ee527_presentation.pptx
TRANSCRIPT
Electrical Engineering DepartmentReliability Assessment of Power Systems EE-
527Term Paper Presentation
Title: RELIABILITY ASSESSMENT OF A WIND-POWER
SYSTEM WITH INTEGRATED ENERGY STORAGE
Supervisor: Dr. M. AlMuhaini
By:Ibrahem M. Hussein
G201405220
May-2015
• Introduction. - Motivation. - Related Work. - Problem Statement. • Problem Formulation. - System Description. - Analysis Flow Chart. • Simulation and Analysis Results. - Four topologies. • Conclusion. - Comparison - Recommendations and improvements.
Outline
Motivation
One man said - in the period from 1962 to 1986 – that “ The stone age did not end for lack of stone, and the oil age will end long before the worlds runs out of oil”. This is the Saudi Arabia minister of oil and minerals resources.
•Due to environmental and energy resources issues RE
• WE is one of those fastest growing RE resources.
• Global annual installed wind power capacity between 1997 and 2014 is about 369553 MW [1].
•Many countries prompt RE to be the main source of power CEI Sustain on RE including WE for 75 day on RE including WE.
Related Work
Problem Statement
• In this paper, the effect of integration of WTG corroborating storage unit will be simulated using Monte Carlo simulation method for one year chronological sampled data for wind generated power and load in different topologies ( four cases in PF)
• Specified load point from Bonneville Power Administration (BPA) transmission and distribution electrical network will be taken into account.• The contribution to this paper are to consider an important
constrains they real available in real life such as :
Contribute to reliability issues in planning process : A wide comparison in term of availability versus the BTS along with changing the WTG capacity allow us to select the required availability lever, battery size and WTG size appropriate for system design (Performing sensitivity analysis ).
Problem Formulation
• SLD:
WTG
Battery Banks
Load bus
Wind Speed
Loads
Reliability Indices G
Grid connection
Battery efficiency, charging rate . vanadium redox flow battery technology [1]
[1]: http://www.redtenergy.com/products#mw (Accessed on May 2015)
Problem Formulation
• Analysis Flow Chart:
Perform sensitivity analysis
Simulation Start
BPA data
WTG+ST WTG+Grid WTG+ST+Grid
Simulate the data with load, get the indices
Compare results
Grid
Impose random outages
Availability
AIDIAIFI
WTSST size
Simulation and Analysis ResultsA. Grid Connected Load
The inverse transform method depends on the failure rate per year and repair rate per hours
(4)
Simulation and Analysis ResultsA. Grid Connected Load
(4)
0 1000 2000 3000 4000 5000 6000 70000
5
10
15
20
25
30
Time in Hours
Load d
em
and in K
W
CaseBattery size
[KWh]Availability
AIFI [f/y]
AIDI [hours]
A - 0.9982 7 12.833
Simulation and Analysis ResultsB. WTG with Storage
(4)
1000 2000 3000 4000 5000 6000 7000 8000 9000 100000.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1
Battery Size in KWh
Availability
50 KW WTG
100 KW WTG
150 KW WTG
200 KW WTG
250 KW WTG
500 KW WTG
Simulation and Analysis ResultsB. WTG with Storage
(4)
0 1000 2000 3000 4000 5000 6000 7000 80000
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Time in hours
Batt
ery
Capacity in K
Wh WTS=50 KW
115 hours
Availability
AIDIAIFI
Depends on
planner !!
Simulation and Analysis ResultsC. WTG Without Storage and Combined with Grid
•Is the WTG can assess the system reliability level ? Availability
AIDIAIFI
Simulation and Analysis ResultsC. WTG Without Storage and Combined with Grid
0
10
20
30
40
50
60
11000 11050 11100 11150 11200 11250 11300
GRID LOAD WTG
Po
we
r in
KW
Time in Hours
Simulation and Analysis ResultsC. WTG Without Storage and Combined with Grid
CaseBattery size
[KWh]Availability AIFI [f/y]
AIDI [hours]
A - 0.9982 7 12.833
C - 0.9985 6 10.5
Case C Case A
Simulation and Analysis ResultsD. WTG with Storage Combined with Grid
WTG
Battery Banks
Load bus
Wind Speed
Loads
Reliability Indices G
Grid connection
Let us discuss this case !
