earned value management (evm) chart analysis · evm chart analysis evm 202 september 2016 3 how to...
TRANSCRIPT
![Page 1: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/1.jpg)
EVM 202 September 2016 1
Earned Value Management (EVM) Chart Analysis
Introduction A key component of Earned Value Management (EVM) is analyzing EVM data, charts, and
reports to assess cost and schedule performance trends as part of an integrated program
management approach. EVM chart and report analysis provides insight into the accuracy of the
performance measurement baseline (PMB) and is useful in determining whether a contractor’s
estimate at completion (EAC) is reasonable, or needs to be explained and/or adjusted based on
EVM data trends.
This job aid provides an overview of the following EVM charts and report:
Cumulative Variance Trend chart
Cost and To-Complete Performance Indexes (CPI/TCPI) chart
Cost/Schedule Variance Trends chart
Estimates at Completion (EAC) chart
Six-Period Summary report
![Page 2: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/2.jpg)
EVM Chart Analysis
EVM 202 September 2016 2
Cumulative Variance Chart The Cumulative Variance chart shows the contractor’s predicted variance at completion (VAC),
cumulative schedule variance (SVCUM), and cumulative cost variance (CVCUM), plotting time on
the x-axis and dollars in millions on the y-axis. You can use this chart to compare a contractor’s
predicted performance against their actual performance.
Sample Cumulative Variance Chart
Note: This sample Cumulative Variance chart, and other charts in this job aid,
display data in a slightly different way than Empower. Depending on the software tool
used by your organization, the charts you see outside of the EVM 202 classroom
may look different from what you see here or in Empower.
![Page 3: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/3.jpg)
EVM Chart Analysis
EVM 202 September 2016 3
How to Analyze this Chart The VAC is the cost variance the contractor predicts at
the end of the contract. SCHED (SVcum) and COST
(CVcum) are the contractor's data calculations of actual
schedule and cost performance. The 0 line is the point at
which work is exactly at budget and on schedule.
If the VAC is positive, then the contractor is predicting an
underrun; their EAC is less than the budget at completion
(BAC). If the VAC is negative, then the contractor is
predicting an overrun; their EAC is more than the BAC.
If the SVCUM is positive, then the contractor has
accomplished more work than planned. If the SVCUM is
negative, then the contractor has accomplished less work
than planned. If the SVCUM is trending down, (i.e., the SVCUM line is sloping downward), then
schedule performance is getting worse.
Note: Negative SVCUM does not necessarily mean that the contract is behind
schedule. You must look at the network schedule to determine if the tasks are on the
critical path before making assumptions about schedule impact.
Note: At contract completion, SVCUM will always be 0 because BCWS will equal
BCWP.
If the CVCUM is positive, then the contractor has spent less than planned to accomplish the work.
If the CVCUM is negative, then the contractor has spent more than planned to accomplish the
work. If the CVCUM is trending down, (i.e., the CVCUM line is sloping downward), then cost
performance is getting worse. In other words, the overrun is increasing or the underrun is
decreasing.
To determine whether the contractor’s EAC is reasonable, compare the contractor's VAC to the
CVCUM. Based on the CVCUM trend data:
If the VAC and CVCUM are approximately the same, then the contractor’s EAC is
reasonable.
If the VAC is more than the CVCUM and the trends are diverging (i.e., getting farther
apart), then it is less likely the contractor can achieve their EAC. If the trends are
converging (i.e., coming closer together), then the EAC is more likely achievable.
Analysis in Action In the previous sample Cumulative Variance chart, the contractor is predicting an underrun
because the VAC is positive (2.3). However, the contractor’s EAC is unreasonable because the
CVCUM has consistently been much less than the VAC, and it is trending downward away from
the VAC. In addition, the VAC and CVCUM trends are diverging, which also indicates that the
contractor's EAC may be unreasonable.
Key EVM Formulas
VAC = BAC − EAC
Positive VAC = Underrun
Negative VAC = Overrun
SV = BCWP − BCWS
Positive SV = Finished more
work than planned
Negative SV = Finished less
work than planned
CV = BCWP − ACWP
Positive CV = Underrunning
Negative CV = Overrunning
![Page 4: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/4.jpg)
EVM Chart Analysis
EVM 202 September 2016 4
Cost and To-Complete Performance Indexes Chart The Cost and To-Complete Performance Indexes (CPI/TCPI) chart shows the contractor’s
cumulative and current cost performance indexes (CPICUM and CPICUR), and the to-complete
performance index for the BAC and contractor’s EAC (TCPIBAC and TCPIEAC). The chart plots
time on the x-axis and index of dollars on the y-axis. You can use this chart to compare a
contractor’s demonstrated efficiency with the efficiency needed to meet a cost target.
Sample CPI/TCPI Chart
How to Analyze this Chart The CPICUM and CPICUR reflect the contractor’s
demonstrated efficiency. The CPICUM is the
contractor’s cumulative cost efficiency, while
the CPICUR is their monthly cost efficiency. The
CPICUR tends to be volatile so it is not a good
measure of total performance.
