electricity as a good or a service: some “shocking ... as a good or a service: some “shocking”...

4
C Electricity as a Good or a Service: Some “Shocking” Developments Credit providers may be shocked to learn that the courts have reached conflicting decisions over whether elec- tricity is a “good,” entitled to Bankruptcy Code Section 503(b)(9) priority status 1 , or a service that is not entitled to any priority protection. e United States Bankrupt- cy Court for the District of Puerto Rico in In re PMC Marketing Corporation, and the United States District Court for the Southern District of New York in Hudson Energy Services, LLC v. e Great Atlantic & Pacific Tea Company, Inc. (A&P) both recently considered whether electricity is a “good” or a “service.” e PMC Court held that electricity is a “service” and not a “good,” because it was provided by a government owned utility. On the other hand, the A&P District Court vacated and remanded the order of the United States Bankruptcy Court for the Southern District of New York, rejecting the A&P Bankruptcy Court’s hold- ing that electricity is a “service” and not a “good” and directing that an evidentiary hearing be conducted on this issue. In re Erving Industries, Inc. e PMC Court and the A&P District Court focused on the District of Massachusetts Bankruptcy Court’s hold- ing in In re Erving Industries. In Erving, Constellation NewEnergy, Inc., an electricity reseller, timely asserted a Section 503(b)(9) priority claim in the amount of $281,667.88 on account of electricity delivered to the debtors Erving Industries, Inc. and two affiliates (col- lectively, Erving) within 20 days of Erving’s bankruptcy filing. Erving objected to Constellation’s Section 503(b) (9) claim and argued that electricity was a “service” and not a “good.” e Erving Court held that the electricity Constellation had resold to Erving was a “good.” First, applying the definition of “goods” contained in Section 2-105(1) of the Uniform Commercial Code (UCC), the Erving Court held that electricity is movable and identifiable because it can be measured at the point it passes through a customer’s meter. Section 2-105(1) defines goods as “all things...which are movable at the time of identifica- tion to the contract for sale.” e Erving Court rejected Erving’s argument that electricity ceases to be movable when it is measured by the meter because identification and consumption occur simultaneously. Instead, elec- tricity does not simply cease to exist when it reaches a customer’s meter, but moves through the meter and continues to move throughout the customer’s electrical wiring until the customer ultimately uses it. e Erving Court also focused on Constellation’s role as a wholesale energy supplier and the relevant terms of the parties’ contract. Constellation had purchased elec- tricity from third parties and resold that electricity to Erving and other consumers. Moreover, Constellation was not a “utility” because it was not subject to govern- mental regulation, did not possess a monopoly as the sole source of electricity available to Erving, and was not included in the list of utilities maintained by the rel- evant state agencies. e Erving Court also relied on the terms of the parties’ contract that described a purchase/ sale relationship, and not the provision of a “service.” The PMC Marketing Corporation Case PMC Marketing Corporation filed a Chapter 11 peti- tion on March 18, 2009. PMC’s case was converted to a Chapter 7 case on May 21, 2010. P.R. Electric Power Authority (PREPA) filed a motion seeking payment of a Section 503(b)(9) claim in the amount of $89,336.42. PREPA argued that it was entitled to Section 503(b)(9) priority status because its claim was based on its sale of, and PMC’s receipt of, electricity during the 20-day peri- od (February 26, 2009 and March 17, 2009) before PMC’s bankruptcy filing. Selected topic BRUCE NATHAN, ESQ. AND ERIC CHAFETZ, ESQ. 1 BUSINESS CREDIT NOVEMBER/DECEMBER 2013 The United States Bankruptcy Court for the District of Puerto Rico and the United States District Court for the Southern District of New York both recently considered whether electricity is a “good” or a “service.” THE PUBLICATION FOR CREDIT & FINANCE PROFESSIONALS $7.00 NATIONAL ASSOCIATION OF CREDIT MANAGEMENT NOVEMBER/DECEMBER 2013

Upload: hoangdat

Post on 29-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

CElectricity as a Good or a Service: Some “Shocking” Developments

Credit providers may be shocked to learn that the courts have reached conflicting decisions over whether elec-tricity is a “good,” entitled to Bankruptcy Code Section 503(b)(9) priority status1, or a service that is not entitled to any priority protection. The United States Bankrupt-cy Court for the District of Puerto Rico in In re PMC Marketing Corporation, and the United States District Court for the Southern District of New York in Hudson Energy Services, LLC v. The Great Atlantic & Pacific Tea Company, Inc. (A&P) both recently considered whether electricity is a “good” or a “service.”

