otis layout. In addition, ensure that all air gaps around the machine space door are sealed (i.e. threshold, weather stripping, etc.). Self closing mechanism cannot protrude into the machine space at any time. The machine space door knob shall have a blank plate on the hoistway side of the door. The door frame must be securely mounted to the wall to sustain a cantilevered / horizontal force exerted by the electrical disconnect(s), electrical conduit, and wiring up to an approximate 150 lb. load. Install per Machine Room / Machine Space Prep / Work and Electrical Requirements. The door should be able to open fully (180°). The machine space will be in the hoistway behind the metal door installed per Hoistway and Pit Prep / Work above with ventilation in accordance with all applicable codes and regulations. The machine space is to be maintained at a temperature between 32°F (0°C) and 104°F (40°C). Relative humidity not to exceed 95% non-condensing. Local codes may require tighter temperature ranges. The temperature and humidity range shall be permanently posted in the machine room / machine space. Please check with your local code authority for the exact requirements in your area.

elevator

controller

cabinet

door

valve sound

isolation box and

cover panels

Spring hinges on door

Blank plate on hoistway side

of door

Page 63: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

14

For machine space applications a GFCI convenience outlet located inside the machine space door and a suitable light located outside the machine space door on the lock jamb side, of not less than 200 Lux (19FC) as measured at floor level must be provided per Otis layout. The machine space light circuit shall be a dedicated circuit separate from other lighting circuits. (NEC 620-23 or CEC Rule 38-023) Provide a Class “ABC” fire extinguisher, minimum 10 lbs., in a location convenient to the machine space.

GFCI convenience outlet either inside the machine space (mounted to shroud) or immediately adjacent to machine space door (lock side)

Light switch on lock side of machine space door, light located above door

Page 64: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

15

Machine Room Provide a suitable dry machine room with access and ventilation in accordance with all applicable codes and regulations. The machine room is to be maintained at a temperature between 60°F and 100°F, with relative humidity is not to exceed 95% non-condensing. Local codes may require tighter temperature ranges. Please check with your local code authority for the exact requirements in your area. Provide Class “ABC” fire extinguisher in the machine room.

Only elevator equipment is allowed in an elevator machine room and hoistway (no access panels). If a sprinkler system is required contact local code authority.

Machine room doors - shall be self-closing and self-locking and rated per machine room construction.

Furnish a 3-phase, electrical feeder system with a separate equipment grounding conductor terminating in the machine room. Size of the feeders and grounding conductor to suit elevator power characteristics. A fused disconnect switch or circuit breaker capable of being locked in the open position, for each elevator per the National Electrical Code (ANSI/NFPA 70) with feeder or branch wiring to controller (NEC 620-51) must be provided. Where practical, disconnects shall be located adjacent to the door of the machine room enclosure. Switch must be in sight of elevator machine and shall be the type that cannot be engaged with door open.

Page 65: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

16

Disconnect should be equipped with a microswitch when ERU units are being furnished. (NEC 620.91-C) Examples of ERU auxiliary contacts - Square D - #EK300-2, I.T.E. - SC-3, West. Elec. - EK-1 A separate 120-volt AC, 15-ampere single-phase branch circuit and SPST fused disconnect switch or circuit breaker, arranged to be locked in the open position, to supply the car lights, receptacles, auxiliary lighting power source and ventilation on each car in compliance with the National Electrical Code must be provided. Suitable light and GFCI convenience outlets must be provided in machine room with light switches located within 18” (456 mm) of lock jamb side of machine room door. Electric power for light, tools, hoist, etc.; must be provided during installation as well as electric current for starting, testing and adjusting the elevator.

Telephone in elevator cab connected to a 24-hour maintained location. (It should be wired and, upon entry into the machine room, piped to the elevator controller).

