early warning radar
TRANSCRIPT
-
7/28/2019 Early Warning Radar
1/41
Change IdentificationEarly Warning Radar
Durward E. Timmons, Esq.Sherman & Howard, LLC
Colorado Springs, COApril 12, 2011
-
7/28/2019 Early Warning Radar
2/41
Why Worry About Claims?
Claims on construction projects are:
1. Time consuming;2. Disruptive;
3. Expensive; and
4. Career limiting.
-
7/28/2019 Early Warning Radar
3/41
Out of Scope Work
Contractor: I had to do more work than the
contract required!
Owner: Lets compare what you say you did tothe contracts scope of work.
Here Comes a Claim!!!!!
-
7/28/2019 Early Warning Radar
4/41
Delay
Contractor: You took too much time to review
my shop drawings and it delayed my work.
Owner: Lets compare your as-plannedschedule with you as-built schedule.
Here Comes Another Claim!
-
7/28/2019 Early Warning Radar
5/41
Increased Costs
Contractor: This job is costing me more than
my bid price. Im losing my shirt!
Owner: What does your resource-loadedschedule show your costs should have been?
Yet Another Claim!!!!
-
7/28/2019 Early Warning Radar
6/41
Project Basics
Proper
PreparationPrevents
Poor
Performance
-
7/28/2019 Early Warning Radar
7/41
Ten Commandments for ProjectManagers
1. Know well thy contract.
2. Keepeth to thy schedule.
3. Giveth not away thyleverage, for thybargaining power issacred.
4. If thou asketh not, thoushall not receive.
5. Keepeth holy thydocumentation.
6. Surpriseth not thy elders.
7. Delay not thy response toadversity.
8. Prepareth and preserveththy pricing.
9. Seeketh early the help of
the wise.10. Stompeth not the ants
while the elephantsrunneth around wild.
-
7/28/2019 Early Warning Radar
8/41
Construction Project Are Unique
Construction projects:
1. are notnever-ending production lines;
2. are planned, executed and controlled;
3. have physical structures;
4. are constrainedby resources (e.g. time,
funding, craft labor);5. have a means to determine project start
and completion.
-
7/28/2019 Early Warning Radar
9/41
The Key Project Activities
Claims prevention focuses on:
1. Scope Control;2. Schedule Maintenance; and
3. Cost Management.
-
7/28/2019 Early Warning Radar
10/41
Organized projects follow a 3-step, serialprocess:
1. Scope defineWHATs to be done
2. Schedule establishWHEN its to be done
3. Cost estimate HOW MUCH it will cost
Three Step Planning Process
-
7/28/2019 Early Warning Radar
11/41
Project Management Tasks
Managing scope, schedule and costrequires:
Planning What are we going to do?
Defining Exactly how are we going to do it?
Verifying Have we really planned and defined?
Controlling Are we sticking to the plan?
-
7/28/2019 Early Warning Radar
12/41
Scope tracking allowsidentification ofWHATshappening on the project.
Scope Tracking
-
7/28/2019 Early Warning Radar
13/41
Scope Planning
Scope planning asks:
What are the projects goals andrequirements to meet those goals?
Effective scope planning includesstakeholder participation andagreement.
Do we all agree on what were goingto do?
-
7/28/2019 Early Warning Radar
14/41
Scope Planning
Are the projects goals stated interms of:
1. Design Requirements;2. Performance Requirements; or
3. Both?
-
7/28/2019 Early Warning Radar
15/41
Design vs. PerformanceRequirements
Design Specifications specify howsomething is to be done and permit no
deviations.
Performance Specifications specify theultimate goal to be achieved and require
the contractor to determine the best wayto achieve that goal.
-
7/28/2019 Early Warning Radar
16/41
Assignment of Risk
SpecificationType
Design
Performance
Risk Allocation
Owner
Contractor
Keys to Success
1. Clear, complete plans
and specifications.2. Leave means andmethods to contractor.
1. Establish objective,
verifiable measures ofsuccess.
2. Dont change thecriteria.
-
7/28/2019 Early Warning Radar
17/41
Scope Definition
Scope definition identifies all project
deliverables and divides them into thesmallest measurable units for whichcost and duration estimates can be
made.
-
7/28/2019 Early Warning Radar
18/41
Work Breakdown Structure
A WBS divides each project activityinto the smallest logical components
which can be assigned to individuals or
project units for completion.Example: Foundation Work
1. excavate 4. pour concrete
2. set forms 5. strip forms
3. tie rebar 6. inspect
7. backfill
-
7/28/2019 Early Warning Radar
19/41
Scope Verification
Scope verification formalizes keystakeholder understanding and acceptanceof a projects scope.
Effective verification includes a detailedreview of the WBS to ensure agreement bythe contracting parties on contract
requirements.
-
7/28/2019 Early Warning Radar
20/41
Contractor Protection
A WBS is a roadmap of a project
against which to measure projectprogress and assertions of changes inscope.
Contractors should prepare a WBSprior to construction start-up.
