ECONOMIC DISPATCH
AT GOLDEN VALLEY
Cory BorgesonGVEA President & CEO
August 23, 2018
Alaska Power Association 67th Annual Meeting
1
Golden Valley Electric Assn.
GVEA at a Glance
▪ Total Services in Place: 44,635
▪ Serving nearly 100,000 residents
▪ 5,973 square miles
▪ 3,229 miles of power lines
▪ Fairbanks, Delta Junction, Nenana, Healy,
Denali Park, Cantwell
▪ 2017 Retail Sales: 1.24 billion kWh
▪ 381 MW Generation Capacity
2
Where Our Power Comes From
6%
29%
27%
32%
6%
2016
GVEA Fuel Supply
5%
26%
30%
34%
5%
2017
Hydro
Coal
Natural Gas
Oil
Wind
3
GVEA Generation
Healy Unit 1 & 2
(28 & 50 MW coal)Eva Creek
Wind – 25 MW
North Pole
(120 MW oil)Delta (27 MW oil)
North Pole
Expansion
(60 MW oil)
Fairbanks
(41 MW oil)
4
Power Purchases
25 MW Aurora Energy (coal) - IPP
60 MW Chugach / ML&P / MEA / HEA
(natural gas)
Intertie limited to 75 / 80 MW
of economy energy
5
Power Purchases
6
Alaska Environmental Power
(Delta Wind)
Bradley Lake Hydro
16.9% share of 120MW
SNAP Renewable Energy Producers
199 producers (96% solar & 3% wind & 1% cogen)
Alaska
Railbelt – 1970s
• Pre-Intertie
7
• GVEA
• MEA
• ML&P
• CEA
• HEA
• Seward
Alaska
Railbelt – 1980s
• Alaska Intertie Built
• Alaska Intertie Agreement
8
• GVEA
• MEA
• ML&P
• CEA
• HEA
• Seward
Alaska
Railbelt –1990s
Added……
• Bradley Lake Hydro
• Bradley
Transmission Lines
• Ft. Knox Gold Mine
9
• GVEA
• MEA
• ML&P
• CEA
• HEA
• Seward
Railbelt Today -
- 2000sAdded…
• Northern Intertie
• Battery Energy Storage
System (BESS)
• Ground Based Missile
Defense
• Alyeska Pump #9
• Pogo Gold Mine
• North Pole to Carney
Transmission Line
• Clear AFB
10
GVEA w MEA w ML&P w CEA w HEA w Seward
Dispatching Power…by the minute
11
GVEA Economic Energy Purchases
12
Alaska Railbelt Update▪ The Railbelt utilities continue to work on a
voluntary basis towards:▪ A power pooling agreement
▪ The formation of a Railbelt transmission company
▪ Railbelt Reliability Council
▪ 2018 Goals:▪ Utilities file CPCN application & proposed tariffs w/ RCA
▪ RCA ruling approving Transco CPCN filing
▪ RRC formation
13
Healy 2 Update
• Steady Progress
• July 12th/13th - Fired on oil (27 MWh).
• July 28th - Fired on coal (59 MWh).
• July 31st - Fired on coal (81MWh).
• Aug 5th - Fired on coal (249 MWh).
• Aug 15th – Coal during day/oil at night
• Aug 22nd – 24hrs a day on coal
14
GVEA’s Solar Project
• Size: 563 kW Solar PV System
• Annual energy production is estimated to equal the annual energy used in 71 homes (using an average of 660 kWh/month).
• Footprint is 3 acres
• Panel manufacturer: CSUN
• Each of the 1,760 panels will generate 320 watts.
• Contractor: ABS Alaskan, Inc.
• Estimated to be online: October 2018
• Cost: $850,000 after a $225,000 grant supplied from United States Dept. of Agriculture (USDA) Rural Energy for America Program (REAP)
15
Questions?
16