Page 66: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Electrical Requirements

Page 67: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply-Hydraulic Approval

Customer:

OTIS ELEVATOR COMPANY

Project: Contact:

Phone:

NOTE: Manufacture will not be started until the owner or the owner's representative signs and returns this form to Otis Elevator

Company. This form must be completed, signed and returned by _____ to meet the scheduled completion date of _ _ ___ .

A. POWER CONFIRMATION

Our records indicate the supply to be as indicated below. You are requested to verify (or correct) this information and confirm its

accuracy by your signature in the space provided. Should a change in the information provided subsequently occur, immediate

notification of the change is necessary.

1. Dedicated ______ volts, balanced utility three phase, three wire, 60 hertz and a separate solidly grounded equipment

grounding conductor.

Note: If three phase power is simulated by use of a phase converter, a digital phase converter must be used.

Please consult Otis Representative in your location.

2. Voltage variations to be within 10% of normal. Frequency variations to be within 2 hertz. If voltage or frequency

variation exceeds these limits, please give details.

3. Car Lighting: 125 volt, single phase, 15 ampere, 60 Hertz dedicated branch circuit.

The above power supply characteristics are confirmed.

SIGNED BY: __________________________________ DATE: ________________

B. ELECTRICAL REQUIREMENTS (SEE ANSI/NFPA 70)

To assist you in the planning of the electrical requirements to be provided by other trades prior to the installation of our equipment,

we are pleased to supply the AC current data as detailed below. The following data are based upon the power supply as noted above.

Should your confirmed power supply be of a different characteristic than that shown, please request revised data from your local Otis

representative. Additional electrical requirements are listed on the next page.

The AC line current data below are based on the power supply information provided in Part A, item 1, above.

ELEVATOR

NAME OR

NUMBER

ELEVATOR

CONTRACT

NUMBER(S) DUTY

CAR

SPEED

REFER TO ANSI/NFPA 70, SECTION 620-13

(For Code Versions Prior to 1996 Refer to Section 620-14)

NAMEPLATE

HORSE

POWER

NEC

LETTER

RATED

MOTOR

CURRENT

PEAK STARTING OR

ACCELERATING

CURRENT

Elevator controller terminations for 3 phase wiring are rated for 75 C. Refer to NEC ANSI/NFPA70 Section 110-14.

Elevators supplied to this document are rated at 10,000 Amps RMS Symmetrical Short Circuit Current (SCCR.)

Elevator Feeder Short Circuit protection by others shall limit the Available Short Circuit Current (ASCC) in the machine room / space to 10,000

Amps maximum symmetrical RMS.

Comments: Master file : AAA29000AR_PWR_CONF.zip

SA Pwsuphyd.doc REV 03/16/2012

CN281791

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 68: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply - Hydraulic Approval

To assist you in providing proper electric service, the items required BY OTHERS have been checked below:

ALL HYDRAULIC ELEVATORS

X All 125 volt, 15 or 20 ampere single phase receptacles installed in pits, machinery spaces, hoistways, and elevator car tops shall

be of ground fault circuit interrupter type. All 125 volt, 15 or 20 ampere single phase receptacles installed in machine rooms /

spaces shall have ground fault circuit interrupter protection. A separate single phase receptacle supplying a permanently installed

pit sump pump shall not require GFCI protection. [620-85]

X A three (3) phase, electrical feeder system must be enclosed in EMT with a separate equipment grounding conductor

terminating in the machine room / space. Feeder conductors and grounding conductor must be copper. Size of the feeders and

grounding conductor to suit elevator power characteristics. A fused disconnect switch or circuit breaker (not acceptable in all areas),

capable of being locked in the “off” position, for each elevator per the National Electrical Code (ANSI/NFPA 70) with feeder or

branch wiring to controller [620-51] and [620-61(D)]. Fuses are to be current limiting class RK1 or equivalent, see section B for

elevator equipment SCCR. Circuit breakers are to have current limiting characteristics equivalent to class RK1 fuses, see section B

for elevator equipment SCCR. Fuses or circuit breakers are to be time delay to cover the full load up accelerating current as listed in

Section B above. [Note: If the 3 phase power to the control system is simulated (not from the utility), by use of a phase converter

system, the phase converter must have all three phases balanced. Digital phase converter is required.]

