FINANCIAL YEAR
PROJECT NAME PROJECT ACTIVITY (SCOPE AND TARGET AREA)
PROJECT COST (KSHS)
STATUS REMARKS
2013/14 AIC Eldama Ravine Health Center
Completion of the dispensary admission wing-plastering, ceiling, floor, ablution block, verandah etc
1,000,000 Complete
2013/14 Bondeni Village Water Project
Piping of water to Bondeni village and its environs
100,000 Complete This was emergency funding FY 2013/2014
2013/14 Eldama Ravine Girls High School
Construction of dormitory-walling and roofing
1,700,000 Ongoing
2013/14 Eldama Ravine Girls High School
Construction of 6-door toilets 350,000 Complete This was a reallocation from sports-250,000 and Kapchebokel ECD-100,000 approved vide CDF Board letter dated July, 4, 2014 and referenced CDF BOARD/ELDAMA RAVINE/VOL.1/14
2013/14 Eldama Ravine Town Modern Public Toilet
Connection of power, and water to the facility
100,000 Complete Toilet complete and handed over the Baringo County Government
ELDAMA RAVINE NG-CDFPROJECT IMPLRMENTATION STATUS AS AT MAY 2016
2013/14 Kamelilo Kware Water Project
Purchase of pipes anf fittings to reticulate water to main tank funded by CDF
500,000 Complete
2013/14 Kamelilo Youth Polytechnic
Construction of two classrooms 1,000,000 Complete PMC constructed one big workshop. This was a reallocation from sports-250,000 and St Patricks Shimoni (Proposed) Sec-750,000 approved vide CDF Board letter dated July, 4, 2014 and referenced CDF BOARD/ELDAMA RAVINE/VOL.1/14
2013/14 Milimani Nubian ECD
Completion of classroom-plastering, painting an other finishing works
200,000 Complete This was emergency funding FY 2013/2014
2013/14 St. Patricks Shimoni (Proposed) Secondary School
Construction of 1No classroom and toilets in the proposed school
NIL Reallocated
Funds Reallocated and Approved Vide CDFB letter dated July 4, 2014 and referenced CDF BOARD/ELDAMA RAVINE/VOL.1/14
2013/14 Kabimoi High School Construction of destroyed dormitory roof and walls
365,000 Complete This was emergency funding FY 2013/2014
2013/14 Kasoe Water Project Construction of masonry tank (100 cubic meters)
800,000 Ongoing PMC requested the funding to be used for purchase of pipes. Tank funded by Baringo County Government
2013/14 Kimamoi Primary School
Construction of 8 door toilets 400,000 Ongoing
2013/14 Benonin Secondary School
Construction of new administration block
1,000,000 Ongoing CDFC to assess the project for value for money
2013/14 Kabiyet Dispensary Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
NIL Reallocated
These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Mochongoi Primary School
Completion of 3 classrooms-Plastering, painting, floor and other finishing works
450,000 Ongoing
2013/14 Mochongoi Water Project
Construction of masonry tank and rehabilitation of Narasura pipeline
1,000,000 Complete Meeting with project stakeholders held on 10th October 2014 t resolved pending issues and agreed a tank of 75 m3 be constructed. Pipeline renovations also done
2013/14 Tabare Cattle Dip Crush construction and fencing 50,000 Complete
2013/14 Uhuru High School Kabiyet
Completion of the laboratory-plastering, painting, floor works, gas chambers and other fittings
400,000 Complete Project officially opened on 19th September 2014
2013/14 Chemelil ECD Construction of 1 No new classroom
400,000 Ongoing Require more funds for completion. There was evident value for money in the project
2013/14 Kabulkulet Water Project
Renovations of leaking roof 300,000 Complete This was emergency funding FY 2013/2014
2013/14 Kiplombe Kaplesir Water Project
Repair of pipeline and fittings 150,000 Complete This was emergency funding FY 2013/2014
2013/14 Kiplombe Secondary School
Completion of dormitory-plasetering floor, walls, ceiling, painting, window glasses and other finishing works
500,000 Complete
2013/14 Kokorwonin Primary School
Completion of 2No Classroom-cementing floor, plastering walls, fixing windows and doors, painting etc
250,000 Complete Project completed, commissioned and in use
2013/14 Muserechi Secondary School
Construction of 1No new classroom
500,000 Complete Classroom complete. Close monitoring and evaluation to be done
2013/14 Nakurtakwei Dispensary
Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
NIL Reallocated
These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Nakurtakwei Primary School
Construction of 1No new Classroom
500,000 Ongoing Funds for completion needed
2013/14 Posta Kaplesir Water Project
Purchase of pipes for reticulation of water from Kaplesir Water Project
500,000 Ongoing Merger with Oinoptich water project agreed
2013/14 Kabor Primary School
Construction of 1No new Classroom
500,000 Ongoing Funds to be used to construct administration block. CDFC to assess for value for money
2013/14 Kiptuno Secondary School
Construction of 1No new classroom
500,000 Ongoing Project complaints resolved and new PMC requested CDFC to use the funds for completion of 2No classrooms and construction of toilets. The school require more funding to construct classrooms and administration block
2013/14 Kewangoi Primary School
Completion of 1No classroom from lintel level-Roofing, plastering, fixing doors and windows, painting and othe completion works
250,000 Complete
2013/14 Kipkuyang Secondary School
Completion of laboratory-plastering, painting, floor, veranda, gas chambers, fitting sinks etc
500,000 Complete
2013/14 Lalut Primary School Completion of 2No Classrooms-Plastering, fixtures and fittings, painting etc
