early delivery systems status
DESCRIPTION
Early Delivery Systems Status. Daryl Cote. EDS Status Update. Sep. Oct. Nov. Dec. Jan. 2008. 2007. Feb. E1 R2. ICCP Fail-over / P2P. SE Verification. E2 R3. R3: SE / Telemetry Criteria (SE Tuning). Reporting. Network Model Verification. NOMCR Checkout. E2 R4. - PowerPoint PPT PresentationTRANSCRIPT
January 21, 2008
TPTF
Early Delivery SystemsStatus
Daryl Cote
2TPTF1/21/2008 2
EDS Status Update
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
R4: NOMCR / Network Model verification
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
E4 R9 R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 1 Exit Criteria % of MPs
% of Points
Comments
MPs have completed PtP checkout and topology review for all submitted Nodal points (MP5)
95%(95%)
99%(99%)
37 of 38 MPs tested. XTend remains to be tested, positive communications recently.
ERCOT has completed local failover testing with each MP (MP6) 97%(87%)
n/a 37 of 38 tested. XTend remains to be tested.
ERCOT has completed Alarm Processing configuration and testing n/a n/a Alarm processing configuration and testing will be implemented with EMS 5.
ERCOT has completed all PtP process documentation to support checkout for new construction / future changes to telemetry
100%(95%)
n/a Final process handoff and transition to Operations completed in December.
Outstanding ICCP issues <= 3% per MP (MP5) 100% n/a Overall error rate ~1%.
Quality Code Retesting (MP5) 100% n/a 37 of 37 MPs regression tested with quality code fix.
Reporting
Legend: % in parentheses are from the 11/05 TPTF update
EDS 1 Approach will be submitted to TPTF for completion approval on Feb 8
3TPTF1/21/2008 3
Alarm Processing Approach – Expected Delivery Schedule
• Alarms Highlighted in Yellow have been configured and Tested by Market Participants:
– Reliant– CenterPoint – Luminant
• The processing of the remaining Alarms require code upgrades which will be included in the EMS 5 delivery.
• Target delivery for EMS 5 is May ‘08
# Category Name Definition
1 Frequency DeviationWhen frequency deviation is above the RRS recovery limits 3 x
When RRS is deployed partially and frequency deviation above RRS limit 3 x
If the real time frequency is above defined threshold 3 x
When reserve capacity is below Operator specified limits 3 x
When un-deployed regulation-up is below Operator entered threshold 3
When un-deployed regulation-down is below Operator entered threshold 3
When telemetered HSL is higher than Net Dependable Capability 3When difference between HASL and total energy req < Operator threshold 3
When the difference between HDL sum and total energy req < Operator threshold 3
If scheduled LAAR and RT LAAR are differed by threshold 3 x
Need to send selected alarms to MIS 3System Operating Limits When SOL is more than 95% of the limit specified 2 x
SCADA Overloads When MVA line or trans flow > 98% dynamic emor rating or 100% normal rating 2
SE Overloads When MVA line or trans flow > 98% dynamic emor rating or 100% normal rating 2 x x x x 19-Dec-07
When RT flow close to 95% of SPS triggering condition 2 x
If real time status of SPS goes disabled, alarms shall be generated 2
When 345Kv bus voltages are outside specified limits 2 x
When 138/69 Kv bus voltages are outside specified limits 2 x
4 Resource Control Errors When RE (Resource Error) is outside the limits defined by the Operator 3 x
Forced line/transformer outages for 345Kv 2 x
Forced Bus outages for 345Kv 2 x
Planned line/transformer outages for 345Kv 2 x