A separate 125 volt AC, 15 ampere single phase branch circuit and SPST fused disconnect switch or circuit breaker, capable of

being locked in the “off” position, to supply the car lights, receptacles, auxiliary lighting power source and ventilation on each car

in compliance with the National Electrical Code. [620-53]

The disconnecting means shall be located adjacent to the door of the machine room enclosure or behind the door of the machine

space on an Otis supplied metal shroud per Otis layout.

Provide branch circuit wiring to each controller.

For machine room applications, a convenience outlet and a suitable light, of not less than 200 Lux (19FC) as measured at floor level

must be provided in the machine room with a light switch located within 18” (456 mm) of lock jamb side of machine room door.

For machine space applications a convenience outlet located inside the machine space door and a suitable light located outside the

machine space door on the lock jamb side, of not less than 200 Lux (19FC) as measured at floor level must be provided per Otis

layout. The machine space light circuit shall be a dedicated circuit separate from other lighting circuits. (NEC 620-23 or CEC Rule

38-023)

A convenience outlet and light fixture in the pit with switch located adjacent to the pit access door. [620-24]

Provide 125 volt AC, 20 ampere electric power for light, tools, hoist, etc. during installation.

X Refer to National Electrical Code, Article 430-52 “Exceptions” to select applicable ratings for protective devices. This exception

should be fully utilized in order to provide the maximum capacities listed for the various type protective devices.

EMERGENCY RETURN UNIT

__ The disconnecting means required by the National Electrical Code shall be provided with an auxiliary contact with wiring to the

controller [see ANSI/NFPA70-1996, section 620-91(c)]. The auxiliary contact is to be positively open when the main

disconnecting means is open. The auxiliary contact shall cause the ERU power source to be disconnected from its load when the

disconnecting means is in the open position. Size of main contacts to suit elevator power characteristics. Heat sensors, when used

to automatically disconnect the main line power supply prior to the application of water from sprinklers, shall be provided with a

normally closed contact with wiring from the sensing device to a controller designated by Otis. The normally closed contact shall

be closed when the heat sensor is not activated and shall be open when the heat sensor is activated.

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 69: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply - Hydraulic Approval

EMERGENCY (STANDBY) POWER REQUIREMENTS

A power transfer switch to monitor both normal and standby power conditions and to perform the transfer from one to the other.

Switch to have an inhibit function which will delay the completion of the transfer to normal and/or standby power by an

adjustable period of 0 - 5 seconds. Switch to have a phase monitor feature that will prohibit the transfer of power between “live”

sources unless the sources are in phase with each other.

Note: The building Emergency (Standby Power) Generator system used to supply the elevator(s) shall be capable of supplying

non-linear loads.

When more than one elevator is subject to the same standby power system and the standby power system is not large enough to

run all elevators at once, the transfer switch must include one set of normally closed dry contacts that open when the switch is in

the standby power position.

A 125 volt, 15 ampere, single phase car light supply.

COMMUNICATION REQUIREMENTS

Separate 125 volt, 15 ampere single phase power supply with fused SPST disconnect switch or circuit breaker with duplex outlet

located as required for inter-communicating system power supply. Circuit to be arranged for feeding from the building standby or

emergency lighting supply if provided. Conduit and wiring for remotely located inter-communicating stations (in Engineer’s

office, etc.).

X One (1) dedicated outside “Analog” (i.e. capable of carrying voice and data) telephone line to the elevator machine room / space

must be furnished. The telephone line must meet the following requirements:

Loop Current: Min 20mA, Max 120mA Nominal AC Line Impedance = 600 ohms

Line Voltage: On Hook – Min 15Vdc, Max 56.5Vdc Ring Voltage: Min 40Vac(rms), Max 150Vac(rms)

Off Hook – Min 8.75Vdc Ring Frequency: 15-68Hz

SMOKE DETECTORS

Smoke detectors, located as required, with wiring from the sensing devices to the controller(s) designated by Otis.