300,000 Complete
2013/14 Sigoro Secondary School
Completion of laboratory and attached offices-plastering, ceiling, painting, floor, verandah etc
800,000 Complete Laboratory officially opened on 19th September 2014 by MP
2013/14 Arama Health Centre
Completion of maternity wing-plastering, floor, walls, ceiling, doors, windows, painting and other finishing works
800,000 Ongoing Funding for external works and finishes allocated
2013/14 Arama Secondary School
Completion of dormitory-plasetering, painting, fixing toilets, plumbing and other finishing works
400,000 Complete This was a reallocation from Tulwob Kosom Bridge-228,485 and Sports-400,000 approved vide CDF Board letter dated July, 4, 2014 and referenced CDF BOARD/ELDAMA RAVINE/VOL.1/14
2013/14 Kamngoech Primary School
Completion of one classroom from lintel level-roofing, plastering walls and floor, doors and windows, painting etc
250,000 Complete
2013/14 Kapcholoi Dispensary
Partitioning of the dispensary, ceiling and repair of toilets
500,000 Ongoing MOH requested to post nurses and Clinical officer. Funds for toilets and finishing works allocated in FY 2015/2016
2013/14 Kapcholoi Secondary School
Purchase of assorted furniture for the administration block fully funded by CDF
350,000 Complete
2013/14 Metipso Primary School
Completion of 2No Classrooms from lintel level-Roofing, plastering, fixing doors and windows etc
500,000 Complete
2013/14 Siloi ECD Completion of ECD Classroom-plastering, painting, window glasses etc
100,000 Complete
2013/14 Sinonin Dispensary Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
1,457,520 Ongoing These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Sinonin Dispensary Purchase of furniture including chairs, office tables, files and drugs cabinet and examination table
249,466 Complete This was emergency funding FY 2013/2014
2013/14 Sinonin Secondary School
Painting of 2No classrooms and administration block with various offices and staffroom
100,000 Complete This was emergency funding FY 2013/2014
2013/14 Sinonin-Tuikoin Water Project
Complete feasibility study, Environmental Impact Assessment and technical design
300,000 Complete This was emergency funding FY 2013/2014
2013/14 Boito Primary School Cementing of 6 Classrooms floors and verandah
600,000 Ongoing PMC requested to use the funds to construct four classrooms foundation
2013/14 Chemeswon Primary School
Plastering of 1No Classroom and painting of 5 Classsrooms
300,000 Ongoing Complaint on use of funds by PMC received and forwarded to
2013/14 Kirima Primary school
Completion of 1 classroom from lintel level and pay outstanding balance for the purchase of land funded in FY 2011/2012
500,000 Ongoing Land payment completed and conveyancing in process. School require more funds for classrooms
2013/14 Tambarass Primary School
Construction of 1No new classroom
500,000 Ongoing CDFC to undertake close monitoring and evaluation of the project
2013/14 Tinet Health Center Construction of septic tank for the health facility
300,000 Complete PMC to provide returns
2013/14 Tinet Primary School Construction of collapsed boys toilets
150,000 Complete This was emergency funding FY 2013/2014
2013/14 Tinet Water Project Purchase of pipes and fittings to to reticulate water from source to main tank funded by CDF
400,000 Complete Phase completed. Water pumped using hydrum to tank funded by CDF 100m3
2013/14 Blue Gum ECD Completion of ECD Classroom from lintel-roofing, doors and windows, plastering, painting etc
250,000 Ongoing
2013/14 Maji Mazuri Girls Secondary School
Water harvesting, purchase of tanks and construction of pavement for dormitories
500,000 Ongoing To provide returns for funds disbursed
2013/14 Maji Mazuri RC Primary School
Construction of 8 door toilets with reinforced foundation to avoid periodic sinking
400,000 Ongoing Evident case of lack of value for money investigated and audit report avziled. Tendering for the new toilets done by CDFTC
2013/14 Makutano Majimazuri Water Project
Completion of 4 tanks, connection of power and rehabilitation of pump
700,000 Ongoing CDFC closely monitoring project implementation due to lack of transparency by PMC. Project now under devolded functions
2013/14 Makutano Police Station
Connection of power and wiring 100,000 Complete This was emergency funding FY 2013/2014
2013/14 St. Joseph Makutano Primary
Construction of collapsed toilets 150,000 Complete This was emergency funding FY 2013/2014
2013/14 Emkwen Primary School
Construction of 1No new Classroom
500,000 Ongoing Require funds for completion
2013/14 Equator Health Center
Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
NIL Reallocated
These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Equator Primary School
Construction of 1No new Classroom
500,000 Ongoing
2013/14 Kiplongon Primary School
Construction of 8 door toilets with fully reinforced foundations
500,000 Complete Complete and in use. Remainin funds used to commence teachers toilets
2013/14 Mumberes Girls Secondary
Purchase of beds for the CDF funded dormitory
400,000 Complete This was emergency funding FY 2013/2014
2013/14 Mumberes Primary School
Construction of collapsed toilets wall, repair of classroom floor and roof
200,000 Complete This was emergency funding FY 2013/2014
2013/14 Soymining (Proposed) Secondary School
Construction of 1No new classroom
500,000 Ongoing To provide returns for funds disbursed
