earned value: ideas and exercises - new leaf project...
TRANSCRIPT
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 1 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
500 Thoreau Street Concord, MA 01742 USA +978.369.9009 [email protected]
Earned Value: Ideas and Exercises (for PMBOK 5th Edition)
Exercises to calculate earned value and other project metrics
John M. Nevison, PMP Introduction Earned value calculations can give a project manager a picture of the project’s progress to date. With this information the manager can project the total project cost and schedule and then make appropriate adjustments to the project. The exercises in this article will show you how to predict where your project is going so you can make adjustments before it’s too late. The project shown in Figure 1 below has an original cost, or Budget at Completion (BAC), of 1000 staff-days and an original schedule of 10 months. The calculations begin with the “s-curve” chart of information that depicts the project’s planned value from start to end, and two actual lines from the project start to the current date. One of the two “actual” lines depicts the actual cumulative cost to date, the other the actual cumulative earned value to date. The last bits of information in the graph are the present date and the planned value to date. Figure 1. A typical earned value chart.
When you are ready to earn your PDUS: Please return to www.NewLeafPM.com • Click on the “White Papers” tab. • Select “White Paper Power Quizzes for PDU Credit.” • Choose this quiz (Part 1).
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 2 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Figure 2. A typical project task list.
Terms Earned value is an expression of cumulative achievement, or what has been accomplished “to date.” In Figure 1 the vertical axis is labeled “Cumulative Value” and three measures of accumulated (or “to date”) activity are graphed across the horizontal project duration.
Planned Value. The first of the three measures is the planned value, the sum of the budgets (including overhead) for all activities scheduled to be worked on within a given period of time (in our example, the periods are the whole project and the project-to-date). Actual Cost. The second measure is the total cost incurred in accomplishing the project objectives during a given time period (in our example, the project-to-date). Earned Value. The third measure is the sum of the budgets (including overhead) for all the activities that have been completed to date.
The units of value are most commonly staff-hours for white-collar projects, but they could just as well be dollars, staff-days (“stays”), staff-months, or milestones. To simplify the numbers, the units of value in this example will be staff-days. In the exercises that follow, the units will vary. Background In order to use earned value analysis to help assess a project’s performance to date, the project must have begun with a plan that assigns a value to each task. This value is the “planned” value that can later be “earned” when the activity is completed. These values appear in the plan’s task table, part of which is shown in Figure 2. (The words task and activity will be used
Task ListEarned Date completed
Task name Plan Actual Value Planned Actual. . .MONTH 3 240 268 238 31-MarPink 16 14 16 2-Apr 5-AprViolet 12 16 12 5-Apr 10-AprRed 18 22 18 5-Apr 8-AprVermillion 8 10 8 15-Apr 20-AprBlue 18 24 18 20-Apr 18-AprBrown 8 22-AprGreen 10 16 10 22-Apr 28-AprYellow 10 25-AprMONTH 4 340 370 320 30-AprBrown* * 22-AprYellow* * 25-AprBeige 2 2-MayApricot 2 5-MayPink 3 5-May. . .
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 3 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
interchangeably in this article.) The task table shows that Month 4's activities have been totaled to arrive at the 370, 340 and 320 cumulative staff-days shown in the diagram in Figure 1.
The monthly cumulative totals count only those tasks that have been completed. Two tasks, “Yellow” and "Brown," have not been worked on and will be rolled forward into the next month's accounting. CPI and SPI Are Stable Data from hundreds of projects have shown that a project’s earned value behavior, as represented by the CPI and the SPI, stabilizes within the first 15% of the project’s schedule and remains relatively constant over the remaining 85%. This stability allows these ratios to be used with confidence. Simplifying Assumption Sometimes a task is only partially complete at the end of a measuring period. In order to make our calculations simple, we will assume in all our examples that there are no partially completed tasks. At the moment of measurement, all tasks either have been totally completed or have not started. A Typical Problem In the example in Figures 1 and 2, the total plan for the project involved 1000 staff-days of value (the Budgeted at Completion or BAC) accumulated over 10 months with a staff of 5 full-time people. At the 4-month mark, with no open tasks, the total accumulated earned value is 320 staff-days. The plan at this point is for 340 staff-days to have been earned. Alas, the actual amount spent (because extra staff time has already been spent on this project) is 370 staff-days. A summary of the facts:
1. Original project cost: 1000 staff-days 2. Original project schedule: 10 months 3. Planned value: 340 staff-days at 4 months 4. Actual cost: 370 staff-days 5. Earned value: 320 staff-days 6. Current monthly staff: 5 people The earned value questions that are often asked are:
1. What is the current cost shortfall in as measured by the Cost Variance (CV? 2. What is the current work productivity as measured by the Cost Performance Index (CPI? 3. What is the current schedule shortfall in as measured by the Schedule Variance (SV? 4. What is the current schedule efficiency as measured by the Schedule Performance Index
(SPI? 5. What is the projected total cost Estimate at Completion (EAC)?