X I. For each group of elevators, provide a normally closed contact representing the smoke detector at the designated return

landing.

X II. For each group of elevators, provide a normally closed contact representing all smoke detectors located in lobbies, hoistways,

or machine rooms/machine space, but not the smoke detector at the designated return landing (see above) or the smoke detectors

as described in a & b below:

a) If a smoke detector is located in the hoistway at or below the lower of the two recall landings, it shall be wired to activate the

same normally closed contact as the smoke detector located in the lobby at the lower of the two recall landings.

b) If the machine rooms/machine space is located at the designated return landing, the smoke detectors located therein shall be

wired to activate the same normally closed contact as the smoke detector at the designated landing.

III a. For a single unit, or group of elevators having one common hoistway, or one common machine room and one common

hoistway, provide one additional normally closed contact representing the hoistway smoke detectors.

III b. If the group contains more than one hoistway, and hoistway smoke detectors are installed, or if the group has more than

one machine room, provide one normally closed contact for each elevator. The contact is to represent the smoke detector in the

machine room for that particular elevator, and / or hoistway containing that particular elevator.

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 70: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply - Hydraulic Approval

HEATING, VENTILATION, AIR CONDITIONING

X Temperature in the machine room shall be maintained between 60°F (15°C) and 100°F (38°C). Temperature in the machine

space shall be maintained between (32°F (0°C) and 104°F (40°C). The relative humidity in the machine room / space should not

exceed 95% non-condensing. When a machine room is used, temperature to be measured 6’ (1829 mm) above the floor and 1’

(305 mm) out from car controller. Ventilation to suit Otis heat release requirements shown below. Local codes may require

tighter temperature ranges and higher ventilation levels. Please check with your local code authority for the exact requirements in

your area. Heat release includes allowance for average service of 40 elevator starts per hour in the up direction.

ELEVATOR NAME OR NUMBER

ELEVATOR CONTRACT NUMBER

DUTY HEAT RELEASE PER CAR (BTU/HR)

TOTAL BTUs

SA Pwsuphyd.doc REV 03/16/2012

CN281791

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 71: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply-Hydraulic Approval (Canada)

Customer:

OTIS CANADA INC.

Project: Prepared by:

Phone:

Fax:

NOTE: Manufacture will not be started until the owner or the owner's representative signs and returns this form to Otis Canada Inc.

This form must be completed, signed and returned by __ ___ to meet the scheduled completion date of _____ .

A. POWER CONFIRMATION

Our records indicate the supply to be as indicated below. You are requested to verify (or correct) this information and confirm its

accuracy by your signature in the space provided. Should a change in the information provided subsequently occur, immediate

notification of the change is necessary.

1. Dedicated _____ volts, balanced utility three phase, three wire, 60 hertz and a separate solidly grounded equipment

grounding conductor.

Note: If three phase power is simulated by use of a phase converter, a digital phase converter must be used.

Please consult Otis Representative in your location.

2. Voltage variations to be within 10% of normal. Frequency variations to be within 2 hertz. If voltage or frequency

variation exceeds these limits, please give details.

3. Car Lighting: 125 volt, single phase, 15 amperes, 60 hertz dedicated branch circuit.

The above power supply characteristics are confirmed.

SIGNED BY: __________________________________ DATE: ________________

B. ELECTRICAL REQUIREMENTS

To assist you in the planning of the electrical requirements to be provided by other trades prior to the installation of our equipment,

we are pleased to supply the AC current data as detailed below. The following data are based upon the power supply as noted above.

Should your confirmed power supply be of a different characteristic than that shown, please request revised data from your local Otis

representative. Additional electrical requirements are listed on the next page.

The AC line current data below are based on the power supply information provided in Part A, item 1, above.

