EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeNovember 14, 2017
![Page 2: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/2.jpg)
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
![Page 3: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/3.jpg)
3
Eglinton Station Update
![Page 4: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/4.jpg)
4
Eglinton Station Updates
Ongoing
• Early morning deliveries
• Shoring stage 1
• THESL 2B – Hillsdale (partially complete), Yonge (ongoing)
Upcoming
• Shoring stage 2
• THESL 2A
• Water site service connections
![Page 5: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/5.jpg)
5
Shoring Stage 1 – Ongoing
![Page 6: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/6.jpg)
6
Shoring Phase 2 – Upcoming
![Page 7: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/7.jpg)
7
THESL Relocation 2B
![Page 8: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/8.jpg)
8
THESL Relocation 2A
![Page 9: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/9.jpg)
9
Construction Progress Picture
ROAD DECKING INSTALLATION AT DUPLEX
AND EGLINTON
![Page 10: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/10.jpg)
10
Mount Pleasant Station Update
![Page 11: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/11.jpg)
11
Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROXIMATE DURATION
NOVEMBER – DECEMBER 2017
Support of Excavation (Piling)
• NE sidewalk closure North side of Eglinton Ave E Ongoing into January 2018
Hydro Vault ConstructionSoutheast corner of Eglinton Ave E and Mt. Pleasant Rd
One (1) week remaining
Watermain Service Work
• Overnight water shut-off (Nov 22)North side of Eglinton Ave E Beginning the week of November 13
Launch Shaft Construction
• Taunton Rd closure at Eglinton Ave ETaunton Rd at Eglinton Ave E Ongoing until early February 2018
Sewer Relocation
• NE sidewalk closureSecondary Entrance As early as November 30 for one (1) week
JANUARY 2018
Receiving Shaft ConstructionSouth side of Eglinton Ave E, east of Brownlow Ave
Week of January 8 until early March 2018
Tunneling and Storm Sewer Installation South side of Eglinton Ave E Week of January 8 for three (3) weeks
![Page 12: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/12.jpg)
12
Current Construction Staging
Began October 2017
HYDRO VAULT WORK
LAUNCH SHAFT
![Page 13: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/13.jpg)
13
Upcoming Construction Staging
Beginning as early as mid-November 2017 until January 2018
RECEIVING SHAFT
(STARTING JAN 2018)
LAUNCH SHAFT
NE SIDEWALK CLOSURE
![Page 14: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/14.jpg)
Storm Sewer Installation
• Launch Shaft (at Taunton Road):
Began October 2017 until approximately early February 2018
• Receiving Shaft (east of Brownlow Avenue):
Beginning the week of January 8 until approximately early March 2018
• Tunneling and Storm Sewer Installation (24/7):
Beginning January 8 for approximately three (3) weeks
![Page 15: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/15.jpg)
Support-in-Place (SIP) – Toronto Hydro
• SIP is an alternative method to relocating utility infrastructure, whereby hydro infrastructure is temporarily supported using concrete encasement and steel beams
• Advantage of SIP is reduced impact to road users and pedestrians as well as less power interruptions for properties in the vicinity of the future station
• The SIP method will be used at Mount Pleasant during the shallow excavation periods
![Page 16: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/16.jpg)
16
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
![Page 17: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/17.jpg)
17
Mount Pleasant Station Main Entrance
*60% rendering
![Page 18: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/18.jpg)
18
Mount Pleasant Station Secondary Entrance
*60% rendering
![Page 19: Eglinton & Mount Pleasant Construction Liaison Committee - November 2017](https://reader034.vdocuments.us/reader034/viewer/2022050614/5a64e5537f8b9ac21c8b7891/html5/thumbnails/19.jpg)
Mount Pleasant Station Construction Progress
19
WATERMAIN SERVICE WORK
LAUNCH SHAFT CONSTRUCTION
INSTRUMENT INSTALLATION