earned value sos section 3.7 1 541sp8jan24ev3. earned value analysis one approach to measuring...
TRANSCRIPT
![Page 1: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/1.jpg)
Earned Value
SOS section 3.7
1541Sp8Jan24ev3
![Page 2: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/2.jpg)
Earned Value Analysis
One approach to measuring progress in a software project is to calculate how much has been accomplished. This is called earned value analysis. It is basically the percentage of the estimated time that has been completed. Additional measures can be calculated.
Although this is based on estimated effort, it could be based on any quantity that can be estimated and is related to progress.
2541Sp8Jan24ev3
![Page 3: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/3.jpg)
Basic Measures - 1
Budgeted Cost of Work (BCW): the estimated effort for each work task.
Budgeted Cost of Work Scheduled (BCWS): the sum of the estimated effort for each work task that was scheduled to be completed by the specified time.
Budget at Completion (BAC): the total of the BCWS and thus the estimate of the total effort for the project
3541Sp8Jan24ev3
![Page 4: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/4.jpg)
Basic Measures - 2
Planned Value (PV): the percentage of the total estimated effort that is assigned to a particular work task. PV = BCW/BAC
Budgeted Cost of Work Performed (BCWP): the sum of the estimated efforts for the work tasks that have been completed by the specified time.
Actual Cost of Work Performed (ACWP): the sum of the actual efforts for the work tasks that have been completed
4541Sp8Jan24ev3
![Page 5: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/5.jpg)
Progress Measures
Earned Value(EV) = BCWP/BAC
the sum of the PV’s for all completed work tasks
Schedule Performance Index (SPI) = BCWP/BCWS
Schedule Variance (SV) = BCWP – BCWS
Cost Performance Index (CPI) = BCWP/ACWP
Cost Variance (CV) = BCWP – ACWP
5541Sp8Jan24ev3
![Page 6: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/6.jpg)
Example – as of 4/1/08 task Est
effortActual effort
Est Comp Date
Actual Date Comp
1 75 60 1/25/08 2/1/08
2 25 40 2/15/08 2/15/08
3 120 80 5/15/08
4 40 50 4/15/08 4/1/08
5 60 50 7/1/08
6 80 70 9/01/08
![Page 7: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/7.jpg)
For next Tuesday – 1 or 2 people
Use the data from slide 6. Assume that the rest of the tasks finish 1 month late.
Calculate EV, SPI, SV, CPI, and CV at half month intervals from Jan 1 through the finish of the project.
Plot the values as line graphs. Turn in hard copy of the spreadsheet and the graphs.
25 points
7541Sp8Jan24ev3
![Page 8: Earned Value SOS section 3.7 1 541Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much](https://reader035.vdocuments.us/reader035/viewer/2022072015/56649ed15503460f94bdfd2f/html5/thumbnails/8.jpg)
Tuesday, Jan 29 – post mortem
Read two articles– Anreas Birk,”Postmortem: Never Leave a
Project without It”– June Vernier “In-House Software
Development: What Project Management Practices Lead to Success”
– Making Meaning for each – upload together on Monday
8541Sp8Jan24ev3