The PMC Court held that electricity is a “service” and not a “good,” because it was provided by a government owned utility. On the other hand, the A&P District Court vacated and remanded the order of the United States Bankruptcy Court for the Southern District of New York, rejecting the A&P Bankruptcy Court’s hold-ing that electricity is a “service” and not a “good” and directing that an evidentiary hearing be conducted on this issue.

In re Erving Industries, Inc.The PMC Court and the A&P District Court focused on the District of Massachusetts Bankruptcy Court’s hold-ing in In re Erving Industries. In Erving, Constellation NewEnergy, Inc., an electricity reseller, timely asserted a Section 503(b)(9) priority claim in the amount of $281,667.88 on account of electricity delivered to the debtors Erving Industries, Inc. and two affiliates (col-lectively, Erving) within 20 days of Erving’s bankruptcy filing. Erving objected to Constellation’s Section 503(b)(9) claim and argued that electricity was a “service” and not a “good.”

The Erving Court held that the electricity Constellation had resold to Erving was a “good.” First, applying the definition of “goods” contained in Section 2-105(1) of the Uniform Commercial Code (UCC), the Erving

Court held that electricity is movable and identifiable because it can be measured at the point it passes through a customer’s meter. Section 2-105(1) defines goods as “all things...which are movable at the time of identifica-tion to the contract for sale.” The Erving Court rejected Erving’s argument that electricity ceases to be movable when it is measured by the meter because identification and consumption occur simultaneously. Instead, elec-tricity does not simply cease to exist when it reaches a customer’s meter, but moves through the meter and continues to move throughout the customer’s electrical wiring until the customer ultimately uses it.

The Erving Court also focused on Constellation’s role as a wholesale energy supplier and the relevant terms of the parties’ contract. Constellation had purchased elec-tricity from third parties and resold that electricity to Erving and other consumers. Moreover, Constellation was not a “utility” because it was not subject to govern-mental regulation, did not possess a monopoly as the sole source of electricity available to Erving, and was not included in the list of utilities maintained by the rel-evant state agencies. The Erving Court also relied on the terms of the parties’ contract that described a purchase/sale relationship, and not the provision of a “service.”

The PMC Marketing Corporation CasePMC Marketing Corporation filed a Chapter 11 peti-tion on March 18, 2009. PMC’s case was converted to a Chapter 7 case on May 21, 2010. P.R. Electric Power Authority (PREPA) filed a motion seeking payment of a Section 503(b)(9) claim in the amount of $89,336.42. PREPA argued that it was entitled to Section 503(b)(9) priority status because its claim was based on its sale of, and PMC’s receipt of, electricity during the 20-day peri-od (February 26, 2009 and March 17, 2009) before PMC’s bankruptcy filing.

S e l e c t e d t o p i cBruCe NaThaN, esq. aNd eriC ChafeTz, esq.

1 B u s i n e s s C r e d i t n o v e m B e r / d e C e m B e r 2 0 1 3

the united states Bankruptcy Court for the district of Puerto rico and the united states district Court for the southern district of new York both recently considered whether electricity is a “good” or a “service.”

The PublicaTion For crediT & Finance ProFessionals $7.00

n a T i o n a l a s s o c i a T i o n o F c r e d i T M a n a g e M e n T

NO

VEM

BER

/DEC

EMBE

R 2

013

PREPA argued that its aforementioned claim for the electric-ity provided to PMC was entitled to Section 503(b)(9) priority treatment because the electricity was a “good” within the UCC’s definition of that term. According to PREPA, the elec-tricity was both moveable (from when it was metered and afterwards) and identifiable (to a customer’s contract at the time it was metered at the consumer’s place of business).2

The PMC Court recognized the division among the courts over whether electricity is a “good” or a “service.” The court held that the electricity supplied by PREPA, a utility,3 was a service, not a good. The court defined the term “utility” as a provider of a service, such as light, power or water. The court also observed that a utility refers to a “business organization ([such] as an electric company) performing a public service and subject to special governmental regulations,” that has “some special position with respect to the debtor,” and has “a monopoly in the area so that the debtor cannot easily obtain comparable service from another.”

