earn value case study

87
Cost Management-Case Study 1. Contract award 2. Organize the work 3. Work package 4. Scheduling 5. Budget 6. Execute 7. Control 8. Report 9. Analyse

Upload: gustaf88

Post on 26-Nov-2015

29 views

Category:

Documents


2 download

TRANSCRIPT

  • Cost Management-Case StudyContract awardOrganize the workWork packageSchedulingBudgetExecuteControlReportAnalyse

  • Case StudyPart 1

    Here comes your footer Page *

  • Contract AwardYou are the program manager, I. M. TazYou just won a contract to eliminate varmints within the state of Arizonabirds (tweetie and road runner types)small animalsYou have an organization of highly trained specialistsL. M. Fudd Sil Vester the catWile E. CoyoteDaffie Duck (your deputy and the CAM for management)You have allocated the following budgets from your $50,000 awardwascally rabbits ($5,000)squirrels ($5,000) tweetie birds ($20,000)road runners ($10,000)program management ($10,000)

  • Organize the workBuild a simple work breakdown structureVarmint Control1.3Program Mgt1.2.1tweetie1.2Birds1.1 Small Animals1.2.2road runner1.1.1wascally wabbits1.1.1wascally wabbits1.1.2 squirrels

  • Organize the workersBuild a simple organization breakdown structureI.M. TazProgram ManagerDaffie DuckProgram MgtSil Vestertweetie birdsL. M. Fudd,small animalsWile E. Coyoteroad runners

  • Build a RAM and allocate work

    Sil Vester

    L. M. Fudd

    Wile E. Coyote

    Daffie Duck

    1.1.1

    wascally wabbits

    1.1.2

    squirrels

    1.2.1

    tweetie birds

    1.2.2

    road runner

    1.3

    program management

  • Build a RAM and allocate work

    Sil Vester

    L. M. Fudd

    Wile E. Coyote

    Daffie Duck

    1.1.1

    wascally wabbits

    $5,000

    1.1.2

    squirrels

    $5,000

    1.2.1

    tweetie birds

    $20,000

    1.2.2

    road runner

    $10,000

    1.3

    program management

    $10,000

  • Rules of Thumb for Control Account sizeintegrated cost and schedule baselinethree legged stool legs (cost, schedule, technical) are equalhomogeneity of workwhat is logical to manage every daylook at:character of workbreakout of laborspan of controltypically6 - 18 months for discrete effortlevel of effort can be longerWhat makes a good control account?

  • CONTROL ACCOUNT PLANCAM name: ______ WBS: _______ Total Budget: _________

    Work

    Work

    Work

    $$$$$$$$$ BUDGETLabor 1,000 hrsLabor $ 75,000Material $ 25,000 SCHEDULE

    TIER 1

    TIER 2

    So, whats in a Control Account?SOW

    1.3.4.1 Build ejection seat

  • Development of Control Account PlansMAY break down the control account budget into smaller work packagesWork Packagessubset of control accountreasonably short in durationsingle element of cost (e.g., labor)single technique for earning valueconsistent with detail scheduleshas same characteristics as control accountscope of workmilestone completion criteriasingle performing organizationstart and end datesWork Package

  • discrete and measurableproducts or accomplishmentsexamples:design drawing packageconduct design reviewinstall rudderrolling wavedetailed plans made for near term work packagesplanning packages are for future work and are not detailedCAMs periodically plan another increment of work packagesopen vs. closed packagesWork Package Characteristics

  • Earned Value techniquesDiscretephysical, tangible end productApportioneddiscrete, dependent on another discrete work packageexample: quality assuranceplanned as historical estimating factor (e.g., 7%)Level of Effortno tangible end productbasis of measurement: timewhen clock starts ticking, you automatically accumulate earned valueno schedule varianceexample: management personnelShould be a quantitative and discrete way to measure the workMay tie in with success criteria or technical measuree.g., successful completion of a specific test, reliability growth curveWays of Earning Value

  • Discrete EV Techniques:

    MethodHow Value is Earned

    0/100no EV at opening, 100% EV at close of WP

    50/5050% EV at opening, 50% EV at close of WP

    Units Completedsame budget value for identical units

    Equivalent Unitsplanned unit standards, allows partial credit

    Weighted Milestoneeach milestone weighted based on planned resourcesideal to have a milestone each month

    Percent Completesubjective (least desirable)

    Be Discrete!

  • Material and SubcontractsEarned Value: taken no earlier than receipt define order receipt payment to inventory usage

    accurate cost accumulation and assignment to contractshould perform price and usage variancesshould match earned value to payment periodotherwise, take estimated actuals to avoid artificial cost varianceMaterial Concerns

  • Scheduling system characteristicscompleteall work includedformaleveryone uses same scheduletraceablevertical (Master, Intermediate, Detail)horizontal (between tasks)consistentidentifies sequence of tasks, interdependenciesScheduling

  • CASE STUDYPart 2

  • Contract SOWSOW Paragraph 1.2.2:

    The contractor shall design, build, and install a systemto capture and eliminate the species Road Runner within the state of Arizona.