ELEVATOR

NAME OR

NUMBER

ELEVATOR

CONTRACT

NUMBER(S) CAPACITY CAR

SPEED

REFER TO CSA Standard C22.1, Canadian Electrical Code – Part 1

NAMEPLATE

HORSE

POWER

NEC

LETTER

FULL-LOAD

RATED

MOTOR

CURRENT

PEAK STARTING OR

ACCELERATING

CURRENT

Elevator controller terminations for 3 phase wiring are rated for 75 C. Refer to C.E.C. – C22.1

Elevators supplied to this document are rated at 10,000 Amps RMS Symmetrical Short Circuit Current (SCCR.)

Elevator Feeder Short Circuit protection provided by others shall limit the Available Short Circuit Current (ASCC) in the machine room / space to

10,000 Amps maximum symmetrical RMS.

Comments: Master file: AAA29000AR_PWR_CONF.zip SA Pwhydcsa.doc REV 03/16/2012

CN281791

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 72: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply - Hydraulic Approval (Canada)

To assist you in providing proper electric service, items required BY OTHERS have been checked below:

ALL HYDRAULIC ELEVATORS

X All 125 volt, 15 or 20 ampere single-phase receptacles installed in pits, machinery spaces, hoistways, and elevator-car tops shall be of

ground fault circuit interrupter type. All 125 volt, 15 or 20 ampere single phase receptacles installed in machine rooms / spaces shall

have ground fault circuit interrupter protection. A separate single phase receptacle supplying a permanently installed pit sump pump

shall not require GFCI protection.

X A three (3) phase, electrical feeder system must be enclosed in EMT with a separate equipment grounding conductor

terminating in the machine room / space. Size of the feeders and grounding conductor to suit elevator power characteristics. Feeder

conductors and grounding conductor must be copper. A fused disconnect switch or circuit breaker, capable of being locked in the

“off” position, for each elevator per the Canadian Electrical Code (C22.1) with feeder or branch wiring to controller CEC [Rule 38-

013(2)(a)]. Fuses are to be current limiting class RK1 or equivalent, see section B for elevator equipment SCCR. Circuit breakers are

to have current limiting characteristics equivalent to class RK1 fuses, see section B for elevator equipment SCCR. Fuses or circuit

breakers are to be time delay to cover the full load up accelerating current as listed in Section B above. [Note: If the 3 phase power to

the control system is simulated (not from the utility), by use of a phase converter system, the phase converter must have all three

phases balanced. Digital phase converter is required.]

A separate 125 volt AC, 15 ampere single phase branch circuit and SPST fused disconnect switch or circuit breaker, capable of being

locked in the “off” position, to supply the car lights, receptacles, auxiliary lighting power source and ventilation on each car in

compliance with the Canadian Electrical Code [Rule 38-053].

The disconnecting means shall be located adjacent to the door of the machine room enclosure or behind the door of the machine space

on an Otis supplied metal shroud per Otis layout.

Provide branch circuit wiring to each controller CEC [Rule 38-013(2)(a)].

For machine room applications, a convenience outlet and a suitable light, of not less than 200 Lux (19FC) as measured at floor level

must be provided in the machine room with a light switch located within 18” (456 mm) of lock jamb side of machine room door.

For machine space applications a convenience outlet located inside the machine space door and a suitable light located outside the

machine space door on the lock jamb side, of not less than 200 Lux (19FC) as measured at floor level must be provided per Otis

layout. The machine space light circuit shall be a dedicated circuit separate from other lighting circuits. (NEC 620-23 or CEC Rule

38-023)

A convenience outlet and light fixture in pit with switch located adjacent to the pit access door CEC [Rule 38-054].

Provide 125 volt AC, 20 ampere electric power for light, tools, hoist, etc. during installation.

EMERGENCY RETURN UNIT

___ The disconnecting means required by the Canadian Electrical Code shall be provided with an auxiliary contact with wiring to the

controller. The auxiliary contact is to be positively open when the main disconnecting means is open. The auxiliary contact shall

cause the ERU power source to be disconnected from its load when the disconnecting means is in the open position. Size of main

contacts to suit elevator power characteristics.