2013/14 Soymining Secondary School
Completion of classroom 50,000 Complete This was emergency funding FY 2013/2014
2013/14 Perkerra Water Project
Purchase of pipes for distribution of water from main reservoir tank to other tanks in the area
1,000,000 Ongoing
2013/14 Simotwet Secondary School
Construction of 1No new classroom
500,000 Complete Funds used to complete 2No classrooms and construct 2No toilets
2013/14 Toniok Health Center
Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
1,521,665 Complete These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Cheraik Water Project
Purchase of pipes for reticulation of water from the reservoir tank
800,000 Ongoing Require funds for completion
2013/14 Kaimoi Water Project
Construction of big masonry tank and purchase of fittings
2,000,000 Ongoing Funds disbursed towards construction of intake weir and 2No Break Pressure Tanks. Gravity main funded by Ravine Roses and distribution piping funded by CDF and Baringo County Government
2013/14 Saos Primary School Repair of classrooms dilapidated roof
250,000 Ongoing To provide returns for funds disbursed
2013/14 Awee Water Project Completion of tank roof, plastering and fittings
150,000 Ongoing To provide returns for funds disbursed
2013/14 Kirobon Primary School
Construction of collapsed toilets 150,000 Complete This was emergency funding FY 2013/2014
2013/14 Kokwomoi Primary school
Completion of 8No classrooms-plastering, painting, doors, windows, fixtures and fittings and other finishing works
1,000,000 Ongoing Project now roofed and require more funds for doors, windows, plastering, painting, wiring, fixtures and fittings and other finishing works. CDFTC to award full contract to complete this project
2013/14 Lebolos Primary School
Construction of collapsed toilets 150,000 Complete This was emergency funding FY 2013/2014
2013/14 Naitili Primary school
Construction of 1No new classroom
400,000 Ongoing
2013/14 Solian Day (Proposed) Secondary School
Construction of 1No Classroom and toilets for the proposes school
750,000 Complete
2013/14 Bikwen Primary School
Completion of 2No Classrooms from lintel level-Plastering floor and walls, roofing, fixing doors and windows and other works
600,000 Ongoing
2013/14 Emnyunguny ECD Construction of 1No new classroom
500,000 Ongoing
2013/14 Kapchebokel ECD Construction of 1No new classroom
NIL Reallocated
Reallocated vide CDFB letter dated July 4, 2014 to Arama Secondary-400,000 and Eldama Ravine Girls-100,000
2013/14 Torongo Girls Secondary School
Construction of phase 2 of the dormitory
1,000,000 Complete Project commissioned and in use
2013/14 Torongo Primary School
Completion of 3 Classrooms-plastering, painting, doors and windows, verandah and other completion works
450,000 Complete
2013/14 Tugumoi Health Center
Construction of standard design prefabricated houses for health workers to improve accomodation and availability of health workers
1,434,785 Ongoing These funds were allocated as conditional grant for construction of prefabricated health workers houses and used to construct Tugumoi, Sinonin and Toniok Dispensaries after tendering by CDFTC
2013/14 Tugumoi Koibatek Secondary School
Construction of new science laboratory
1,200,000 Ongoing PMC constructed a storeyed building. Ground floor require minor finishing works
2013/14 Tugumoi Youth Polytechnic
Construction of collapsed toilets 150,000 Complete This was emergency funding FY 2013/2014
2013/14 Administration and Recurrent Expenditure
To cater for CDFC allowances, payment of rent, salaries and supporting other administrative programmes in the Constituency
3,792,876 Complete
2013/14 Bursary, Mocks and CATs
To assist bright but needy students in Secondary and Tertiary Institutions from the Constituency through bursary and scholarships awards to enable them pursue their studies in various Institutions of learning across the Country
14,010,822 Complete
2013/14 Bursary, Mocks and CATs
To assist bright but needy students in Secondary and Tertiary Institutions from the Constituency through bursary and scholarships awards to enable them pursue their studies in various Institutions of learning across the Country
300,000 Complete This was emergency funding FY 2013/2014
2013/14 Constituency Development Fund Committee Office
To commence the construction of a CDF Office that shall house the modern Constituency Library facility, Constituency Offices, modern cyber, Uwezo fund Offices, Huduma Office and other critical offices in the Constituency
5,000,000 Ongoing Tendering for designs and construction of phase one done. Project consisting of library and offices ongoing and Project Implementation committee consisting of CDF, Ravine Roses Joint Body, Waitrose Foundation, Baringo County and EREF undertaking monitoring with asistance of project engineers.
2013/14 Constituency Sports Activities
To enable the support of varies sports activities in the constituency including Athletics, Volley Ball and Football through provision of training kits and boots
NIL Reallocated
Funds reallocated to Eldama Ravine Girls-250,000 and Kamelilo Youth Polytechnic-250,000 vide CDFB letter dated July 4, 2014
2013/14 Environment To undertake a feasibility study and technical proposal on the use of biogas, solar and other green energy to reduce environmental degradation
400,000 Pilot boigas project (24M3) complete at Eldama Ravine Girls and testing ongoing. CDFTC set to construct another one.