    Contractors Winning Design:

    The basic system shall consist of five miles of road, a fake tunnel painted on a side of the mountain,plus a device to drop an anvil on the Road Runner.

  • BEEP BEEP INDUSTRIESCONTROL ACCOUNT AUTHORIZATION

    Control Account: Roadrunner

    Control Account Manager: Wile E. Coyote

    Reason for Issue: Contract to rid Arizona of all unwanted creatures,F33657-96-C-0221

    Scope Description: Perform scope in accordance with Statement of Work. WBS Element 1.2.2

    Schedule Requirement: Perform in accordance with Control Account Plan

    Budget Authorization: $10,000

  • Schedule InformationThe contract was awarded in Month 1, and will be complete by the end of Month 6.You can begin building the road immediately, and plan on it taking about one month to complete one mile of road.It will take approximately three months to develop, build, and quality test the anvil support mechanism (ASM). You should begin the ASM install during the last month of the build cycle, during quality test. The ASM will take three months to install, and should be the last item completed on the contract, in Month 6. Based on past experience, you believe that it will take you two months to paint the fake tunnel. You will start it one month before the anvil support mechanism (ASM) begins installation.The anvil supplier, Acme Anvils, has been a good supplier for you in the past. The anvil is commercial off-the-shelf equipment. You need delivery one month before the install is complete.

  • Budget Estimate - BAFO

    Budget Estimate1. Procure anvil (sole source - ACME Anvil)$1,500

    2. Paint fake tunnel$1,000

    3. Build 5 miles of road$3,000

    4. Develop and build anvil support mechanism (ASM)$3,000design drawings complete & signed off (CDR) (Milestone 1)($1,000)build unit (Milestone 2)($1,000)quality test (Milestone 3)($1,000)

    5. Install system on-site$1,500

    Total$10,000

  • CAP

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP

    BCWS5005005001,500

    5Install ASM% complete

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    BLANK

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS

    1Procure Anvil

    BCWP

    BCWS

    2Paint Fake Tunnel

    BCWP

    BCWS

    3Build Road

    BCWP

    BCWS

    4Build ASM

    BCWP

    BCWS

    5Install ASM

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    EV

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth00-1,600-4001,300700

    cumulative00-1,600-2,000-7000

    Actual Costs7001,7001,3002,3005,2002,10013,300

    Cost Variancemonth-100-100-800-100-1,300-900

    cumulative-100-200-1,000-1,100-2,400-3,300

    &CCONTROL ACCOUNT PLAN

  • CAP

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP

    BCWS5005005001,500

    5Install ASM% complete

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    BLANK

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS

    1Procure Anvil

    BCWP

    BCWS

    2Paint Fake Tunnel

    BCWP

    BCWS

    3Build Road

    BCWP

    BCWS

    4Build ASM

    BCWP

    BCWS

    5Install ASM

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    EV

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth00-1,600-4001,300700

    cumulative00-1,600-2,000-7000

    Actual Costs7001,7001,3002,3005,2002,10013,300

    Cost Variancemonth-100-100-800-100-1,300-900

    cumulative-100-200-1,000-1,100-2,400-3,300

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

  • basic rules of the road...

    value is earned using the same method as it was planned sum of the work packages equals the control account budget sum of the control accounts equals the budget baseline span of lower tier schedules supports upper schedules

  • More Acronyms!Apparently, youre starting to understand this!

  • UBUndistributed Budget= authorized work held at top level until it can be planned in detail (will eventually have performance measurement) PMBPerformance Measurement Baseline = time phased budget plan= detailed planning + UBMRManagement Reserve= amount withheld at top level for control purposes (no performance measurement)= used for unforeseen changes that are within scope of the contractCBBContract Budget Base= PMB + MR= contract at costat the total contract level....

  • Rolling Up the Work$time$$$$$$$UBCONTROL ACCOUNTSPERFORMANCE MEASUREMENT BASELINETIME NOWMGT RESERVEPROFITCONTRACT VALUECBB

  • Plans are in place..The baseline is now in placeyouve broken down all the workassigned it to teamsscheduled the work and integrated the schedules,and assigned budget resources.. schedules and budgets roll up to match the contract Lets take the time to evaluate the realism of the baselineIntegrated Baseline Review (IBR)joint contractor/government team within 6 months of contract award or major changeId rather be doing an IBR

  • Case Study IBRDid we fully plan all work? Do we understand the work?Do we have a reasonable schedule, with logic indicated?Do we have enough budget?Are the earned value techniques valid?Is the program manager paying attention?