•What about the reliability level ? It’s also depends on planner
Availability
AIDIAIFI
Simulation and Analysis ResultsD. WTG with Storage Combined with Grid WTG
Battery Banks
Load bus
Wind Speed
Loads
Reliability Indices G
Grid connection
1000 2000 3000 4000 5000 6000 7000 8000 9000 100000.975
0.98
0.985
0.99
0.995
1
1.005
X: 7000Y: 1
Battery Size in KWh
Ava
ilabi
lity
WTS 50KW
WTS 100KWWTS 150KW
WTS 200KW
WTS 250KW
WTS 300KW
WTS 350KW
WTS 400KWWTS 450KW
WTS 500KW
CaseBattery size
[KWh]Availability
D 6000 0.9998
Oversize !
Simulation and Analysis ResultsD. WTG with Storage Combined with Grid
1000 2000 3000 4000 5000 6000 7000 8000 9000 100001
1.5
2
2.5
3
3.5
4
4.5
5
5.5
6
Battery Capacity in KWh
AIF
I per
yea
r
50 KW WTS
1000 2000 3000 4000 5000 6000 7000 8000 9000 100000
2
4
6
8
10
12
14
Battery Capacity in KWh
AIDI
in H
ours
50 KW WTS
AIFI AIDICase
Battery size [KWh]
AIFI [f/y]
AIDI [hours]
D 6000 1 1.5Oversize !
ConclusionSummary
CaseBattery size
[KWh]Availability AIFI [f/y]
AIDI [hours]
A - 0.9982 7 12.833
B 6000 0.3497 268 4682
C - 0.9985 6 10.5
D 6000 0.9998 1 1.5
Recommendation for increasing the reliability level, Modularity ! As future Work, Integrate an ARMA model to this work and perform the analysis as well.
Results Summary :
Video !
References [1] Global Wind Energy Council, Global Wind Statistics 2014, pp. 3-4. http://spectrum.ieee.org/energywise/energy/renewables/costa-rica-runs-on-renewables-for-75-days (Accessed on April 2015). • [2] Jiang Cheng, Zhang Jianhua and Yu Lei, “Reliability probability evaluation of wind turbine based on Monte-Carlo simulation,” IEEE CICED Conf, Sep 5-6, pp. 1-4, 2012.•[3] Bagen and Roy Billinton , “Impact of energy storage on power system reliability performance,” IEEE Saskatoon Conf., 1-4 May 2005. pp 494-497, May 2005.• [4] Xinwei Wang, Jianhua Zhang, Cheng Jiang, Lei Yu, Dexian Liu and Yunkai Weng, “Reliability Assessment of Wind Farm Active Power Based on Sequential Monte-Carlo Method,” IJEE, vol.3 no.4, pp. 122-129, Aug 2013.•[5] Billinton, R, Bagen and Cui, Y., “Reliability evaluation of small stand-alone wind energy conversion systems using a time series simulation model,” IEE proceeding. vol. 150, no. 1, Jan 2003.•[6] Rajesh Karki, Po Hu and Roy Billinton, “A Simplified Wind Power Generation Model for Reliability Evaluation,” IEEE Trans. Energy Conv., vol.21, no.2, pp.553-540, June. 2006.•[7] R. Billinton and A. A. Chowdhury, “Incorporation of wind energy conversion systems in conventional generation capacity adequacy assessment”, IEE Proceedings—C, Vol. 139, no. 1, January, 1992, pp. 47-56. •[8] A. J. M. van Wijk, N. Halberg, and W. C. Turkenburg, “Capacity credit of wind power in the Netherlands”, Electric Power Systems Research, vol. 23, 1992, pp. 189-200. •[9] to [15], included in the paper.
Thank You !