Applying these various definitions and concepts, the PMC Court concluded that PREPA was a utility provider because: (i) like other traditional utilities, it is subject to governmental regulation, (ii) enjoys a “special relationship” with PMC as PREPA is the only electricity provider in Puerto Rico, (iii) has a monopoly, and (iv) is owned by the government and direct-ed by a government board. Accordingly, the PMC Court held that electricity in this specific context was a “service” and PREPA was not entitled to an administrative priority claim under Bankruptcy Code Section 503(b)(9).

The PMC Court distinguished the Erving Court’s holding that electricity is a good eligible for Section 503(b)(9) priority sta-tus. The court noted that the claimant in Erving, Constella-tion, was a private alternative energy provider that sold elec-tricity as a “competitive supplier” and was not a public utility provider, like PREPA, that was responsible for the ultimate delivery of electricity to a customer as a “service.”

The a&P district Court decisionOn April 27, 2011, Hudson Energy Services, LLC filed a motion seeking the allowance of a Section 503(b)(9) claim in the amount of $875,943.90 on account of electricity Hudson had sold to Great Atlantic & Pacific Tea Company, Inc. and its affiliates (collectively, A&P). A&P objected to Hudson’s motion, arguing that the electricity provided to A&P was not a “good” under Section 503(b)(9).

The A&P Bankruptcy Court had ruled that electricity is a service, and not a good, and, therefore, is not entitled to Sec-tion 503(b)(9) priority status. The court noted that electricity does not fall within the UCC’s definition of “goods” even though electricity is a commodity that can be bought and sold. The electricity at issue was not “movable at the time of identification to the contract” and was “not identifiable until the moment it reaches [the customer’s] meter, and at that point it is used.” The court also relied on UCC Section 2-105(4) in concluding that electricity is not an “identified

bulk of fungible goods” because it is “simply a stream of elec-trical energy… identified… at the point of delivery.”4 As such, “it is hard to see that [electricity] is actually moveable at the time of identification…[and] in essence disappears at that moment.”

Significantly, the A&P Bankruptcy Court disagreed with the Erving Court’s holding that electricity is a “good,” despite the fact that both Hudson and Constellation (the claimant in Erv-ing) were non-utility suppliers of electricity that did not per-form a delivery service. The A&P Bankruptcy Court disre-garded Hudson’s status as a seller of electricity as reflective of industry deregulation and not determinative of whether the UCC’s definition of “goods” includes electricity. Hudson appealed the A&P Bankruptcy Court’s order to the A&P District Court.

Hudson argued that the A&P Bankruptcy Court erred in holding, without any evidentiary support, that electricity is not a good. Hudson asserted that the electricity it had pro-vided A&P was movable when it was identified to the contract at the following two discrete points: (i) when Hudson pur-chased the electricity and it was subsequently released into the grid5, and (ii) when the electricity exited the grid, was measured, and passed through a customer’s meter.6 Hudson also argued that electricity qualified as “an identified bulk of fungible goods” like “oil in a pipeline or grain in an elevator,” because any unit of electricity is identical to any other unit and the electricity that Hudson had purchased on behalf of its customers (including A&P) was an undivided share of all the electricity included in the entire power grid.

A&P countered that the electricity it had purchased from Hudson could not have been identified to a contract of sale as soon as it entered the power grid. In addition, A&P had already consumed the electricity when it was identified to its contract with Hudson at the time it was measured at the meter. As such, A&P could not return the electricity to Hud-son after it was measured at the meter. Moreover, just because A&P could store a de minimis amount of electricity did not mean that the A&P Bankruptcy Court erred in holding that the electricity was not “moveable at the time of identification to the contract.” A&P also countered Hudson’s argument that electricity is “an identified bulk of fungible goods” by ques-tioning the plausibility of Hudson’s argument that the entire power grid is a “bulk” of goods, especially as electricity is con-stantly being “generated, transmitted and consumed” and was not capable of identification.