    Bottom line: where are the risks to the program?Historical Data from other Beep Beep programs1. Average historical cost per mile of road = $7502. Contractor has no experience in painting tunnels.3. Contractor has never worked in this part of the country before.4. Price of raw aluminum on the open market just recently skyrocketed due to heavy demand.

  • Execute!

    Here comes your footer Page *

  • Can only charge to open work packagescontractor system sets procedureContractor maintains baseline log which tracks:distribution of budget from Undistributed Budget (UB) to control accountsdistribution of Management Reserve (MR)additions of authorized worktotal equals Contract Budget BaseContract changes incorporated in disciplined mannercannot start work without authorization or budgetBaseline changes are controlledInternal re-planningOver Target Baseline, Over Target ScheduleAuthorizing the Work

  • more rules of the road...

    cannot move budget and work independently cannot use management reserve to cover overruns may replan open work packages as necessary contractor sets internal policy maintain valid performance information cannot change budgets or costs for completed work except to fix errors

  • Case StudyPart 3

    Here comes your footer Page *

  • EV Update and End of Month ActualsMonth 1:1 section of road built ($700)

    Month 2:Design drawings were completed and signed off ($980)1 section of road built ($720)

    Month 3:The work package for the fake tunnel was opened ($200)A labor strike prevented a section of road from being built ($300)The ASM began to be built, but the unit was not complete ($800)

    Month 4:The tunnel was not completed ($400)The crew went back on the job, and got paid overtime. 2 road sections built for $1500.Milestone 2 for the ASM was finally complete. Quality test was pushed out 1 month. ($400)The install of the ASM was delayed, due to the delay in build.The anvil was ordered.

    Month 5:The anvil was delivered and final cost was $1,700.The tunnel was complete ( painted). ($500)The last section of road was built for $700.Qual test completed. ($1,900)The CAM estimated that the install was approximately 20% complete ($400)

    Month 6:Additional work crews were hired, and the installation was completed.The additional crews cost an additional $1,000. ($2,100 total)

  • CAP

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP

    BCWS5005005001,500

    5Install ASM% complete

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    BLANK

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS

    1Procure Anvil

    BCWP

    BCWS

    2Paint Fake Tunnel

    BCWP

    BCWS

    3Build Road

    BCWP

    BCWS

    4Build ASM

    BCWP

    BCWS

    5Install ASM

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    EV

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

    EV with actuals

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth00-1,600-4001,300700

    cumulative00-1,600-2,000-7000

    Actual Costs7001,7001,3002,3005,2002,10013,300

    Cost Variancemonth-100-100-800-100-1,300-900

    cumulative-100-200-1,000-1,100-2,400-3,300

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

  • Control

    Here comes your footer Page *

  • ControlSo, your project has been baselined and work has startedIs everything going according to plan?Next step in the process:figure out your statusfigure out the problemsfigure out what you need to do to fix themfigure out what the impact might be

  • Status ReportingAssumption: An accurate management control system yields accurate dataBasic principles:Report on periodic basicweeklymonthlyOnly ask for the data that you really need and usecan eliminate certain formatsWBS versus organizational reportingtailor level of reporting to match riskTailor the data to match how youre managingIPTs?Make it as real time as possible

  • Contractor ReportsCost Performance Report (CPR)Format 1:cost and schedule progress by WBS (specified reporting level usually at level 3)Format 2:cost and schedule progress by organizationFormat 3: changes to performance measurement baselineFormat 4:manpower forecastFormat 5:variance analysiscurrent and cum data

  • Formats 1 and 2Contentsheader:basic contract information (target, ceiling, name of contractor, etc.)range of final estimatesbodyperformance datavariancesbudget at completion, estimate at completion

  • WBS or ORGANIZATION

    Sheet1

    CURRENTCUMULATIVEAT COMPLETION

    BCWSBCWPACWPSVCVBCWSBCWPACWPSVCVBUDGETESTIMATEVARIANCE

    ELEMENT

    ELEMENT

    ELEMENT

    ELEMENT

    ELEMENT

    ELEMENT

    TOTAL

    UB

    PMB

    MR

    TOTAL

  • Cost/Schedule Status Report (C/SSR)Similarities to CPRFormat 1 (WBS)Format 5 (Problem Analysis)DifferencesDoes not require use of approved management system & criteriaNo current period reportingBCWS and BCWP may be calculated by logical means at higher levelsApplicationnon-major contracts

  • Contractor format acceptableElectronic submission requiredANSI X12 data setTailoringOnly ask for the data that you are really going to useTimingflash data (early submittal of performance data before variance analysis)Reform Initiatives

  • Analysis Techniquesor

    figuring out where the problems are

    Here comes your footer Page *

  • Analysis TechniquesSort on significant varianceseliminate almost complete, just starting, etc.Graph and analyze trendsLook at comparative datae.g. cumulative performance vs. projected performanceExamine written analysis by contractordoes it answer why?adequacy of corrective action plansAnalysis of schedule trends, critical pathAnalysis of EAC realismwhat are the drivers?what can we do about them?

