effect of pipe roof support on the ground …
TRANSCRIPT
EFFECT OF PIPE ROOF SUPPORT ON THE
GROUND SETTLEMENT INDUCED BY
SHALLOW TUNNEL EXCAVATION
MOHD FANDEY BIN ABDUL LATIF
UNIVERISITI SAINS MALAYSIA
2016
brought to you by COREView metadata, citation and similar papers at core.ac.uk
provided by Repository@USM
EFFECT OF PIPE ROOF SUPPORT ON THE GROUND SETTLEMENT
INDUCED BY SHALLOW TUNNEL EXCAVATION
by
MOHD FANDEY BIN ABDUL LATIF
Thesis submitted in fulfilment of the requirements for the degree
of Master of Science
December 2016
ii
ACKNOWLEDGEMENT
In the name of Allah, the Entirely Merciful and the Especially Merciful.
Alhamdulillah, all praises to Allah and salawat to Nabi Muhammad S.A.W. I
am so grateful to Allah for all the time, the strength, the health and the convenience
that had been given to me to in completing this thesis. First, I would like say my
deepest love and gratitude to my parents for their unconditional prayers for my
grateful achievement and successfulness. I would like to express my highest
gratitude to my supervisor, Professor Ir. Dr. Mohammad Razip Selamat for all his
sharing of knowledge, motivation, sincere comments and suggestions throughout the
past years until the completion of this thesis. A great appreciation also goes to my
co-supervisors, Dr. Mohd Ashraf Mohd Ismail and Dr. Muhd Harris Ramli for their
dedication, active co-operation and passion in providing useful information and tools
regarding the research. I also would like to express my gratitude Encik Bani
Faidzzainami Baniyamin, Assistant Engineer of computer laboratory for his
assistance during my presence at the lab. Last but not least, my beloved wife, Siti
Asma Abd Latif for her support, love and patient.
-Mohd Fandey Abdul Latif, May 2014
-
iii
TABLE OF CONTENTS
Page
ACKNOWLEDGEMENT ii
TABLE OF CONTENTS iii
LIST OF TABLES v
LIST OF FIGURES vii
LIST OF ABBREVIATIONS ix
LIST OF SYMBOLS x
ABSTRAK xiiii
ABSTRACT xiv
CHAPTER ONE: INTRODUCTION
1.1 Introduction to Shallow Tunnelling 1
1.2 Challenges in Shallow Tunnelling 2
1.3 Application of Pipe Roof System in Shallow Tunnelling 4
1.4 Problem Statement 8
1.5 Objectives 9
1.6 Scope of the Study 9
1.7 Organization of the Thesis 11
CHAPTER TWO: LITERATURE REVIEW 123
iv
2.1 Introduction 13
2.2 Pipe Roof System 144
2.3 Method of Construction 144
2.3.1 Auger system 177
2.3.2 Slurry system 188
2.3.3 Vacuum 188
2.3.4 Pilot tube 18
2.4 The Advantages of Pipe Roof System 20
2.5 The Effect of Shallow Tunneling on Settlement 21
2.5.1 Introduction 21
2.5.2 Settlement in Shallow Tunneling 21
2.5.3 Causes of Settlement in Tunneling 23
2.5.4 Settlement of Twin Tunnels 27
2.6 The Prediction of Settlement due to Shallow Tunneling 30
2.6.1 Introduction 30
2.6.2 Finite Element Method of the Settlement 31
2.6.3 Closed-Form Solution for Tunnel Deformations 33
2.7 Estimation of Rock Mass Using Hoek-Brown Failure Criterion 34
CHAPTER THREE: METHODOLOGY
3.1 Introduction 36
3.2 Finite Element Method with PHASE2 36
3.2.1 Boundary Condition of the Finite Element Model 40
3.2.2 Excavation Boundary 42
3.2.3 Stage Boundary VS Material Boundary 42
v
3.2.4 Mesh Generation 43
3.2.5 Element Types and Aspects 45
3.2.6 Field Stress Installation 47