a. If we assume cost variance was atypical (and the rest of the project will go as originally planned)?
b. If we assume cost variance was typical [recommended by New Leaf] (and the rest of the project will have a proportional variance)?
c. If we assume we can re-plan the remaining project and make a whole new estimate?
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 4 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
6. What is the projected schedule Estimate at Completion (EACt)? a. If we assume schedule variance was atypical (and the rest of the project will be as
originally planned)? b. If we assume schedule variance was typical [recommended by New Leaf] (and the
rest of the project will have a proportional variance)? c. If we assume we can re-plan the remaining project and make a whole new estimate?
7. What are the remaining cost-to-complete and schedule-to-complete figures for each of a, b, and c?
8. What is the intensity of work required to finish the work with the available funds? (These funds can be defined as either the original Budget at Completion (BAC) or the current Cost Estimate at Completion (EAC).)
9. And, if making the original schedule is important, what are the Remaining Work Index (RWI) and the Staffing-to-Schedule Index (StSI) – [both invented by Nevison], and how do these indexes suggest that we recover the schedule and preserve the shape of the project’s staffing pattern?
CV and CPI? The Cost Variance is the earned value minus the actual cost. The Cost Performance Index is the earned value divided by the actual cost of the project-to-date. If everything is going according to plan the cost variance is 0 and the CPI is 1.0. However, the cost variance is usually negative and the CPI is usually less than 1. In this example we have completed 320 staff-days of earned value with 370 staff-days of effort.
Cost Variance = 320 – 370 = -50 Cost Performance Index = 320 / 370 = .86
Note: Because the CV is usually negative, we will call a negative CV a cost shortfall and define it to be the absolute value of the negative cost variance [New Leaf definition].
Section 1.01 Cost Shortfall = |-50| = 50 SV and SPI? The Schedule Variance (SV) is the earned value minus the planned value. The Schedule Performance Index (SPI) is the earned value divided by the planned value (of the project-to-date). If the project is going according to plan the Schedule Variance is 0 and the SPI is 1.0. However, the Schedule Variance is usually negative and the SPI is usually less than 1. In this example we have completed 320 staff-days of earned value in the time we had planned to complete 340 staff-days of planned value.
Schedule Variance = 320 – 340 = -20 Schedule Performance Index = 320 / 340 = .94
Note: Because the SV is usually negative, we will call a negative SV a schedule shortfall and define it to be the absolute value of the negative schedule variance. [New Leaf definition]
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 5 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Schedule Shortfall = |-20| = 20 Projected Total Cost? To decide on a cost Estimate at Completion (EAC) we must decide how our project will behave between now and the end.
a. If we assume the cost variance was atypical and the rest of the work will be performed at the original budgeted rate, then the cost EAC will be the original Budget at Completion plus the current cost shortfall. In our example:
Cost EAC (if atypical variance) = 1000 + |320 – 370| = 1050 staff days
b. If we assume the cost variance was typical [recommended by New Leaf] and the rest of the work will be performed at the present CPI, then the cost EAC will be the original Budget at Completion, or BAC, divided by the Cost Performance Index, or CPI. In our example:
Cost Estimate at Completion (EAC) = 1000 / (320 / 370) = 1000 / 0.86 = 1156 staff-days
c. If we assume we can re-plan the remaining project and make a whole new estimate, then the EAC is the some number larger than the current actual cost.