Planned Bus outages for 345Kv 2 x
Switching Device Status When 345Kv/unit breakers change status 1 x x x x 19-Dec-07
Forced line/transformer outages for 138/69Kv 2 x
Forced Bus outages for 138/69Kv 2 x
Planned line/transformer outages for 138/69Kv 2 x
Planned Bus outages for 138/69Kv 2 x
When 138Kv/unit breakers change status 1 x x x x 19-Dec-07
When 69Kv/unit breakers change status 1 x x x x 19-Dec-07
Forced Outage Detector When FOD detects Forced unit outages 2 x
Planned Outage When FOD detects Planned unit outages 2 x
ICCP Link 1 x
TCM, Dynamic Ratings, SE, NSA, PI 2
LFC, SCED, VSAT, TSAT, FOD 3
System Status Generate system alarms for, Site Failover, EMS failover, MMS failover 3 x
EMS Security For unauthorized logins to EMS system 2
Application Status
8
Switching Device Status
7
6
Forced Outage Detector
Planned Outage
SPS3
Voltage Limits
Forced Outage Detector
5Planned Outage
2 Ancillary Service Capacity
1 Frequency Deviation
4TPTF1/21/2008 4
Release 3 – State Estimator and Telemetry
2007 2008Sep Oct Nov Dec Jan Feb
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
E1 R2
E2 R3SE Verification
EDS 2 Release 3 Exit Criteria % Complete
Comments
TSP/QSE data points reasonably conform to Telemetry and SE Performance criteria
70% • ~1000MW delta in Generation data• ~4000 TSP points need investigation
ERCOT Operations have operating procedures in place to address performance issues
30%(30%)
8 of 27 procedures have been updated. The remaining will be completed when Release 3 processes are verified.
Network Security Analysis functions are verified and ERCOT Operations have procedures in place to manage
76%(76%)
Latest releases addressed some issues and a release in Late January should address the remaining issues.
ERCOT SE is tuned and meets performance criteria 43%(15%)
Convergence and Tolerance – see slide 6Unobservable – see slide 8
Load Modeling restructured, load adaptation and bus load forecast verified
75%(50%)
Schedules loaded into EDS in early November.
EDW reports correctly post to MIS and can be accessed
40% SE Performance reports are completing FAT testing. Telemetry reports will be provided using a workaround until early 2008.
EDW reports have been verified within ERCOT and by MPs
0% Telemetry and State Estimator standards in stakeholder process.
Legend: % in parentheses are from the 11/05 TPTF update
5TPTF1/21/2008 5
SCED Inputs (Telemetry and ICCP to SCADA)
• 100% of requested data received by ERCOT. Verification of data in process:
– Austin Energy, AEP, APX, Brazos, BP, BTU, Calpine, Constellation, Coral, CPS, Exelon, FPL, Garland, LCRA, NRG, OXY, Reliant, STEC, Suez, Tenaska, and Luminant
– Does not include weather data
• This status reflects efforts by ERCOT to complete all ICCP and SCADA mapping.
• ERCOT is developing reports to isolate quality issues and will be contacting QSEs & TSPs directly to help resolve issues
6TPTF1/21/2008 6
Convergence Rate
SE Status
0
10
20
30
40
50
60
70
80
90
100
2-Jan
3-Jan
4-Jan
5-Jan
6-Jan
7-Jan
8-Jan
9-Jan
10-Jan
11-Jan
12-Jan
13-Jan
14-Jan
15-Jan
16-Jan
17-Jan
Date
Co
nve
rgen
ce
0
20
40
60
80
100
120
To
lera
nce
Convergence Rate (%) ToleranceNo Convergence due to
System Outage
7TPTF1/21/2008 7
EDS 2 – State Estimator and Telemetry Criteria
Telemetry Criteria Status Comment
Data Quality (MW/MVar Tolerance) At 100 Moved it back to 100 after upgrade
Telemetry Availability tbd Need EDW Report
Critically Important Telemetry tbd Need EDS Report
Availability for Critically Important Telemetry tbd Need EDW Report
