Eden BO 1448(44) Alternatives Presentation MeetingTH 13 – Bridge #23 over the White Branch of Gihon RiverOctober 23, 2017
Introductions
Rob Young, P.E.VTrans Design Project Manager
Laura Stone, P.E.VTrans Scoping Engineer
Purpose of Meeting
Provide an understanding of our approach to the project Provide an overview of project constraints Discuss alternatives that were considered Discuss our recommended alternative Provide an opportunity to ask questions and voice
concerns
Location Map
13
Bridge 23Project Location
Meeting Overview
VTrans Project Development Process Project Overview
– Existing Conditions– Alternatives Considered– Recommended Alternative Maintenance of Traffic Schedule Summary Next Steps Questions
VTrans Project Development Process
Project Definition
Project Design Construction
ProjectFunded
ProjectDefined
ContractAward
Quantify areas of impact
Environmental permits
Develop plans, estimate and specifications
Right-of-Way process if necessary
Initiated
Identify resources & constraints
Evaluate alternatives Public participation Build Consensus
Who are you representing?
A. Municipal OfficialB. ResidentC. Local BusinessD. SchoolE. Emergency ServicesF. Independent
OrganizationG. Other
Prior to the closure, how often did you use this segment of Knowles Flat Road?
A. DailyB. WeeklyC. MonthlyD. RarelyE. Never
Prior to the closure, how often did you walk over the bridge?
A. DailyB. WeeklyC. MonthlyD. RarelyE. Never
Prior to the closure, how often did you bike over the bridge?
A. DailyB. WeeklyC. MonthlyD. RarelyE. Never
What is your reason for attending this meeting?
A. Specific ConcernB. General InterestC. Live in Close VicinityD. Other
Project Overview
Existing Conditions
Alternatives Considered
Recommended Alternative
Description of Terms Used
Beams (Superstructure)
Deck
Abutment (Substructure)
Bridge Rail
Cross Section of Bridge
Existing Conditions – Bridge #23 Roadway Classification – Local Road Bridge Type – Bridge Removed in 2016 Due to
Failure Ownership – Town of Eden
Existing Conditions – Bridge #23
The existing twin corrugated galvanized metal plate pipe arches FAILED and have been removed
The previous culverts probably didn’t meet the ANR standard for BFW
Survey has not been completed– Expect to have all resource requests complete by January
2018
Existing Conditions - Bridge #23 TH 13 exceeds minimum standard for width Utility Relocation Likely
Looking North Over the Culvert
ADT of 720 veh/day DHV of 150 veh/hr % Trucks: 11.0 Design Speed of 35 mph Class II wetlands within majority of the project area
Design Criteria and Considerations
Disinvestment– Two good bypass routes– Eden Central School is located on Town Highway 13 – this alternative
includes the option for a pedestrian bridge• The school serves as Eden’s primary Red Cross emergency shelter and is only
accessible via VT Route 100, limiting access in an emergency– Includes bus turnaround at each approach
Full Bridge Replacement – Buried Structure– May be discounted based on hydraulic findings– 80 year design life
Full Bridge Replacement – Bridge– 80 year design life
Alternatives Considered – Bridge #23
Proposed Typical Section
Recommended Alternative - Bridge #23 Full Bridge Replacement
– Maintain current roadway width to match existing conditions (9’/4’ typical)
– Meet minimum hydraulic recommendations for the site– ROW and utility relocation may be needed– Bridge to remain closed through construction
Proposed Example - Bridge #23 Slab Bridge
What Will the New Bridge Look Like?
Maintenance of Traffic Options Considered
Bridge has been closed since 2016 – makes sense to keep it closed through construction
ROW to be requested after survey is complete – may be needed even with a bridge closure
Road Closure (Replacement Option) Detour signed by Town Road Closed since 2016 3.4 miles end-to-end
Traffic Control – Local Detour
The shortest local detour route, has an End-to-End distance of 3.4 miles
Recommended Scope
Replace entire structure with structure meeting hydraulic and geotechnical recommendations:– Bridge to remain closed throughout construction– Utility relocation may be needed– ROW may be needed– Construction – Summer 2021
Eden BO 1448(44)
Permanent Closure Full Bridge Replacement
No Access Pedestrian Bridge Buried StructureSingle Span
Bridge
Total Project Costs(Including E & C)
$333,600 $483,600 $1,045,020 $1,197,260
Town Share (%) $8,340 (2.5%) $24,180 (5%) $52,250 (5%) $59,860 (5%)
Project Development Duration 3 years 3 years 3 years 3 years
Construction Duration 2 months 3 months8 months 8 months
Utility No Change No Change Possible Relocation Possible Relocation
ROW Acquisition Possible – ROW not Plotted
Design Life N/A 80 years
Alternatives Matrix Recommended
Which would you be most concerned about?
A. Bridge AestheticsB. Environmental
ImpactsC. Recreational ImpactsD. OtherE. Not Really Concerned
Which design aspect is the most important to you?
A. Shoulder width/bicycle accommodations
B. Aesthetics – Bridge Railing
C. Construction YearD. Construction DurationE. CostF. Other
Did you find this presentation to be?
A. Too technical in nature
B. Too simplifiedC. Just about rightD. Not much use at all
Do you find the recommended scope of work satisfactory?
A. YesB. No
This is a list of a few important activities expected in the near future and is not a complete list of activities.
Wait for Town response to recommendation on proposed project Develop Conceptual plans and distribute for comment Process local agreements Right-of-Way process (if needed) Updates on project plans and estimates at each
submittal Request a Pre-Closure Meeting (optional here) Town is responsible for any chosen detour route
Next Steps – Bridge #23
Eden BO 1448(44)Questions and CommentsTown Highway 13– Bridge #23 over the White Branch of Gihon RiverOctober 23, 2017
For more information: https://outside.vermont.gov/agency/vtrans/external/Projects/Structures/16J176