dutch six sigma newsletter lean basic controls januari 2017

5
1 Lean Basic Controls, The business case Leo Monhemius, Dutch Six Sigma, Partner of Change Vision January 2017, [email protected] Shareholders drive results in the financial motivation of the Operational Excellence Program (OPEX). The accountancy is telling us to reduce costs against a so-called baseline. This way the baseline itself is taken for granted. But at the same time the processes are pushed against the limits. In this article, we will analyze the impact of this pressure and demonstrate the new risks that should be controlled in the first place. Especially in human based processes (project management) the impact of unexpected costs can exceed the benefits claimed by OPEX efforts, only these costs are disguised as unavoidable incidents. Maybe even acceptable as excuses for shareholders? The mission of this article is to set the business case for basic controls in an organization in parallel of OPEX activity. Later newsletters will expand in the details of implementation. This article will follow my own work experience from process industry via semiconductor manufacturing into project management. 1 The story of Process Industry At University, we were trained in advanced and complex control algorithms. When arriving in my first job at DSM chemicals, it was an eye-opening experience that a Naphtha cracker unit would have some 5000 control loops (wow). But less than a handful complex ones! The majority were simple alarms that would switch safety valves eventually. Some were dynamic controls with a basic setting. The actual control was based upon skilled operators, with a deep understanding of the complexity, that ran the process. Key objectives are uptime and safety. The illustration splits the control activity in three layers (pictograms to illustrate the type of action): 1. The actual processes are completely industrial, including the measurements. 2. The interface is also 100% instrumented, the controls are automated and responding on deviations from the operating window. 3. The operator is managing the process, and has a limited influence on the performance. A good operator will anticipate and avoid automated controls to come into action. Typical actions are prescribed in protocols. Process feed Measurements output Control Interface, control room output human interpretation Intervention (maintenance) Process interface, Valves 1 2 3

Upload: leo-monhemius

Post on 21-Apr-2017

38 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dutch Six Sigma newsletter Lean Basic Controls Januari 2017

1

Lean Basic Controls,

The business case

Leo Monhemius, Dutch Six Sigma,

Partner of Change Vision

January 2017, [email protected]

Shareholders drive results in the financial motivation of the Operational Excellence Program

(OPEX). The accountancy is telling us to reduce costs against a so-called baseline. This way the

baseline itself is taken for granted. But at the same time the processes are pushed against the

limits.

In this article, we will analyze the impact of this pressure and demonstrate the new risks that should

be controlled in the first place. Especially in human based processes (project management) the

impact of unexpected costs can exceed the benefits claimed by OPEX efforts, only these costs are

disguised as unavoidable incidents. Maybe even acceptable as excuses for shareholders?

The mission of this article is to set the business case for basic controls in an organization in

parallel of OPEX activity. Later newsletters will expand in the details of implementation.

This article will follow my own work experience from process industry via semiconductor

manufacturing into project management.

1 The story of Process Industry

At University, we were trained in advanced and complex control algorithms. When arriving in my first job at

DSM chemicals, it was an eye-opening experience that a Naphtha cracker unit would have some 5000

control loops (wow). But less than a handful complex ones! The majority were simple alarms that would

switch safety valves eventually. Some were dynamic controls with a basic setting. The actual control was

based upon skilled operators, with a deep understanding of the complexity, that ran the process. Key

objectives are uptime and safety.

The illustration splits the control activity in three layers (pictograms to illustrate the type of action):

1. The actual processes are completely industrial, including the measurements.

2. The interface is also 100% instrumented, the controls are automated and responding on

deviations from the operating window.

3. The operator is managing the process, and has a limited influence on the performance.

A good operator will anticipate and avoid automated controls to come into action. Typical

actions are prescribed in protocols.

Process feed Measurements output

Control Interface,

control room

output

human

interpretation

Intervention

(maintenance)

Process interface,

Valves

1

2

3

Page 2: Dutch Six Sigma newsletter Lean Basic Controls Januari 2017

2

The iceberg is illustrating that incidents should never happen:

1. Red, top of the iceberg, illustrates explosions and spills.

2. Response on deviating process conditions is automated, and made visual in the

control room. (amber)

3. During normal operation, the factory generates money, keeping conditions within the

window. (green)

In this type of processes, cost reductions can have impact if headcount is reduced or if maintenance is

compromised. As a direct consequence, the frequency of amber will increase and probably uptime of the

plant will be reduced. This results in a direct economical trigger to enforce the basic controls again. Normal

work in a “green” plant is boring; focus in on monitoring and early warning. Alertness is a key talent for

employees.

Example:

Imagine a circulation pump suddenly stops because of malfunction. The system will generate almost

immediately an alarm in the control room. The panel operator will switch to the spare pump; it may be

necessary to send another operator into the plant for manual setting. When the spare pump is started in

time, the levels of liquids will stay within windows. Subsequent alarms are avoided and the process will

continue without interruptions. After taking the malfunctioning pump into service, the operator will trigger

maintenance for replacement or repair.

