east leeds orbital route(elor) phase 3 · 2020-03-04 · east leeds orbital route(elor) phase 3 feb...

59
EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020

Upload: others

Post on 03-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

EAST LEEDS ORBITALROUTE(ELOR)

Phase 3Feb 2020

Page 2: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Aim• Scheme overview & update• Programme

– High level summary– Works planned for the next 3 months

• Construction of intersecting junctions• Closure of Coal Road & Thorner Lane• Traffic management and Public Rights of Way

(PROW)

Page 3: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Overview

• Infrastructure required to allow the construction of 5000 new homes withinthe East Leeds Extension and to ease congestion on surrounding routes

• Planning Approval PGranted• Land Acquisition Process PDone• Improvements to a number of existing Outer Ring Road junctions• Phase 3 – Main works from A6120 Red Hall to Manston Lane Junction

• 6.8Km new carriageway• Segregated cycleway/footpath• Extensive landscaping• 5 New round-about junctions + 1 Tie in to existing junction• 2 bridges• 3 footbridges

Page 4: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Programme Overview• 2 Year main construction works programme starting after Easter, Spring 2020 – Summer 2022• Preconstruction works from January 2020 –

• land access, site clearance, surveys, archaeological works, main site compound• Offline junctions prioritised to gain access to the site and allow SU service diversion works to commence• Start offline bulk earthworks on 3 working fronts;

• Manston Lane• Barwick Rd roundabout• A64 roundabout

• Structures to commence June 2020 until October 2021

Page 5: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

High Level Summary – Overall Programme

PHASE J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Overall ELOR Phase 3 ProgSite Clearance/Archaeological Works (trenches)Start Main Works (After Easter 2020)Junction Works (5 no)Bulk EarthworksRoadworksVerge & FootwaysStructures (6 no)Landscaping & Planting

2020 2021 2022

Whinmoor

Scholes

Red Hall

Manston

Swarcliffe

Page 6: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

High Level Summary - Junctions

PHASE J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Overall ELOR Phase 3 Prog

Ch.0-60 - A6120 Redhall RoundaboutCh740-900 - A58 RoundaboutCh.2340-2480 - Skeltons Lane RoundaboutCh.3240-3460 - A64 RoundaboutCh.5040-5160 - Barwick Road Roundabout

2020 2021 2022

Whinmoor

Scholes

Red Hall

Manston

Swarcliffe

Page 7: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Works planned for the next 3 months (Upto May 2020)

• Site Compound – Main/Satellite• Access/SU Service utilities protection works• SU Service utilities diversion works• Archaeological trial trenches and recording• Site clearance• Setting out/fencing works• Commence main works:

• Junction works – Offline

• SU Service diversions

• Topsoil strip

• Bulk earthworks

• Ponds

• Drainage

Site Compound

Site Clearance Setting Out Archaeological Trenches

Page 8: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Works in the next 3 Months – Earthworks/Access

PHASE 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May

Fencing - Site BoundarySite ClearanceAccess/Haul Routes/Satellite CompoundsTopsoil Strip Start after Easter

Excavation/Fill Earthworks Start after Easter

Ground ImprovementsSU Service Utilities Diversion Works Start after Easter

March April May

Whinmoor

Scholes

Red Hall

Manston

Swarcliffe

Page 9: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Works in the next 3 Months – Junction Works

PHASE 02-Mar 09-Mar 16-Mar 23-Mar 30-Mar 06-Apr 13-Apr 20-Apr 27-Apr 04-May 11-May 18-May 25-May

Access/Crossing Points/Satellite CompoundsCh.0-60 - A6120 Redhall Roundabout OFFLINE WORKS SU Diversions (to June 21) Topsoil Strip

Ch740-900 - A58 Roundabout OFFLINE WORKS Topsoil Strip SU Diversion

Ch.2340-2480 - Skeltons Lane Roundabout OFFLINE WORKS Topsoil Strip

Ch.3240-3460 - A64 Roundabout OFFLINE WORKS Topsoil Strip Bulk Earthworks/Complete Topsoil Strip

Ch.5040-5160 - Barwick Road Roundabout OFFLINE WORKS Topsoil StripDra inage Bulk Earthworks Settlement

March April May

Whinmoor

Scholes

Red Hall

Manston

Swarcliffe

Page 10: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Junctions – GeneralConcept

• Minimise disruption to road users and pedestrians. shortconstruction duration, keep the traffic flowing.