2013/14 Prefabricated Health Workers Houses
Construction of prefabricated workers houses
68,789 Available Funds remained after tendering for Tugumoi Health Center, Sinonin Health Center and Toniok Health Center
2013/14 Project Technical Designs and Planning
To enable the development of technical designs and Bills of Quantities for construction projects and preparation of Eldama Ravine Constituency water master plan
350,000 Complete Funds utilized for EIA and Payment of NEMA fees and other technical inputs for projects
2013/14 Training, Monitoring and Evaluation
To cater for training of CDFC and PMC members as well as monitoring and evaluation of new and ongoing projects across the Constituency
1,896,438 Complete
67,697,361
FINANCIAL YEAR
PROJECT NAME PROJECT ACTIVITY (SCOPE AND TARGET AREA)
PROJECT COSTS (KSHS)
STATUS REMARKS
Date…………………………………………
2014/15 Constituency Development Fund Office
To continue the construction of phase 2 of a CDF Office that shall house the modern Constituency Library facility, Constituency Offices, modern cyber, Uwezo fund Offices, Huduma Offices and other critical CDF activity related offices in the Constituency
10,000,000 Ongoing Kshs 500,000 balance that was outstanding with CDF Board received and to be released to Project account
2014/15 Eldama Ravine Girls High School
Completion of dormitory-plastering, window glasses, ablution block plastering, doors, floor tiles, outside keying, skirting, ceiling, wiring, painting and other finishing works
3,500,000 Complete work complete and facilty Commisioned and in use
2014/15 Kamelilo Primary School
Construction of pupils toilets 300,000 Complete This was an emergency funding FY 2014/2015. 10 door toilet constructed
2014/15 Koibatek Primary School
Construction of 2No new classrooms from foundation
1,000,000 Complete Project complete and in use. Balance of funds used to construct gate
2014/15 Koibatek Technical Training Institute
To cater for construction of workshop and classrooms for the proposed Koibatek Technical Training Institute co-funded with the Ministry of Education Science and Technology
5,000,000 Ongoing Balance of Kshs 5M allocated in FY 2015/2016 towards completion of the TTI as pledged in CDF cofunding. Facility expected to be ready and opened in January 2015
2014/15 St Patricks Shimoni Primary School
Construction of 2No Classroom from foundation
1,000,000 Complete Project to be commissioned
2014/15 Kabimoi High School
Completion of Administration block funded under the economic stimulus programme-Plastering walls, floor, ceiling, windows and doors, stairs, verandah, painting, outside finishing and other completion works.
2,000,000 Ongoing Project require more funds for completion
2014/15 Kabimoi High School Piping of water to the school 100,000 Funds not yet disbursed
This was an emergency funding FY 2014/2015
2014/15 Kimamoi Primary School
Construction of 1 No classroom from foundation
500,000 Funds not yet disbursed
2014/15 Orongai Cattle Dip Payment for the purchase of land 100,000 Ongoing This was an emergency funding FY 2014/2015. Require more funds for completion of land purchase and conveyancing
2014/15 Sagat Primary School Construction of teachers toilets 100,000 Complete This was an emergency funding FY 2014/2015
2014/15 Tolmo Secondary School
Wiring and connection of power 100,000 Complete This was an emergency funding FY 2014/2015
2014/15 Kabiyet Benonin Water Project
Construction of 100 Cubic Meters masonry tank
1,000,000 Ongoing Project currently at 6 courses. expected to be complete in 21 days
2014/15 Kiplombe Kaplesir Water Project
Construction of 100 Cubic Meters Masonry Tank
1,000,000 Complete Project complete and in use. Balance of funds used to construct water trough
2014/15 Kiplombe Primary school
Renovation of 6No classrooms-Cementing floors, renovation of windows, doors, walls and painting
500,000 Complete
2014/15 Mandina Primary School
Completion of 2 classrooms 200,000 Complete This was an emergency funding FY 2014/2015
2014/15 Muserechi Day Secondary School
Construction of 1No new classroom from foundation
500,000 Ongoing Require more funds to complete the classroom-window glasses, floor, keying and painting
2014/15 Muserechi Primary School
Construction of collapsed toilets 200,000 Ongoing This was an emergency funding FY 2014/2015. Require more funds for completion
2014/15 Muserechi Secondary School
Purchase of lockers and chairs 200,000 Complete This was an emergency funding FY 2014/2015
2014/15 Kipkuyang Primary School
Completion of classrooms-Windows, door, other fixtures, fittings and painting
200,000 Complete
2014/15 Kewangoi Primary School
Construction of new 88-bed dormitory for boys
2,000,000 Ongoing Project currently at lintel level. More funds form
2014/15 Sigoro Secondary School
Construction of 1No new classroom from foundation
500,000 Complete Project complete and commissioned
2014/15 Tamket Primary School
Construction of 2No permanent classrooms from foundation
800,000 Ongoing Finishing works ongoing. Project to be commisioned soon
2014/15 Arama Secondary School
Construction of 120 beds boys dormitory
2,500,000 Ongoing PMC to be asked to expedite construction works
2014/15 Sinonin Health Center
Construction of drugs shelves, cabinets and water harvesting and electricity
195,000 Complete This was an emergency funding FY 2014/2015
2014/15 Sinonin Tuikoin Water Project
Construction of intake and purchase of pipes for reticulation of water this being phase I of the project
7,000,000 Ongoing Funds yet to be disbursed. Tendering for intake weir complete. PMC currently finalizing on statutory compliances required suc h as NEMA, WARMA, KFS, Hydrological Survey and water analysis