3.2.7 Material Properties 48
3.3 The Review of Finite Element Method Installation Procedures 49
3.4 Conversion of Mohr-Coulomb Strength Parameter into Hoek-Brown 53 StrengthParameter
CHAPTER FOUR: RESULTS AND DISCUSSION
4.1 Introduction 55
4.2 Tunnel Depth and Spacing 55
4.2.1 Effect of Tunnel Depth and Spacing to Ground Settlement Trough in 56 Circular Twin Tunnel
4.2.2 Comparison of Settlement Profile between Different Tunnel Shapes 63
4.3 Tunnel Case Study 67
4.3.1 Introduction 67
4.3.2 Padang Rengas Pipe Roof Twin Tunnels 68
4.3.3 Two Dimensional Finite Element Analysis 70
4.3.4 Surface Settlement 722
CHAPTER FIVE: CONCLUSIONS AND RECOMMENDATIONS
5.1 Conclusions 75
5.2 Recommendations 76
REFERENCES 78
LIST OF PUBLICATIONS
vi
LIST OF TABLES
Page
Table 2.1 Ground loss for cohesive soils (O’Reilly, 1988) 26
Table 2.2 Ground loss for cohesionless soils (O’Reilly, 1988) 27
Table 3.1 Specifications of the composite ‘beam’ 50
Table 3.2 Rock mass parameters for the composite ‘beam’ using 53 Hoek-Brown Failure Criterion
Table 3.3 Material Properties of the In-situ (Maxi, 2007) 52
Table 4.1 Result Summarization of Figure 4.1 58
Table 4.2 Tunnelling projects that have had analysis conducted on the 61
surface settlement based on the usage of Pipe Roof system
Table 4.3 Result Summarization of Figure 4.9 65
Table 4.4 Comparison of maximum settlement based on tunnel shape by 70 previous researches.
Table 4.5 The Properties of Materials used in the Finite Element Analysis 71
vii
LIST OF FIGURES Page
Figure 1.1 The cross and longitudinal section of forepolling method 6 (Ocak, 2008)
Figure 1.2 Overview of forepolling method (Ocak, 2008) 6
Figure 1.3 Schematic view of pipe roof system 8
Figure 2.1 The cross-section of the arrangement of pipe roof system of 17 typical tunnel shape (Ahuja et al., 2008; Otani et al., 2003; Yao et al., 2004)
Figure 2.2 Five Separate Independent System of Microtunnelling 17 (Joon et al., 2005; Osgoui et al., 2011; Sofianos et al., 2004)
Figure 2.3 Schematic diagram of microtunnelling and pipe jacking 18 operation (Australian Society for Trenchless Technology, 2005)
Figure 2.4 A Normal Probability Distribution of Settlement of Tunnel 24 (Peck, 1969)
Figure 2.5 The simulation of ground loss that contributes to settlement 28 (Lee et al., 1992)
Figure 2.6 The Profile of Settlement after the Excavation of Right Tunnel 29 (Ercelebi et al., 2010)
Figure 2.7 The Profile of Settlement after the Excavation of Both Tunnels 30 (Ercelebi et al., 2010)
Figure 2.8 Combined Plastic Deformation Mechanism for Two Identical 31 Tunnel in Clay (Osman, 2010)
Figure 2.9 The Settlement Profile of Different Spacing between Tohid 32 Tunnels (Chakeri et al., 2011)
Figure 2.10 3D FE-Mesh (Left) and 2D FE-mesh (right) for Tunnel 34 (Yoo, 2009)
Figure 2.11 2D element mesh in two layered soils (Zhang et al., 2011) 33
Figure 3.1 Research activity flowchart 38
Figure 3.2 Basic structure of PHASE2 program 39
Figure 3.3 Boundary condition for twin-tunnel employed in the modeling 40
Figure 3.4 Boundary condition for single tunnel employed in the modeling 41
viii
Figure 3.5 Two and three layers excavated tunnel 42
Figure 3.6 Mesh type (Curran, 2013a) 44
