east busway project presentation

Upload: satyavan-l-roundhal

Post on 03-Jun-2018

227 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/12/2019 East Busway Project Presentation

    1/46

    The Martin Luther King Jr.East Busway

    A Cost-Benefit Analysis

  • 8/12/2019 East Busway Project Presentation

    2/46

    Overview

    Pre-1978 History

    Port Authoritys CBA (1978)

    Revising Port Authoritys CBA

    Actual Results

  • 8/12/2019 East Busway Project Presentation

    3/46

    History of the East Busway

    The busway was part of theEarly Action Plan (EAP)

    EAP consisted of 3 otherprojects

    EAP was largest transit projectin Pennsylvania ever

    Construction was to begin in1971

  • 8/12/2019 East Busway Project Presentation

    4/46

  • 8/12/2019 East Busway Project Presentation

    5/46

    Delay of the East Busway

    Lawsuit delayed the project 6 years until1978

    Factors that increased project costs:Oil crises

    Spiraling inflation

    Right of way dispute with railroads

    Construction was completed in 1983

  • 8/12/2019 East Busway Project Presentation

    6/46

    Port Authoritys 78 CBA

    Capital Costs

    Operating Costs

    Benefits

    Benefit Cost Ratio

  • 8/12/2019 East Busway Project Presentation

    7/46

    Capital cost estimates grew

    during the delay

    15

    3440

    78

    110

    9

    21

    33

    68

    110

    0

    20

    40

    60

    80

    100

    120

    70 71 72 73 74 75 76 77 78

    Year

    Cost(Million

    s)

    1978 Dollars Nominal Dollars

  • 8/12/2019 East Busway Project Presentation

    8/46

    Port Authoritys Capital Costs

    Project Costs

    Original Project $20,000,000

    Cost of Delay (from inflation) $20,000,000

    Additional Cost of Property Over Estimate $6,800,000

    Costs for Adjustments to Conrail

    Cost to Accommodate Conrail $36,900,000

    Vertical Separation $6,000,000

    Improvement CostsNeville Ramp Addition $10,600,000

    East Liberty Station Improvements $3,200,000

    Additional Changes $6,500,000

    Capital Costs Total $110,000,000

  • 8/12/2019 East Busway Project Presentation

    9/46

    Port Authoritys Operating Costs

    Per Year

    Maintenance Costs $700,000

    Total Operating Costs $700,000

  • 8/12/2019 East Busway Project Presentation

    10/46

    Port Authoritys Financing Costs

    Per Year

    Busway cost: $110M at 5.6% for 30

    years

    $6,160,000

    Total Costs $6,160,000

  • 8/12/2019 East Busway Project Presentation

    11/46

    Benefits promised during the delay

    Quantified Benefits: $82.4M time savings for current passengers $29.4M savings for new passengers (time and auto costs) $21.8M in time savings for drivers from reduced congestion $11M in additional property tax revenue

    At the peak construction level, 670 workers will be employed on the PATways. Theirearnings will total $13 million.

    Non-quantified benefits: provide benefits to job opportunities, urban renewal and economic development have been

    calculated in the hundredes of millions of dollars unquantifiable quality of life benefits" "intangible benefits of new mobility will not be measurable in dollars and cents"

    improve mobility in decaying neighborhoods, raising property values and inspiring renewal. inspire new construction of all kinds --- commercial, residential, and industrial. provide "new suburban employment, medical, and recreational opportunities to ghetto

    residents. enhance environmental quality, pollution reduced due to fewer cars on the road

  • 8/12/2019 East Busway Project Presentation

    12/46

    Port Authoritys Benefits

    Project Benefits

    Operating Time Savings $ 819,000

    (97 hours per day @ $28 per hour) (=29,100 hours/year)

    Riders Time Savings $7,770,000

    (10 minutes per round trip for 54,000 daily riders)

    (8633 hours per day @ $3 per hour) (=300 days/year)