Requests for Redundant Telemetry tbd Need Critical Measurement functionality
State Estimator Criteria Status Comment
SE Convergence Stable at 50MW variance when application is running (e.g. not down due to hardware or database loads)
Transmission Element SE Accuracy tbd Need EDW Report
Critical Transmission Element SE Accuracy tbd Need EDW Report
Critical Bus Voltage Accuracy tbd Need EDW Report
SCADA Measurement Accuracy tbd Need EDW Report
Status of SE and Telemetry Criteria
8TPTF1/21/2008 8
Observability Status
9TPTF1/21/2008 9
Release 4 – NMMS / NOMCR
2007 2008Sep Oct Nov Dec Jan Feb
R4: NOMCR / Network Model verificationE2 R4NOMCR Checkout Network Model Verification
Start of EDS 2 - R4 NOMCR has been moved to week of 3/17/2008 NMMS will be available in a “Sandbox” environment enabling market participants to
become familiar with the system starting week later this week Software defects with severity one have been experienced in FAT testing, which are
causing delay for starting the EDS 2 Release 4 - NOMCR NMMS/NOMCR overview training have been completed by the market participants Citrix connections have been successfully installed and validated for 90% of the testing
participants
10TPTF1/21/2008 10
Release 4 –NOMCR Schedule
# TSPNetwork Model
Management TrainingEDS Training
2 days @ ERCOTEDS Testing
5 days @TSP Site
1 AEP/CPL 10/29 to 11/1/2007 4/7 to 4/8/2008 4/9 to 4/15/2008
2 AEN 1/2 to 1/4/2008 4/16 to 4/17/2008 4/18 to 4/24/2008
3 COD-City of Denton 1/8 to 1/10/2008 5/7 to 5/8/2008 5/9 to 5/15/2008
4 COG-City of Garland 1/2 to 1/4/2008 4/16 to 4/17/2008 4/18 to 4/24/2008
5 BEC 1/2 to 1/4/2008 4/28 to 4/29/2008 4/30 to 5/6/2008
6 CPS 1/2 to 1/4/2008 4/16 to 4/17/2008 4/18 to 4/24/2008
7 MVEC 1/2 to 1/4/2008 4/28 to 4/29/2008 4/30 to 5/6/2008
8 PUB 1/8 to 1/10/2008 4/28 to 4/29/2008 4/30 to 5/6/2008
9 TNMP 1/2 to 1/4/2008 5/7 to 5/8/2008 5/9 to 5/15/2008
10 STEC (1) 1/2 to 1/4/2008 5/7 to 5/8/2008 5/9 to 5/15/2008
11 ERCOT CRR TEAM 1/8 to 1/10/2008 3/26 to 3/27/2008 3/28 to 4/3/2008
12 ERCOT Planning Group 1/8 to 1/10/2008 3/26 to 3/27/2008 3/28 to 4/3/2008
13 BTU 1/8 to 1/10/2008 5/19 to 5/20/2008 5/21 to 5/27/2008
14 CSTX City of College Station 1/8 to 1/10/2008 3/26 to 3/27/2008 3/28 to 4/3/2008
15 GEUS-Greenville 1/8 to 1/10/2008 3/17 to 3/18/2008 3/19 to 3/25/2008
16 MEC 1/2 to 1/4/2008 5/19 to 5/20/2008 5/21 to 5/27/2008
17 CNP 1/8 to 1/10/2008 3/17 to 3/18/2008 3/19 to 3/25/2008
18 TXUED 1/8 to 1/10/2008 5/19 to 5/20/2008 5/21 to 5/27/2008
19 RCEC-Rayburn Country Electric 1/8 to 1/10/2008 4/28 to 4/29/2008 4/30 to 5/6/2008
20 TMPA 1/2 to 1/4/2008 5/7 to 5/8/2008 5/9 to 5/15/2008
21 STEC (2) 1/8 to 1/10/2008 3/26 to 3/27/2008 3/28 to 4/3/2008
22 LCRA 1/2 to 1/4/2008 5/7 to 5/8/2008 5/9 to 5/15/2008
11TPTF1/21/2008 11
Release 5 - SCED
2007 2008
SCED R5.1 SCED R5.3: RT ICCP SCED R5.4: LMP Post
Sep Oct Nov Dec Jan Feb
SCED R5.2
ICCP Fail-over / P2P
R3: SE / Telemetry Criteria (SE Tuning)
R4: NOMCR / Network Model verification
E1 R2
E2 R3
E2 R4
E3 R5
E3 R6 LFC R6.1: ACE
E3 R7 CRR R7.1
E4 R9 R9
6-month LMP Posting
SE Verification
RT ICCP
NOMCR Checkout Network Model Verification
EDS 3 Release 5 Exit Criteria % Complete
Comments
QSEs w/ Resources able to submit COP & TPO for entire portfolio
100% •Known issues with Output Schedules and Performance issues (root cause analysis done on performance issues and passed to teams)
SCED Inputs verified: HRL, LRL, SURAMP, SDRAMP, HDL, LDL; GTBD, ICCP
40%(40%)
Mobilizing team to monitor inputs much more rigorously over the next two-three weeks.
