Page 1: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 2: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

2

Table Of Contents1. Introduction 32. About this Manual 33. Contacting YZ Systems 34. Vessel Components 45. Specifications 56. Application 67. Theory of Operation 78. DuraSite Installation & Use 89. Cylinder Maintenance 1010. Diagrams

DuraSite Sample Vessel 12Adjustable Relief Valve (Optional) 13

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 3: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

3

1. Introduction:Congratulations on your purchase of the DuraSiteSample Vessel. You've made a wise measurementinvestment for your company.

Before you begin installation, insure that all of thenecessary components are present. TFE tape,Stainless Steel Tubing, and Tubing Fittings may berequired.

2. About This Manual:This User's Guide provides a step-by-step descrip-tion of the information you need to operate theDuraSite Sample Vessel.

3. Contacting YZ Systems, Inc.:If the answer to your question can not be foundwithin this manual please contact YZ Systems at1.936.788.5593. When calling please have on handthis manual for potential review. Also be prepared toprovide the following:

The model and serial number of the DuraSiteSample Vessel. The model and serial number areprinted on the Pre-Charge head of the samplevessel.

This manual and its version number, listed on thefront cover.

A description of the difficultly and the activity at thetime of occurrence.

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 4: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

4

4. Vessel Components:The primary components of the DuraSite SampleVessel are illustrated here.

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 5: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

5

5. Specifications:Working Pressure: 1800 psi*Tested Pressure: 3000 psi*Visual Level Indication: MagneticPrimary Materials: 316 Stainless Steel and AluminumCarrying Case: OptionalSize: 3000 cc

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 6: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

6

6. Application:

Accurate sampling and storage of natural gas and liquidhydrocarbons equates to revenue, and in many casesa large amount of revenue. One of the major links in thesample storage process is the sample container orsample cylinder.

In recent years, the Constant Pressure Cylinder hasbecome the storage cylinder of choice, principally dueto it's unique design. This type cylinder allows thecollected product to be stored at a constant pressurethroughout the sample period and/or in final labanalysis, or lab use.

The DuraSite Sample Vessel permits the user toremove a liquid or gas hydrocarbon sample from apipeline, sampling device, or other location. This isaccomplished without changing the pressure of theproduct or exposing it to a contaminant fluid. Ifproperly used and maintained the DuraSite will pro-vide many years of safe, accurate and clean samplestorage.

The DuraSite is a very safe device to use. As with anyequipment dealing with flammable products, it ismandatory that a good, thorough operator trainingprocedure be established prior to use.

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 7: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

7

7. Theory of Operation:The DuraSiteSample VesselThe DuraSite Sample Vessel consists of a metalcylinder precisely machined and polished on theinside surface with removable end heads for easyaccess to the inside of the cylinder. The heads aredrilled and tapped to incorporate isolation valves,gauges, and pressure rupture disc assemblies.

Contained inside of the cylinder is a moving pistonfitted with seals to ensure a leak-free seal betweenthe sample and pre-charge side of the cylinder.The piston is able to move freely within the cylinderwhile maintaining the segregation between the twoends of the cylinder. This piston also incorporatesa set of magnets to interface with the magneticsensor to determine the level of the sample fluidwithin the vessel. A visual level indication can beobserved on the DuraSite vessel by the position ofthe magnetic level marker on the vessel.

In operation an inert gas pressure is applied to thepre-charge end of the sample cylinder. This inertgas pressure should exceed the anticipatedequilibrium vapor pressure of the product by100psi. This will ensure the sample is maintainedin a single phase.

Product should be introduced to the cylinder fromthe product end. The cylinder should never be filledover 80% full by volume, to allow a safe cushionfor any expansion of the product due to changes inthe temperature.