The TCPIBAC and TCPIEAC reflect the efficiency
the contractor needs to achieve the BAC and their EAC, starting Day 1 of the next month.
Note: With regards to TCPI, the smaller the BAC or EAC, the greater the efficiency
needed to achieve it.
Note: In the TCPIEAC formula, you may use the contractor’s EAC or the Government
EAC to determine the TCPI for that specific EAC.
Key EVM Formulas
CPI = BWCP
ACWP
TCPIBAC = Work Remaining
Budget Remaining=
BAC − BCWPCUM
BAC − ACWPCUM
TCPIEAC = Work Remaining
Budget Remaining=
BAC − BCWPCUM
EAC − ACWPCUM
![Page 5: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/5.jpg)
EVM Chart Analysis
EVM 202 September 2016 5
If the CPICUM is 1.00, then the contractor’s cost efficiency is as planned. If it is greater than 1.00,
the contractor is more than 100% efficient, or more efficient than budgeted. If the CPICUM is less
than 1.00, the contractor is less than 100% efficient, or less efficient than budgeted. If the
CPICUM is trending down (i.e., the CPICUM line is sloping downward), the contractor’s efficiency is
getting worse. If the CPICUM is trending up (i.e., the CPICUM line is sloping upward), their
efficiency is improving.
To determine whether the contractor’s EAC is reasonable, compare the CPICUM (efficiency
demonstrated) to the TCPI required to achieve the BAC or EAC (efficiency needed).
If the contractor’s CPICUM is greater than the TCPI, then they are more likely to achieve
the cost target because they are more efficient than what is needed to meet that target.
If the contractor’s CPICUM is less than the TCPI, then they are less likely to achieve the
cost target because they are less efficient than what is needed to meet that target.
If the trends for CPICUM and TCPI are diverging (i.e., getting farther apart), then the
likelihood of the contractor achieving the cost target is decreasing because the gap
between the efficiency demonstrated and the efficiency needed is increasing.
If the trends for CPICUM and TCPI are converging (i.e., coming closer together), then the
likelihood of the contractor achieving the cost target is increasing because the gap
between the efficiency demonstrated and the efficiency needed is decreasing.
A delta of 10% or more between TCPI and CPICUM is used as an early warning indication
that the targeted budget could be unrealistic.
Analysis in Action In the previous sample CPI/TCPI chart, the contractor's CPICUM is 0.929. In other words, for
every $1 spent (ACWP), $0.929 worth of work was accomplished (BCWP). The contractor's
EAC is unreasonable because the CPICUM is less than the TCPIEAC (1.072) and TCPIBAC (1.022).
In addition, the difference between the CPICUM and the TCPIEAC is more than 10% (14.3%), and
the difference for the TCPIBAC is nearly 10% (9.3%), which also indicates that the contractor's
EAC may be unreasonable.
![Page 6: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/6.jpg)
EVM Chart Analysis
EVM 202 September 2016 6
Cost/Schedule Variance Trends Chart
The Cost/Schedule Variance Trends chart, also known as the cone chart, shows the contract
start and completion dates, the contractor’s SVCUM and CVCUM, the ±10% threshold bands, the
contractor and Joint Program Office (JPO) VACs, and management reserve (MR). The chart
plots time on the x-axis and dollars in millions on the y-axis. You can use this chart to compare
cost and schedule performance trends to the JPO’s and contractor’s VAC.
Sample Cost/Schedule Variance Trends Chart
![Page 7: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/7.jpg)
EVM Chart Analysis
EVM 202 September 2016 7
How to Analyze this Chart Similar to the Cumulative Variance chart, if the VAC is
positive for either the JPO or the contractor, then that
entity is predicting an underrun; their EAC is less than the
BAC. If their VAC is negative, then they are predicting an
overrun; their EAC is more than the BAC.
If the CVCUM is positive, then the contractor has spent
less than budgeted to accomplish the work. If it is
negative, then the contractor has spent more than
budgeted to accomplish the work. If the CVCUM is trending
down, (i.e., the CVCUM line is sloping downward), then
performance is getting worse. In other words, the overrun
is increasing or the underrun is decreasing.
If the SVCUM is positive, then the contractor has
accomplished more work than planned. If it is negative,
then the contractor has accomplished less work than planned. If the SVCUM is trending down,
(i.e., the SVCUM line is sloping downward), then schedule performance is getting worse.
Note: Negative SVCUM does not necessarily mean that the contract is behind
schedule. You must look at the network schedule to determine if the tasks are on the
critical path before making assumptions about schedule impact.
Note: If the contractor has a large number of 50/50 work packages, a positive SVCUM
could result from the contractor opening work packages early.
To determine whether the contractor’s EAC is reasonable, compare the cost and schedule
performance trends to the trend required to reach the JPO and contractor estimates (i.e., the
VACs) and look for changes in trends.
A negative SVCUM trend is often followed by a negative CVCUM trend.
Normally, the best a contractor can do is to flatten the CVCUM trend, meaning there are
no additional overruns. However, when the CVCUM trend to date is negative, it is rare for
a contractor to spend less than planned in the future to cause the trend to improve, or
track up. For this reason, if the CVCUM trend needs to improve drastically to reach the
JPO or contractor VAC, the contractor would need a good explanation for how this
change could occur.
