electrical power distribution in experiments w.iwanski
TRANSCRIPT
Electrical power distribution in experiments
W.Iwanski
W.Iwanski 2
Outline
• Supplying network at CERN• Power quality• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 3
• Supplying network at CERN• Power quality• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 4
Powering grid at CERN
25/10/2011 ESE seminar
W.Iwanski 5
Major power consumers at LHC
LHC Magnets
Cryogenics
CV
Experiments
Services
RF
0 5 10 15 20 25 30
15
30
20
25
15
15
Aparent power [MVA]
25/10/2011 ESE seminar
W.Iwanski 6
Electrical supply of the LHC experiments
ALICE supply
25/10/2011 ESE seminar
W.Iwanski 7
Electrical supply of the LHC experiments
Separation of the Machine network from the LHC General Service network in each experiment
Individual 18/0.4 kV transformers to feed separate systems
Filters on the Machine network of all LHC experiments
25/10/2011 ESE seminar
W.Iwanski 8
• Supplying network at CERN
• Power quality• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 9
Quality of power supply at CERN(Extract from the document LHC-EM-ES-0001 rev 2.0)
25/10/2011 ESE seminar
W.Iwanski 10
P(active)
P
P … active Power
Q(reactive)
Q
Q … reactive Power
S
S … apparent Power
S
Phasor Diagram Real Life
without SVC
What is reactive power?
Source: K.Kahle
25/10/2011 ESE seminar
W.Iwanski 11
P(active)
P
P … active Power
Q(reactive)
Q
Q … reactive Power
S’
S … apparent Power
S
Phasor Diagram Real Life
with SVC
What is reactive power?
Source: K.Kahle
-QSVC
25/10/2011 ESE seminar
W.Iwanski 12
F2 F3 F5TCR F7 F11 F13 HF1 HF2Pulsating
TransformerEHT2
EMD2/BE 18 kV
Load
reactive power
50% SPS
TCR
150 Mvar
filters
-130 Mvar
SPS mains
90 Mvar
Reactive power compensation
Source: K.Kahle
25/10/2011 ESE seminar
W.Iwanski 13
Reactive power taken from EDF is almost zero!
Reactive power consumed by SPS Mains
Reactive power generated by SVC
Reactive power compensation
Source: K.Kahle
25/10/2011 ESE seminar
W.Iwanski 14
TCR for PSB
Reactive power compensation• Up to 130 MVAr at LHC
Filtering of harmonic distortions• SPS: 20% --> 0.5%
Voltage stabilization• SPS: 14% --> 0.75%
…. But when being energized, they generate fast transient on the powering network• Turning them ON is
coordinated by the CCC with experiments
Benefits of having the Static Var Compensators
25/10/2011 ESE seminar
W.Iwanski 15
20 30 40 50 60 70 80 90 100 110
-45%
-40%
-35%
-30%
-25%
-20%
-15%
-10%
-5%
0%
Voltage variations vs. Length of events
20102011
Temps (ms)
Varia
tion
Operating conditions
Perturbations on powering grid recorded at CERN
Source: D.Arnoult
25/10/2011 ESE seminar
W.Iwanski 16
Power Quality Monitor
PQM monitors state of the filters in the experiment’s zone as well as on the LHC loop
It spies on alarms from the analyzers recording events happening on the 18 kV Machine and GS LHC loop networks
PQM is ready to monitor signals from local analyzers to be connected to register events on selected 400 V branches
Acknowledgeable alarms are launched on the Alarm screen in the Control Room whenever supervised equipment changes its state
Applications developed for the moment for Atlas and Alice experiments.
ALICE Power Quality Monitor synoptic view
ATLAS Power Quality Monitor synoptic view
25/10/2011 ESE seminar
W.Iwanski 17
• Supplying network at CERN• Power quality
• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 18
Auto-transfer
Source: G.Cumer/F.Duval
Auto-transfer process managed by the controllers of the bus-bars BE9, SEM12 and ME9 during the Major Event of 07/2011
25/10/2011 ESE seminar
W.Iwanski 19
Auto-transfer
Source: G.Cumer/F.Duval
Auto-transfer process managed by the controllers of the bus-bars BE9, SEM12 and ME9 during the Major Event of 07/2011
Loss of supply for the GS Network
25/10/2011 ESE seminar
W.Iwanski 20
Auto-transfer
Source: G.Cumer/F.Duval
Auto-transfer process managed by the controllers of the bus-bars BE9, SEM12 and ME9 during the Major Event of 07/2011
Attempt to re-feed the GS from the Meyrin side
25/10/2011 ESE seminar
W.Iwanski 21
Auto-transfer
Source: G.Cumer/F.Duval
Auto-transfer process managed by the controllers of the bus-bars BE9, SEM12 and ME9 during the Major Event of 07/2011
Loss of Meyrin supply due to inrush current
25/10/2011 ESE seminar
W.Iwanski 22
Auto-transfer
Source: G.Cumer/F.Duval
Meyrin side re-powered from the Swiss supplier
Auto-transfer process managed by the controllers of the bus-bars BE9, SEM12 and ME9 during the Major Event of 07/2011
25/10/2011 ESE seminar
W.Iwanski 23
Redundancy of supply: Re-powering
Re-powering is used at different levels of hierarchy to provide an alternative source of power in case of a failure or a maintenance up-stream
Typically, the re-powering is taken from the general service network
25/10/2011 ESE seminar
W.Iwanski 24
Redundancy of supply: Doubled systems
Source: B.Saint-Sulpice
Additional transformer provides power from other network, following switchboards re-power each other
Redundant compressors are fed from different networks
Modifications of supply of the Cryogenic system in Atlas after the major event in 07/2011
25/10/2011 ESE seminar
W.Iwanski 25
• Supplying network at CERN• Power quality• Redundancy of supply
• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 26
AUG
Daisy-chain of AUG sensors in particular zone
Cut of supply in the zone at the level of 18/0.4 kV transformer
Supervision by ENEL SCADA
Generation of L3 alarms
Interface to DSS of experiments
25/10/2011 ESE seminar
W.Iwanski 27
Types of supply
See mains perturbations ?