• Road speed limit reduced to 30mph• Working Hours:

– 0800 – 1800hrs Weekdays

– Peak

– Off Peak

– Minimise night-time and weekend working

– Minimise lane & road closures

• Build Offline to allow SU servicediversion works

• SU service diversion Works• Online carriageway works• Tie-In Works• Island Construction• Final Surfacing

Example ofvisiting driversflash card

Offline

Offline

Tie-InTie-In

Island

Island

Controlled accessfor deliveries

• Redhall Lane –No access toconstructiontrafficOnline (Existing Rd)

New C/Way& R/about

SU ServiceDiversion Works

Page 11: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.0-60A6120 Redhall Roundabout

Page 12: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.0-60A6120 Redhall R/abt• Offline construction for SU service utilities

diversion works

• Extensive site clearance – ongoing

• New access to main site compound

• Extensive cut/fill earthworks

• Road speed limit reduced to 30mph

• Narrow Lanes – Offline works

• Ability to divert 2 way traffic onto new offlineroundabout to construct remainder of online

• 2 Way traffic signals – SU & carriageway tie-ins

• Minimum Closures – Surfacing

• Pedestrians managed through the works tonorth side.

Page 13: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch740-900A58 Roundabout

Page 14: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch740-900A58 Roundabout• Road crossing for construction traffic

• Offline construction for SU service utilitiesdiversion works

• Access maintained to The Wellington pub

• Low volume of fill earthworks

• Road speed limit reduced to 30mph

• Narrow Lanes – Offline works

• Ability to divert 2 way traffic onto new offlineroundabout to construct remainder of onlineworks

• 2 Way traffic signals – Off peak works

• Minimum closures – Surfacing

• Pedestrian route maintained whilst east sideconstructed offline then divert to new westfootpath

Page 15: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 1 –Temp Access Points• Temporary access for materials

delivery and inter-site earthworksmovements.

• 2 way traffic signals

Page 16: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 2 –Offline Works• Offline works to provide new

corridor for SU service utilitiesdiversion works

• Narrow lane running.

• Pedestrians managed locallythrough the works.

• Public rights of way adjacent tosite diverted onto approvedroutes

Page 17: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 3 –SU Service Diversions

• Offline SU service utilitiesdiversion routes with existingtraffic on narrow lane running.

• 2 way traffic signals for SUservice utilities connections

• Footpath construction on newalignment

Page 18: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 4 –Tie-in to Existing Rd

• Tie-in to existing road.

• Complete carriageway alignmentto service strip following SUservice utilities diversion works

• Off-peak 2 way traffic signals

• Pedestrians remain on existingroad alignment.

Page 19: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 5 –Tie-in to Existing Rd

• Switch 2 way traffic onto eastside of new roundabout.

• Narrow lane running.

• Complete tie-in and service stripalignment west side of existingroad.

• Pedestrian re-routed onto newfootpath alignment to east side ofnew roundabout

Page 20: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 6 –Islands• Traffic switch onto east and west

carriageway with through trafficonly to allow construction of newtraffic islands

• Pedestrians remain on east sideof new roundabout.

Page 21: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 7 –Final Surfacing• 2 way traffic switched to east

side of new roundabout

• Maximise working area for finalsurfacing to westside ofroundabout

• Pedestrians remain on east sideof new roundabout.

Page 22: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 8 –Final Surfacing• 2 way traffic switched to west

side of new roundabout

• Maximise working area for finalsurfacing to east side ofroundabout

• Pedestrians switched to westside of new roundabout.

Page 23: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 9 -Tie-in Surfacing• Short term closure of Wetherby

road to complete final surfacingto tie-ins

• Both east and west footpathsavailable for pedestrians. Localclosures to suit progress of theworks.

