electricity storage for large enterprisesjp/workshop/slides/pimmaj.pdf · 2016. 6. 21. · school...
TRANSCRIPT
School of somethingFACULTY OF OTHER
School of Chem. and Proc. Eng.FACULTY OF ENGINEERING
Electricity Storage for Large Enterprises
Andrew Pimm
Centre for Integrated Energy Research
Energy storage workshop at University of Leeds
14 June 2016
Introduction
Energy storage of interest to businesses/universities/hospitals,
particularly those with on-site generation
Economics of storage to enterprises poorly understood
Many revenue streams exist
Lancaster University interested in installing electricity storage
Case Study on Lancaster
University
Carried out case study with Lancaster
University after presentation given there in
January 2016
13k students, 4.5k staff, 8 halls of residence
on campus
Annual elec. demand ≈ 22 GWh; spend ≈
£2m pa
MD ≈ 6 MW
2.35 MW wind turbine, 50 kW PV and 1.9
MWe CHP on-site
2 days w/o power in early Dec due to floods
Energy Manager (Jan Bastiaans) interested
in installing up to 4MW / 4MWh of mixed
storage devices
0
1
2
3
4
J F M A M J J A S O N DMo
nth
ly E
lec.
(G
Wh
)
Month
Import WT CHP
0
2
4
6
8
0
0.5
1
1.5
2
2.5
3
J F M A M J J A S O N D
Max
imu
m M
on
thly
Dem
and
(M
W)
Mo
nth
ly E
lec.
Imp
ort
(G
Wh
)
Month
2014 (import) 2015 (import)
2014 (MD) 2015 (MD)
2014
Electricity Prices
Price made up of commodity and non-commodity components
Non-commodity = DUoS + TNUoS + RO + FiT + BSUoS + BS
+ HDC
Commodity price set after forward purchase and trading by
broker (Inenco)
0% 20% 40% 60% 80% 100%
Red
Amber
Green
% of marginal price
DU
oS
Tim
e B
and
DUoS REO BS BSUoS HDC FiT Energy Cost (avg.)
Time periods
Red Time
Band
Amber Time
Band
Green Time
Band
Mon to Fri 16:00 – 19:0009:00 - 16:00 00:00 - 09:00
19:00 - 20:30 20:30 - 24:00
Sat and Sun 16:00 – 19:0000:00 - 16:00
19:00 - 24:00
DUoS charges for HV meters in north west region
Electricity Prices
Time-varying marginal price is of interest to storage operator
LU’s marginal price of electricity, 04/2015-04/2016
(Mean commodity price of ~£0.06/kWh used, not including
Triads)
Transmission Network Use of
System (TNUoS) Charges
HH metered customers charged for use of transmission
network according to consumption during “Triads”
Triads: 3 half-hours of highest GB system demand between
Nov-Feb (separated by at least 10 days)
Since 1990/91, >80% have
been 17:00-17:30
Triad alerts issued by electricity
suppliers and utility
management companies
Optimisation Algorithm
Modified arbitrage optimisation algorithm to take into account generation and
demand (excess generation effectively costs the storage 4.91 p/kWh)
Results below for no generation… currently trying to work out how to synthesise
total demand and so half-hourly export based on monthly export figures
Optimisation Algorithm
Modified arbitrage optimisation algorithm to take into account generation and
demand (excess generation effectively costs the storage 4.91 p/kWh)
Results below for no generation… currently trying to work out how to synthesise
total demand and so half-hourly export based on monthly export figures
Savings Breakdown
Breakdown of savings available to Lancaster University and required expenditure.