    Sub-Total $8,589,000

    Less Annual Maintenance Cost $ 700,000

    Total Net Benefits $7,889,000

  • 8/12/2019 East Busway Project Presentation

    13/46

    The Rise and Fall of 82 Ridership

    ProjectionsProjected Ridership

    46

    60

    74

    9080

    0

    20

    40

    60

    80100

    1973 1975 1976 1978 1982

    Thousands

    ProjectedRidership

  • 8/12/2019 East Busway Project Presentation

    14/46

    Port Authoritys CBA

  • 8/12/2019 East Busway Project Presentation

    15/46

    Whats missing from Port

    Authoritys analysis?

    Missing benefits

    No loan principal No NPV

    No discount rate

    The benefit-cost ratiomay be inflated

  • 8/12/2019 East Busway Project Presentation

    16/46

    Port Authoritys Benefit Problems

    78 analysis indicates many potential benefitswithout any attempt at measurement: Vehicle Emissions

    Safety 78 analysis points to future benefits ($10

    million/yr) for future riders without analyzingassociated costs:

    Service ExpansionUnidentified Improvements

    Previously mentioned benefits gone!

  • 8/12/2019 East Busway Project Presentation

    17/46

    Port Authority inflated BC ratio

    using annualized costs Their BC ratio = 1.28

    Used annualized values basedon a representative year

    This hides the fact that benefitsdo not start until five yearsafter costs.

    Total: BC Ratio = 1.06

    Result: BC Ratio = 1.25

    Year Time Total Cost Total Benefit Ratios

    1978 0 -6,160,000 0

    1979 1 -6,160,000 0

    1980 2 -6,160,000 0

    1981 3 -6,160,000 0

    1982 4 -6,160,000 0

    1983 5 -6,860,000 8,589,000 1.25

    1984 6 -6,860,000 8,589,000

    1985 7 -6,860,000 8,589,000

    Total -202,300,000 214,725,000 1.06

  • 8/12/2019 East Busway Project Presentation

    18/46

    Their Way

    Time Savings 7,770,000

    Operating Savings 819,000

    Maintenance Cost -700,000

    Annualized Benefits 7,889,000

    Finance Cost -6,160,000

    Annualized Costs -6,160,000

    Annualized BC Ratio 1.28

  • 8/12/2019 East Busway Project Presentation

    19/46

    Our Way

    Time Savings 7,770,000

    Operating Savings 819,000

    Annualized Benefits 8,589,000

    Finance Cost -6,160,000

    Maintenance Cost -700,000

    Annualized Costs -6,860,000

    Annualized BC Ratio 1.25

  • 8/12/2019 East Busway Project Presentation

    20/46

    Adding the loan principal makes a

    difference

    No principal payments:

    NPV = 12,425,000

    With principal payments:

    NPV = -32,346,343

    Assumes 0% discount rate over 30 years. Thus NPV = net benefits

  • 8/12/2019 East Busway Project Presentation

    21/46

    Estimating a discount rate for 1978

    Nominal yields on corporate AAA bonds 8%

    Nominal T-bill rates 7.57%

    Inflation 7.6% Corporate tax est.40%

    Individual tax est. 20%

  • 8/12/2019 East Busway Project Presentation

    22/46

    Reasonable social or

    institutional nominal discountrates range from 7.5% to 13%

    rz= Marginal Rate of Return on Private InvestmentAAA Corporate Bond Yields 8.00%

    Average corporate investment taxes 40%

    After tax nominal rate (bond yield/1-tax rate) 13.33%

    pz= Marginal Social Rate of Time Preference

    T-bill Rate of Return 7.57%Average personal investment taxes 20%

    After tax nominal rate (T-bill rate/1-tax rate) 9.46%

  • 8/12/2019 East Busway Project Presentation

    23/46

    Discounting actually

    improves NPV

    Rate NPV

    Undiscounted 0% -32,346,344Untaxed Rz 7.57% -31,284,651

    Aftertax Rz 8.00% -31,141,424

    Untaxed Pz 9.46% -30,635,167

    Aftertax Pz 13.33% -29,230,007

  • 8/12/2019 East Busway Project Presentation

    24/46

    Discounting improves NPV because it reduces the presentvalue of heavy loan payments during first few years