  • Where are the significant problems?sorted by CV $

  • Graphing TechniquesOverall cost and schedule trendEAC realismgraphs show overall trend...are you getting better,or worse?

  • CURRENT OR CUM TO DATE

    Schedule Variance SV ($)=BCWP - BCWS

    SV (%) =BCWP - BCWS x 100% BCWS

    Cost VarianceCV ($)=BCWP - ACWP

    CV (%) =BCWP - ACWP x 100% BCWPAnalysis of Variances

  • CASE STUDYPart 4

    Here comes your footer Page *

  • Month 1road$700700Month 2road$720 drawings$9801,700Month 3road$300 tunnel $2001,300 ASM $800Month 4road $1,500 tunnel $4002,300 ASM $400Month 5road $700 tunnel $500 ASM $1,900 5,200 anvil $1,700 install $400Month 6 install $2,1002,100total$13,300 Case Study - Accounting Data

  • CAP

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP

    BCWS5005005001,500

    5Install ASM% complete

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    vv

    BLANK

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS

    1Procure Anvil

    BCWP

    BCWS

    2Paint Fake Tunnel

    BCWP

    BCWS

    3Build Road

    BCWP

    BCWS

    4Build ASM

    BCWP

    BCWS

    5Install ASM

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    EV

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

    EV with actuals

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth00-1,600-4001,300700

    cumulative00-1,600-2,000-7000

    Actual Costs7001,7001,3002,3005,2002,10013,300

    Cost Variancemonth-100-100-800-100-1,300-900

    cumulative-100-200-1,000-1,100-2,400-3,300

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

  • CAP

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP

    BCWS5005005001,500

    5Install ASM% complete

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    BLANK

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS

    1Procure Anvil

    BCWP

    BCWS

    2Paint Fake Tunnel

    BCWP

    BCWS

    3Build Road

    BCWP

    BCWS

    4Build ASM

    BCWP

    BCWS

    5Install ASM

    BCWP

    TOTAL CONTROL ACCOUNT PLANBCWS

    BCWP

    Schedule Variancemonth

    cumulative

    Actual Costs

    Cost Variancemonth

    cumulative

    &CCONTROL ACCOUNT PLAN

    EV

    EV Techniques0/100, 50/50, Units Complete,

    % Complete, Milestones

    CONTROL ACCT. TITLE: RoadrunnerCONTROL ACCOUNT MANAGER: Wile E. Coyote

    BUDGET: $10,000

    TIER I MILESTONEKT AWDKT COMP

    WP#WORK DESCRIPTIONEV METHODMONTH 1MONTH 2MONTH 3MONTH 4MONTH 5MONTH 6TOTAL BAC

    BCWS1,5001,500

    1Procure Anvil0/100

    BCWP1,500

    BCWS5005001,000

    2Paint Fake Tunnel50/50

    BCWP500500

    BCWS6006006006006003,000

    3Build Roadunits complete

    BCWP6006000.01,200600

    BCWS1,0001,0001,0003,000

    4Build ASMmilestone123

    BCWP1,0000.01,0001,000

    BCWS5005005001,500

    5Install ASM% complete

    BCWP0.03001,200

    TOTAL CONTROL ACCOUNT PLANBCWS6001,6002,1002,6002,60050010,000

    BCWP6001,6005002,2003,9001,20010,000

    Schedule Variancemonth00-1,600-4001,300700

    cumulative00-1,600-2,000-7000

    Actual Costs7001,7001,3002,3005,2002,10013,300

    Cost Variancemonth-100-100-800-100-1,300-900

    cumulative-100-200-1,000-1,100-2,400-3,300

    &CCONTROL ACCOUNT PLAN

    vv

    vv

    vv

    vv

    vv

    vv

  • 1.0.91.1GOODBAD1.2.8COST PERF INDEX (CPI) = BCWP ACWP

    SCHED PERF INDEX (SPI) = BCWP BCWSCPISPITIMEPerformance Indices

  • % scheduled = BCWS x 100% BAC

    % completed = BCWP x 100% BAC

    Months ahead or behind = SV $ Average monthly BCWS $BCWSBCWPTIME NOWMONTHS BEHINDSchedule Statuscompare

  • budget status

    % spent = ACWP x 100% BACcompare: % spent vs. % complete

    example: 60% spent vs. 50% completeBudget Status

  • Format 5 variance analysis should address:separate discussion of CV, SV (current and cum) and VACclear description of reason for variancequantity variances (e.g., price vs. usage)be specific, not generalcorrective actiontechnical, schedule, and cost impactsimpact to estimate at completion

    should be written by CAM!Variance Explanations A big hammer for a big variance!