Figure 3.7 3-noded triangle and 4-noded quadrilateral (Curran, 2013) 45
Figure 3.8 6-noded triangle and 8-noded quadrilateral (Curran, 2013) 46
Figure 3.9 Elements with good and bad aspects ratios (Curran, 2013) 46
Figure 3.10 The magnitude and orientation of initial stress (Möller, 2006) 47
Figure 3.11 Surface settlement trough for different K0 values (Moller, 2006) 48
Figure 3.12 Details of Composite Beam (Hefny et al., 2004) 52
Figure 4.1 Two-Dimensional FE-Mesh for Circular Twin Tunnel with 58 Pipe Roof
Figure 4.2 Settlement Profile at Different Depth for Circular Non-Pipe 59 Roof and Pipe Roof Twin Tunnel
Figure 4.3 Settlement Profile between Different Tunnel Shapes 65
Figure 4.4 Overview Plan of Berapit Tunnel 69
Figure 4.5 Location of different tunnelling methods of Berapit Tunnel 69
Figure 4.6 Cross Section Details of the Pipe Roof System 70
Figure 4.7 A Simple Representation of Soil Profile of the Padang Rengas 73 Pipe Roof Twin Tunnels
Figure 4.8 The Location of Monitoring Point of N, M and S 73
Figure 4.9 The Comparison between monitored datas and 2D finite 76 element analysis
ix
LIST OF ABBREVIATIONS
2D Two-dimensional
CCTV Close-circuit television
ELS Electronic laser system
EPB Earth pressure balance
FE Finite element
FEM Finite element model
HDD Horizontal Directional Drilling
MT Microtunnelling
MTBM Microtunnelling boring machine
NATM New Australian Tunnelling Method
PLUS Projek Lebuhraya Utara-Selatan
PTMT Pilot tube microtunnelling
RCP Reinforcement concrete pipe
TBM Tunnel boring machine
x
LIST OF SYMBOLS
a Tunnel radius
c Cohesion
cu Undrained shear strength
d Tunnel diameter
E Young’s modulus
g Gap parameter
GP Spacing between tunnel crown and lining
h Vertical distance from the ground surface to the center of tunnel i Inflection point
i Value of y-axis corresponding to point of inflection of Gaussian trough n Number of dimension
Ø Angle of friction
p0 Initial total vertical stress
pi Uniform tunnel pressure
R Radius of volume loss
r Distance from center of tunnel
Smax Maximum settlement
Sp Spacing between two identical tunnels
Sz Vertical displacement
U3D A spatial elastic-plastic deformation which contribute to the three dimensional displacement in front of the tunnel path
xi
Vexc Volume of excavated soil
Vs Volume of Gaussian settlement trough per meter length
w Vertical deflection
wmax Maximum settlement
x Horizontal distance
Z Vertical distance
Z0 Vertical distance from the undeformed surface to tunnel axis Z0 Ground level
α Exponent for volumetric compressibility
γ Unit weight of soil
δ Ovalization effect
ε Uniform radial displacement
σ Normal stress
σ0 Effective overburden stress
τ Shear stress
ω workmanship parameter
xii
KESAN PENGGUNAAN PENYOKONG ATAP PAIP TERHADAP
MENDAPAN PERMUKAAN TANAH OLEH PENGGALIAN TEROWONG
CETEK
ABSTRAK
Masa kini, ruang bawah tanah telah menjadi bahagain penting di dalam
kemajuan manusia yang melibatkan ekonomi, sosial dan keperluan. Sesetengah
kawasan yang membangun amat memerlukan penyelesaian yang lebih baik untuk
sistem pengangkutan yang effisien. Terowong cetek biasanya dibina di bawah
jalanraya yang sedia ada dan di bawah kawasan yang mempunyai ruang yang terhad.