    T

    e

    Benefits 1/(1+r)^t

    scoun e a

    13.33%

    0 -7,652,378 1.00 -7,652,378

    1 -7,652,378

    0.88 -6,752,297

    2 -7,652,378 0.78 -5,958,084

    3 -7,652,378 0.69 -5,257,288

    4 -7,652,378 0.61 -4,638,920

    5 236,622 0.53 126,570

    6 236,622 0.47 111,683

    7 236,622 0.42 98,5468 236,622 0.37 86,955

    Textbook problems usually assume costs occur at T=0, but if costs happen

    later, they get discounted too.

  • 8/12/2019 East Busway Project Presentation

    25/46

    Additional problems with Port

    Authoritys analysis Funding too aggregated

    Economic impact of taxes ignored

    Time savings understated

    Option value ignored

    Accounting for futureinflation ignored

    No recognition of uncertainty

  • 8/12/2019 East Busway Project Presentation

    26/46

    Funding was more complicated

    than a single bond issue

    $88M federal grants

    $11M in statecontributions

    $11M local funding

    10%

    10%

    80%

    Federal

    State

    Local

  • 8/12/2019 East Busway Project Presentation

    27/46

    How were funds raised?

    Locally, Port Authority intended sell bonds

    (30 years, @5.6% payment=$765K)

    Likely serviced debt with county propertytaxes

    State funding: 50% income and 50% sales

    taxes Federal funding: income taxes

  • 8/12/2019 East Busway Project Presentation

    28/46

    When were the funds raised?

    State and federal fundingto be appropriated eachyear over the construction

    project (4-5yrs)

    Local funding servicedover 30 years

    Distribution of Funding

    18%

    21% 22% 21%

    18%

    0%

    5%

    10%

    15%

    20%

    25%

    Y1 Y2 Y3 Y4 Y5

    Construction Year

  • 8/12/2019 East Busway Project Presentation

    29/46

    How much did they cost to raise?

    Amount Rate METB

    Local property taxes 22,957,134 17.0% 3,902,713

    State income taxes 5,500,000 25.0% 1,375,000

    State sales taxes 5,500,000 43.5% 2,392,500

    Federal income taxes 88,000,000 43.5% 38,280,000

    Total 45,950,213

  • 8/12/2019 East Busway Project Presentation

    30/46

    With METB and more realistic fundingassumptions NPV gets worse, except for

    undiscounted case

    Rate NPV

    Undiscounted 0% -32,346,344

    Untaxed Rz 7.57% -31,284,651

    Aftertax Rz 8.00% -31,141,424

    Untaxed Pz 9.46% -30,635,167

    Aftertax Pz 13.33% -29,230,007

    Rate NPV

    Undiscounted 0% 29,317,653

    Untaxed Rz 7.57% -68,520,605

    Aftertax Rz 8.00% -70,579,163

    Untaxed Pz 9.46% -76,261,658

    Aftertax Pz 13.33% -84,552,731

    Previous Assumptions With realistic funding and METB

  • 8/12/2019 East Busway Project Presentation

    31/46

  • 8/12/2019 East Busway Project Presentation

    32/46

    Port Authoritys benefits could have

    been higherProject Benefits

    Operating Time Savings $ 819,000

    (97 hours per day @ $28.00 / hour) (29,100 hours/year)

    Riders Time Savings $8,100,000

    18.5 minutesper round trip for 34,300daily riders

    10,617hours per day @ $3 per hour, 256days/year

    Sub-Total $8,919,000

    Option Value

    (Assumes Bus Commuters to Car Commuters 1:1)