Switched off by AUG ?
Back up by Diesel set ?
Downtime ?
Normal EBD Yes Yes No
YesMains downtime
Normal EXD Yes Yes or No* Yes* or No
YesMains downtime
Assured EAD Yes Yes Yes
Yes30s to 90s
SafetyESD Yes No Yes
Yes30s to 90s
UPSEOD No Yes or No Yes or No
NoBattery autonomy :
10min to 2h
48 VDCECD No No Yes
NoBattery autonomy :
2h to 3h
* Cas unique EXD4/15A
Levels of availability of electrical supply
25/10/2011 ESE seminar
W.Iwanski 28
Diesel supply
Supply of safety installations• Elevators• AUG• Anti-panic lighting• Ventilation• Back-up of 48 VDC supply• …
Back-up of UPS installations
Detector-specific installations which shall provide power in emergency cases (fed from experiment Diesel generators)• Magnet Heaters in Atlas• Chillers of the
Thermosiphon in Atlas
Diesel generator Normal supply
Safe power: Normal supply when power is ON or Diesel power during a power cut. There is always a short voltage loss before Diesel starts feeding the network
25/10/2011 ESE seminar
W.Iwanski 29
UPS with a little autonomy
UPS and the by-pass are fed from the normal network
Double AC/DC DC/AC conversion + batteries are used for filtering perturbations on the mains.
Autonomy of UPS is not important but is long enough to be able to shut down equipment fed from the UPS in case of a power cut.
25/10/2011 ESE seminar
W.Iwanski 30
UPS with a significant autonomy
UPS and the by-pass are fed from the normal network
During a power cut the UPS power is available as long as batteries allow (typically not longer than 2 hours)
25/10/2011 ESE seminar
W.Iwanski 31
UPS with a Diesel back-up
EBD1/15
UPS is fed from the safe network while the by-pass from the normal network
During a power cut, safe network is fed from Diesel which practically assures unlimited UPS power availability
25/10/2011 ESE seminar
W.Iwanski 32
Redundant UPS with a significant autonomy + Diesel back-up + power management
UPS is fed from the safety network while the by-pass fed from the normal network
Redundant UPS increases power availability and is convenient for long operation
During a power cut, safety network is fed from Diesel which practically assures unlimited UPS power availability
In case of a power cut and the Diesel failure, a PLC manages autonomy of the UPS by cutting less important users after 10 min
25/10/2011 ESE seminar
W.Iwanski 33
• Supplying network at CERN• Power quality• Redundancy of supply• Power availability
• Monitoring and control of electrical infrastructure
• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 34
9
Global view of electrical SCADA system
Source: S.Infante
25/10/2011 ESE seminar
Drawer number 2
HMIDCS
ModBus/TCP/IP
ModBus/JBus
DIRIS Drawer number 1
Concentrator Crate Acquisition Crate
ModBus/JBus
ENS
S SS
HMIDCS
RACK
Concentrator Crate
ModBus/JBus
ENS
TWIDO
Distribution chassis
ModBus/JBus
ModBus/TCP/IP
ATLAS/CMSALICE/LHCb
Supervision and control architecture in experiments
Source: S.Infante
25/10/2011 ESE seminar W.Iwanski 35
W.Iwanski 36
Basic infrastructure for controlling and monitoring
Rack’s supplying box Concentrating PLC
Expert panel
Concentrating PLC makes state of the system available to the supervising database (CCC) and user application (DCS)
Concentrating PLC communicates with the local PLCs in supplying boxes/cabinets (ATLAS/CMS) or reads state of powering drawers (ALICE/LHCb)
Local PLCs execute ON/OFF commands on powering breakers and monitor their state (opened/closed/tripped)
LHC Control Room (CCC)
Experiment’s Control Room
Powering drawers
25/10/2011 ESE seminar
W.Iwanski 37
Rack Control applications
PLC in the supplying box above the rack allows for monitoring of local breakers in the repartition box (ATLAS/CMS)
25/10/2011 ESE seminar
W.Iwanski 38
Rack Control applications
One supplying drawer brings power to few racks. No monitoring is possible of power distribution inside the rack (ALICE/LHCb)
25/10/2011 ESE seminar
W.Iwanski 39
Control of supply of computers
Powering of 30-40 computers installed in one rack requires special attention:
Six AC Smart Start modules controlled via Ethernet provide staggered start-up of 12 blocks of 4 outlets (ALICE, 6 racks of that kind)