2B u s i n e s s C r e d i t n o v e m B e r / d e C e m B e r 2 0 1 3

PrePA argued that its aforementioned claim for the electricity provided to PmC was entitled to section 503(b)(9) priority treatment because the electricity was a “good” within the uCC’s definition of that term.

The A&P District Court’s Decision and ObservationsThe A&P District Court concluded that insufficient evidence was presented to determine whether the electricity that Hud-son had sold to A&P was a good, and, therefore, entitled to Section 503(b)(9) priority status. Accordingly, the A&P Dis-trict Court vacated and remanded the A&P Bankruptcy Court’s decision and ordered that an evidentiary hearing be held on whether the electricity that was subject to the parties’ contract satisfied the UCC’s definition of a good, moveable at the time of identification to the contract, or identified as a bulk of fungible goods.

Although the A&P District Court did not decide whether the electricity that Hudson had sold to A&P was a “good” or a “service,” the court made several interesting observations regarding whether and when electricity can be considered a “good.” First, the court relied on the UCC’s definition of “goods” for determining whether electricity is a good that is entitled to Section 503(b)(9) priority status.

Second, the A&P District Court observed that it would likely agree with Hudson’s argument and conclude that the electric-ity Hudson had sold to A&P is a “good” if Hudson can prove that the “electricity passes through the meter at the customer’s location and is at that moment identified and thereafter con-sumed.” The court also observed that if Hudson’s theory about electricity does not hold up, the court would need to under-take an “individual assessment” of the exact arrangement between A&P and Hudson to determine whether the electric-ity that Hudson had sold to A&P is a “good.” The court further observed that the terms “purchase” and “sale” in the parties’ contract could be relied upon as further support for charac-terizing electricity as a “good” and not a “service.”

Third, the A&P District Court considered the economics sur-rounding the sale and delivery of electricity. Electricity can be “provided by integrated utilities that generate, sell, deliver and service [electricity],” or by entities like Hudson, that make “money simply by buying electricity from generators at a lower price than that at which it sells to customers, but is oth-erwise hands off.” Complicating matters further, companies can fall between traditional utilities on one far end of the spectrum and companies on the other end, like Hudson, that solely buy electricity and sell it to their customers. Complicat-ing matters even further is that not all courts disqualify utili-ties from enjoying Section 503(b)(9) priority status.8

Finally, the A&P District Court discounted A&P’s argument that electricity is static and does not change from case to case. In rejecting this argument, the court focused on the conflict-ing court holdings over whether electricity is a “good” or a “service.” Based on those conflicting decisions, the court determined that it needed to conduct an evidentiary hearing on whether the electricity Hudson had sold to A&P was a good or a service.

ConclusionThe most important lesson for electricity providers can be summed up by the A&P District Court9 as follows:

I recognize that the possibility of individualized fact-find-ing regarding the nature of the claimant’s business, how it physically provides the electricity, its arrangements with generators, etc.—is less desirable than a bright-line rule that electricity always or never is a “good.” But individual-ized analysis may be what the statute requires.

While the ideal result for electricity providers would be for electricity to always be considered a “good,” the A&P District Court’s and PMC Court’s holdings make clear that many courts will likely not adopt such a straightforward approach. Accordingly, there will likely continue to be significant litiga-tion concerning whether electricity is a “good” or a “service,” since the issue arises in many factual scenarios.

Complicating matters further, this litigation will not just focus on the physical attributes of electricity, but will also focus on each claimant’s unique interaction with electricity in a specific debtor’s bankruptcy case. Illustrating this point, the PMC Court was able to conclude that PREPA was a “service” pro-vider because it was a government owned and operated utility that had a monopoly on electricity sales in Puerto Rico. Based on these facts, the PMC Court distinguished the Erving Court’s decision, where the claimant was not a utility. How-ever, the decisions by the A&P District Court and Erving Court demonstrate that utilities, like PREPA, occupy only one end of the spectrum related to dispositions of electricity and there are numerous other points on the spectrum. Because individualized assessments of the electricity being provided will have to be undertaken, the courts and litigants will be forced to engage in case-by-case analyses of each electricity provider’s interaction with a debtor (including those instances

3 B u s i n e s s C r e d i t n o v e m B e r / d e C e m B e r 2 0 1 3

Although the A&P district Court did not decide whether the electricity that Hudson had sold to A&P was a “good” or a “service,” the court made several interesting observations regarding whether and when electricity can be considered a “good.”