SCED Outputs verified: QSE’s ability to receive Resource Base Points and LMPs via ICCP
35%(35%)
Mobilizing team to monitor inputs much more rigorously over the next two-three weeks.
Base Point and LMP calculation verified for Resources with Offer Curves or Output Schedules
0% Mobilizing team to monitor inputs much more rigorously over the next two-three weeks.
Reports 100%(50%)
Reports related to SCED are available in draft form on MIS and nodal.ercot.com
LMPs verified for Reasonability and posted to MIS for Market Participant review 0%
Expected completion by Feb 15th
Reporting
Legend: % in parentheses are from the 10/22 TPTF update
12TPTF1/21/2008 12
Release 6 - LFC
2008Jan Feb Mar Apr May Jun
E3 R6 R6.1: ACE & RLC
EDS 3 Release 6.1 Exit Criteria % Complete Comments
Test Time Scheduled 100% Dates have been set with all QSEs with Resources. Schedule provided on next slide. First two QSEs had to be moved due to ERCOT upgraded taking longer than expected
Completed Test Form Received back from MP 9% 2 of 22 submitted. Note the test form has been updated and reposted on 1/17/08. Forms due to ERCOT 2 business days before the scheduled test date.
RLC Validation Completed 0% Completed most of the testing effort on Tenaska. ERCOT working to resolve Responsive Reserve Deployment Flag and RLC logic issues
Emergency Base-Point Validation Completed 0%
Legend: % in parentheses are from the 10/22 TPTF update
R6.2: QSE Testing R6.3: TST
Link for LFC Documents & Status: http://nodal.ercot.com/readiness/eds3/documents/index.html
13TPTF1/21/2008 13
Release 6.1 – LFC Testing Status & Schedule
• Testing for BP Energy and CPS was rescheduled due to ERCOT software update
• Testing for Tenaska was conducted Thursday January 17th; completed ~ 80%
• ERCOT Issues:– Responsive Reserve
Deployment Flag– RLC logic
• Will proceed with tests scheduled for week of 1/21– Regression test as needed
QSE List / Sub QSE rider Sub, Sub QSE Test Date Test Time Submitted Finalized Test Complete
AEN - Austin Energy 30-Jan 1:00 PMAEP - American Electric Power 18-Feb 1:00 PMAPX 13-Feb 9:00 AM
ANP Funding 13-Feb 9:00 AMIPA Marketing-SQ1 13-Feb 9:00 AM
Eagle Energy 13-Feb 9:00 AMEagle - SQ1 13-Feb 9:00 AM
Fulcrum 13-Feb 9:00 AMFulcrum - SQ1 13-Feb 9:00 AMFulcrum - SQ2 13-Feb 9:00 AM
Scurry County Wind 13-Feb 9:00 AMJ. Aron 13-Feb 9:00 AMTopaz 13-Feb 9:00 AM
Topaz - SQ1 13-Feb 9:00 AMWestar - SQ1 13-Feb 9:00 AM
BEC - Brazos Electric Coop 19-Feb 9:00 AMBP Energy 29-Jan 2:00 PM
BPE - SQ1 29-Jan 2:00 PMBPE - SQ2 29-Jan 2:00 PMBPE - SQ3 29-Jan 2:00 PM
BTU - Bryan Texas Utilities 12-Mar 9:00 AMGVES 12-Mar 9:00 AM
Calpine Power Management 12-Feb 9:00 AMConstellation Energy 5-Feb 9:00 AM