2 The story of Semiconductor Manufacturing

At Philips Semiconductors (now NXP) the key problem was a high-tech process. Some 500 sequential,

critical process steps were required to make the product. Despite automation efforts, a factory is even

today a cleanroom with many machines which are loaded – programmed – started - unloaded by skilled

operators. My roommate Dough would tell me:” Leo, Hightech is a myth; it is just a lot of Lowtech, but all of

it must work at the same time”. Most controls were protocols and checklists, followed by operators. Some

controls were more advanced and based upon manually executed measurements, analyzed by Statistical

Process Control (SPC) and acted upon by Out of Control Action Plans (OCAP’s). Six Sigma methodology is

the only way to achieve a reasonable yield in this type of manufacturing, which is the key objective.

The illustration again splits three layers (pictograms to illustrate the type of action):

1. Production, fully automated and manually operated as routine work.

2. Process interface by visual presentations. Operator to take direct (protocol) action if

needed.

3. On top of the direct work and the direct responses, the operator is the first line for full

interpretation of the situation. But problems can be escalated to first line supervision

and supporting staff.

Operated

machines Raw input Visual inspection and

measurement yield

Control Interface,

visual management

Logistics by

operators

human

interpretation

Root cause removal

(maintenance)

Process interface,

adjustments

1

2

3

Page 3: Dutch Six Sigma newsletter Lean Basic Controls Januari 2017

3

The top of this iceberg is less spectacular than in process industry, therefore more

acceptable to exist?

1. Red would this time mean defect product delivered, and maybe causing a recall of

electronics?

2. Amber is the continuous struggle to keep the processes within windows.

3. Green is the dream of such manufacturing, all equipment running smooth at the same

time, the less incidents the higher the yield.

In this type of processes, employees are active in all three levels. Therefore, operations are more organic.

Pressure on costs, resulting in higher workloads may easily impact the performance because attention of

employees is stretched over all three levels. Therefore, basic controls at the highest level may suffer. But

also in this case economics will support restore focus again, although weaker.

Normal work in a “green” factory without problems is still hard work because of the many routine handling

and operations. Key talents are precision and accuracy. And the capacity to oversee all three levels.

Example:

An operator in a semiconductor factory is running a plasma deposition machine. They layer thicknesses of

the last three production lots were not alarming high, but he was aware of the potential trend when loading

a fourth lot. It seemed to her that the vacuum pumping time was longer than normal. She dropped a line in

the machine logbook to trigger the maintenance people to have a look. Maintenance could now intervene

before a process deviation occurred.

3 The story of Project Management

At different clients, this story is developed over the last ten years; reason to use an imaginary example of a

construction firm, also referred in earlier newsletters. The construction firm delivers a series of projects;

each is different, and many are parallel, using the same engineering capacity. Small specialized teams

have specific skills to perform a step in the project. A team leader is the pivot for skills and capacity.

Engineers typically find their own way and processes are too complex to be fully described. Previous

projects, help from colleagues, shared excel sheets are used to cope with each new challenge.” The control

mechanism is “Second pair of eyes by a colleague. But do corrections only effect the present project, or

also improve the process for next time? And is a full verification of all work done? Seldom the planning

allows a double engineering budget. Mistakes will inevitably slip through the controls; especially in the case

of blind spots of the team. Until here the work is individually based.

At project level, stage gates will perform the required checks for integration and typically risk assessments

are used to validate the design. These activities are team efforts, making it more difficult to avoid time

pressure having impact on the results. Since the client is aware of the results, and maybe even takes part

in some stage gates, an extra barrier for sharing doubts is introduced. The high visibility of gate reviews

Single, Unique

design Client Self-Control by specialists,

second pair of eyes? design

Stage gates for progress

and project interfacing

Project-

management

Balancing

time, cost, quality

Intervention in running

project (maintenance)

Lessons learned,

for next time?

Page 4: Dutch Six Sigma newsletter Lean Basic Controls Januari 2017

4

encourages informal preparation talks. Although effective for the smooth projectflow (key objective!),

information on “amber” feedback becomes invisible, and cannot be used for future improvements.

To illustrate the three layers (pictograms to illustrate the type of action):

1. Daily work is individual, maybe with informal colleague cooperation. A basis of

standard work with room for individual creativity.

2. Professional checks. Formal verification of the output, but if an error is found it

could be offending for the engineer involved. Most criticism is shared informally,

before or after a stage gate meeting. And errors are corrected but remain

undocumented. This is a complicated layer of control with group dynamics.

3. Integrity of project checks. This should be the control level of anticipation too high

amber levels can be answered by increasing project headcount. But if most amber events are

invisible for the project manager, how can this work?