  • What is a significant variance?% variance (e.g., >10%)$ variance (e.g., >$50,000)critical path elementrisk/complexityimpact to other elementsTop 10, Top 20, etc.contractor definedSignificant Variances

  • Case Study Analysis(month 5)Variance Analysis Report

    The program is now 88% complete. We have now spent $1,200 more than our original budget, primarily driven by two problems: 1) building the sections of roads (unforeseen grading problems) 2) manufacturing and quality testing of the ASM (increase in the price of raw stock and higher rates than forecast for quality personnel)

    We are only 20% complete on installation, instead of our scheduled 66%. In order to meet contract schedule, we will have to expend overtime. Costs will increase by an expected $1,000. Performance Report, Month 5

    Chart1

    1600600700

    2220022002400

    3430027003700

    4690049006000

    59500880011200

    6100001000013300

    BCWS

    BCWP

    ACWP

    Month

    Road Runner Control Account

    Chart2

    0.85714285711

    0.91666666671

    0.72972972970.6279069767

    0.81666666670.7101449275

    0.78571428570.9263157895

    CPI

    SPI

    Month

    CPI and SPI

    Sheet1

    Month123456

    BCWS6001600210026002600500

    BCWP6001600500220039001200

    ACWP70017001300230052002100

    cum

    123456

    BCWS600220043006900950010000

    BCWP600220027004900880010000

    ACWP7002400370060001120013300

    123456

    CPI0.85714285710.91666666670.72972972970.81666666670.78571428570.7518796992

    SPI110.62790697670.71014492750.92631578951

    percent compl0.060.220.270.490.881

    EAC (CPI)11666.666666666710909.090909090913703.703703703712244.897959183712727.272727272713300

    Sheet2

    Sheet3

    Sheet4

    Sheet5

    Chart1

    1600600700

    2220022002400

    3430027003700

    4690049006000

    59500880011200

    6100001000013300

    BCWS

    BCWP

    ACWP

    Month

    Road Runner Control Account

    Chart2

    0.85714285711

    0.91666666671

    0.72972972970.6279069767

    0.81666666670.7101449275

    0.78571428570.9263157895

    CPI

    SPI

    Month

    CPI and SPI

    Sheet1

    Month123456

    BCWS6001600210026002600500

    BCWP6001600500220039001200

    ACWP70017001300230052002100

    cum

    123456

    BCWS600220043006900950010000

    BCWP600220027004900880010000

    ACWP7002400370060001120013300

    123456

    CPI0.85714285710.91666666670.72972972970.81666666670.78571428570.7518796992

    SPI110.62790697670.71014492750.92631578951

    percent compl0.060.220.270.490.881

    EAC (CPI)11666.666666666710909.090909090913703.703703703712244.897959183712727.272727272713300

    Month 5

    BCWSBCWPACWPSVCVCV %

    Procure Anvil1,5001,5001,7000-200-13%

    Paint Fake Tunnel1,0001,0001,1000-100-10%

    Build Road3,0003,0003,9200-920-31%

    Build ASM3,0003,0004,0800-1,080-36%

    Install ASM1,000300400-700-100-33%

    9,5008,80011,200-700-2,400

    Sheet2

    Sheet3

    Sheet4

    Sheet5

    Chart1

    1600600700

    2220022002400

    3430027003700

    4690049006000

    59500880011200

    6100001000013300

    BCWS

    BCWP

    ACWP

    Month

    Road Runner Control Account

    Chart2

    0.85714285711

    0.91666666671

    0.72972972970.6279069767

    0.81666666670.7101449275

    0.78571428570.9263157895

    CPI

    SPI

    Month

    CPI and SPI

    Sheet1

    Month123456

    BCWS6001600210026002600500

    BCWP6001600500220039001200

    ACWP70017001300230052002100

    cum

    123456

    BCWS600220043006900950010000

    BCWP600220027004900880010000

    ACWP7002400370060001120013300

    123456

    CPI0.85714285710.91666666670.72972972970.81666666670.78571428570.7518796992

    SPI110.62790697670.71014492750.92631578951

    percent compl0.060.220.270.490.881

    EAC (CPI)11666.666666666710909.090909090913703.703703703712244.897959183712727.272727272713300

    Month 5

    BCWSBCWPACWPSVCVCV %

    Build ASM3,0003,0004,0800-1,080-36%

    Build Road3,0003,0003,9200-920-31%

    Procure Anvil1,5001,5001,7000-200-13%

    Paint Fake Tunnel1,0001,0001,1000-100-10%

    Install ASM1,000300400-700-100-33%

    9,5008,80011,200-700-2,400

    Sheet2

    Sheet3

    Sheet4

    Sheet5

  • Estimate at Completion (EAC)defined as actual cost to date + estimated cost of work remainingcontractor develops comprehensive EAC at least annuallyreported by WBS in cost performance reportshould examine on monthly basisconsider the following in EAC generation performance to dateimpact of approved corrective action plansknown/anticipated downstream problemsbest estimate of the cost to complete remaining work also called latest revised estimate (LRE), indicated final cost, etc.What will be the final cost?ACWP + ETC = EAC