Page 24: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.2340-2480Skeltons Lane Roundabout

Page 25: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.2340-2480Skeltons Lane• Road crossing for construction traffic

• Offline construction for SU service utilitiesdiversion works

• Very limited earthworks

• Road speed limit reduced to 30mph

• 2 Way traffic signals for tie-in to existingcarriageway works and online works, diverttraffic onto new roundabout for mainsurfacing

• Minimum closures – final surfacing at tie-ins

• No existing pedestrian footpath

• Access for Country Park Underpassstructure

No Entry forConstructionTraffic

Page 26: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.3240-3460A64 Roundabout

Page 27: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.3240-3460A64 Roundabout• Minimise disruption to road users

narrow lane running where possible

• Road speed limit reduced to 30mph

• Minimise impact on Mortec Park &Morwick Farm – staged working

• Thorner Lane permanent closuretiming tbc, as late as possible.

• Temp. relocate bus layby.

• Construct offline for SU serviceutilities diversion works.

• Pedestrian management throughthe works

Mortec Park

Morwick Farm

Thorner Ln

Scholes Ln

A64York Rd

Page 28: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 1 –Temp Access Points

• Temporary access points -protection for existing SU serviceutilities.

• Temporary access/road crossingpoints – Materials delivery andearthworks movements fromother sections of the new works

• Traffic to remain on currentalignment.

Page 29: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 2 –Offline Works• Traffic islands and turning lanes in

middle of road removed.

• Traffic realigned to run undernarrow lanes on north side of thecarriageway.

• Thorner Lane to remain open.

• Mortec Park access maintained.

• This provides a working lane onsouth side of carriageway to allowmaintenance of footpath during theconstruction period.

• Off line areas of new roundabout tobe constructed to allow SU serviceutility diversions.

Page 30: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 3 –SU Service Diversions

• Traffic realigned to run undernarrow lanes on north side of thecarriageway.

• Thorner Lane to remain open.

• Mortec Park access maintained.

• Off peak traffic lights required attie-in points for SU serviceutilities and connections.

Page 31: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 4 –Tie-in to Existing Rd

• Traffic realigned to run undernarrow lanes on north side of thecarriageway.

• Thorner Lane to remain open.

• Mortec Park access maintained.

• SU service utility works completeallowing completion of the Southcarriageway.

• Off peak traffic lights required atcarriageway tie-ins.

Page 32: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 5 –Relocate local access

• Traffic realigned to run undernarrow lanes on north side of thecarriageway.

• Thorner Lane to remain open.

• Mortec Park and Morwick Farmaccesses to switch to newalignment.

• This allows completion of thesouth carriageway.

Page 33: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 6 –Tie-in to Existing Rd

• Traffic realigned onto new southcarriageway.

• Thorner Lane be closedpermanently.

• Footpath to be realigned ontonorth side of new roundabout.

• Completion of north carriagewaywith off-peak traffic lights requiredat carriageway tie-ins.

Page 34: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 7 –Final Surfacing

• Traffic on new south carriageway.

• Thorner Lane be closedpermanently.

• Footpath to be realigned ontosouth side of new roundabout.

• Final surfacing and white lining tonorth side of roundabout.

Page 35: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 8 –Final Surfacing

• Traffic realigned onto new northcarriageway.

• Thorner Lane be closedpermanently.

• Footpath to be realigned ontonorth side of new roundabout.

• Final surfacing and white liningto south side of roundabout.

Page 36: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 9 -Tie-in Surfacing

• Off peak closure of A64 requiredto complete surfacing and whitelining at tie-ins.

• Closures kept to a minimum byundertaking off line surfacing instages 7 and 8.

Page 37: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.5040-5160Barwick Road Roundabout

Page 38: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.5040-5160Barwick Rd R/abt• Road crossing for construction traffic due to

earthworks material movements

• Offline construction for extensive SU serviceutilities diversion works

• Road speed limit reduced to 30mph

• 2 Way traffic signals for tie-ins to existingcarriageway works

• Divert traffic onto south side of newroundabout for online works

• Minimum closures – final surfacing

• Pedestrian access maintained through theworks via local diversions to suit phasing ofthe works.