-
7/28/2019 Early Warning Radar
21/41
Scope Change Control
Change control involves:
1. Influence control factors whichtypically lead to changes and ensure only
beneficial changes occur;2. Attention - determine when
unanticipated changes occur;
3. Management - when they do occur,limit the impact.
-
7/28/2019 Early Warning Radar
22/41
Change Control
Measure all potential changes against thecontracts scope of work.
Ask yourself:
1. Is the change qualitatively orquantitatively more or less than required?
2. If so, to what extent?
-
7/28/2019 Early Warning Radar
23/41
Schedule tracking helpsidentifyWHEN something
happens.
Schedule Tracking
-
7/28/2019 Early Warning Radar
24/41
Tracking the Project Schedule
Project scheduling involves:
Defining activities
Sequencing activitiesEstimating activity durations
Schedule preparation
Schedule control
-
7/28/2019 Early Warning Radar
25/41
Critical Path Scheduling
The Critical Path Method (CPM) ofscheduling is the most widely used in the
industry.Critical Path is the series of activities which
controls the pace of the work. Any delay to acritical path activity will result in a day-for-daydelay in the projects completion date.
-
7/28/2019 Early Warning Radar
26/41
The Key Project Schedules
As-Planned Schedule - describes whenthe work is supposed to be done.
Periodic Updates - describe when theworkis being done.
As-Built - final schedule which recordswhen the workwas actually done.
-
7/28/2019 Early Warning Radar
27/41
-
7/28/2019 Early Warning Radar
28/41
Resource-Loaded Schedule
AResource-Loaded Schedule identifies all:
1. labor;
2. materials;
3. equipment; and
4. other resources
required to complete each task.
-
7/28/2019 Early Warning Radar
29/41
Resource-Loaded Schedule
Example:Activity: Excavate foundation
Resource Quantity CostLabor 200 manhours $50/hrMaterials metal shoring $500
Equipment 1 - bull dozer $75/hr4 - dump trucks $30/hrOther fuel, oil, lubricants $5/hr
-
7/28/2019 Early Warning Radar
30/41
Activity Sequencing
Activity sequencing identify allactivity interdependencies.
Ask yourself: In what order must allactivities be completed to finish theproject?
Activity sequencing requires familiaritywith construction process and judgmentbased on experience.
-
7/28/2019 Early Warning Radar
31/41
Activity Sequencing
Example:Activity: Drywall Installation
1. Estimate drywall materials
2. Order drywall and materials
3. Stage drywall
4. Hang drywall5. Tape and mud drywall
6. Finish sand drywall
-
7/28/2019 Early Warning Radar
32/41
Activity Duration Estimating
Duration estimating determine thetime required to complete each activity.
Activity float is the bandwidth of time
within which an activity may begin andstill be completed on time.
Activity durations form the basis for
measuring schedule impacts.
-
7/28/2019 Early Warning Radar
33/41
Schedule Development
Preparing a schedule requires:
1. Input of activities, sequencing, anddurations into a scheduling software application
e.g. Primavera or MicroSoft Project.2. Confirming the logic of the overallschedule.
While scheduling software will create aproject schedule - BEWARE - Garbage In,Garbage Out.
-
7/28/2019 Early Warning Radar
34/41
Schedule Control
Schedule control requires:1. Influence manage the factors which
impact the schedules - ensure onlyfavorable changes to the schedule;
2. Attention - determining when theschedule has been changed;
3. Revision incorporate schedule impactsinto the current schedule as they occur.
-
7/28/2019 Early Warning Radar
35/41
Cost Tracking helpsdetermine how much it will
COST
Cost Tracking
-
7/28/2019 Early Warning Radar
36/41
Monitoring Project Costs
Project Cost Management includes:
Resource planning;
Cost estimating;Cost budgeting;
Cost control.
-
7/28/2019 Early Warning Radar
37/41
Resource Planning
Resource planning requiresdetermining what labor, materials andequipment are required to performparticular tasks.
Reference back to the WBS is critical toadequate resource identification.
-
7/28/2019 Early Warning Radar
38/41
Cost Estimating
Cost estimating involves approximatingall resource costs needed to complete projectactivities.
Cost estimates form thebaseline againstwhich changes to the work can be measuredin terms of cost.
-
7/28/2019 Early Warning Radar
39/41
Cost Budgeting
A Cost Budget allocates overall costestimates to individual activities.
Cost budgeting will result in a time-phasedbudget.
Cost budgeting is based on:
1. cost estimates;
2. the WBS;
3. the project schedule.
-
7/28/2019 Early Warning Radar
40/41
Cost Control
Effective cost control requires:
1. monitoring cost performance against the time-phased cost baseline;
2. recording authorized changes in the costbaseline;
3. change order accounting;
4. informing stakeholders of authorized changesto the cost baseline.
-
7/28/2019 Early Warning Radar
41/41
Cost Control
Costs
j ij j l
$0
$100,000
BudgetCosts
ActualCosts
UnderBudget
OverBudget