2014/15 Sigoro Primary School
Renovation of 3 classrooms 300,000 Complete This was an emergency funding FY 2014/2015
2014/15 Chemeswon Primary School
Construction of 1No new classroom from foundation
500,000 Ongoing Complaint on utilization of funds received and forwarded to SCIO
2014/15 Kirima Primary School
Construction of 1No new classroom from foundation
500,000 Ongoing Project at lintel level. Roofing materials being sourced
2014/15 Tinet Secondary School
Sawing of timber for dormitory 200,000 Ongoing This was an emergency funding FY 2014/2015
2014/15 Maji Mazuri Forest Primary
Completion of ICT center 200,000 Ongoing This was an emergency funding FY 2014/2015. More funds needed
2014/15 Maji Mazuri RC Primary School
Construction of 8 door pupils toilet and completion of 6 door toilet
500,000 Complete This was an emergency funding FY 2014/2015. 8 door toilet complete and in use. Completion of 6 door ongoing
2014/15 St Joseph Makutano Primary School
Completion of toilets 100,000 Complete This was an emergency funding FY 2014/2015
2014/15 St Joseph Makutano Primary School
Construction of 2No classrooms from foundation
1,000,000 Ongoing PMC to provide returns for assessment before more funds are released
2014/15 St. Mary’s Andama Primary School
Construction of 2 classrooms 1,000,000 Ongoing Compeletion works ongoing. Evident value for money on works done
2014/15 Boito Primary School Completion of 4 classrooms-walling, roofing, plastering, fixtures and fittings, painting and other finishing works
1,500,000 Complete Four classrooms constructed and commisioned. PMC have requested for more funds towards payments for works done
2014/15 Emkwen Primary School
Completion of classroom 100,000 Ongoing This was an emergency funding FY 2014/2015
2014/15 Equator Primary School
Construction of collapsed pupils toilets
300,000 Complete This was an emergency funding FY 2014/2015
2014/15 Equator Primary School
Construction of 1No new Classroom from foundation
500,000 Ongoing Monitoring and evaluation to be done
2014/15 Kaprorwa Primary School
Cementing of dilapidated classroom floor
150,000 Complete This was an emergency funding FY 2014/2015
2014/15 Mumberes Water Project
Purchase of pipes for reticulation of water from Equator tank to Kiplongon Tank funded by CDF
2,000,000 Ongoing Piping done. Pump taken for repair. Remaining sections to be completed in FY 2015/2016 and project handed over to County Government
2014/15 Mumberes Secondary School
Purchase of a water purification unit to be a pilot project for secondary schools in the Constituency
1,000,000 Ongoing PMC requested to use the funds to construct a new dormitory. Works done at four courses and more funds allocated in FY 2015/2016
2014/15 Sigowet Primary School
Completion of 1No classroom from lintel level-Roofing, plastering, windows, doors and other finishing works
226,646 complete
2014/15 Soymining Day Secondary School
Construction of 1No Classrooms from foundation
500,000 Complete
2014/15 Soymining Primary School
Construction of pupils toilets 300,000 Complete This was an emergency funding FY 2014/2015
2014/15 Soymining Primary School
Construction 1No new classroom from foundation
500,000 Ongoing
2014/15 Tambarass Primary School
Construction of 1No new classroom from foundation
500,000 Ongoing
2014/15 Projects Technical Input
Environmental Impact Assessment, designs, feasibility study and technical input to projects
400,000 Complete This was an emergency funding FY 2014/2015
2014/15 Simotwet Secondary School
Purchase of chairs and lockers 105,259 Complete This was an emergency funding FY 2014/2015
2014/15 Toniok Girls High School
Completion of dining hall-Walling, cementing floor, doors and windows
1,000,000 Ongoing Project at walling level. Dispute with Contractor resolved and technical input to be adhered to
2014/15 Sabatia Chief's Office Purchase of furniture and erection of uni-huts for the administration police
150,000 Complete This was an emergency funding FY 2014/2015. Require more funds for erection of more unit huts
2014/15 Sabatia Primary School
Completion of dormitory-Roofing, plastering, windows, doors, fixtures and fittings and other finishing works
600,000 Ongoing Require more funds to complete the dormitory
2014/15 Solian Day Secondary School
Construction of 2No new Classrooms from foundation
1,000,000 Ongoing Good worksmanship noted
2014/15 Solian Girls Secondary School
Construction of new science lab from foundation
1,500,000 Ongoing PMC requested to expedite works
2014/15 Tekeltee Water Project
Completion of piping and fitting works
150,000 Complete This was an emergency funding FY 2014/2015
2014/15 Cheptililik Primary School
Completion of 3No new classroom-Plastering, windows, doors, window glasses, verandah and painting
600,000 Ongoing PMC to provide returns for assessment before more funds are released
2014/15 Kaimoi Water Project
Purchase of fittings, repair of Tolmo water tank and piping works
500,000 Complete This was an emergency funding FY 2014/2015
2014/15 Kemtilil Water Project
Construction of intake to reticulate water to Saos/Kibias Location of Eldama Ravine Constituency
500,000 Funds not yet disbursed
PMC requested for change of activity to purchase of pipes. Intake weir funded by County
2014/15 Sagat Secondary School
Construction of new science lab from foundation
1,500,000 Ongoing Monitoring and evaluation to be done
2014/15 Tolmo Primary School
Construction of 1No classroom from foundation
500,000 Ongoing Funds disbursed
2014/15 Tolmo Secondary School
Completion of Administration block-Walling, lintel, and upper floor slab