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 8: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

8

Typical use of the vessel would be as follows:

Step 1: In The LabConnect a regulated inert gas supply to the pre-chargevalve. The product valve should be open. By carefullycontrolling the pre-charge valve and the regulator, thevessel can be slowly charged with pre-charge gas(NOTE: This should be done slowly to prevent slam-ming the piston down to the opposite end). The pres-sure on the pre-charge pressure gauge should bebrought to a reading of 10-50 psi above the expectedpressure of the product in the field. Close the pre-charge valve and disconnect the gas supply. Check thepre-charge valve, relief device, and the pre-chargepressure gauge for leaks. Any leaks should be stoppedbefore continuing. The vessel should be placed in apadded carrying case and made ready for field use.

Step 2: In The FieldConnect the pre-charged sample vessel to the productsupply (NOTE: the pre-charge pressure gauge readingshould be greater than the product supply pressurereading. If not, repeat Step 1 above).

Step 3:Once the vessel is connected to the product supply, itis necessary to vent a small amount of product prior tofilling the vessel. This assures fresh product andremoves any air or gas when dealing with liquids. Thiscan be done by loosening the product purge valve a verysmall amount until the product is purged. After thoroughpurging, the product purge valve should be tightened.

Step 4:The product pressure gauge reading should be 10-50psi below the pre-charge pressure gauge reading. Bycarefully opening the pre-charge valve, the pressurebecomes equalized. The pre-charge valve should becarefully controlled so as to not vent the pre-charge gastoo fast. The pre-charge port should then be connectedto a pipeline connection or relief valve (page 11), whichwill allow movement of the piston while maintaining pre-charge on the vessel.

8. DuraSite Installation & Use:

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 9: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

9

Step 5:When the vessel becomes a maximum of 80% full(see volume indicator), all valves should be closed.The product connection is slowly broken in order tovent any trapped product. After vessel removal, allconnections should be checked for leaks and thepre-charge and product valve ports capped to pre-vent leakage.

Step 6:The vessel should be labeled and placed back intothe padded case and made ready for shipment.

Step 7: In The LabPrior to analysis, the product should be mixed. Thisis accomplished simply and efficiently by invertingthe vessel end-over-end, causing the mixing ball tofall through the product. Approximately 10-12 trips ofthe mixing ball through the product assures a ho-mogenous solution.

Step 8:The regulated pre-charge gas should be recon-nected to the pre-charge side of the vessel. The pre-charge gas supply should remain open during analy-sis.

Step 9:Purging a small amount of product from the vesselremoves unmixed product from the tee, relief device,gauge, etc. The unit can now be connected to achromatograph and the product analyzed.

Step 10:After analyzing, the remainder of the product shouldbe dumped and the vessel properly cleaned. Normalcleaning can be accomplished by rinsing the productend with a petroleum solvent and flushing with ac-etone. If a more thorough cleaning is required, thevessel should be disassembled.

8. DuraSite Installation & Use:

WARNING: A sample vessel should never befilled to more than 80%. This allows a 20% pre-charge cushion to absorb thermal expansion ofthe product.

Shipping: Extreme care should be taken whenpreparing a vessel for shipment. Both valves shouldbe capped to prevent possible leakage. The vesselshould be placed in a snug-fitting, well-padded anddurable case. All applicable DOT regulations shouldbe adhered to.

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 10: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

10

Maintenance:Time, Temperature, Pressures, Sample Quality, and the number of Sample Cycles will all havean affect on the need for maintenance.

· Preventative MaintenanceIn general, a preventative maintenance program is for the purpose of trying to anticipate possiblemaintenance that will be required and to choose when to perform that maintenance prior to the actualneed for the maintenance, thus eliminating most emergency responses for the maintenance, orpossible ending up with out a sample.

· Reactive MaintenanceThis is when maintenance is only performed as a reaction to the cylinder not being capable ofcontaining a sample properly due to some type of component fatigue.

