electricity planning in the parry sound-muskoka area · 2017-01-24 · solutions and demand...
TRANSCRIPT
Electricity Planning in the Parry Sound-Muskoka area Local Advisory Committee Meeting #2
September 26, 2016
Parry Sound-Muskoka Regional Planning Process and Timeline
2
Discuss key priorities for future LAC meetings
Seek input from the LAC on the draft recommendations
Review the electricity needs and options in the Parry Sound-Muskoka area
Purpose of today’s meeting
3
Recap: Types of Electricity Planning
4
Recap: Scope of Regional Planning:
5 5
Note: Connection assessment of
generation resources for procurement
programs, such as the Feed-in-Tariff and,
the Large Renewable Procurement, are
beyond the scope of regional planning.
Options to address electricity needs
Transmission System
Distribution System
Centralized
Generation
Distributed
Generation
6
Electricity Demand Growth in this Region
Planning forecast includes the peak demand impact of planned conservation efforts and distributed generation
Conservation and embedded generation is expected to reduce the electricity demand by about 35 MW over the
planning period (about 25% of demand growth)
7
230kV Transmission Infrastructure
8
44kV Sub-Transmission Infrastructure
9
44kV Service Reliability and Performance
Transformer Station Capacity in the
Parry Sound and Waubaushene Areas
Load Restoration on 230kV Orillia-
Muskoka Transmission system
Parry Sound-Muskoka: Summary of Electricity Needs
10
11
44KV SERVICE RELIABILITY AND PERFORMANCE
Some of the 44kV networks in this Region are performing below provincial average in terms of frequency and durations of outages
12
** Note: The highlighted areas are approximate and provide general indications of the 44kV networks
that are performing below provincial average.
Main Causes of these 44kV Outages
13
Tree-Related Outages
Equipment
Failure Off-Road Distribution Facilities
Crews have limited access to these facilities
leading to increased restoration time.
Increased exposure to
tree, wildlife contact, and
weather.
Long 44kV lines
(40-100km)
Status of Maintenance and Outage Mitigations Initiatives
Vegetation management
Vegetation management was last completed in these areas in 2015/2016
Full clearing for these areas is planned for 2021/2022
Hydro One has committed $20M in 2016 in the Districts of Muskoka and Parry Sound to reduce tree-related
outages for its customers
Line patrols are conducted on a 6-year cycle
Data is collected to help identify and prioritize the need to replace distribution poles and/or potentially defective
equipment
Last line patrolling cycle for these priorities areas occurred between 2010-2012
The next line patrolling cycle is scheduled for 2016-2021
Mid-cycle hazard tree program
Visual inspection to identify potential risk of tree-related contact
This program would be conducted in this region in 2018/2019 period
Distribution System Management & Grid Modernization
Distribution management system will be implemented in this region by end of 2016 and will enable
operators to have greater grid visibility and to response to outage in a timely manner
A broader grid modernization initiative is underway to identify opportunities for distribution automation
14
Opportunities to Improve Service Reliability
Distribution Solutions and Mitigation Measures:
Increase vegetation management to reduce exposure
Install distribution automation and fast-acting switching devices to
restore power in a timely manner
Relocate “Off-Roads” 44kV lines to roadside to allow crews to better
access to these distribution facilities
Strengthen ties within the 44kV network to allow adjacent 44kV lines to
service as a back-up supply in the event of an outage
15
The cost, feasibility and effectiveness of these solutions depends on the solution type, the
geography and the nature of the 44kV distribution network
Bracebridge, Gravenhurst, the Township of Muskoka Lakes, and the Township of Seguin are supplied by long 44kV lines (60-100 km) from Muskoka transformer station.
Currently, the Bracebridge transformer station
supplies only one industrial customer and would
have sufficient capacity to accommodate new
customers.
To shorten 44kV line exposure, new 44kV lines can
be built (~ up to 15 km) to resupply these areas from
Bracebridge TS at a cost of $3-6 M.
Unlike Muskoka TS, Bracebridge TS only has a
single source of transmission supply.
A second transformer station or/and a combination
of switching facilities ($5- 30 M) can be installed to
provide a second source of supply and to minimize
the impact of potential transmission outages
Option to Resupply from Bracebridge TS
16
Draft Recommendations
17
The Working Group recommends the following:
To further examine the cost-benefit and cost responsibility of transmission and
distribution options to improve 44kV service reliability in the Muskoka area:
Hydro One Transmission and affected LDCs (Hydro One Distribution, Lakeland Power and Veridian
Connections) will examine the cost-benefit and cost responsibility of these options through a local
planning study
The status and results from the local planning study will be discussed with the LAC and affected
communities
To explore opportunities to improve resilience and service reliability at the
community level:
Facilitate discussion with the LAC and affected communities about community energy planning
activities and the cost-benefit of community-based solutions to improve resilience and service reliability
18
TRANSFORMER STATION CAPACITY IN THE PARRY SOUND AREA
• Limited supply capacity is remaining on
the two transformer stations supplying
Parry Sound, Waubaushene and
surrounding areas
• Electricity demand at Parry Sound and
Waubaushene transformer stations is
expected to grow at a rate of 1-2 MW/year
over the planning period
• By 2035, additional transformer station
capacity will be required at: Parry Sound TS (23 MW)
Waubaushene TS (11 MW)
Transformer Stations Supplying Parry Sound -Waubaushene and surrounding areas
19
Potential Options
20
Option 1: Resupplying some customers in the Parry Sound and Waubashene areas
from other adjacent transformer stations using existing and new distribution facilities
The existing 44kV system can transfer up to 10 MW to neighboring transformer stations from
Waubaushene transformer station.