Projected Schedule? To find a Schedule Estimate at Completion (EACt), we must decide on how our project will behave between now and when it ends.
a. If we assume schedule variance was atypical and the rest of the work will be performed at the original budgeted rate, then the schedule EACt will be the original schedule times (the original budget plus the present schedule shortfall)/(the original budget). This is a New Leaf formula that is not included in the PMBOK 4th.
In our example:
Schedule EACt (if atypical variance) = 10 x (1000 +20)/1000 = 10 x 1.02 = 10.2 months [New Leaf formula]
b. If we assume the schedule variance was typical [recommended by New Leaf] and the rest of the work will be performed at the present SPI, then the schedule EACt will be the original schedule divided by the schedule performance index, or SPI. In our example:
Schedule Estimate at Completion (EACt) = 10 / (320 / 340) = 10 / 0.94 = 10.6 months
c. If we assume we can make a whole new estimate, then the new schedule is some date later than the current actual date.
Cost ETC? To make a cost Estimate to Completion (ETC), we must decide how our project will behave between now and the end. a. If we assume the cost variance was atypical and the rest of the work will be performed
at the original budgeted rate, then the cost ETC will be the difference between our atypical-variance cost EAC and the current actual cost. In this example:
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 6 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Cost ETC (if atypical variance) = 1050 - 370 = 680 staff days
b. If we assume the cost variance was typical [recommended by New Leaf] and the rest of the work will be performed at the present CPI, then the cost ETC will be the typical-variance cost EAC less the current actual cost. In our example:
Cost Estimate to Completion (ETC) = 1156 – 370 = 786 staff-days
c. If we assume we can re-plan the remaining project and make a whole new estimate, then the ETC is a new value that is the result of our re-plan.
Remaining Schedule? (Schedule ETCt) The PMBOK(C) 4th uses the term “remaining schedule.” It does not use the term or the abbreviation “schedule ETCt.” The term “schedule ETCt” is a New Leaf term that parallels the cost ETC. To find the remaining schedule (a “Schedule Estimate to Complete”), we must decide on how our project will behave between now and when it ends.
a. If we assume schedule variance was atypical and the rest of the work will be performed at the original budgeted rate, then the remaining schedule will be the atypical-variance schedule EACt less the present time. In this example:
Remaining schedule (with an atypical variance) = 10.2 – 4 = 6.2 months
b. If we assume the schedule variance was typical [recommended by New Leaf] and the rest of the work will be performed at the present SPI, then the remaining schedule will be the schedule EACt less the present time. In our example:
Remaining schedule (with typical variance) = 10.6 – 4 = 6.6 months
c. If we assume we can make a whole new estimate, then the remaining schedule is the difference between the new end date and the current actual date.
To-Complete Performance Index (TCPI)? To make a To-Complete Performance Index (TCPI), we must decide whether we are indexing on our original budget (BAC) or on our current Cost Estimate at Completion (EAC). In either case, the TCPI will measure the “work remaining over the funds remaining” and tell us how efficiently we will need to work to meet our goals with the target funds. The TCPI is the only index where bad news is greater than 1.0, while good news is less than 1.0. If we assume that we want to complete within the BAC, then the TCPI is the work remaining, (BAC – EV), divided by the funds remaining (BAC – Actual Costs). In this example:
To-Complete Performance Index (TCPI) = (1000 – 320) / (1000 – 370) = 680/630 = 1.08 We must work with a greater cost efficiency than originally planned if we are to finish within our original BAC.