Dalam kajian ini, penyokong atap paip telah dikaji untuk mendapatkan fungsi
optimum sistem tersebut yang bertindak sebagai penyokong sementara bagi
membolehkan kerja penggalian terowong dijalankan dengan selamat. Atap paip
penyokong tersebut dibina dengan memasang serta menyusun beberapa cerucuk
konkrit di bahagian atas terowong dengan menggunakan mesin penggali terowong
mikro (MTBM). Analisis tersebut telah dijalankan dalam beberapa kes yang
berasingan dengna menggunakan model 2D-Finite Element. Model-model tersebut
telah dibandingkan berdasarkan tiga bentuk terowong iaitu bulat, ladam kuda, dan
empat segi sama. Setiap bentuk terowong telah menjalani beberapa analisa seperti
kesan penggunaan penyokong atap pain terhadap kedalaman (0.0d, 0.5d, 1.0d and
2.0d) dan jarak di antara dua terowong berkembar (0.0d, 0.5d, 1.0d and 2.0d).
Bahagian terakhir analisa adalah mengenai pembuktian magnitud mendapan hasil ke
atas projek yang menggunakan system penyokong atap paip di Padang Rengas,
Perak. Berdasarkan analisis yang telah dijalankan, keputusan menunjukkan bahawa
mendapan telah berkurang sehingga 90% dengan pemasangan atap paip penyokong
tersebut. Magnitud mendapan telah berkurang sehingga 60% apabila kedalaman
xiii
terowong ditingkatkan. Bagi terowong berkembar, mendapan telah bertambah
daripada sehingga 70% di terowong kedua kesan daripada penggalian yang
dilakukan di terowong yang pertama yang menyebabkan gangguan terhadap
kekuatan tanah.
xiv
EFFECT OF PIPE ROOF SUPPORT ON THE GROUND SETTLEMENT
INDUCED BY SHALLOW TUNNEL EXCAVATION
ABSTRACT
Nowadays, underground space has become an important part of human
development involving economics, social and needs. Some areas especially in the
urbanized surroundings are in need of a better solution for an efficient transportation
system. Shallow tunnel usually constructed beneath an existing highway or an area
with limited spaces to improve transportation network. In the present study, pipe roof
support was analyzed to determine the optimum function of its system that acts as a
temporary support. The pipe roof is formed by installing a number of horizontal
concrete piles at the crown of the tunnel by using microtunnelling boring machine
(MTBM). The analyses were done in a few separate cases by using 2D-Finite
Element modeling. The models were differentiated according to three tunnel shapes
which are circular, horseshoe and square. Each tunnel had been analyzed according
to the effect of the pipe roof tunnel to depth (0.0d, 0.5d, 1.0d and 2.0d) and spacing
between twin tunnels (0.0d, 0.5d, 1.0d and 2.0d). The last part of the analyses is the
verification study on a pipe roof tunnel project at Padang Rengas, Perak. A simple
ground profile of the tunnel project had been created by using the information
gathered from the bore log of the in-situ. Based on the analyses, the results had
shown that the settlement has been reduced up to 90% with the installation of pipe
roof system. As the tunnel depth increase, the magnitude of settlement above the
tunnel has reduced up to 60%. Meanwhile, for the twin tunnels, the magnitude of
settlement has increased up to 70% at the second tunnel due to the excavation of the
first tunnel that cause disturbance to the soil strength. The magnitude of settlement
xv
of a twin tunnels also reduced from up to 58% when the spacing between the tunnels
increase.
1
CHAPTER ONE
INTRODUCTION
1.1 Introduction to Shallow Tunnelling
The underground engineering nowadays is very crucial especially when
dealing with a limited space. It is part of the infrastructure that influences the
lifestyle of the modern society and had been applied for a wide range of services
such as highways, railways, subways, material storage, sewage and water transport
(Hashash et al., 2001). For the last century, the worldwide development has shown
the conflict between the demand and supply. The increasing in demand will
simultaneously increase in supply. In urban areas, the acquired consciousness of
preservation of building and environment together with the requirement of life
improvement has raised many issues and difficulty in executing a tunnelling project.
