Page 1: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

EASiHE

Gary WillsBill WarburtonLester Gilbert

E-Assessment in Higher EducationA JISC project in Institutional Innovation

Page 2: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

2/18

The brief

Address institutional change by engaging academics and students in co-design and co-deployment.

Place the quality of student learning as the first objective. Implement an open source1 solution to institutional e-assessment. Integrate open standards1 services currently available within the

JISC eFramework.The project addresses technical and institutional issues in formative e-assessment by deploying the EdSpace repository and integrating a variety of JISC-funded project tools and standards.

1 Koper, R. (2008). Open Source and Open Standards. In J. M. Spector, M. Merrill, J. van Merriënboer & M. P. Driscol (Eds.), Handbook of Research on Educational Communications and Technology (3rd ed.). New York: Routledge.

Page 3: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

3/18

Formative e-Assessments

Page 4: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

4/18

EdShare

Page 5: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

5/18

Quality metrics

Page 6: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

6/18

Interoperable, accessible, mobile

Page 7: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

7/18

‘New’ e-assessment

Page 8: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

8/18

Existing assets

Page 9: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

9/18

Web 2.0

Page 10: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

10/18

Duration & staffing

Duration Start October 2008, fully funded 18 months From March 2010, institutionally funded 12 months

Project staff Onjira Sitthisak, Project Manager Susan Walters, Research Fellow David Bacigalupo, Research Fellow Bart Nagel, Research Assistant Pei Zhang, Research Assistant Steve Bennett, Veronica Gale, Consultants

Page 11: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

11/18

Investigators

Management group Dr Gary Wills, ECS, PI Dr Bill Warburton, iSolutions, CAA Officer Lester Gilbert, ECS

Steering group Management group, plus: Dr Richard Crowder, ECS Exams officer Dr Hugh Davis, UoS Director of eLearning Dr Ian Giles, LATEU Director Dr Pete Hancock, iSolutions, Core Mission Engagement Manager

Page 12: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

12/18

Collaborating projects

EdSpace / EdShare (Dr Hugh Davis, ECS) AQuRate (Dr Graham Alsop, Kingston) Faroes (Dr Dave Millard, ECS) LexDis (Dr Mike Wald, ECS) MCQFM (Dr Steve Bennett, Univ. Hertfordshire) mPLAT (Dr Dave Millard, ECS) Peer Pigeon (Dr Dave Millard, ECS) Question Mark (John Kleeman) Macfob (Dr Mike Wald, ECS)

Page 13: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

13/18

Schedule

Calendar yearMonths O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M

Budget yearAcademic year

Task

Co-design (tech requirements)Co-design (cultural & institutional)Enhancements prototypingCommunity input, mgmt engagement

Co-deployment user support & education

Institutional culture & practice changes

User support & institutional barriers

KEY: ISS LSL Snr LSL Jnr

Embedding

Evaluation

Year 1YTD Mar 09

Co-deployment pilots

Updates & adjustments

Large-scale deployment

20102008 2009

Initiation

Apr09 - Mar10

Report & review

2011

Apr10 - Mar11Year 2 Year 3

Preliminary evaluation

Page 14: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

14/18

Tasks (first 6 months)

M1-2 Co-design Technical and cultural & institutional requirements for change Processes and information Identify schools which will participate

(initial targets include Medicine, Law, and Mathematics, later Electronics and Computer Science, Engineering, Geography, and Psychology)

M3-6 Technical team: prototype EASiHE repository, integrate services, tools, and standards

M3-6 Institutional team: engage with senior management, selected Schools, students, and other communities

M6 Review

Page 15: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

15/18

Tasks (second 6 months)

M7-8 Co-deployment. Selected users (staff and students) supported (technical team) and educated (institutional team) (facilitated by consultancy)

M9 Evaluation M10-12 Technical team: Adjustments and enhancements M10-12 Institutional team: Support culture and practice changes,

prepare for larger-scale deployment M12 Review

Page 16: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

16/18

Tasks (after 12 months)

M13-16 Co-deployment . Six Schools, Semester 1, supported (technical team and institutional team). Document emerging practice (facilitated by consultancy).

M17 Evaluation M18 Review

M19-30 Embedding. EASiHE embedded within the University infrastructure, made available to all Schools.

Page 17: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

17/18

Deliverables

EASiHE repository and services Documentation on pedagogical design of e-assessments and on

e-assessment management policies Dissemination materials & reports, including co-design and co-

deployment , institutional change, & exemplary practice Project Web site, blog, & wiki Final project report Journal & conference papers on re-use of e-Framework services,

incorporation of MathQTI, student experience of EASiHE, institutional change, & benefits of Web 2.0

Page 18: EASiHE Gary Wills Bill Warburton Lester Gilbert E-Assessment in Higher Education A JISC project in Institutional Innovation

18/18

Thank you!

Questions, comments, discussion…