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 7 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
If the BAC is no longer a reasonable goal, we assume we will want to complete within the current EAC and the TCPI becomes the work remaining, (BAC – EV), divided by the funds remaining (EAC – Actual Costs). In this example:
To-Complete Performance Index (TCPI) = (1000 – 320) / (1156 – 370) = 680/786 = .87
We can work with a lower cost efficiency than originally planned and still finish within our current EAC. How Many Extra People? To calculate the number of extra people needed to finish on time, follow these four steps: [Nevison invented both the RWI and the StSI] With a planned monthly staff = 5 people:
1. Remaining work index (RWI) = remaining planned work / remaining actual work = (1000 – 340) / (1000 – 320) = 660 / 680 = .97 2. Staffing-to-schedule Index (StSI) = Remaining Work Index * CPI = .97 * .86 = .84 3. Workers needed per month = Planned staff / StSI = 5 / .84 = 6.0 persons
4. Extra workers needed = persons needed – persons on board. = 6 - 5 = 1.0 persons Reservations The 1.0 extra persons (extra full-time equivalents) in the above example is a minimum number. It makes several optimistic assumptions:
• The new people can be found right away • The new people will be as productive as the old hands right away • The larger team will communicate with the same efficiency • The work can be accelerated by bringing on extra people
None of these assumptions is strictly true. So the prudent manager will want to bring on a little more than the number calculated in order to take effective corrective action. A simple rule of thumb is round up any fractional head count. In the above example where we need 1.0 persons and we have no fractional count, so we make sure we search for one very experienced person. Exercises Following are four exercises and their answers. Please try each exercise on your own before checking on the answers.
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 8 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Exercise 1 A summary of the facts: 1. Original project cost: 1200 staff-days 2. Original project schedule: 12 months 3. Planned value: 500 staff-days at 5 months 4. Actual cost: 550 5. Earned value: 450 6. Current staffing: 5 full time people Questions: (Staff-days and months) 1. What is the current Cost Variance (CV)? 2. What is the current Cost Performance Index (CPI)? 3. What is the current Schedule Variance (SV)? 4. What is the current Schedule Performance Index (SPI)? 5. What is the projected total cost estimate at completion (EAC)?
a. If we assume cost variance was atypical (and the rest of the work will be performed at the original budgeted rate)?
b. If we assume cost variance was typical [recommended by New Leaf] (and the rest of the work will be performed at the present CPI)?
6. What is the schedule “estimate at completion” or (EACt): a. If we assume schedule variance was atypical (and the rest of the work will be
performed at the original budgeted rate)? b. If we assume schedule variance was typical [recommended by New Leaf] (the rest
of the work will be performed at the present SPI)? 7. What are the remaining cost-to-complete and schedule-to-complete figures for a and
b? 8. What is the To-Complete Performance Index (TCPI) for the BAC? The TCPI for the
EAC with a typical cost variance? 9. If making the original schedule is important, what are the Remaining Work Index
(RWI) and the Staffing-to-schedule Index (StSI), and what extra staffing is required to recover the original schedule?
Exercise 2 A summary of the facts: 1. Original project cost: 320 staff-days 2. Original project schedule: 4 months 3. Planned value: 80 staff-days at 1 month 4. Actual cost: 82 5. Earned value: 75 6. Current staffing: 4 people Questions: (Staff-days and months) 1. CV: __ staff-days 2. CPI: __ 3. SV: __ staff-days 4. SPI: __ 5. Cost EAC a: __ staff-days b: __ staff-days 6. Schedule EACt: a: __ months b: __ months
