eco slab presentation
DESCRIPTION
Study of the Retrofit of the ground floor of a Victorian Terraced House in Westminster conservation area, London using the Eco-Slab systemTRANSCRIPT
Queens Park Conservation Area TSB Retrofit For the Future, London 2011
2-bedroom, 2-storey Victorian terraced properties built around1865
In a Conservation Area of approximately 400 other similar properties
Client - City West Homes Contractor - United House Project Manager – Anna Debenham
Refurbishment of social housing in Queens Park, Westminster, London
Lead Architect - Mark Elton Associate Director at Energy Conscious Design On the RIBA ‘sustainable futures’ committee
Special Interest in: The potential for reducing carbon emissions through
retrofit of the existing stock Refurbishment schemes that combine super-insulated
fabric improvements with integrated renewables
Project Architects: Energy Conscious Design (ECD)
Internal wall insulated to the exterior solid walls Roof insulated Doors and windows improved and replaced Acoustic insulation fitted to the party walls of bedrooms Ground floor suspended timber floors removed and
replaced with an Eco-Slab floor system Mechanical ventilation heat recovery (MVHR) installed
Key Improvements to Property
Thermal image showing heat loss
Project funding
Retrofit for the Future project is funded by the Technology Strategy Board (TSB) to find ‘innovative and replicable measures to make deep cuts in carbon dioxide emissions from existing properties in the social housing sector’
Driving Innovation in Retrofit
UK Technology Strategy Board (TSB) funding was specifically designed to stimulate the implementation of innovative cost effective solutions within the demonstrator houses that can then be applied across the UK.
Evaluation
SAP tests before and after retrofit Used by BRE as a Pilot for their
‘BREEAM Domestic Refurbishment standard
Evaluated alongside BRE EcoHomes XB target criteria and discussed with the local conservation officer
Typical Heat Loss Pattern
Generally agreed that 15% of heat is lost through the ground floor but it can be higher in older properties
Heat is lost through draughts in the floor boards as well as through the fabric
Draughts in a typical Victorian House
‘THERMAL ENVELOPE’
Insulate the property to keep heat inside in winter and outside in summer and maintain a constant internal temperature
Create an airtight seal to eliminate heat loss from draughts
Thermal Image of Interior of Victorian Terraced House
Retrofitting the Ground FloorSchedule of Works
Disconnect Services Remove joists and floor timbers Fill void Reroute and reinstall services Lay new floor
Challenges of the Site when Retrofitting the Ground floor
CHALLENGES OF THE BUILDING SITE
Work had to be carried out in a confined space which meant: Confined space working Health and Safety Act had to be observed so no petrol
driven machinery Materials and installation had to be handled manually Labour intensive options not possible No room for storing materials in building Delivery of materials had to be tailored to the demands of restricted site access
The original Victorian features had to be protected The integrity of the Substructure had to be maintained Services had to be re routed Void had to be filled and ventilated The material effects of retrofit on adjoining properties had to be considered Party Wall Act applied Security had to be maintained at all times
Challenges of the Street When Retrofitting the Ground floor
New Road and Street Works Act:
Health and Safety conditions Relate to the control of deliveries
Needed road signs and barriers
Traffic control
Timed deliveries
Make good any damage to road or footpath
Local Council By Laws:
The by laws change depending on the Borough
Not able to start work before 9am
Road had to be cleared and swept by 5pm
No weekend working
Noise and dust restrictions
The traditional approach
15 tons of aggregates were delivered, stored on the road and shoveled and barrowed in to the house to fill the void at a rate of a ton a day
Diesel driven whacker plate was used to create a flat surface putting pressure on substructure and creating toxic fumes in confined space violating Health and Safety laws
The Eco-Slab solutionFEATURES OF ECO-SLAB
SYSTEM
‘Just in time engineering’
Foaming concrete was delivered by a Lorry
mounted pump, located outside the working
area
Foaming concrete used to fill deep void
BENEFITS OF ECO-SLAB SYSTEM
Minimal materials to store and
organise
No complications or concerns with Council
Bylaws,
Conditions of working in Confined
Spaces Health and Safety Act and New
Road and Street Works Act were satisfied
Replaced 15 tons of granular material
Pump set up, filled the void cleaned up
and left within one in an hour with no
manual handling
Minimal Impact on the Street:
Site Activity, Traffic movement, Noise and
Dust all substantially reduced
Minimal supervision to organise delivery
Eco-Slab Module
Method Statement for Retrofitting Ground Floor with Eco-Slab
FEATURES OF ECO-SLAB SYSTEM
‘Just in time engineering’
Eco-Slab was programmed to be delivered
on a light commercial vehicle on day of
installation
Installed by hand by a single semi skilled
operative in one day
Eco-Slab was laid directly onto the foam concrete
base
Service and ventilation void was provided by
100mm legs
75mm thick fibre reinforced wearing slab was
poured to finished floor level
BENEFITS OF ECO-SLAB SYSTEM
Hand off loaded and no storage required
Unloading and installing completed in one
operation.
No machinery required so easily met
‘Confined space working Health and
Safety Act
No pressure or penetration of the existing
walls
Allowed for simple rerouting of services and
Under floor ventilation
Reinforcement was in the concrete so delivery and
fixing of reinforcement was not needed
All Local Council By Laws and New Road and
Street Works Act easily met as
noise, dust, site activity etc. reduced
Insulation Values & Carbon Reductions
Eco-Slab is made from Carbon Enriched Jablite EPS which has an
A+ rating in the BRE Green Guide
The unique lap & ledge system ensured a continuous 100mm of
insulation throughout the ground floor
200mm Edge beam system gave a U value of zero at the wall/ floor
interface
The Eco-Slab floor provided the base for the thermal envelope
In conjunction with other technologies the energy use for the building was
reduced from 16000 kilo watts per year to 2000 kilo watts without
renewables
ECD Architects – Eco-Slab system ground floor section
Conclusions Traditional methods of construction cannot meet the demands and complexities of professional
retrofitting on the scale required
We need to employ new ways of working and new materials
Modern methods of construction and in particular ‘just in time engineering can assist in meeting the challenges
The Eco-Slab system offers a fast and cost effective solution for retrofitting the ground floor when working in a confined urban environment
It is particularly cost effective when retrofitting several houses in one area and the costs of hiring the pump can be shared among several properties
The Eco-Slab retrofit system using foaming concrete and the Eco-Slab base significantly reduced the operational and embodied carbon compared to traditional retrofit methods and combined successfully with other technologies to create a thermal envelope
www.eco-slab.com