• Access for Wood Lane footbridge structure

Page 39: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 1 –Temp Site Access• Temporary access points -

protection for existing SU serviceutilities.

• Temporary access/road crossingpoints – Earthworks movementsfrom other sections of the newworks

• Traffic to remain on currentalignment.

• Pedestrians remain on northside.

Page 40: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 2 –Offline Works• Construct offline new roundabout

earthworks to enable SU serviceutilities diversion works

• Traffic maintained on existingalignment.

• 2 way traffic signals for tie-inworks adjacent to existingcarriageway.

• Pedestrians remain on northside.

Page 41: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 3 –SU Diversion Works• Complete SU service utilities

diversion works offline and onlineservice connections.

• 2 way traffic signals for SUservice utilities connectionworks.

• Construct carriageway andfootpath works offline

Page 42: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 4 –Online Service Strip• Complete offline footpath works.

• 2 way traffic signals to completeonline service strip once SUservice utilities have beendiverted

Page 43: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 5 –Tie-in Works• Switch 2 way traffic onto new

carriageway using narrow laneson south side of roundabout.

• Remove service strip to centre ofroundabout and completecarriageway construction.

• 2 way traffic signals to completetie-in works.

Page 44: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 6 –Traffic Islands• Reduce roundabout to single

lane to each side of roundaboutfor through traffic only toconstruct traffic islands

Page 45: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 7 –Final Surfacing• Off peak traffic control

• Live traffic to south side of newroundabout

• Maximise working area to thenorth for final surfacing works

Page 46: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 8 –Final Surfacing• Traffic management switch to

maximise working area to thesouth for final surfacing works

• Off peak traffic control

• Live traffic to north side of newroundabout

Page 47: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Stage 9 –Final Surfacing• Short term closure to complete

final surfacing to tie-in withBarwick Road

Page 48: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Ch.6770Manston Ln Tie-In• Tie-in to newly constructed

roundabout on Manston Lane• Temp access west of proposed

road whilst new embankmentconstructed

• Early access to structures andground improvement locations.

• SU service utilities diversionlocal to existing roundabout

• Public Rights of Way –Alternative routes

Page 49: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Closure of Coal Road &Thorner Lane

Page 50: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Coal Road• Only close when necessary• Multiple SU service utilities

diversions, new and slew/lowerexisting. Temporary lane or fullclosures maybe required oncemore detailed information isreceived from the Stat’sUndertakers.

• New carriageway construction

RM1

Page 51: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Slide 50

RM1 Carriageway construction May 2021Redmond, Martin, 24/02/2020

Page 52: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Thorner Lane• Only close as necessary• Multiple SU service utilities

diversions, working room at SUservice tie-in locations to beconfirmed

• New carriageway construction• Carriageway tie-in location• Location of bus layby• Access option for large sized

deliveries for bridge structures tothe north.

Page 53: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Public Rights of Way

Page 54: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Temporary footpathclosures• Footpaths will not be closed until

works are being undertaken inthat area.

• Closure of footpaths expected tobe on a rolling programme ofclosures from April – June untilcompletion of project.

• Permanent routes – Footbridges• Advanced notification signs

where the public rights of wayleave the roadside.

• Regular inspections of signs

Page 55: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

A6120 Redhall to A58

• Temporary closure & diversion route using alternative routes where existing PROW crosses the new carriageway• Footpaths at junction locations will be managed with local footpath diversions

Page 56: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Skeltons Lane to A64

• Footpaths at junction locations will be managed with local footpath diversions

Page 57: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

A64 to Barwick Road

• Temporary closure & diversion route using alternative routes where existing PROW crosses the new carriageway• Footpaths at junction locations will be managed with local footpath diversions

Page 58: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Barwick Rd to Manston Lane

• Temporary closure & diversion route using alternative routes where existing PROW crosses the new carriageway• Footpaths at junction locations will be managed with local footpath diversions

Page 59: EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 · 2020-03-04 · EAST LEEDS ORBITAL ROUTE(ELOR) Phase 3 Feb 2020. Aim • Scheme overview & update • Programme – High level summary –

Example of project scheme sign – Phase 1

ContactDetails