With some reinforcements on the 44kV distribution network (~ about $7M), up to 6 MW can be
transferred to neighbouring stations from Parry Sound transformer station. These reinforcements
would also improve the service reliability for Township of Muskoka Lakes and Township of Seguin.
Option 2: Upgrade the transformers at the existing Parry Sound and Waubaushene
transformer stations ($25-30M per transformer upgrade)
Option 3: Defer the transformer upgrade using targetted demand management and
distributed energy resources
Opportunities to defer transformer station upgrades
Given the modest growth in this area, there is a large value for deferring (i.e., about $2M per year) the transformer station upgrades using community-based solutions.
At this time, the Working Group has limited information on the cost and feasibility of distributed energy resources and demand management in this area. More work needs to be done to determine whether it is cost-effective and feasible to rely on these solutions to address the local needs.
Pilots and emerging
technologies
(e.g., thermal energy storage,
microgrid)
Local hydroelectric potential
(According to OWA, 38 MW potential
in the Parry Sound District)
21
Initiatives to identify opportunities to
improve heating efficiency
(e.g., energy baselines through community
energy plans)
Examples of community-based solutions:
End of Life Replacement of Transformers
Based on the typical service life, transformers at Parry Sound and
Waubaushene could be reaching end of life in the early 2030s.
Depending on the demand growth and management, it may be cost effective to
advance the end of life replacement and to replace the aging assets with
upgraded/upsized facilities.
22
Draft Recommendations
The Working Group recommends the following:
To manage near-term growth:
Resupply some of customers in the Parry Sound and Waubaushene areas from neighbouring
transformer stations using existing and new distribution facilities.
To better understand the cost and feasibility of implementing distributed energy
solutions and demand management in the Parry Sound area:
Initiate a local potential study on distributed energy resources/demand management
Leverage local knowledge and community energy planning activities
Identify opportunities for targeted conservation and energy efficiency opportunities in First Nations
communities and municipalities.
To determine if there is an opportunity to align the end of life replacement with
transformer station capacity needs:
Monitor the demand growth and the results from the local potential study
Work with Hydro One Transmission to actively monitor and assess the conditions of these transformers
Revisit this need in the next iteration of the plan
23
24
LOAD RESTORATION ON 230KV ORILLIA-MUSKOKA TRANSMISSION SYSTEM
• Today, about 450 MW are being supplied by 230kV Orillia-Muskoka
system
• In the event of a major outage on the 230kV Orillia- Muskoka system, all
loads would be interrupted and there is limited ability to restore the load
in a timely manner. This does not meet Ontario’s planning standards.
• According to Ontario’s planning standards, no more than 600 MW can be
interrupted following a major outage. Demand on the 230kV Orillia-Muskoka system is expected to increase up to 600 MW by
early 2030s
Load Restoration on 230kV Orillia-Muskoka system
25
Potential Options In the event of a 230kV transmission outage, the following fast-acting
isolating devices can be installed to minimize the impact of supply
interruption to customers
Motorized Switches (~$5-7M): Isolates sections of the transmission line
following an outage within 30 min and would enable power to be restored to
customers in a timely manner.
Breakers (~$20-25 M): Immediately isolates sections of the transmission line
that are not directly impacted by the outage and would reduce the total number
of customers that would be affected by a transmission outage.
26
Draft Recommendations
The Working Group recommends the following:
To restore up to 300 MW within 30 minutes following a major outage on the 230kV
Orilla-Muskoka transmission system by:
Install motorized switches at the Orillia transformer station.
Given the uncertainty demand forecast over the longer term and the substantial cost of installing
breakers, it is not recommended that breakers be installed at this time.
27
• End of life replacement of a transformer station planned at Minden within the next five
years
• Additional supply may be required on the Orillia-Muskoka 230kV transmission system
over the longer-term (beyond 2030s)
• Voltage and power quality concerns
Other Considerations
28
Next Steps and Timeline
29
NEXT STEP:
LAC members to provide comments
on the draft recommendations by
Oct 15, 2016
Parry Sound-Muskoka Technical Working Group’s Priorities
Priority #2:
Better understand the potential,
cost and feasibility of demand
management and distributed energy
resources in the area
Priority #3:
Keep LAC members and affected
communities posted on the status of
the IRRP recommendations
Priority #4:
Keep LAC members and affected
communities posted on demand
growth and conservation activities
Priority #5:
Coordinate regional and community
energy planning activities
Priority #1:
Get the LAC’s input on the draft
recommendations
LAC members to provide comments by Oct
15, 2016
Final report will be posted by Dec 2016
Engage with LAC to assist with local potential study
Identify opportunities for targeted conservation and
energy efficiency opportunities in First Nations
communities and municipalities by leveraging local
knowledge and community energy planning activities
Determine cost-effective and feasible community-
based solutions that may be implemented to help
defer the transformer station needs in the area
Provide a status update on the local planning
study to examine cost-benefit and cost
responsibility of the options to improve 44kV
service reliability in the Muskoka area
Provide a status update on any near-term
projects and outcomes from the local potential
study
Review electricity demand growth and
conservation activities in Parry-Sound
Muskoka with LAC
Facilitate a discussion with the LAC and affected
communities about community energy planning activities
and local solutions to improve resilience and service
reliability
Use LAC meetings to share best practices and to
coordinate regional and local energy planning activities
30
31
DRAFT LAC ROADMAP