  • Common EAC Formulae:

    EAC =BACCPI

    = ACWPcum + Budgeted Cost of Work Remaining CPI3

    =ACWPcum + Budgeted Cost of Work Remaining .8(CPI) +.2(SPI)

    = ACWPcum + Budgeted Cost of Work Remaining CPI * SPI

    One method: statistical formulae

  • Other methods of EAC calculationGrass Roots or formal EACdetailed build-up from the lowest level detailhours, rates, bill of material, etc.Average of statistical formulaeShow range of EACs (optimistic, most probable, pessimistic)Complete schedule risk analysis for remaining work, estimate work remaining

  • Variance at Completion vs. Contractor Loss

    Positive VAC: EAC < BACunderruncontractor gain

    Negative VAC:EAC > BACshare areacontractor partial lossEAC > ceilingoverruncontractor loss (100%)

    Government develops top level EAC for comparisongovernment will limit progress payments if EAC is greater than ceilinggovernment needs forecast of fund requirementsMay still have time to change the final outcomeWhy do we need accurate EACs?

  • over 800 military programs show that ......

    no program has ever improved performance better than the following EAC calculation EAC = BAC CPIat 15% complete point in program

    early stages!no one pays enough attention in theSurvey says..

  • Managing with Earned Value Data

    Here comes your footer Page *

  • Managing with EVMSChange the mindsightTailor to how the contractor actually managesMake it forward lookingAssign responsibility within the government program officeSet up a faster response timeAcquire and use software analysis tools

  • The New Way to Do BusinessOwnership by program managers and IPTsIndustry taking lead to make EVMS a basis business practiceUse of earned value reporting as management tool to avoid cost overruns (forward looking)Schedule management an integral part of project managementNew focus for reviewsbaseline realism, executabilityinsight, not oversight

    EVMS is a cultural change for program managers

  • How can we manage programs using Earned Value?In order for Earned Value to be used as a management tool.

    We must tailor it to reflect the management structure, policy, and operating culture of the contractor.

    Otherwise, it will be seen simply as an external report that reports history!

  • Forward LookTime nowWhere weve beenETCBCWRCum SV$Cum CV$SPICPI3 month avgVariance explanationTCPI-LRETCPI-BACProjected variancesSchedule riskTechnical risk

  • The Control Account ManagerCONTROLACCOUNTMANAGER(CAM)GOVERNMENTCONTROLACCOUNTMANAGER(GCAM)COSTSCHEDULETECHNICALEmpowered by program manager...Manage assigned effort: Technical Schedule CostMonthly variance analysisUnderstand the baseline

  • Analysis within the SPOAssign to technical managers within program officesGovernment Control Account managers (GCAMs)Conduct monthly team variance meetings Open, honest communication essentialOral, e-mail, and face-to-face discussionsContinuing dialogue dramatically improves Format 5Early warning analysisTop level cost and schedule analysis by EVMS and schedule analystsCAM/GCAM analysis at lowest levelWork closely with DCMC teamShare results of analysis with contractor

  • Early Warning SystemFlash data received ASAP, no written analysisEVMS and schedule managers review dataTeleconference with DCMCevaluate cost and schedule variancesevaluate trendsevaluate against program master schedulePrepare top level analysis to program manager and IPT leadsrecommend elements for further analysisGCAMs discuss their elements with CAMswrite up own variance analysisDont wait until you get the report to communicate!

  • New Advances in Software Analysis ToolsCAMGCAMPAPERCPR &SCHEDULECPR &SCHEDULE

  • Let software tools do the number crunching

  • Joint Use of Software ToolsTrend Analysis - Where Have we Been?Lowest WBS level or IPT levelcolor codes, chartsProjection of future - How Bad Can it Get?EAC trendscomparison of cost efficienciesFocus on problems - What are the significant drivers?Sort by elements, trends, CAM namesautosync to program scheduleFormat 5 Analysis - What are we doing about it?Joint analysis, corrective plans, risk mitigationReport generatorall formatscan go paperless

  • Notable EVMS QuotesAre we looking good, or are we in trouble? And, how do we know?CAPT Joe Dyer, USNF/A-18E/F Prog MgrIt forces you to plan, and then to manage to the plan.Lt Col Paul Vancheri, USAFJSTARS Production Prog Mgr

  • SummaryMeasures of Successful ReformEVMS used to make daily decisions about program executioncontractor and governmentReports are not seen as burdensome andPrograms are completed on time and within budget

  • Additional References

    Here comes your footer Page *

  • SCHEDULE TYPES Gantt Chart - Activities Show a Specific Start and Stop Date

    Milestone Chart - Major Event Oriented. Shows Start or Stop Date of Activity

    Line of Balance - Depicts Production Activity. Actual versus Planned Output

    Networking - Identifies and Defines all Activities and Events for a Program and Links Them in Logical Cause and Effect Sequences