Two breakers controlled by the PLC via Ethernet feed two powering lines having NTC thermistors on each phase (ATLAS, ~100 racks of that kind
25/10/2011 ESE seminar
W.Iwanski 40
Electricity Distribution Monitor
Simple but very reliable system, used for monitoring of the electrical infrastructure
Shows status of all electrical supplying cabinets important for experiment
System based on voltage presence sensors being read by the ELMB card interfaced to a local DCS station
Application developed by Atlas and integrated with the global monitoring environment of the experiment
25/10/2011 ESE seminar
W.Iwanski 41
• Supplying network at CERN• Power quality• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure
• Operation • Summary
25/10/2011 ESE seminar
W.Iwanski 42
Testing and maintenance of electrical infrastructure
In order to keep operability, regular testing of active components is required. Possibly in nominal conditions• Monthly testing of Diesel generators• Yearly testing of the Auto-transfer
Nominal conditions are not easy to achieve as experiment equipment typically is preventively switched off to avoid unnecessary losses. This does not help to tune settings of the protective circuits (see Major Event of 07/2011)
Periodic maintenance is planned typically for the LHC shut-down periods• UPS: every year
Redundancy of the UPS allows to keep the UPS supply running• Diesels: every year• Switchboards: every 5 years• Transformers: every 3 years
25/10/2011 ESE seminar
W.Iwanski 43
Lessons learnt from the Major Events
Many UPSs ran out of batteries before the GS network came back. It can happen but it’s not comfortable situation when supervising systems fed from the GS network via UPS are not running anymore while supervised electronics fed from the Machine network is working fine.• Either to move supply of UPS from the GS network to the Machine one
or supply UPS from both networks Atlas lost big volume of Helium when long cut on the GS
network caused stoppage of the cooling, the Shield compressors and 400 V distribution for the Cryo services for long• Redundant Shield compressors to be fed from the GS and Machine
networks• Additional transformer fed from the Machine network to provide
redundant supply for 400 V distribution of the Cryo services
25/10/2011 ESE seminar
W.Iwanski 44
Summary
Monitoring and control of the electrical infrastructure are key elements to provide efficient operation
Despite being in operation since several years, the electrical infrastructure is still evolving. Consolidation work is in progress
While the robustness of power supply assures quick recovery from crisis situations, the regular maintenance and testing guarantees long operability
25/10/2011 ESE seminar
W.Iwanski 45
• Supplying network at CERN• Power quality• Redundancy of supply• Power availability• Monitoring and control of electrical infrastructure• Operation • Summary
Thank you for your attention !
25/10/2011 ESE seminar
W.Iwanski 46
Supporting slides
25/10/2011 ESE seminar
W.Iwanski 47
Power delivered to the LHC experiments during operation
ALICE ATLAS CMS LHCb0
2
4
6
8
10
12
14
16
18
2018.2
7.7 7.6
17.6
0.11 0.170.88
0.10.52 0.42 0.5 0.4
Regular power [MW] UPS power [MW] Diesel power [MW]
25/10/2011 ESE seminar
W.Iwanski 48
Active and reactive power consumed from the CERN network
Power converters
Cryogenics
CV
Experiments
Services
020
4060
80100
120
105
50
37
26
10
91
25
17
12
5
53
43
32
23
9
Active power [MW] Reactive power [MVAr] Apparent power [MVA]
25/10/2011 ESE seminar
W.Iwanski 4925/10/2011 ESE seminar
W.Iwanski 5025/10/2011 ESE seminar
Parent-child architecture for DCS
PLC Concentrator
DCS
ENS
TGBT ABB
Coupler
Coupler
TWIDO PLCTWIDO PLC
RACKS
HM
I
CPU
Coupler
Coupler
Normal distribution
JBus
JBus
Normal distribution
SDX1
1 TGBT – 6 FEEDERS6 DISTR. SWITCHBOARDS – 40 FEEDERS
Source: S.Infante
5125/10/2011 ESE seminar W.Iwanski
PLC Concentrator
DCS
ENS
TGBT ABB
INPU
T
OU
TPUT
RACKS
HM
I
CPU
Coupler
Coupler
Normal distribution
Parent-child architecture for DCS
UX15
INPU
T
OU
TPUT IN
PUT
OU
TPUT
Arrivée
2 TGBT 400V - 10 FEEDERS6 DISTRIBUTION SWITCHBOARDS
Source: S.Infante
5225/10/2011 ESE seminar W.Iwanski