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 9 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
7. CTC: a: __ staff-days b: __ staff-days Schedule-to-complete: a: __ months b: __ months 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people Exercise 3 A summary of the facts: 1. Original project cost: 1808 staff-hours 2. Original project schedule: 64.5 days 3. Planned value: 824 staff-hours at 32 days 4. Actual cost: 919 5. Earned value: 736 6. Current staff: 3.5 Questions: (Staff-hours and days) 1. CV: __ staff-hours 2. CPI: __ 3. SV: __ staff-hours 4. SPI: __ 5. Cost EAC: a: __ staff-hours b: __ staff-hours 6. Schedule EACt: a: __ days b: __ days 7. CTC: a: __ staff-hours b: __ staff-hours Schedule-to-complete: a: __ days b: __ days 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people Exercise 4 A summary of the facts: 1. Original project cost: 7368 staff-hours 2. Original project schedule: 48 weeks 3. Planned value: 4392 staff-hours at 29.4 weeks 4. Actual cost: 4144 5. Earned value: 3632 6. Current staff: 5 people Questions: (Staff-hours and weeks) 1. CV: __ staff-hours 2. CPI: __ 3. SV: __ staff-hours 4. SPI: __ 5. Cost EAC: a: __ staff-hours b: __ staff-hours 6. Schedule EACt: a: __ weeks b: __ weeks
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 10 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
7. CTC: a: __ staff-hours b: __ staff-hours Schedule-to-complete: a: __ weeks b: __ weeks 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people ANSWERS Exercise 1. Staff-days and months 1. CV: -100 staff-days 2. CPI: .82 3. SV: -50 staff-days 4. SPI: .90 5. Cost EAC: a: 1300 staff-days b: 1467 staff-days 6. Schedule EACt: a: 12.5 months b: 13.3 months 7. CTC: a: 750 staff-days b: 917 staff-days Schedule-to-complete: a: 7.5 months b: 8.3 months 8. TCPI for BAC: 1.15 TCPI for EAC (typical): 0.82 9. RWI: .93 StSI: .76 Revised staffing: 6.5 people
Exercise 2. Staff-days and months 1. CV: -7 staff-days 2. CPI: .91 3. SV: -5 staff-days 4. SPI: .94 5. Cost EAC a: 327 staff-days b: 350 staff-days 6. Schedule EACt: a: 4.1 months b: 4.3 months 7. CTC a: 245 staff-days b: 268 staff-days Schedule-to-complete: a: 3.1 months b: 3.3 months 8. TCPI for BAC 1.03 TCPI for EAC (typical) .91 9. RWI: .98 StSI: .90 Revised staffing: 4.5 people
Exercise 3. Staff-hours and days 1. CV: -183 staff-hours 2. CPI: .80 3. SV: -88 staff-hours 4. SPI: .89 5. Cost EAC a: 1991 staff-hours b: 2258 staff-hours 6. Schedule EACt: a: 67.6 days b: 72.2 days 7. CTC: a: 1072 staff-hours b: 1339 staff-hours Schedule-to-complete: a: 35.6 days b: 40.2 days
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 11 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
8. TCPI for BAC: 1.21 TCPI for EAC (typical): 0.80 9. RWI: .92 StSI: .74 Revised staffing: 4.8 people
Exercise 4. Staff-hours and weeks 1. CV: -512 staff-hours 2. CPI: .88 3. SV: -760 staff-hours 4. SPI: .83 5. Cost EAC: a: 7880 staff-hours b: 8407 staff-hours 6. Schedule EACt: a: 53 weeks b: 58 weeks 7. CTC: a: 3736 staff-hours b: 4363 staff-hours Schedule-to-complete: a: 23.6 weeks: b: 28.6 weeks 8. TCPI for BAC: 1.16 TCPI for EAC (typical): 0.88 9. RWI: .80 StSI: .70 Revised staffing: 7.2 people Now that you have completed all four exercises, you may answer the first PDU questionnaire (Part 1) for a total of 4 PDUs.
Mechanical Tools For 2 additional PDUs, solve the four additional exercises (5 through 9) below and answer the second PDU questionnaire. To be sure your answers are correct:
1. Construct a spreadsheet with all the formulas. 2. Check out your spreadsheet with the first four exercises to be sure your formulas give
the correct answers. 3. Use the spreadsheet to generate answers to Exercise 5-8.
When you are ready to earn your PDUS: Please return to www.NewLeafPM.com • Click on the “White Papers” tab. • Select “White Paper Power Quizzes for PDU Credit.” • Choose this quiz (Part 1).