EMERGENCY (STANDBY) POWER REQUIREMENTS

A power transfer switch to monitor both normal and standby power conditions and to perform the transfer from one to the other.

Switch to have an inhibit function which will delay the completion of the transfer to normal and/or standby power by an adjustable

period of 0 - 5 seconds. Switch to have a phase monitor feature that will prohibit the transfer of power between “live” sources unless

the sources are in phase with each other.

Note: The building Emergency (Standby Power) Generator system used to operate the elevator(s) shall be capable of supplying non-

linear loads.

When more than one elevator is subject to the same standby power system and the standby power system is not large enough to run all

elevators at once, the transfer switch must include one set of normally closed dry contacts that open when the switch is in the standby

power position

A 125 volt, 15 ampere single phase car light supply.

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 73: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Confirmation of Power Supply - Hydraulic Approval (Canada)

COMMUNICATION REQUIREMENTS

Separate 125 volt, 15 ampere single phase power supply with fused SPST disconnect switch or circuit breaker with duplex outlet

located as required for inter-communicating system power supply. Circuit to be arranged for feeding from the building standby or

emergency lighting supply if provided. Conduit and wiring for remotely located inter-communicating stations (in Engineer’s office,

etc.).

X One (1) dedicated outside “Analog” (i.e. capable of carrying voice and data) telephone line to the elevator machine room / space must

be furnished. The telephone line must meet the following requirements:

Loop Current: Min 20mA, Max 120mA Nominal AC Line Impedance = 600 ohms

Line Voltage: On Hook – Min 15Vdc, Max 56.5Vdc Ring Voltage: Min 40Vac(rms), Max 150Vac(rms)

Off Hook – Min 8.75Vdc Ring Frequency: 15-68Hz

SMOKE DETECTORS Smoke detectors, provided either voluntarily or when required by the National Building Code of Canada [subsection 3.2.6],

located as required, with wiring from the sensing devices to the controller(s) designated by Otis.

I. For each group of elevators, provide a normally closed contact representing the smoke detector at the designated return

landing.

II. For each group of elevators, provide a normally closed contact representing all smoke detectors located in lobbies, hoistways,

or machine rooms/machine space, but not the smoke detector at the designated return landing (see above) or the smoke detectors

as described in a below:

a) If a smoke detector is located in the hoistway at or below the lower of the two recall landings, it shall be wired to activate the

same normally closed contact as the smoke detector located in the lobby at the lower of the two recall landings.

b) If machine rooms/machine space is located at the designated return landing, the smoke detectors located therein shall be wired

to activate the same normally closed contact as the smoke detector at the designated landing.

III a. For a single unit, or group of elevators having one common hoistway, or one common machine room and one common

hoistway, provide one additional normally closed contact representing all the hoistway smoke detectors.

III b. If the group contains more than one hoistway and hoistway smoke detectors are installed, or if the group has more than one

machine room, provide one normally closed contact for each elevator. The contact is to represent the smoke detector in the machine

room for that particular elevator, and / or hoistway containing that particular elevator.

HEATING, VENTILATION, AIR CONDITIONING

X Temperature in the machine room shall be maintained between 60°F (15°C) and 100°F (38°C). Temperature in the machine space

shall be maintained between 32°F (0°C) and 104°F (40°C). The relative humidity in the machine room / space should not exceed 95%

non-condensing. When a machine room is used, temperature to be measured 6’ (1829 mm) above the floor and 1’ (305 mm) out from

car controller. Ventilation to suit Otis heat release requirements shown below. Local codes may require tighter temperature ranges

and higher ventilation levels. Please check with your local code authority for the exact requirements in your area. Heat release

includes allowance for average service of 40 elevator starts per hour in the up direction.