1,000,000 Ongoing Upper slab finalized. Completions works funded in 2015/2016
2014/15 Lebolos Primary School
Construction of 1No classroom from foundation
500,000 Ongoing Monitoring and evaluation to be done
2014/15 Tarigo Primary School
Cementing of dilapidated classrooms
100,000 Complete This was an emergency funding FY 2014/2015
2014/15 Timboroa Secondary School
Construction of 2No toilets 600,000 Ongoing Monitoring and evaluation to be done
2014/15 Emnyungung Primary School
Completion of classroom 100,000 Funds not yet disbursed
This was an emergency funding FY 2014/2015
2014/15 Kibarassoi Primary School
Construction of teachers toilets 50,000 Complete This was an emergency funding FY 2014/2015
2014/15 Nerkwo Primary School
Cementing destroyed floors of 5No classrooms in the school
400,000 Complete
2014/15 Torongo Girls Secondary
Completion of dormitory ablution block-plastering, floor, fixtures and fittings and purchase stand by 30KVA generator
2,000,000 Ongoing 30KVA Generator purchased from Rift Valley Machinery Services in use, Dormitory complete
2014/15 Torongo Primary School
Construction of dilapidated boys toilets
200,000 Complete This was an emergency funding FY 2014/2015
2014/15 Mwachon Primary School
Construction of ICT Centre (1,500,000) and plastering, floor, walls, keying, painting and other finishing works of classroom (250,000)
1,750,000 Ongoing Classrooms complete. ICT center to be completed with funds in FY 2015/2016
2014/15 Tugumoi Koibatek Secondary School
Construction of new science laboratory-walling, upper floor slab, doors and windows
1,500,000 Ongoing More funds needed for finishing works
2014/15 Tugumoi Primary School
Rehabilitation 3No Classrooms-Cementing floor and dwarf walls, renovation of walls and roof
837,931 Ongoing One clasroom complete, the other at lintel level more funds to complete the classroom
2014/15 Constituency Strategic Plan
To cater for the development of a five year strategic plan to guide the CDF Committee and Constituency in projects planning, identification, prioritization and funding for equitable growth and development
1,000,000 Ongoing Strategic plan data collected and analyzed. Plan ongoing and stakeholders meeting to be connvened to deliberate and approve the plans
2014/15 Committee Expenses Payment of Committee sitting allowances, transport, conferences
1,807,800 Complete
2014/15 Employees Salaries Payment of staff salaries 1,582,623 Complete2014/15 Goods and Services Purchase of fuel, repairs and
maintenance, printing, stationery, telephone, travel and subsistence, office tea, etc.
1,546,160 Complete
2014/15 NHIF Payment of NSSF Deductions 30,000 Complete
2014/15 NSSF Payment of NSSF Deductions 30,000 Complete
2014/15 Purchase of 1No Computer and creation of Website
Purchase of 1 CDF Lap top computer and development of Constituency website
500,000 Complete
2014/15 Purchase of Furniture/equipments
Purchase of furniture and office equipment
300,000 Complete
2014/15 Bursary Secondary Schools
To assist bright but needy students from the Constituency in secondary schools through bursary support
4,200,000 Complete Funds disbursed to vetted students in secondary and tertiary institutions
2014/15 Bursary Special Schools
To assist students from the Constituency in special schools through bursary support
400,000 Complete Funds utilized
2014/15 Bursary Tertiary Schools
To assist bright but needy students from the Constituency in colleges and universities through bursary support
11,000,000 Complete Funds disbursed to vetted students in secondary and tertiary institutions
2014/15 Mocks and Continuous Assessment Tests
To cater for Mock and Continuous Assessment Test for Primary and Secondary Schools in the Constituency
400,000 Complete Funds disbursed for assessment test for secondary and primary
2014/15 Constituency Environment Activities
To cater for installation of biogas green energy units in 3 Secondary Schools (Baringo High School , Solian Girls High School, Poror High School) and tree planting to reduce environmental degradation in the Constituency
500,000 Funds not yet disbursed
Funding to be used to consytruct another biogas unit and supply tree seedlings to schools
2014/15 CDFC/PMC Capacity Building
Undertake Training of the PMCs/CDFCs on CDF Related issues
898,290 Complete
2014/15 Committee Expenses Payment of Committee sitting allowances, transport, conferences
1,000,000 Complete
2014/15 Goods and Services Purchase of fuel, repairs and maintenance, printing, stationery, Airtime, travel and subsistence, etc
1,000,000 Complete
2014/15 Athletics Kenya Koibatek Sub Branch
Towards purchase of training kits (Branded track suits and spikes) to Eldama Ravine Athletics Club in the Constituency
150,000 Complete
2014/15 Football Kenya Federation Koibatek Sub Branch
Towards purchase of training kits (Branded jerseys, balls and boots) for teams in the provincial league each Kshs 31,250 (Poror Mote FC, Kapcholoi FC) and County League (Solian FC, Lebolos FC, Kabimoi FC, Maji Mazuri FC, Messegon FC, Toniok FC)
250,000 Complete
2014/15 Kenya Volleyball Federation Koibatek Sub Branch
Towards purchase of training kits (Branded jerseys, nets and sports shoes) to Eldama Ravine Volleyball Club in the Constituency
100,000 Complete
96,609,709 FINANCIAL
YEARPROJECT NAME PROJECT ACTIVITY (SCOPE AND
TARGET AREA) PROJECT COSTS
(KSHS) STATUS REMARKS
2015/16 Employees Salaries Payment of staff salaries and staff gratuity
2,038,377 Ongoing
2015/16 Goods and Services Purchase of furniture, laptop, fuel, repairs and maintenance, printing, stationery, telephone, travel and subsistence, office tea, etc.