  • SCHEDULE TYPES (contd)MILESTONE CHART LINE OF BALANCE TECHNIQUE

  • MATERIAL EARNED VALUE METHODOLOGIES

    Here comes your footer Page *

    Category

    Definition

    Earned Value Approach

    Material

    Raw materials, piece parts, and low value purchased items

    Percent complete against total projected purchase requirement. Milestones by order

    Major Material

    High cost items that are standard products such as from a catalog. These are individually tracked due to their cost or criticality to the program

    Each item represents an individual milestone

    An order of multiple items may use percent complete against the total quality

    Fixed Price Subcontracts

    High cost (usually negotiated) items purchased against specification or drawing. These items require individual management

    Milestones against deliveries or subcontract milestones. May require estimated actuals or percent complete if no progress payments or interim deliveries

    Cost Subcontracts

    High cost (usually negotiated) items purchased against a specification or drawing. These items require individual management

    Flow down of Cost/Schedule Status Report (C/SSR) or C/SCSC requirements. If small may use payments and negotiated

    subcontract milestones.

  • PERFORMANCE STATUS...KEY THINGS TO TRACK DO I HAVE ANY SIGNIFICANT COST/SCHEDULE VARIANCES?Schedule VarianceCost VariancePlus (+) is goodPlus (+) is goodMinus (-) is badMinus (-) is badWhat is the variance % What is the variance %Is it on the critical path Schedule slack?Is it in an area that has been identified as a risk element?

    WHAT IS THE TREND (GETTING BETTER OR WORSE)? Chart the Cost/Schedule variance trends Does my contractor tell the same story as the data? When do I think the trend will improve?

    WHAT AM I DOING ABOUT IT? Causes Corrective actions Impact to the program

  • USE DATA FOR DECISION MAKING Behind Schedule - How critical is schedule? - Can I afford to work overtime to recover? - Can I do tasks concurrently? - Are there technical innovations which could speed up the process? - Am I gold plating instead of just meeting requirements? - Should I do a schedule risk assessment to project impact to program?

    Over Cost - Can I reschedule tasks? (Timephasing) - Is there a less costly facility I can use? - Are there tasks which can be deleted? - Should the element be added to my risk management profile?

  • GOAL: To Verify That Effective Variance Analysis Processes Are Applied To Identify, Correct, And Report Problems

    POTENTIAL PROBLEM INDICATORS: Zero variances

    Monthly trends turning negative or downward

    Schedule variances generally indicate cost will follow

    Actuals > Latest Revised Estimates (LRE)

    BCWP increases with no increase in ACWP

    Negative data elementsEARNED VALUE PROBLEM INDICATORS

  • DO I THINK THE CONTRACTOR WILL COME IN ON BUDGET?

    COST PERFORMANCE INDEX:

    CPI = cost efficiency for work performed to date(The value of work accomplished for each dollar spent)

    $1000= = = $2400 = .42

    Compare the CPI to the TCPI-BAC:

    TCPI(BAC) = Efficiency necessary to complete on budget

    $5000 - $1000= = = $5000 - $2400

    PERFORMANCE EFFICIENCY AND EACsBCWPACWPWORKACCOMPLISHEDACTUALSBAC-BCWPBAC-ACWPWORKREMAININGBUDGETREMAINING = $4000$2600= 1.54HISTORYFUTURE

  • PERFORMANCE EFFICIENCY AND EACs (contd)

    SCHEDULE PERFORMANCE INDEX: SPI = schedule efficiency with which work has been accomplished(The rate at which work is being accomplished)

    WORK BCWP ACCOMPLISHED $1000= BCWS = WORK = $2000 = .50 SCHEDULED

  • PERFORMANCE EFFICIENCY AND EACs (contd) IS THE CONTRACTOR'S EAC (LRE) REASONABLE?Compare the CPI to the TCPI-LRE

    TCPI(LRE) = Efficiency necessary to complete at the contractors estimate

    WORK $5000 - $1000 $4000= BAC-BCWP = REMAINING = $6400 - $2400 = $4000 = 1.00 LRE-ACWP ESTIMATE REMAINING

    Cumulative performance to date (CPI) = .42

    Contractor has been performing at 42% efficiency, but expects to complete remaining work at 100% efficiency! reasonable?

  • Ten Wisdom Principles of EVMS1. Use a single management control system to provide accurate and timely performance data.

    2. Integrate the scope of work, schedules, and costs using a common project language, such as a work breakdown structure.