This time the top of the iceberg is spectacular. Project management is by

nature focusing on the product instead of on the underlying process. Since

problems will surface later, or maybe even remain unnoticed, it is tempting to

push uncertainties forward in time.

1. Red means potential impact on the final project. If a red choice is made

during the engineering phase, a lot of time is left to deal with the issue in a

later stadium.

2. Amber would indicate all project activity that is not wrong but still not in

the safe window of work. Assumptions? Wrong versions used? Time

pressure during checking or inexperienced engineer performing the second pair of eyes? Any error

found in stage gates can be an indication of too high amber levels.

3. Green is the situation in which the engineers stay well within their competence comfort zones.

Project managers with high skills can sometimes achieve this situation. But would the parallel

projects try to withdraw capacity from a green project? And individual engineers contributing to two

parallel projects, how do they divide their time and attention? If the green project is neglected; it is

bound to become amber again …

In project management, the barriers between “production” and “control” are fading. Iterative development is

a normal mechanism, but how to differentiate with a control loop that identifies defects and corrects the

working methods? Criticizing colleagues for incomplete work is not easy, you just make an adaptation and

tell them afterwards. At the same time, each employee is under a time pressure from project management.

The group of people working for a project will have a strong bond and sense of achievement. Shared pride

is felt when the deliverables are in time and when the client is satisfied. You can sometimes recognize

teams by a logo, or by sweaters with a print.

Example:

In a construction firm the start of projects is critical. Roofbeams have the longest lead time for ordering. The

team lead of the roof construction department complains he must work with estimates, anticipating the

design phase. Today again, he finds out after ordering the materials, that the architecture people have

slightly changed the specifications. Normally he can deal with that within the margins, and only strength

calculations must be adjusted. This time, however, margins are exceeded and he is forced to defend

himself in the project meeting. Ordering new roofbeams will delay the project and increase costs. Under the

group pressure, including a member of the board, he feels tempted to give in and allow a margin which is

very thin. At the same time, his department is the last line of defense, having the unique expertise. He

thinks this pressure is getting worse over last few years. He expresses this in in a presentation to the board

as follows: “We are engineering on the edge, so you should not push us too hard. It is a cliff.

Remember the roof collapse we suffered eight years ago! [see newsletters Jan and Feb 2015]”. The

1

2

3

Page 5: Dutch Six Sigma newsletter Lean Basic Controls Januari 2017

5

team leader is aware that some board members did not like this presentation at all. But support from the

CEO and the operations Excellence manager gave him the courage to persist.

4 Lean Basic Controls

Of course, the above examples are simplified. My purpose was just to illustrate how the basic

structure of process control could be applied. Each organization has several types of work, for

instance a chemical plant (first example) will also have a maintenance department (working like the

second example) and will have projects for plant improvements that are characterized by the third

example.

The human role is different in the three situations. In process industry, the automation prevails and

the highest level is protocolled. In manufacturing, manual work and interpretation come into the

picture. In project management, protocols exist at work level, and higher levels are subject to

teamwork with a complex force field of performance against control. Professional responsibility is a

vital last fence, along the cliff of incidents.

My experience so far, is that most incidents or deviations have a trigger moment in time before any

formal control could have alarmed. This trigger moment is an individual, recognizing a moment of

unease. If we could trace these moments, that would be the perfect “amber alarm”. In fact, the Lean

tool “JIDOKA” tells employees to stop the work at any inconvenience. In practice, most employees

ignore this moment, and only a fraction of the trigger moments will surface again at formal controls.

Best examples are found in safety, everybody knows the “Last Minute Risk Assessment? (LMRA).

But few people saw an engineer perform an LMRA before uploading an excel sheet for a critical

calculation?

How would a Lean Basic Controls organization look like?

1. This approach is automated in the first

example of process industries.

2. It is protocolled in mass production.

3. But in project organizations we seem to act

only on the “red alarms” and leave the “amber

area” to informal and not reported cooperation.

Unexpected incidents can present a business case in

itself, but also reputation and safety can suffer.

Finally pride of workmanship can be frustrated,

eventually resulting in burnouts or reduced engagement.

Each OPEX program should consist of two pillars, the pushing for cost reduction should be

balanced with a strong Lean Basic Controls pillar. Without Lean Basic Controls also Continuous

improvement will suffer, because the employees will resist to:

“be pushed against the cliff …. Without a solid fence”.

In next newsletters, I will try to explore the topic of Lean Basic Controls in more detail.

In the meantime, I would invite you to share ideas or best practices, this article was not meant to insult the

way of work in many companies. I just hope to trigger a discussion on the topic.

Earlier newsletters connected to this article (let me know if you like a pdf copy):

January 2015 Lean in projects February 2015 Iceberg of Lean projects

March 2015 Lean transformation August 2015 Organic Lean

September 2015 Organic Lean, example December 2015 Lean Project Selection

November 2016 Lean Project selection December 2016 Kotter & Kaizen Events