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 12 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Exercise 5 A summary of the facts: 1. Original project cost: 400 staff-days 2. Original project schedule: 4 months 3. Planned value: 80 staff-days at 1 month 4. Actual cost: 80 5. Earned value: 75 6. Current staffing: 4 people Questions: (Staff-days and months) 1. CV: __ staff-days 2. CPI: __ 3. SV: __ staff-days 4. SPI: __ 5. Cost EAC: a: __ staff-days b: __ staff-days 6. Schedule EACt: a: __ months b: __ months 7. CTC: a: __ staff-days b: __ staff-days Schedule-to-complete: a: __ months b: __ months 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people Exercise 6 A summary of the facts: 1. Original project cost: 1800 staff-hours 2. Original project schedule: 60 days 3. Planned value: 800 staff-hours at 30 days 4. Actual cost: 900 5. Earned value: 700 6. Current staff: 3.5 Questions: (Staff-hours and days) 1. CV: __ staff-hours 2. CPI: __ 3. SV: __ staff-hours 4. SPI: __ 5. Cost EAC: a: __ staff-hours b: __ staff-hours 6. Schedule EACt: a: __ days b: __ days 7. CTC: a: __ staff-hours b: __ staff-hours Schedule-to-complete: a: __ days b: __ days 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 13 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
Exercise 7 A summary of the facts: 1. Original project cost: 7400 staff-hours 2. Original project schedule: 48 weeks 3. Planned value: 4400 staff-hours at 30 weeks 4. Actual cost: 4100 5. Earned value: 3600 6. Current staff: 5 people Questions: (Staff-hours and weeks) 1. CV: __ staff-hours 2. CPI: __ 3. SV: __ staff-hours 4. SPI: __ 5. Cost EAC: a: __ staff-hours b: __ staff-hours 6. Schedule EACt: a: __ weeks b: __ weeks 7. CTC: a: __ staff-hours b: __ staff-hours Schedule-to-complete: a: __ weeks b: __ weeks 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people Exercise 8 A summary of the facts: 1. Original project cost: 7000 staff-hours 2. Original project schedule: 48 weeks 3. Planned value: 4000 staff-hours at 30 weeks 4. Actual cost: 4100 5. Earned value: 3900 6. Current staff: 5 people Questions: (Staff-hours and weeks) 1. CV: __ staff-hours 2. CPI: __ 3. SV: __ staff-hours 4. SPI: __ 5. Cost EAC: a: __ staff-hours b: __ staff-hours 6. Schedule EACt: a: __ weeks b: __ weeks 7. CTC: a: __ staff-hours b: __ staff-hours Schedule-to-complete: a: __ weeks b: __ weeks 8. TCPI for BAC: ___ TCPI for EAC (typical): ___ 9. RWI: __ StSI: __ Revised staffing: __ people
© 2010-2013 New Leaf Project Management Earned Value: Ideas & Exercises (Earn PDUs for reading this article.) 14 You may not post the PDF to a web page. You may, however, link to its source: www.newleafpm.com
For 2 additional PDUs, answer the second PDU questionnaire (Part 2).
Further Reading When you have mastered the calculations that show you the earned value analysis for your project, you may want to read Mark Durrenberger’s An Earned Value Tutorial to see a bit more about what it’s like to use these tools on a real project. If you would like more details on the RWI and the StSI, read John Nevison’s The Remaining Work Index (RWI) and the Staffing-to-Schedule Index (StSI): How to use two new indexes to adjust staffing and make your schedule. Both articles are available on New Leaf’s web site (www. NewLeafPM.com) and both can be studied to earn additional PDUs.
About the Author John M. (Jack) Nevison, PMP is the author of six books and numerous articles on computing and management. During the course of his business career, Nevison has built and sold two businesses, managed projects, managed project managers, and served as both an internal and external consultant to Fortune 100 companies. He is past president of the Mass Bay Chapter of the Project Management Institute (PMI®), a past president of the Greater Boston Chapter of the Association for Computing Machinery (ACM), a certified Project Management Professional (PMP), and a Phi Beta Kappa graduate of Dartmouth.
About New Leaf Project Management New Leaf is a provider of premier project-management training and consulting. Our comprehensive approach blends training with coaching for sustained practice improvement. We offer project management training for all levels of experience, from novice to veteran including preparation for the Project Management Professional (PMP) Exam. We often customize programs to meet individual client needs. By benchmarking project managers with our proprietary PM Competency Assessment we address our client’s greatest needs first.
For more information, contact us at [email protected] or call 978-369-9009.
When you are ready to earn your PDUS: Please return to www.NewLeafPM.com • Click on the “White Papers” tab. • Select “White Paper Power Quizzes for PDU Credit.” • Choose this quiz (Part 2).