1,869,059 Ongoing
2015/16 NSSF Payment of NSSF Deductions 30,000 Ongoing
2015/16 NHIF Payment of NSSF Deductions 45,000 Ongoing
2015/16 Committee Expenses Payment of Committee sitting allowances, transport, conferences
2,154,800 Ongoing
2015/16 5% Emergency Fund To cater for various emergency interventions that shall arise during the Financial Year 2015/2016 in the Constituency that are allowable in the CDF Act.
5,767,647 Ongoing
Funds not yet received2015/16 Bursary Secondary
SchoolsTo assist bright but needy students from the Constituency in secondary schools through bursary support
5,000,000 Ongoing
Cheques Released2015/16 Bursary Tertiary
SchoolsTo assist bright but needy students from the Constituency in colleges and universities through bursary support
10,000,000 Ongoing
Cheques Released2015/16 Mocks and
Continuous Assessment Tests
To cater for Mock and Continuous Assessment Test for Primary and Secondary Schools in the Constituency
300,000 Ongoing
2015/16 Bursary Special Schools
To assist students from the Constituency in special schools through bursary support
700,000 Ongoing
2015/16 Kapcholoi Dispensary
Finishing works-fixing of drug shelves, painting, wiring and connection of power
500,000 Ongoing
Project completion works ongoing before handover
2015/16 Arama Health Center
Completion of maternity wing-veranda, painting, external pavement and other finishing works
500,000 Ongoing
Project completion works ongoing before handover
2015/16 Omoja Lelechwa Community Road
Opening up of the road connecting Kaplelechwa to KCC and Eldama Ravine town approximately 1KM
400,000 New
Funds not yet received2015/16 Esageri Sagat Road Opening up of the road
connecting Esageri and orongai area approximately 5KM
500,000 New
Funds not yet received2015/16 Sabatia Primary
SchoolCompletion of dormitory-Wiring, Painting, ablution block, purchase of 60No beds and renovation of existing dormitory
1,500,000 Ongoing
Funds not yet received2015/16 Tolmo Primary
SchoolConstruction of 4No classrooms rom foundation slab-walling, roofing, plastering and other finishing works
2,000,000 Ongoing
Kshs 1M disbursed to the Institution. Balance awaited from NGCDFB
2015/16 Tugumoi Primary School
Completion of 1No classrooms from lintel level-Walling, roofing, plastering, cementing floors, doors and windows, keying and other finishing works
400,000 Ongoing
Funds not yet received2015/16 Kewangoi Primary
SchoolCompletion of dormitory from window level-walling, roofing, plastering, external works and other finishing works
2,000,000 Ongoing
Funds not yet received
2015/16 Mwachon Primary School
Completion of the ICT Center-flooring, walls, external keying, painting, plumbing, wiring and other finishing works
2,000,000 Ongoing
Require more funds for completion works
2015/16 Tiripkatoi Primary School
Completion of 2No Classrooms-flooring, wall plastering, fixing windows, doors, keying and other external works
500,000 Ongoing
Funds not yet received2015/16 Nyakio Primary
SchoolCompletion of administration block-walling, roofing, plastering floors and windows and other finishing works
800,000 Ongoing
Funds not yet received2015/16 Kokwomoi Primary
schoolCompletion of 8No classrooms and offices done using interlocking blocks-plastering, doors, windows and window glasses, stair cases, fixtures and fittings, external works and other finishing works
3,000,000 Ongoing
Project assessment and preparation of tender documents ongoing. Funds not yet received
2015/16 Naitili Primary school
Completion of 1No classroom from window level-Roofing, plastering, windows, doors and other finishing works
300,000 Ongoing
Funds not yet received2015/16 Nakurtakwei
Primary SchoolCompletion of 6 No classrooms-Window glasses, floor, painting, keying, verandah and minor finishing works
300,000 Ongoing
Funds not yet received
2015/16 Kabor Primary School
Completion of administration block from lintel level-roofing, doors and windows, cementing of floors and painting
500,000 Ongoing
Funds not yet received2015/16 Kapkitet Primary
SchoolCompletion of 2No Classrooms-verandah, fixing of window glasses and doors, partitioning wall etc
200,000 Ongoing
Funds not yet received2015/16 Igure Primary School Construction of 1No new
classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Tulwomoi Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Kokorwonin Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Kipkaber Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Soibei Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Kamngoech Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Ngarie Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Kipkoriony Primary
SchoolConstruction of 1No new classroom from foundation using labor based contract
550,000 New
Funds not yet received2015/16 Toniok Girls High
SchoolCompletion of dining hall-Walling, cementing floor, doors and windows
1,000,000 Ongoing
Funds not yet received
2015/16 Tugumoi Koibatek Secondary School
Completion of science lab-Painting, window glasses, floor and other finishing works
500,000 Ongoing
Equipment suplied by Safaricom Ltd
2015/16 Tolmo Secondary School
Completion of Administration block-Plastering, windows and doors, painting, fixtures and fittings
800,000 Ongoing
Require more funds for completion works
2015/16 Kabimoi High School
Completion of Administration block-Plaster upper floor-Plastering walls, floor, ceiling, windows and doors, stairs, verandah, painting, outside finishing and other completion works.