ELEVATOR NAME OR NUMBER

ELEVATOR CONTRACT NUMBER

DUTY HEAT RELEASE PER CAR (BTU/HR)

TOTAL BTUs

SA Pwhydcsa.doc REV 03/16/2012

CN281791

waldschg
TextBox
This form is in the Approval package and provides the information that the (sub)contractor will need to meet the elevator requirements.
Page 74: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Common Inspection Violations

Page 75: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

1

Common Inspection Violations Before the elevator(s) can be complete and ready for inspection by the state or local inspector, all requirements of the ASME/ANSI A.17.1 Elevator Code and local code requirements must be met. This includes completion of work that must be performed by other trades. Per our agreement, it is Otis’ responsibility to arrange for this inspection. We ask you to ensure that all “work by others” has been completed prior to our agreed upon date for inspection. Note - If the elevator installation does not pass inspection due to uncompleted work by others, then all additional costs associated with a re-inspection will not be the responsibility of Otis. Below is a list of common inspection violations. A review of these items along with the Pre-Inspection Checklist is recommended prior to the inspection process to allow for any necessary corrective action. Elevator Pits

□ Elevator pits shall be waterproof and designed to provide a dry pit area.

Standing water in the pit area is considered a major violation of Code. Note - A sump pump cannot be used alone to meet the requirements of providing a dry pit area. Proper waterproofing is required.

□ Drain holes connected to the building sanitary sewer are not allowed in the

elevator pit under any circumstances. □ The floor of the pit shall be approximately level.

□ Sump pumps must be set into the pit floor and a metal cover provided to cover

the entire sump hole level with the pit floor. It must drain to approved area or oil separator device, not a sanitary sewer. The purpose of the sump pump is to remove casual water from the pit. Note - Check with local code authorities for specific local requirements .

□ Any pit more than 3’-0” deep shall be provided with a non-combustible access

ladder. □ An externally guarded permanent lighting fixture and a GFCI convenience outlet

shall be provided in each pit. The light switch must be located as to be accessible from the pit access door and provide an illumination of not less than 10 foot-candles at the pit floor.

□ Provide patching of pit floor after setting of cylinder assembly to accommodate a

watertight condition.

Page 76: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

2

Elevator Hoistways □ Hoistways serving more than two (2) floors shall be provided with means for

venting smoke and hot gases directly to the outer air or through non-combustible ducts to the outer air in case of fire. Vents shall be located in the side of the hoistway directly below the roof or directly over the hoistway. The clear open area of the vents shall be not less than three and one-half (3 ½) percent of the area of the hoistway, and in no case less than three (3) square feet for each hoistway, whichever is greater. Note - More stringent local building codes will take precedence over elevator code requirements. Special attention is required for hoistway ventilation exposed to weather. Vents shall have an insect screen to prevent the entry of birds, insects, etc.

□ Hoistway enclosures shall have substantially flush surfaces. Beams, floor, slabs,

or other building construction shall not project more than two (4) inches inside the general line of the hoistway unless the top and bottom of the projection is beveled at the angle of not less than 75° degrees with the horizontal. Where setbacks occur, the top of the setback shall be beveled at the same angle. Setbacks or recesses at the hoistway vent are included under this requirement. This requirement does not apply to divider beam(s) between elevators.

□ Drywall construction, if used, shall be a tested assembly approved for the use it is

being applied to (partition wall or floor-ceiling assembly). Only non-combustible systems are approved. Penetrations in the dry wall assembly for elevator fixtures are required, and the responsibility for maintaining the fire rating of the dry wall system at these points is borne by the system installer. Note - More stringent local building codes will take precedence over elevator code in regard to the fire rating of elevator hoistways.

□ Hoistway door entrance frames and headers shall be grouted solid to maintain fire

ratings of the hoistway. □ All voids, holes, slots, etc., in the hoistway shall be grouted or pointed up to

maintain fire rating of the hoistway. □ All nails, snap-ties, form straps, and wood shall be removed from the hoistway.

