eastern africa power pool - usea.org · pdf fileeastern africa power pool ... egypt, ethiopia,...

20
Eastern Africa Power Pool Energy Efficiency Workshop Washington- March, 2010 Safaa Hamed Chief Engineer Egyptian Electricity Holding Company

Upload: truonglien

Post on 17-Mar-2018

227 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

Eastern Africa Power Pool

Energy Efficiency WorkshopWashington- March, 2010

Safaa Hamed

Chief Engineer

Egyptian Electricity Holding Company

Page 2: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

2

Definition of Power Pool

A framework for pooling energy resourcesand promoting power exchanges betweenutilities in a given geographic area basedon an integrated master plan andpre-established rules

Page 3: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

3

Objectives of Power Pools• Secure their respective power supply• Provide mutual assistance in case of

failure in their respective power systems• Reduce power supply costs• Provide social , economic and

environmental benefits • Strengthen the relationship between

countries

Page 4: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

4

Establishment of Eastern Africa Power Pool (EAPP)

• On February 24 , 2005 Seven African countries (Congo, Egypt, Ethiopia, Kenya, Rwanda, Burundi, Sudan) signed a MOU.

• The MOU covers issues such as members, obligations, organizational structure, resources, arbitration and enforcement.

• Later on Tanzania, Djibouti and Uganda Joined the EAPP

Page 5: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

5

Eastern Africa Power Pool (EAPP)

Egypt

Sudan ُ◌◌ُEthiopia

Kenya

Tanzania

ogh

CongoDR. Northern Part : Egypt,

Sudan, Djibouti , Ethiopia

Southern Part : Kenya, Uganda, Rwanda, Burundi,

DRC Tanzania.

Page 6: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

6

EAPP Objectives• Secure power supply for countries of the Region• Facilitate in the long term the development of an

electricity market• Optimize the usage of natural energy resources

( Oil & gas- Solar- Hydro-Geothermal )• Increase the population access rate to power• Reduce electricity cost • Create a conducive environment for investments

Page 7: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

7

Key Issues &Difficulties

• Infrastructure –decayed roads, –slow telecommunication,– unsafe airports ,–lack of oil/gas pipelines

• Strain on network & high losses• Relatively low electrification• Missing or not updated data

Page 8: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

8

Sponsoring Agencies

• United Nations Economic Commission for Africa (ECA)

• The African Union (AU) • The Union of Producers, Transporters and

Distributors of Electric Power in Africa (UPDEA)

• Common Market for Eastern and Southern Africa (COMESA).

Page 9: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

9

Main Projects & Financiers•Regional Master Plan & Grid Code Study funded by African Union (NEPAD – IPF)

•Technical Assistance and Capacity Building funded by European Union ( EU)

•Technical Assistance of Operation Coordination Centre & Independent Regulatory Body (Norwegian Government)

Page 10: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

10

Main Projects & Consultants• Consortium of SNC Lavalin (Canada) and Parsons Brinckerchoff (UK) forRegional Master Plan & Grid Code Study

• Mercados - Energy Market International forTechnical Assistance and Capacity Building Studypromoting efficient and sustainable energy markets, designing effective regulation

Page 11: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

11

Regional Master Plan & Grid Code Study (Lavalin )

Objectives• Identify power generation and

interconnection projects • Prepare a master plan • Develop a common Grid Code • Strengthen the Institutional capacity for

EAPP

Page 12: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

12

Study Implementation

Completed activities•Draft of Inception report has been reviewed•Generation and future options have all been collected and reviewed•Final Inception report has been submitted

Page 13: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

13

Study Implementation

Activities in Progress• Preparation of interim report• Preparation of final master plan report • Training• The study shall be completed on January

2011

Page 14: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

14

Contents of final Inception Report

• Opportunities for cross-border interconnections in the region.

• Updates on the proposed methodology for the load forecast and other main activities

• Proposed tables of contents for the Master Plan and Grid Code reports

• Proposed schedule for the home office and local training sessions

Page 15: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

15

Expected Power Exchange • Countries with export potentials are Uganda.

Ethiopia, Rwanda and DRC• Egypt present and future will have 60 % of total

EAPP generation• It is expected that Egypt will not be a net

importer or exporter of electricity or fuel (gas)

• Djibouti , Kenya, Burundi, Sudan and Tanzania are assumed to import

• Most countries would benefit from reserve sharing

Page 16: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

16

Technical Assistance and Capacity Building Study (Mercados)

Objectives• Strengthen the capability of the EAPP to

improve the integration of the electricity markets• Assess the existing and future regional power

market and build a database for strategic planning.

• Establish a long term Strategy for increasing cross border trading, and a business plan

• Introduce regulations and agreements for cross border trading in the region

Page 17: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

17

Mercados Study Implementation

Completed activities

• Draft design of regional power market • Final Inception report has been submitted• The second progress report has been

presented

Page 18: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

18

Mercados Study Implementation

Activities in Progress

• Completion of the power market assessment and trade flows study

• Preparation of a strategic road map to 2025 anda 5 year business plan

• Preparation of a MOU and treaty to supportcross border treaty

Page 19: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

19

The challenges to be Faced

• Infrastructure bonds:– decayed roads, – slow telecommunication, – unsafe airports and railway services.

• Regulations of cross border treaty

• Lack of funding• Political Instability

Page 20: Eastern Africa Power Pool - usea.org · PDF fileEastern Africa Power Pool ... Egypt, Ethiopia, Kenya, Rwanda, ... obligations, organizational structure, resources, arbitration and

20

Conclusion

The East African region has no shortageof resources to generate electricity andhas an environment that is attractive forfinanciers to help the region sustainabledevelopment .