Remember: The SVCUM will always trend back to 0 when work is complete because
BCWP will equal BCWS. This does not mean work will be completed according to the
original schedule, only that all work will eventually be completed and earned value (EV)
will be achieved.
Use of MR is also something to track; early MR use is often an indication of planning
problems.
Key EVM Formulas
VACJPO = BAC − EACJPO
Positive VAC = Underrun
Negative VAC = Overrun
VACKTR = BAC − EACKTR
Positive VAC = Underrun
Negative VAC = Overrun
CV = BCWP − ACWP
Positive CV = Underrunning
Negative CV = Overrunning
SV = BCWP − BCWS
Positive SV = Finished more
work than planned
Negative SV = Finished less
work than planned
![Page 8: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/8.jpg)
EVM Chart Analysis
EVM 202 September 2016 8
The ±10% threshold bands are based upon ±10% of BCWP and provide perspective on
the relative significance of the cost and schedule variances. The goal is to stay within
this cone.
Analysis in Action In previous sample Cost/Schedule Variance Trends chart, the contractor is predicting an
underrun because their VAC is positive. However, the contractor’s EAC is unreasonable
because both CVCUM and SVCUM have consistently trended downward, and show no sign of
improving. Moreover, the change required in the CVCUM trend to reach the JPO and contractor
VACs is significant, which makes this change unlikely.
![Page 9: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/9.jpg)
EVM Chart Analysis
EVM 202 September 2016 9
Estimates at Completion Chart The Estimates at Completion (EAC) chart shows the BAC, the contractor’s EAC, and one or
more formula-based EACs, plotting time on the x-axis and dollars in millions on the y-axis. This
chart is used to compare a contractor’s EAC to formula-based EAC(s) to determine if the
contractor’s EAC is reasonable.
Sample EAC Chart
Note: This sample chart displays one formula-based EAC: EACCPI (also known as
the floor EAC), which uses CPICUM as the performance factor. Other charts may
display additional EACs, such as the ceiling EAC (EACComposite), which uses CPI*SPI
as the performance factor.
See the next section for more information about formula-based EACs and
performance factors.
![Page 10: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/10.jpg)
EVM Chart Analysis
EVM 202 September 2016 10
How to Analyze this Chart The contractor’s EAC is one way to determine what
the contract may cost compared to the original plan.
Formula-based EACs are another way to determine
what the contract may cost. EACs may be calculated by
using different performance factors (PFs).
To calculate a formula-based EAC, substitute an
efficiency factor (e.g., CPICUM or CPICUM * SPICUM) for the
PF. No one factor is better than another. Choose an
efficiency factor based on program history, current
trends, technical performance, and other programmatic
information.
The Six Period Summary report pre-calculates several formula-based EACs. See the
Six Period Summary Report subsection at the end of this job aid for more
information.
EACs are used to assist management decision-making and planning. They are frequently
included in reports, such as budget documents, submitted to upper levels of management. If the
calculated EACs differ greatly from the BAC and/or contractor EAC, then the contractor and/or
the Program Management Office (PMO) should be prepared to explain why.
Analysis in Action In the previous Sample Estimates at Completion (EAC) chart, the contractor is predicting an
underrun because their EAC is less than the BAC. However, the contractor’s EAC is
unreasonable because, it is below the formula-based EAC that uses CPICUM as the PF,
otherwise known as the floor.
Key EVM Formulas
VAC = BAC − EAC
Positive VAC = Underrun
Negative VAC = Overrun
EACPF = ACWP + BAC − BCWPCUM
Performance Factor
EACCPICUM= ACWP +
BAC − BCWPCUM
CPICUM
EACComposite = ACWP + BAC − BCWPCUM
CPICUM ∗ SPICUM
![Page 11: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/11.jpg)
EVM Chart Analysis
EVM 202 September 2016 11
Six Period Summary Report The Six Period Summary report provides current, cumulative, and completion data at the work
breakdown structure (WBS) level for the most recent six periods, ending with the current period.
The last section of this report provides statistical forecasts and independent EACs (i.e., formula-
based EACs).
![Page 12: Earned Value Management (EVM) Chart Analysis · EVM Chart Analysis EVM 202 September 2016 3 How to Analyze this Chart The VAC is the cost variance the contractor predicts at the end](https://reader033.vdocuments.us/reader033/viewer/2022042005/5e6f4bc87a05116962112264/html5/thumbnails/12.jpg)
EVM Chart Analysis
EVM 202 September 2016 12
Statistical Forecasts and Independent EACs Most of the forecasts calculated in this section use the EAC formula and a PF:
EACPF = ACWP + BAC − BCWPCUM
Performance Factor
Similar to the EAC chart, the choice of PF is based on program history, current trends, technical
performance, and other programmatic information.
Calculations that do not use the EAC formula include the User Entered EAC and JPO Entered
EAC. The User Entered EAC is a bottoms-up calculation generated by identifying an EAC
method at lower WBS levels that gets summarized to the total level. The JPO Entered EAC is
also a user input at the total contract level.