    (6 trips per driver a year @ $0.57/trip) $ 184,700

    Total Measurable Benefits $9,103,700

  • 8/12/2019 East Busway Project Presentation

    33/46

    Port Authoritys Benefits

    Project Benefits

    Operating Time Savings $ 819,000

    (97 hours per day @ $28 per hour) (29,100 hours/year)

    Riders Time Savings $7,770,000

    10 minutesper round trip for 54,000 daily riders

    8633hours per day @ $3 per hour 300days/year

    Sub-Total $8,589,000

    Less Annual Maintenance Cost $ 700,000

    Total Net Benefits $7,889,000

  • 8/12/2019 East Busway Project Presentation

    34/46

    New benefits improve NPV, but not

    much

    Rate NPV

    Undiscounted 0% 29,317,653

    Untaxed Rz 7.57% -68,520,605

    Aftertax Rz 8.00% -70,579,163

    Untaxed Pz 9.46% -76,261,658

    Aftertax Pz 13.33% -84,552,731

    Rate NPV

    Undiscounted 0% 42,185,153

    Untaxed Rz 7.57% -64,261,841

    Aftertax Rz 8.00% -66,540,683

    Untaxed Pz 9.46% -72,867,239

    Aftertax Pz 13.33% -82,314,537

  • 8/12/2019 East Busway Project Presentation

    35/46

    Inflation/Uncertainty

    -64 -82M NPV?

    Why bother!

  • 8/12/2019 East Busway Project Presentation

    36/46

  • 8/12/2019 East Busway Project Presentation

    37/46

    Actual results: the good news

    Capital costs were less than 110M

    75 to 101M in 78 dollars

    Maintenance cost 200K rather than 700K

    People reported saving time by riding thebusway

  • 8/12/2019 East Busway Project Presentation

    38/46

  • 8/12/2019 East Busway Project Presentation

    39/46

    Thus ridership benefits were

    overstated by about 3.6M a yearAssuming Port Authoritys assumptions

    about time savings were true except for

    ridership, having 30,000/week rather than54,000 per week cuts time savings in half!

  • 8/12/2019 East Busway Project Presentation

    40/46

    Adding Insult to Injury

    In 1978 Moodys downgraded the countysrating from A-1 to BAA-1.

    Standard & Poors did not follow suit, butbankers (unsurprisingly) insisted on the highercoupon rate.

    Pitt. Press reported a sale of $31M in countybonds at the rate of 6.47% (not 5.6%). A portionwas to go to the East Busway.

  • 8/12/2019 East Busway Project Presentation

    41/46

    Conclusions

    Promises change when you ask for money

    Port Authority CBA wholly inadequate

    Even w/ other benefits, hard to say thebusway was worth it

    In 78 inertia won again

    Still going however

  • 8/12/2019 East Busway Project Presentation

    42/46

  • 8/12/2019 East Busway Project Presentation

    43/46

    Look at these great benefits!

    The extension will attract newcustomers to the system

    13,000 riders (4,000 new)

    Environmental benefits

    Decreases travel times

    Eases traffic congestion

    Adds a decorative greenspace along most of theBusway corridor

    Construction is

    rehabilitating desolate anddeserted areas.

    Provides, at no cost tocommunity residents, variousneighborhood enhancements,such as the rehabilitation of thehistoric Edgewood TrainStationamong many otherimprovements.

    Cost:$62M

  • 8/12/2019 East Busway Project Presentation

    44/46

    Thank You!

  • 8/12/2019 East Busway Project Presentation

    45/46

  • 8/12/2019 East Busway Project Presentation

    46/46

    Capital cost results: looks to be under '78

    budget, but nobody ever bragged about it

    9

    21

    33

    68

    110115

    156

    15

    3440

    78

    110

    75

    101

    0

    20

    40

    60

    80

    100

    120

    140

    160

    180

    70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87

    Year

    Cost(Millions)

    Nominal Dollars 1978 Dollars