Cont PS_C 5-Feb 9:00 AMCoral Power 6-Mar 9:00 AMCPS - City Public Services 23-Jan 2:00 PM 14-JanExelon 31-Jan 9:00 AMFPL 20-Feb 1:00 PM
FPL - SQ1 20-Feb 1:00 PMFPL - SQ2 20-Feb 1:00 PMFPL - SQ3 20-Feb 1:00 PMFPL - SQ4 20-Feb 1:00 PMFPL - Wind 20-Feb 1:00 PM
Garland Power and Light 23-Jan 9:00 AM 17-JanLCRA - Lower Colorado River 24-Jan 9:00 AMLEC - Luminant Energy Company 14-Feb 1:00 PMNRG 22-Jan 9:00 AMOXY - Occidental Power Svcs 12-Feb 1:00 PMReliant 27-Feb 9:00 AMSTEC - South Texas Electric Coop 29-Jan 9:00 AMSuez Energy Marketing 30-Jan 9:00 AMTenaska Power Services 17-Jan 9:00 AM 15-Jan 17-Jan 80%
Barton Chapel 17-Jan 9:00 AM 15-Jan 17-JanDirect Energy 17-Jan 9:00 AM 15-Jan 17-Jan
Enerco 17-Jan 9:00 AM 15-Jan 17-JanFormosa 17-Jan 9:00 AM 15-Jan 17-Jan
Luminant - SQ1 Wind 17-Jan 9:00 AM 15-Jan 17-JanRio Nogales 17-Jan 9:00 AM 15-Jan 17-Jan
Sweetwind 5 (Wind) 17-Jan 9:00 AM 15-Jan 17-JanTRQ - SQ1 17-Jan 9:00 AM 15-Jan 17-Jan
TRQ - SQ2 17-Jan 9:00 AM 15-Jan 17-JanTRQ - SQ3 17-Jan 9:00 AM 15-Jan 17-Jan
LFC Phase 1 Testing Status Test Form
14TPTF1/21/2008 14
Release 7.1 - CRR
EDS 3 Release 7.1 Exit Criteria % Complete
Comments
Logged-in and accessed the CRR application 0%
Downloaded one of the pre-auction market information 0%
Uploaded a bid/offer portfolio (in either XML or CSV) 0%
Edited a bid/offer within a portfolio (confirms web browser supports java applets)
0%
Downloaded auction market results 0%
Created a sell/buy bilateral trade posting 0%
Accepted a sell bilateral trade posting 0%
Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07
CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR – R7.4 CRR – R7.5 (TBD)
Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07 Jan 08 Feb 08 Mar 08 Apr 08 May 08Dec 07
CRR – R7.0 CRR – R7.1 CRR – R7.2 CRR – R7.3 CRR – R7.4 CRR – R7.5 (TBD)
~80 participants on Kick-off WebEx on 1/18 – see ERCOT calendar for presentation
Completing EDS environment build out putting pressure on Feb 4th start
15TPTF1/21/2008 15
Release 7.1 - CRR participants
Accent Energy
AEPEP
Air Liquide Large Industries U.S. LP
American Electric Power
ANP Funding I LLC
Bank of America
Brazos Electric Power Cooperative Inc.
Brownsville Public Utilities Board
BTU
Calpine Corporation
Cirro Energy
Citi
City of Austin dba Austin Energy
City of Garland
Commerce Energy, Inc.
Coral Power
CPS Energy
DB Energy Trading LLC
Desert Sky Wind Farm
IPA Marketing Inc.
Keystone Energy Partners LP
Lower Colorado River Authority
Luminant Energy Company LLC
Morgan Stanley Capital Croup Inc.
NRG Texas Power LLC
Oxy Energy
Rainbow Energy Marketing Corporation
Reliant Energy Power Supply LLC
Sempra Energy Solutions LLC
South Texas Electric Cooperative, Inc.
StarTex Power
Strategic Energy
Stream Energy
Suez Energy Marketing NA Inc.