Each cylinder must be visibly reinspected at least once a year for deterioration of seals,scratches, dents, and gouges. Components that are deteriorated or damaged must be replacedby factory specified parts as shown on YZ drawings. Components may be replaced by thefactory or user, observing Tie Rod Nut tightening torque values. Additionally at least once ayear, the end caps, tie rods, and cylinder must be thoroughly cleaned with appropriate solventrecommended by the manufacturer. Replace rupture disc every year under normal conditions.A more frequent change out of the rupture disc may be necessary due to corrosion, fatigue,temperature, or adverse conditions. These factors must be evaluated by the user throughactual service experience. However; if the disc is not changed periodically when exposedto these conditions, premature failure (due to elapsed time or pressure) of the rupturedisc may occur, thereby discharging the process media.

Recommended spare parts:

Part Number Description Qty.D3-0052 3" DuraSite Seal Repair Kit 1A3-0084 1800 psi Rupture Disc 2

9. Cylinder Maintenance:

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 11: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

11

Rupture Disc Design:A rupture disc is a thin wafer of metal placed in a specially designed port for the purpose ofprotecting the device and anyone near it from danger due to over pressure of the device. If thedevice is over pressured this device SHOULD burst.This overpressure may be a result of many factors, a couple of the most common causes areoverfilling of the vessel, or a rise in temperature of a vessel that is full of liquids with no gasexpansion area. Rupture disc typically used on our DOT sample vessels are rated at apressure, but has a typical tolerance of +/- 10% @ 72o F. All fluctuations of pressure and/ortemperature begin the weakening process of the rupture disc. that leads to requiredmaintenance.

· Safety Precautions Before Installation1. The special standard flat seat rupture disc is a precision instrument and must be handled

with extreme care. Rupture discs should be installed only by qualified personnel familiar with rupture discs and proper piping practices.2. Do not install rupture disc if there is any damage in the dome area. A damaged rupture disc is any rupture disc with visible nicks or dents.3. Do not install a rupture disc that has been previously installed and removed from the disc holder, as reinstalling may adversely affect the joint sealing capabilities and/or performance of the rupture disc

· Replacement Procedure1. Assure that the vessel has no pressure left in it.2. Remove the rupture disc. retaining nut.3. Remove the old Rupture Disc, and discard it.4. Remove the old Kel-F/TFE washer, and discard it.5. Inspect the retaining nut surface where it contacts the rupture disc, for any nicks, or

deformities. Replace it if any are found.6. Inspect the seat area in the disc pocket for any nicks, or deformities. Replace it if any are

found.7. Install the new TFE washer in the disc pocket.8. Lubricate the face of the retaining nut that contacts the rupture disc, with a thin coat of light

weight grease.9. Install the new rupture disc wafer in the pocket on top of the TFE washer with the dome side

of the disc facing up.10. Install the retaining nut & tighten finger tight.11. Final tightening of the retaining nut should be done with a Torque Wrench ONLY.

Torque to PRECISELY 15 Ft. Lbs.

9. Cylinder Maintenance:

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com

Page 12: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

12

Diagram #1: DuraSite Sample Vessel

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912 Email: [email protected] Website: www.eesgroup.com

Page 13: EASTERN ENERGY SERVICES PTE LTD. · EASTERN ENERGY SERVICES PTE LTD. ... sampling device, ... Contained inside of the cylinder is a moving piston fitted with seals to ensure a leak-free

13

Diagram #2: YZ Systems Adjustable Relief Valve(Optional)

BODY

ADJUSTMENT SCREW

INLET HEAD

1/4" NPT

STANDARD INDICATOR

RV-Relief Valves, Adjustable Pressure Model Number Options0.......................................... 0-15 psig1.......................................... 0-100 psig8......................................... 100-800 psig18....................................... 800-1800 psig23...................................... 1800-2300 psig

Discharge Connection-S Standard visual indicator-4 1/4" FNPT-8 1/8" FNPT

Relieving PressureFactory set per customer specification

Example: Model RV18-8-1450 = relief valve, 800-1800 psig range, 1/8" FNPT discharge connectionwith relieving pressure set at 1450 psig per customer specification

EASTERN ENERGY SERVICES PTE LTD.60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG 415979 SingaporeTelephone: +65-6748 6911 Fax: +65-6748 6912Email: [email protected] Website: www.eesgroup.com