  • 8/13/2019 Earned Value and Weighted Milestones

    1/22

    Earned Value and Weighted

    Milestones

  • 8/13/2019 Earned Value and Weighted Milestones

    2/22

    Lesson Objectives

    Define earned value

    Define performance percent complete

    Review the results of different earnedvalue techniquesRealize the benefits of using earned valuetechniques

    12-1

  • 8/13/2019 Earned Value and Weighted Milestones

    3/22

    Earned Value Analysis

    A technique for measuring projectperformance according to project cost

    and schedule. This technique compares the budgeted(planned) cost of work to the actual cost.

    12-2

  • 8/13/2019 Earned Value and Weighted Milestones

    4/22

    The cost of the work that should havebeen accomplished as of the data date,if the project had proceeded according tothe baseline plan.

    Planned Value Cost =Budget At Completion * Schedule %Complete

    Schedule % Complete specifies how muchof an activitys baseline duration has beencomplete so far.

    Answers the question: How much work should be done?

    Planned Value Cost

    12-2

  • 8/13/2019 Earned Value and Weighted Milestones

    5/22

    Earned Value Cost is the monetary value ofthe work performed by a resource as of thedata date.

    Earned Value Cost =Budget At Completion * Performance %Complete

    The method for computing performance percentcomplete depends on the earned valuetechnique selected at the WBS level.

    Answers the question: How much work is done?

    Earned Value Cost

    12-2

  • 8/13/2019 Earned Value and Weighted Milestones

    6/22

    Actual Cost is the actual total costincurred for the work accomplished asof the data date.

    Actual Cost = Actual Labor Cost + ActualNonlabor Cost + Actual Expense Cost Actual Cost is the same as the Actual Total

    Cost.

    Answers the question: How much did the completed work cost?

    Actual Cost

    12-2

  • 8/13/2019 Earned Value and Weighted Milestones

    7/22

    Performance % Complete can bedifferent from the Activity % Completedepending on the technique used to

    compute it. These techniques are set at the WBS

    level.

    Performance % Complete

    12-8

  • 8/13/2019 Earned Value and Weighted Milestones

    8/22

    Activity percent complete Calculated based on the activitys percent

    complete type

    WBS Milestones percent complete Calculated based on the completion of the

    WBS elements weighted milestones

    0/100 Calculated as 0% after an actual start is

    assigned, then as 100% after an actualfinish is assigned

    Techniques

    12-8

  • 8/13/2019 Earned Value and Weighted Milestones

    9/22

    50/50 Calculated as 50% after an actual start is

    assigned, then as 100% after an actualfinish is assigned

    Custom percent complete Calculated as a user-defined percentage

    after an actual start is assigned, then as100% after an actual finish is assigned

    Techniques cont.

    12-8

  • 8/13/2019 Earned Value and Weighted Milestones

    10/22

    Weighted Milestones

    Weighted milestones can be used whenhigher-level task increments comprise abody of activities and you want to control

    the activities at the WBS level. When you assign weights to the WBS

    milestones, the completion of each

    specific milestone is used to calculatethe performance percent complete of theWBS.

    12-9

  • 8/13/2019 Earned Value and Weighted Milestones

    11/22

    Weight of the milestone can be anynumber between 0 and 999999.

    Performance percent complete iscalculated based on the relative weightsof the completed milestones vs. theincomplete milestones. The performance percent complete is

    applied to all the activities under that WBSlevel, and then rolled back up to the WBS.

    Weighted Milestones cont.

    12-9

  • 8/13/2019 Earned Value and Weighted Milestones

    12/22

    The following option must be set to useweighted milestones: In the WBS window, select the Earned

    Value tab in WBS Details. Mark the WBSMilestone percent complete checkbox.

    Use when calculating earned value.

    Weighted Milestones cont.

    12-9

  • 8/13/2019 Earned Value and Weighted Milestones

    13/22

    Cost and SchedulePerformance Indices

    A way to analyze how efficiently theproject is progressing is to calculate cost

    and schedule performance indices.

    12-17

  • 8/13/2019 Earned Value and Weighted Milestones

    14/22

    Relates the amount of physical earnedvalue accomplished against the dollarsactually spent to accomplish the earnedvalue

    CPI = Earned Value Cost / Actual Cost A value of less than one (1) indicates that

    actual costs have exceeded the value ofthe work performed.

    Cost Performance Index (CPI)

    12-17

  • 8/13/2019 Earned Value and Weighted Milestones

    15/22

    Relates the amount of physical earnedvalue accomplished against the workthat was planned

    SPI = Earned Value Cost / Planned ValueCost A value of less than one (1) indicates that

    less work was actually performed than wasscheduled.

    Schedule Performance Index (SPI)

    12-18

  • 8/13/2019 Earned Value and Weighted Milestones

    16/22

    Techniques for CalculatingEstimate to Complete (ETC)

    P3e contains various techniques forcalculating ETC.

    Techniques take into consideration adelay in the schedule and an overrun incosts.

    Set at the WBS level.

    12-19

  • 8/13/2019 Earned Value and Weighted Milestones

    17/22

    Techniques for Calculating Estimateto Complete (ETC)

    The ETC identifies how much money youare projected to spend from now to theend of the project.

    Calculated using two formulas: ETC = remaining cost for activity

    Remaining Units * Resource Price/Time

    ETC = Performance Factor * (Budget atCompletion Earned Value Cost).

    Where Performance Factor is calculateddepending on the earned-value techniqueselected for the WBS. 12-19

  • 8/13/2019 Earned Value and Weighted Milestones

    18/22

  • 8/13/2019 Earned Value and Weighted Milestones

    19/22

  • 8/13/2019 Earned Value and Weighted Milestones

    20/22

    This is the system default and calculatesETC based on the remaining units. This calculation does not take a

    schedule delay or overspending intoconsideration. Historical evidence shows that these trends

    do not correct themselves over time; theytend to get worse.

    Remaining Cost

    12-21

  • 8/13/2019 Earned Value and Weighted Milestones

    21/22

    Represents a reliable indicator of theminimum total required costs Viewed as the very best the project will do

    based on its history ETC = (1/CPI) * (Budget at Completion

    Earned Value Cost)

    Using CPI to Calculate ETC

    12-22

  • 8/13/2019 Earned Value and Weighted Milestones

    22/22

    Represents a reliable indicator of themaximum total required costs Incorporates the cost overrun to date

    with a behind-schedule condition toproduce a more severe statisticalforecast Viewed as the very worst the project will do

    based on its history

    ETC = [1/(CPI * SPI)] * (Budget atCompletion Earned Value Cost)

    Using CPI and SPI to Calculate ETC

    12-24