    3. Actual performance at the 15% complete point can be used to predict final performance.

    4. Cumulative cost performance index (CPIe) measures efficiency and can be used to predict the final range of costs.

    5. The schedule performance index (SPI) is useful in assessing how much work has been accomplished.

    6. The CPI index provides a statistical basis for a best case final estimate.

    7. The CPI and SPI indices may be combined to statistically forecast the most likely final estimate.

    8. To Complete Performance Index provides a measure of efficiency required for the future work to achieve either a specified budget or estimate.

    9. The periodic cost performance index for performance (CPIp), calculated by actuals/earned value, may be used to monitor weekly or periodic production progress.

    10. Management should use management by exception to focus on significant variances to the plan and apply timely corrective actions.Source: Earned Value Project Management, Quentin W. Fleming & Joel M. Koppelman, Project Management Institute, 1996

  • Key Documents in Understanding EVMSGary Christle, 22 Jan 94, paper, Implementation of Earned Value - A Model Program ApproachUSD(A&T) Letter, 25 Jan 94, Improved Cost and Schedule Performance ManagementGary Christle, 15 Sep 94, paper, The Cost/Schedule Control Systems Criteria and Earned Value Management: A VisionUSD(A&T) Letter, 1 Oct 96, Compliance Responsibility for the Cost/Schedule Control Systems Criteria (C/SCSC)3 Oct 97, Earned Value Management Implementation Guide (Rev 1)USD(A&T) Letter, 14 Dec 96, Industry Standard Guidelines for Earned Value Management SystemsWayne Abba, article in Jan-Feb 97 Program Manager magazine, Earned Value Management - Reconciling Government and Commercial PracticesANSI/EIA 748-1998, Earned Value Management SystemsQuentin W. Fleming & Joel M. Koppelman, book, Earned Value Project ManagementEarned Value web page: www.acq.osd.mil/pm

    8255912There are four basic schedule charts:The Gantt ChartThe Milestone ChartLine of Balance Charts andNetworkingI will discuss each of these on the next slide.

    The Gantt Chart shown here lists program activities with a specified start and stop date.The Milestone Chart is major event oriented. As you can see it shows a start or stop date for an activity but not amount of time the activity takes.Line of Balance charts are used primarily for production activity. It depicts actual versus planned output.The network is the most comprehensive form of scheduling. It identifies all activities and events that must occur on the program and then links them in logical cause and effect sequences. Each activity will show what tasks must occur before it can happen and what tasks it will feed into.19Measuring performance for material is more difficult than for labor.Each contractor has his own method for material performance measurement.This chart lists several methods used along with the type of material they are used for.You may go through these at your convenienceWhen tracking the performance status there are some key things we need to look at.Plus (+) is good and minus (-) is bad in both cost and schedule.A negative variance for one month may not be considered significant, unless it is on the critical path and then it needs to be looked at a little closer. We also need to track it closer if it is an item we have identified as a risk element. We do need to track whether or not the trend is getting better or worse, is the contractor telling the same story the data shows, and are there any indications that the trend will improve.We need to look at the cause of the problem, what corrective action is proposed, and how will it impact the completion of the program. The reason for all of these performance indices to to assist program management is making decisions about their program. When something is behind schedule the PM needs to decide how critical the the schedule is, what is causing it, and what can be done about it. These are some of the issues that should be considered. If schedule is critical and it is continuing to slip, he may want to request a schedule risk assessment to evaluate the impact to the program.

    If cost variances continue to creep up this is some of the things the PM may want to consider. If no more funds are available then he may have to make some changes.

    There may be some lower level items that are causing the problem and the reporting level may need to be changed so he can track them closer and also add them to his risk management profile.Our goal when we are looking at contractor cost data is to verify that effective variance analysis processes will be applied to identify, correct, and report problems when they arise.Quick identification of problems is the key to making this work.We have highlighted some of the situations that are indicators that a problem exists.When there are zero variances -- It is extremely rare for estimated costs to exactly equal actualsMonthly trends turning negative or downward -- Definite indication of a problemSchedule variances usually lead to cost variancesActuals greater than LRE means a new LRE needs to be developed to see what program cost will beBCWP increase with none is ACWP -- Should not be adding budget if actuals are not indicating it is neededNegative data elements -- Unless to correct previous error

    There are several performance indices that help us to understand the current and future status of the program based on his performance to date.The Cost Performance Index (CPI) shows cost efficiency for work performed to date. In this case for each budget dollar spent only 42 cents of value was received.The To Complete Performance Index (TCPI) shows the efficiency necessary to complete on budget. The contractor would have to perform at an efficiency level of 154% or do $1.54 of work for every budget dollar to achieve his BAC.

    The Schedule Performance Index (SPI) shows the schedule efficiency for work performed to date. This SPI shows that the contractor was only accomplishing work at a rate of 50% of what he had planned.The TCPI(LRE/EAC) depicts the efficiency necessary for the contractor to complete at his estimated EAC. Since we had assumed the contractor had resolved all problems it is no surprise that he only has to work at 100% to achieve his EAC. Of course, he was only working at 42%.