Because individualized assessments of the electricity being provided will have to be undertaken, the courts and litigants will be forced to engage in case-by-case analyses of each electricity provider’s interaction with a debtor.

where the electricity provider interacts with the debtor in more than one way).

Accordingly, electricity providers could be in for a shocking and unpredictable ride as it does not appear that the courts will be establishing a bright line test for determining whether electricity is a good that is entitled to Section 503(b)(9) prior-ity status or a service that does not enjoy such protection.

1. Section 503(b)(9) grants goods sellers an administrative priority claim for “...the value of any goods received by the debtor within 20 days before the date of commencement of a case under this title in which the goods have been sold to the debtor in the ordinary course of such debtor’s business.”

2. PMC’s trustee argued that the PMC Court should not have even reached the question of whether electricity was a “good” or a “service” because PREPA did not timely file a Section 503(b)(9) claim, despite being provided notice of the relevant bar date. In addition, according to the trustee, PREPA’s motion was actually a belated proof of claim in “disguise,” which could not be filed three years after the claims bar date set by the PMC Court. However, the PMC Court held that PREPA preserved the right to obtain priority status by filing a general unsecured claim that included invoices paid within 20 days before PMC’s bankruptcy filing, even though the general unsecured claim did not include any refer-ence to Section 503(b)(9). It is unclear whether other courts would reach the same conclusion.

3. The PMC Court also observed that PREPA was a utility that Congress had sought to protect when it enacted Bankruptcy Code Section 366.

4. UCC Section 2-105(4) states that “[a]n undivided share in an iden-tified bulk of fungible goods is sufficiently identified to be sold although the quantity of the bulk is not determined…”

5. Hudson argued that it had made wholesale purchases of electricity from power plants/electricity generators and these purchases could be specifically identified to Hudson’s contract with A&P.

6. Hudson disagreed with the A&P Bankruptcy Court’s holding that once electricity reaches a meter it disappears into use. Instead, Hudson argued that electricity is used at the exact moment it passes into the de-vice that it was intended to power. Hudson also argued that, if batteries are used to store electricity, they can delay the interval between metering and use, meaning, electricity can still be moveable after passing through the customer’s meter.

7. The A&P District Court rejected the A&P Bankruptcy Court’s conclusion that Congress did not intend for electricity to be considered a good under Section 503(b)(9) because electricity cannot be stockpiled.

8. The Western District of Wisconsin in GFI Wis., Inc. v. Reedsburg Util. Comm’n (In re Grede Foundries, Inc.), held that electricity provided by a utility satisfied the UCC’s definition of “goods” and was subject to Section 503(b)(9) priority status.

9. The PMC Court also made the following similar observation: “this Court believes that in deciding the question of whether electricity is a “good” or a “service” under the Bankruptcy Code, a court must carry out an inquiry into the unique facts of each case and thus this analysis cannot be determined without taking into consideration the totality of circumstances of all the relevant facts.”

Bruce S. Nathan, Esq. is a partner in the Bankruptcy, Financial Reorganization and Creditors’ Rights Group in the New York office of the law firm of Lowenstein Sandler LLP. He is a member of NACM and is a former member of the Board of Directors of the American Bankruptcy Institute and is a former co-chair of ABI’s Unsecured Trade Creditors Committee. Bruce is also the co-chair of the Avoiding Powers Advisory Committee working with ABI’s Commission to Study the Reform of Chapter 11. He can be reached via email at [email protected].

Eric S. Chafetz, Esq. is counsel at the law firm of Lowenstein Sandler LLP. He can be reached at [email protected].

*This is reprinted from Business Credit magazine, a publication of the National Association of Credit Management. This article may not be forwarded electronically or reproduced in any way without written permission from the Editor of Business Credit magazine.

4B u s i n e s s C r e d i t n o v e m B e r / d e C e m B e r 2 0 1 3