□ Only equipment required for the operation of the elevator is permitted inside the

elevator hoistway. □ Landing areas for all floors and elevator lobbies shall be completed prior to the

inspection.

Page 77: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

3

Elevator Machine Rooms □ Only machinery and equipment required for the operation of the elevator shall be

permitted in the elevator machine room. Pipes or ducts conveying gases, vapors, or liquid or electrical equipment, wiring, piping and controls not used for the operation of the elevator are prohibited in the elevator machine room.

□ The elevator machine room shall be free of refuse and shall not be used for

storage of any materials not related to the elevator equipment. □ Machine room doors shall have fire rating with labels. Doors shall be self-closing

and self-locking. Minimum height of the door is 6’-0”. Minimum width of the door is 30”. The door lock shall be of the type that can be opened from the inside without a key. However, a key is required to open the door from the outside at all times. Push-button type locks are not allowed in the machine room door.

□ Machine rooms shall have a minimum of seven (7) feet clear headroom under all

obstructions (including hoist beam, light fixtures, etc.). □ Machine room floors shall be smooth and level.

□ Machine rooms shall have adequate ventilation to avoid overheating of the

equipment. Ambient temperature in machine room is to be maintained between 60°-100° all times, or as detailed in our submittal. Relative humidity not to exceed 95% non-condensing.

□ Special attention is required for machine room ventilation and machine room

doors when exposed to the weather. Extra precautions must be taken to prevent entry of blowing rain.

□ Adequate lighting shall be provided in the elevator machine room to provide not

less than ten 19 foot-candles at all areas of the floor level. The light switch shall be located within 18”on the lock-jamb side of the access door.

□ A GFCI type duplex receptacle shall be provided in the elevator machine room.

□ All voids, holes, slots, etc., in the machine room shall be grouted or pointed up to

maintain the fire rating. All nails, snap-ties, form straps, and wood shall be removed from the machine room walls, floor, and ceiling.

□ Provide a Class “ABC” fire extinguisher.

□ A lockable fused disconnect switch in machine room with feeder wires to elevator

controller, all piped in accordance with N.E.C. or C.E.C. (Canadian Electrical Code), and grounded. Switch must be in sight of elevator machine and shall be the type that cannot be engaged with door open. Disconnect should be equipped with a microswitch when ERU units are being furnished. (2.26.4) (NEC 620.91-C) Examples of ERU auxiliary contacts - Square D - #EK300-2, I.T.E. - SC-3, West. Elec. - EK-1

Page 78: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

4

□ Lockable 120V disconnects per power confirmation for cab lighting circuit. Car Enclosures

□ Finish flooring (whether carpet or tile) must be installed prior to final inspection. A

non-slip surface is required. Make sure that final elevator cab drawings are reviewed to obtain the finish floor thickness dimension for which the elevator cab was constructed.

□ Carpet used on elevator car floors must be securely attached to the car platform,

have a tight weave and low pile, be installed without padding, and conform to the following requirements of ASTM E 84, UL 723, NFPA 252 or CAN/ULC-S102.2, whichever is applicable: (a) flame spread rating of 0 to 75 (b) smoke development of 0 to 450

□ Telephones or communications devices within the elevator cab must be installed

and in working order prior to final inspection. They must connect to a source monitored 24 hours a day and comply with ADA requirements, which preclude reliance on voice-only communication devices.

General □ Buildings having emergency power systems and elevators, which will be powered

by this generator, shall have the generator operable at the time of the final inspection.

□ Fire Safety system must be installed and in working order prior to final inspection.

Smoke detectors may be required in each elevator lobby, hoistway, and machine room. Check with local code authority. (2.27.3.2) Furnish normally closed fire system contacts to the elevator controller as per power confirmation.

Page 79: Elevator Installation Processlfportal.eastvaleca.gov/WebLink/0/edoc/2343/hydro... · Guide to the Elevator Installation Process Coordination between the various building trades during

Local Requirements/Options