This recent, many issues regarding settlement of building and highways have
gained the attention of the engineering world. The settlement does not only produce
hazard to the structure around the vicinity, but it also will increase the risk of
accident in the tunnel. There are few reasons that contribute to this problem such as
poor geotechnical condition of the ground, the presence of water table or aquifer, and
the shallow depth of tunnel excavation. Shallow tunnel are usually excavated by
using delicate method to avoid excessive vibration such as hydraulic rock splitter
where a number of holes will be drilled before the hydraulic splitter takes place
inside the drilled holes to create fracture in the rock mass. This method is able to
replace the drill and blast method that normally produce a high impact of vibration.
However, by performing such a method will not guarantee that settlement will not
occur. There are methods that can be incorporated in order to minimize the effect of
2
settlement during the tunnel construction. In this thesis, the author will focus on the
effect of pipe roof application system to the ground surface settlement. Pipe roof
system is a temporary support that helps contractor to hold the overburden while
performing the tunnel excavation work.
Shallow tunnelling is not the first priority when dealing with underground
subway. But sometimes it can be the option to solve many problems that might be
the getaway to bigger improvements that influence the human lifestyle and economy.
One of the closest examples of today shallow tunnelling advantage is the
construction of SMART system in Kuala Lumpur. The 13 km long tunnel was built
for a multiple functions both as an underground road for traffic deviation to reduce
traffic congestion and storm-water diversion duct to mitigate the high risk to flooding
in the center of the city. Thanks to the underground technology that we have today,
we are able to excavate tunnels under small overburden to solve this kind of problem
that usually bring deteriorate effect to the local economy and properties.
1.2 Challenges in Shallow Tunnelling
The challenge in shallow tunnelling is not only related to the technique of
construction, but also the level of sustainability that need to be achieved. The
construction of shallow tunnel either in urban and rural area must abide the law and
regulation of construction and environment. The disturbance created during the
tunnel construction will cause discomfort to the local community as well as
interruption to the integrity of building structure. The interruption that occurs above
the surface has to be handled and analyzed wisely. This includes the appropriate
traffic management on the involved area, well site arrangement, an efficient noise
and dust control, and high safety alert. As an engineer, this is a challenge that needs
3
to be considered so that the disturbance can be reduced to lowest level as possible
and at the same time providing a quality work within the cost and time.
The poor quality of the ground condition is one of the important elements that
need to be considered in the design and construction method of shallow tunnel.
Shallow depth usually consists of loose material of soils such as pit soil that contains
high organic concentration with a very low bearing capacity. The depth of topsoil
can extend until a few millimeters into the ground until the subsoil layer. Without an
appropriate surface treatment, it can be easily washed away by rain and prone to
erosion. An area consists of a man made fill usually brings other kind of difficulty
such as the unwanted of an unknown material that buried under the filled area that
somehow need to be cleared up. This will indirectly increase the amount of cost and
time of the project. On top of that, the remaining of historical relic that exists in the
ground must be handled by the right authorities before the project can begin. The
existing underground cables and services at urban area must be assessed and
identified. Perhaps the risk and possibility of damage caused by the settlement that
induced during the tunnelling process will allows the engineer to think again for
rerouting the tunnel advancement.
Surface settlement due to shallow tunnel excavation is inevitable. Even under
a strict monitoring and control, settlement will always occur due to many factors.
The factors usually related to the quality of ground condition, workmanship, the
application of support pressure during tunnelling, the level of ground water table and
the water flow in aquifer. The stratification of soil due to the process of
transportation and deposition has created a multiple layers of soil that has low
4
residual strength. The lack of experience and the incapability to propose a technical
solution for the settlement issue which consistent to the risk reduction slowly will put
the project into jeopardize. This involves the selection of tunnelling method and the
monitoring system that had been imposed to observe the level of settlement.
Besides the tunnelling method, the other factor that must be given attention is
the internal support pressure that must be greater than the critical support pressure.
This depends on the type of ground that will influence the principal and operational
criteria of the temporary support during the tunnelling such as pipe roof system,
lining system, shotcrete, rock bolts and steel girder. Pipe roof system is currently a
system that utilized steel pipe which contains grout to reinforce the crown of the
tunnel before excavation can be preceded. This system will be thoroughly
highlighted later throughout this thesis as the main focus. Therefore, the effort to
reduce the settlement to the minimum level as possible must be conducted
conscientiously as one the important elements in reducing further problem that
supposedly can be well predicted.