Suez Energy Resources NW, Inc.
Tenaska Power Service Co.
Tex-La Electric Cooperative of Texas Inc.
Trent Wind Farm
West Texas Wind Energy Partners, LP
Direct Energy, LP
Eagle Energy Partners I LP
Edison Mission Marketing & Trading Inc.
EnergyCo Marketing & Trading LLC
EPIC Merchant Energy TX LLC
Exelon
First Choice Power LP
FPL Energy
FPL Energy Pecos Wind I, LP
FPL Energy Pecos Wind II, LP
FPL Energy Upton Wind I, LP
FPL Energy Upton Wind II, LP
FPL Energy Upton Wind III, LP
FPL Energy Upton Wind IV, LP
GEUS
Goldman Sachs
Green Mountain Energy Company
Indian Mesa Wind Farm, LP (LCRA)
Indian Mesa Wind Farm, LP (TXU)
Integrys Energy Services, Inc.
16TPTF1/21/2008 16
EDS 4 Release 9.1
2008Jan Feb Mar Apr May Jun
E4 R9 R9.1: DAM/RUC Submission Testing R9.3: R9.4: DAM/ Adj Period, RT
R9.3: Outage Scheduler
EDS 4 Release 9.1 Exit Criteria % Complete
Comments
Intent to Participate Sent 75%(0%)
Sign-Up Testing Window Scheduled 68%(0%)
See next slide
MP8 - QSE Ability to Submit Transactions Via MIS
0%(0%)
MIS with ERCOT developed UI expected to be in EDS on 1/21
MP9 – QSE Ability to Submit Web Service Transactions
1%(0%)
Reliant completed web services on 1/18EPIC completed Connectivity Test
MP16 - MP EDS-4 Trials Participation 0%(0%)
17TPTF1/21/2008 17
EDS 4 Release 9.1
Alcoa Power MarketingAmbit EnergyAmbridge Energy AquilaBear EnergyBrilliant EnergyCargill Power MarketsCitadel Energy ProductsClearview Electric Duke Energy OhioElectric Now Glacial Energy J AronJuice Energy IncJust Energy Texas Kansas City Power and Light
Keystone Energy Partners Lehman Brothers Commodity Services Liberty Power Corp LPT LLC Merrill Lynch CommoditiesMirant Energy Trading Morgan StanleyMxEnergy Electric Inc QSENational Power Company Pegasus Alliance CorpSitara Energy Spark Energy Texas Retail Energy Texas Star Energy Texpo Power Urban Energy Source Viasyn WCW International
QSEs that have not signed up for a testing window for EDS4 (as of 2 pm 1/18/08)
3 Market Notices sent to date and Account Executives contacted by client services
18TPTF1/21/2008 18
EDS 4 Release 9.1
Signing up for an EDS 4 Release 9.1 Testing Window
If you haven’t yet requested a testing window, please send the following to [email protected]:
Support Window date and AM or PM preference (provide 3 different slots) (testing began 1/15/08 and runs through March)
• ERCOT will make every effort to honor one or more of the preferred dates above; however, we may still need to coordinate around congested schedules.
DUNS number of QSEs & sub-QSEs that will be tested within the support window Indication of desired testing method – MIS, machine-2-machine (Web Services), or both If using Web Services, confirm that QSE’s nodal production system is used for testing
(whether in-house or third party): Yes/No If using Web Services, the listener URL where notifications will be sent
• Note: If your listener is unavailable at the time of sign up, the listener URL must be sent to the [email protected] email address 2 weeks prior to your scheduled testing window
19TPTF1/21/2008 19
EDS Deliverables
R5.4 – SCED
OS Handbook
R9.2
COMs
R8
DAM/RUC
R9.3
Post for TPTF Comment
1/22 Feb 8 Feb 8 Feb 15
Comment Close 1/29 Feb 15 Feb 15 Feb 26
TPTF Vote Feb 4/5 Feb 21/22 Feb 21/22 Mar 3/4/5
Legend: indicates completion
20TPTF1/21/2008 20
Questions?