500,000 Ongoing
This administration block was commenced during the Economic Stimulus Programme Funding. The project shall be officially opened in April 2016
2015/16 Sagat Secondary School
Completion of laboratory-roofing, plastering, painting, doors and windows and other finishing works
500,000 Ongoing
Completion works ongoing2015/16 Mumberes
Secondary SchoolConstruction of dormitory-Walling and roofing
2,000,000 OngoingFunds not yet received
2015/16 Soymining Day Secondary School
Completion of laboratory cofunded by PTA funds
1,000,000 NewCompletion works ongoing
2015/16 Torongo Girls Secondary
Cofund the the purchase of the school bus 51 seater
2,000,000 New
Funds not yet received2015/16 Benonin Secondary
SchoolCompletion of administration block-walling, roofing, plastering floors and windows and other finishing works
2,000,000 Ongoing
Funds not yet received
2015/16 Baringo High School Cofunding the purchase of a 767 seater school bus
4,000,000 New
Funds not yet received2015/16 Lebolos Secondary
School Completion of 5No Classrooms funded by CDF-Cementing floors and walls, painting , external finishes and other works
500,000 Ongoing
Funds not yet received2015/16 Highlands Mixed
Secondary SchoolCompletion of laboratory-plastering, painting, doors and windows, gas chamber, plumbing, wiring and other finishing works
800,000 Ongoing
Completion works ongoing2015/16 Tinet Day Secondary
SchoolCompletion of laboratory-plastering, painting, doors and windows, gas chamber, plumbing, wiring and other finishing works
800,000 Ongoing
Completion works ongoing2015/16 Maji Mazuri Mixed
Secondary SchoolConstruction of a science laboratory-foundation and walling
1,500,000 Ongoing
Funds not yet received2015/16 St. Mary’s Boito
Secondary SchoolCompletion of 1No classroom and construction of another 1No new standard classroom
800,000 Ongoing
Funds not yet received2015/16 Kapcholoi Secondary
SchoolConstruction of gas chambers and ceiling for the CDF funde laboratory
300,000 Ongoing
Completion works ongoing2015/16 Sabatia Secondary
SchoolConstruction of dining hall-Walling and roofing
1,000,000 Ongoing
Funds not yet received2015/16 Koibatek Technical
Training InstituteTo cater for construction of workshop and classrooms for the proposed Koibatek Technical Training Institute co-funded with the Ministry of Education Science and Technology
5,000,000 Ongoing
Project cofunded with the Ministry of Education of Science and Technology. To be opened in September 2016
2015/16 Tugumoi Youth Polytechnic
Completion of tuition block-plastering walls, doors, windows, floor, external works, painting etc
200,000 Ongoing
Funds not yet received2015/16 Mumberes Water
ProjectPurchase of pipes for distribution of water approximately 12KM to Kaptembwo, Kirima, Lelgel and sorrounding areas
2,700,000 Ongoing
Completion works ongoing2015/16 Sinonin Tuikoin
Water ProjectPurchase of pipes aapproximately 6KM and land for tank as well as construction of 200cubic meter masonry tank this being phase 2 of the project
2,000,000 Ongoing
Project intake weir and procurement of pipes ongoing
2015/16 Kiplombe Kaplesir Water Project
Construction of 100 Cubic Meters Masonry Tank and purchase of pipes for the project at Orinie area approximately 5.5KM
1,750,000 Ongoing
Tank complete. Awaiting defects liability period and handover
2015/16 Cheraik Water Project
Purchase of pipes for reticulation of water from the reservoir tank approximately 3KM
300,000 Ongoing
Funds not yet disbursed to PMC
2015/16 Perkerra Water Project
Purchase of pipes for distribution of water from main reservoir tank to other tanks in the area approximately 4.1KM
600,000 Ongoing
Completion works ongoing2015/16 Timboroa Water
ProjectPurchase of pipes for reticulation of water from the reservoir tank approximately 3KM
300,000 Ongoing
Completion works ongoing
2015/16 Bondeni Community Water Project
Purchase of pipes and fittings for distribution of water to bondeni and huruma areas approximately 4KM
400,000 Ongoing
Completion works ongoing2015/16 Ngendui Water
ProjectPurchase of pipes and fittings for distribution of water to tumon and kisarget areas approximately 1.5KM
150,000 Ongoing
Completion works ongoing2015/16 Eldama Ravine
Chief's OfficeConstruction of a chief's Office 791,051 New
Funds not yet received2015/16 Constituency
Strategic PlanTo cater for the finalization of five year strategic plan including final stakeholders meetings and printing
1,000,000 Ongoing
Preparation of strategic plan 2016-2020 ongoing
2015/16 Constituency Environment Activities
To cater for installation of biogas green energy unit in Poror Secondary School and tree planting to reduce environmental degradation in the Constituency
411,364 Ongoing
2015/16 Goods and Services Purchase of fuel, repairs and maintenance, printing, stationery, Airtime, travel and subsistence, etc
1,100,000 Ongoing
2015/16 Committee Expenses Payment of Committee allowances, transport, conferences
1,100,000 Ongoing
2015/16 CDFC/PMC Capacity Building
Undertake Training of the PMCs/CDFCs on CDF Related issues
868,618 Ongoing
2015/16 Constituency Sports Tournament
Carry out Constituency Sports tournament and the winning teams/schools to be awarded with trophies, balls, and games kits
411,364 Ongoing
Funds not yet received2015/16 Constituency
Development Fund Office
To continue the construction of phase 2 of a CDF Office that shall house the modern Constituency Library facility, Constituency Offices, modern cyber, Uwezo fund Offices, Huduma Offices and other critical CDF activity related offices in the Constituency
15,000,000 Ongoing
Phase one expected to be complete by May 2016 for phase two to commence
2015/16 Audit Fee To cater for the audit of Constitutuency Development Funds during the financial year
500,000 Ongoing
Funds not yet received. This funds shall be reallocated to another project
Total (Kshs) 102,287,280