• 2015 demand data &
charges
• 85% round-trip efficiency
• tch ≤ 12.5 hrs
• tdch = 2 hrs
• Hitting all Triads
Total Savings
Total savings
Total annual savings available to Lancaster University = £27,000/MWh
• 2015 demand data &
charges
• 85% round-trip efficiency
• tch ≤ 12.5 hrs
• tdch = 2 hrs
• Hitting all Triads
0
5
10
15
20
25
0
10
20
30
40
50
60
DU
oS
Red
-G
reen
(p
/kW
h)
TNu
oS
Dem
and
(£
/kW
)
Distribution Area
TNUoS DUoS R-G
DUoS charges for HV HH metered customers
effective from 1st Apr 2017 & TNUoS demand
charges effective from 1st Apr 2016
Area ID Area
DUoS for HV HH Metered (p/kWh) TNUoS Demand (£/kW)Red Amber Green
10 Eastern 6.384 0.020 0.004 46.543113
11 East Mids 7.391 0.121 0.021 44.724594
12 London 1.921 0.017 0.000 51.870233
13 Manweb 10.508 0.348 0.180 42.678395
14 West Mids 7.156 0.392 0.007 45.738925
15 North East 7.556 0.364 0.036 42.927953
16 North West 6.265 0.463 0.057 42.828015
17 Scots Hydro 4.044 1.393 0.313 40.966038
18 Scots Power 7.856 0.470 0.017 40.244453
19 South East 7.632 0.097 0.008 49.204313
20 Southern 6.572 0.210 0.044 50.078028
21 South Wales 9.942 1.155 0.055 42.306722
22 South West 19.170 0.117 0.046 48.580421
23 Yorks 6.253 0.476 0.033 42.493827
36.60 38.11
27.97
44.7638.17
34.20 33.52
20.46
31.28
41.09 38.8043.67
69.83
33.82
0
10
20
30
40
50
60
70
80
Val
ue
of
Sto
rage
(£
k/M
Wh
.yr)
Distribution Area
Value of storage to HV HH metered customers in 2017
On-Site Generation
In 2015, Lancaster Uni exported 241
MWh (~1% of demand)
Could potentially have reduced spend in
2015 by £17,500
Detailed analysis not possible due to
lack of dataStephenson Halliday
Payback Period & NPV of
Tesla Powerpack
Tesla Powerpack (May 2016)
Technology Li-Ion
Storage capacity per module 100 kWh
Peak discharge power per module 50 kW
AC-AC efficiency (2 hour system) 82%
AC-AC efficiency (4 hour system) 83%
DC-DC efficiency (2 hour system) 91%
DC-DC efficiency (4 hour system) 93%
Cost per module $47,000
Cost per bi-directional 250 kW inverter $65,000
Cost of cabling & other hardware $2,000+$500/module
Powerpack costs equate to £417,000 for a 1 MWh, 500 kW system
Regular annual savings of £26,000/MWh & 5% discount rate give 33 year
discounted payback period in north-west (but 15 year projected life!)
In the south-west in 2017, annual savings of £65,000/MWh give 8 year
discounted payback period. After 15 years, NPV is £258,000/MWh, giving
13% annual rate of return
EOS Aurora advertised at £138,000/MWh,
but 75% round-trip efficiency
Incentive schemes in US give >£1.6m/MW
for electricity storage (up to 50% of project
cost)
Near-Delivery Electricity
Trading
Investigated value of purchasing on day ahead market,
assuming 2 hr discharge at 16:30-18:30 weekdays Nov-Feb,
optimal schedule elsewhere…
Up to £40,000/MWh.yr in north-west, an increase of
£13,000/MWh.yr over a flat commodity price
Other Revenue Streams
Several other revenue streams exist for small-/medium-scale
storage:
Service Response
Time
Max. Duration Min. Power Trigger
Enhanced Frequency
Response
1 s 9 s 3 MW Static frequency point
Firm Frequency Response
(Primary)
2-10 s 1-2 m 10 MW Static or dynamic frequency
Firm Frequency Response
(Secondary)
30 s 30 m 10 MW Static frequency point
Fast Reserve 2 m 15 m 50 MW NG request
Short Term Operating Reserve 4 h 2 h 3 MW NG request
Curtis M. Overview of the UK Demand Response Market. EPFL Workshop, 11 Sep 2015, University of Reading
Other Revenue Streams
Market size and returns (Curtis, 2015):
Service Overall
Capacity Per
Year (MW)
DR Capacity
Per Year
(MW)
Procurement
Method
Returns Per Year, Per MW
Enhanced Frequency
Response
200 ?? ??? Tender ???
Firm Frequency Response
(Primary)
200-700 ??? Tender £15,000 - £20,000
Firm Frequency Response
(Secondary)
700-1400 ??? Tender £30,000 - £40,000
Fast Reserve ??? ??? Tender ???
Short Term Operating Reserve 2500-3500 200-700 Tender £20,000 - £30,000
EFR aimed specifically at storage
FFR runs 24/7
STOR has 2 daily availability windows (~07:00-14:00 & ~16:00-20:00)
Returns based on availability payment & utilisation payment
Conclusions
• Savings from reducing network charges: £20 - £70/kWh.yr
• South-west highest, north Scotland lowest
• Value increased by on-site generation, up to £17.5/kWh.yr extra at
Lancaster Uni with 2.35 MW WT & 1.9 MWe CHP, 6 MW max. demand
• Additional revenue from near-delivery trading: up to £13/kWh.yr
• Payback period with Tesla Powerpack: 8 yrs in south-west; 33 years in
north-west
School of somethingFACULTY OF OTHER
Electricity Storage for Large
Enterprises
Thank you
Dr Andrew J. Pimm