1.3 Application of Pipe Roof System in Shallow Tunnelling
Pipe roof system generally divided into two which are forepolling method
and pipe arch method. Both methods provide the function as a temporary support for
tunnelling. These methods use the same idea of reducing settlement during the
tunnelling process. Nowadays pipe roof is widely used for tunnel construction
especially in urban area to reduce the settlement that affecting the adjacent structure.
Pipe roof method serves by using trenchless technique which used to build the
underground passage to cross highways, railways and airport runaway. It has been
5
proven to have a good effects in underground construction engineering such as in
Asia as well as Europe (Ge, 2005).
Forepolling method or also known as umbrella arch method (Ocak, 2008)
consists of series of steel or fiber glass pipe that had been arranged parallel to the
tunnel axis or at a certain angle. The inserted pipe will be injected with grout to
create a stiffer reinforcement to allow safe excavation to be conducted in the tunnel.
The function is to maintain the exact ground profile and stabilize the rockmass. It is
functioned as a temporary support and will be added with permanent support such as
bolts and shotcrete (Kontothanassis et al., 2005). It is typically in areas with sandy or
silty soil, squeezing and fragmented rock. Forepolling is also frequently used in
sections of insufficient rock cover for example at the tunnel entrance area where the
jointed roc mass may lack of the horizontal stresses required to keep the rock block
intact (Osgoui et al., 2011). Figure 1.1 shows the cross and longitudinal section of
the forepolling method.
6
Figure 1.1: The cross and longitudinal section of forepolling method (Ocak, 2008)
Figure 1.2: Overview of forepolling method (Ocak, 2008)
The pipes were normally installed at the crown of the tunnel. The diameter of
the pipe usually ranged between 60mm to 200mm with a wall thickness of 4mm to
7
8mm. The length of the pipe are generally depends on the inclination of its angle
where it must consider the depth of the tunnel. The depth of the tunnel usually ranges
between 6m to 12m. The overlapping length usually exists between previous
installed pipe and the next installed pipe as shown in Figure 1.1 and Figure 1.2.
In the other hand, pipe arch method is utilized by installing a series of pipe
which parallel to the tunnels axis. It consists of series of steel pipes that installed
horizontally according to the tunnel axis. Steel pipe are used in this method by
drilling them around the tunnel periphery towards the tunnel axis before excavation
and later supplemented with grouting which inserted through the pipes to form pipe
roof structure to strengthen the surrounding ground (Yang et al., 2008). Sometimes
interlocking steel pipes are being used to strengthen the link between the steel pipes.
The diameter usually ranged between 0.5m to 1.0m. The application of pipe roof
system is normally suitable for a large diameter of shallow tunnel on short distance.
This system is an alternative to cut and cover method where sometimes a certain
infrastructure such as highway needs to be maintained on the location of the shallow
tunnel construction. Further information and details will be given on this system in
the next chapters as the main focus of this thesis. Figure 1.3 shows the schematic
view of the pipe roof system.
8
Figure 1.3: Schematic view of pipe roof system
1.4 Problem Statement
The usage of land has been intensified since many centuries ago for the
purpose of living such as providing human residence and agricultural medium. These
elements are important to provide a better life environment condition. The equal
attention must be given in this respect to the increasing demand by the local
communities to have more areas free of road traffic (Leca et al., 2007). Based on this
matter, the requirement of undertaking the underground construction is almost
inevitable to merge the demand for services and facilities. In order to realize the
demand, the possible effects to the adjacent structures and underground services
must be considered.
Currently, the tunneling induced ground settlement has become one of the
major issues especially in urban tunnel construction. Urban tunneling usually
involves an underground construction with low overburden and shallow depths up to
less than 4m (Osgoui et al., 2011). Pipe roof system has been used in many projects