EGLINTON CROSSTOWN Eglinton-Mount Pleasant March 13, 2018
2
INFORMATION IS CURRENT AS OF MARCH 13, 2018 AND SUBJECT TO CHANGE
3
Agenda
• Eglinton Station Update • Mount Pleasant Station Update
4
Eglinton Station Update
5
Eglinton Station Update
Recently Completed • First three weekends of TTC subway closure works at Berwick Avenue
Ongoing • Shoring on and west of Yonge Street, north and south side of Eglinton • THESL 2B – Hillsdale (partially complete), Yonge (ongoing)
Upcoming • Traffic shift for shoring on the north side of Eglinton Avenue, east of Yonge Street (20-40
Eglinton East) – March 13th • Water site service connections proposed overnight on Eglinton east of Yonge –
tentatively March 15th for 2-3 nights (20-50 Eglinton East affected by water shut off) • Toronto Hydro relocation 2A
– Eglinton Avenue East, Dunfield Avenue, Holly Avenue
• Weekend subway closures for TTC upgrades – May 19/20 is the next weekend closure; another public meeting will be arranged for April
• Shoring on the north side of Eglinton Avenue, west of Yonge Street
6
Next Phase of Shoring – March 13th
7
THESL Relocation 2A – March/April
8
Next Phase of Shoring – April/May
9
Mount Pleasant Station Update
10
Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROXIMATE DURATION
WINTER/SPRING 2018
Support of Excavation (Piling) North side of Eglinton Ave E Ongoing through March 2018
Storm Sewer Installation – Stage 1 Taunton Road and Eglinton Ave E Week of March 12 for three (3) weeks
Pedestrian Rerouting SW sidewalk at Mt. Pleasant Rd and Eglinton Ave E (Brownlow Ave site) As early as March 19, 2018
Storm Sewer Installation – Stage 2 Brownlow Ave and Eglinton Ave E Week of March 26 for two (2) weeks
Traffic Change See map Early April 2018
Traffic Change See map Early May 2018
11
Current Construction Staging
Until April 2018
12
Pedestrian Rerouting
Beginning as early as March 19, 2018
STORM SEWER SITE
STORM SEWER SITE
13
Upcoming Construction Staging
Beginning early April for approximately four (4) weeks
14
Future Construction Staging
Early May 2018
What to Expect: Storm Sewer Installation
• In December 2017, crews began installation of a new storm sewer system along the south side
of Eglinton Ave E, between Taunton Rd and Brownlow Ave
• Work will resume on March 12, 2018
• Crews will use a hand-mining method whereby the sewer pipe will be hydraulically pushed
through the soil from the shaft while soil is simultaneously removed
• The work will be completed in three stages:
• Part 1 – Mining and pipe installation Taunton Rd to Mt Pleasant Rd (three weeks)
• Part 2 – Mining and pipe installation Brownlow Ave to Mt Pleasant Rd (two weeks)
• Part 3 – Connection work (two weeks)
What to Expect
• 24/5 operation, Monday through Friday
• Noise from construction equipment, 25K generator, pumps and fans
• Pedestrian rerouting around Brownlow Ave/Eglinton Ave E work zone
• Truck traffic entering/exiting work zones
16
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
17
Mount Pleasant Station Main Entrance
*60% rendering
18
Mount Pleasant Station Secondary Entrance
*60% rendering
19
Mount Pleasant Station Plan View
STATION BOX