dulles corridor metrorail project phase 2, package a ... · dulles corridor metrorail project phase...
TRANSCRIPT
![Page 1: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/1.jpg)
Dulles Corridor Metrorail Project
Phase 2, Package A
Capital Rail Constructors:
Quarterly Update to MWAA Board of Directors
January 2018
Keith Couch
Capital Rail Constructors
![Page 2: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/2.jpg)
Agenda
1. Safety
2. Schedule
3. Progress
4. Labor Statistics
5. DBE Subcontracts
![Page 3: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/3.jpg)
Scope
![Page 4: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/4.jpg)
Safety
Current Program Focus:
Working adjacent to traffic and within
Maintenance of Traffic (MOT) areas
Track Allocation
Energization of Systems
Since Notice to Proceed:
Manpower Hours: 5,693,721 (As of 12/11/2017)
Recordable Rate: 0.91 (vs. National Average: 3.30)
Lost Time Rate: 0.07 (vs. National Average: 1.70)
![Page 5: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/5.jpg)
Design and Construction: 76%
Construction Status: 74%
Design Status: 99.98%
Overall Project Status
![Page 6: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/6.jpg)
Project Progress Entire Project
NOTES:
• Based on Revised
Baseline Schedule,
with an Aug 1 data
date, agreed with
MWAA on Sep 5,
2017.
![Page 7: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/7.jpg)
Facilities: Dulles Airport Station
Structural Precast erection: Completed
Canopy Steel: Completed
Fiber line relocation: Completed
Track Pedestals and Cable Trough: Sep 2017 - Dec 2017
Train Control rough-in: Dec 2017 - Feb 2018
![Page 8: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/8.jpg)
Facilities: Dulles Airport Station
Platform Granite: Feb 2018 - Mar 2018
Elevator Install: Jan 2018 - May 2018
Storefront Glass: Jan 2018 - Mar 2018
TPSS 16 Install: Jan 2018 - Mar 2018
Mezz. Mechanical/Electrical/Plumbing Rough-In: Ongoing
![Page 9: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/9.jpg)
Elevators: Completed Dec 2017
Mezzanine topping slab pour: Completed Dec 2017
Terminate 34.5 kV in AC switch gear: Completed Dec 2017
South Pedestrian Bridge pour: Completed Dec 2017
Curtain Wall: Completed Dec 2017
Innovation Center Station
![Page 10: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/10.jpg)
Innovation Center Station Pavers: 50% complete
Granite: 95% complete
Metal Roofing: 75% complete
Skylights: 90% complete
Escalators: 50% complete
![Page 11: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/11.jpg)
Innovation Station Pavilions
NORTH:
Retaining wall: 90% complete
Site Ductbank: Underway
SOUTH:
Structural Precast erection: 90% complete
Elevator construction underway
![Page 12: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/12.jpg)
NORTH: 4 Spans SOUTH: 4 Spans
Innovation Station Pedestrian Bridges
1
2
8 7
6
5
# = Span Number
NORTH
PAVILION
SOUTH
PAVILION
4
3
# = Span Installed
![Page 13: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/13.jpg)
Innovation Station Pedestrian Bridges
NORTH:
• All spans and nodes: 100% Erected
SOUTH:
• All spans and nodes: 100% Erected
• Deck Pours: 100% Complete
![Page 14: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/14.jpg)
Facilities: Herndon Station
Metal decking: Complete
Mechanical/Electrical/Plumbing Rough-in: Underway
Roofing/Skylights: Underway
Track through station: Underway
Elevators: Underway
Escalator build-out: Early 2018
![Page 15: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/15.jpg)
Herndon Station Pavilions
NORTH:
Preliminary utility relocation: Underway
Clearing & grubbing: Underway
SOUTH:
Concrete structure: Complete
Utility work surrounding Pavilion: Complete
Precast erection: Underway
![Page 16: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/16.jpg)
NORTH
PAVILION
1
SOUTH
PAVILION
4
# = Span Number
# = Span Installed
5
6
7
4
3
2
SOUTH: 5 Spans
Herndon Station Pedestrian Bridges
8
NORTH: 3 Spans
![Page 17: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/17.jpg)
Herndon Station Pedestrian Bridges
SOUTH:
Spans 4, 5, 6, and 7: Erected
Node erection: Complete
NORTH:
Spans 2 & 3: Erected
Deck Pours: Begin Mar 2018
![Page 18: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/18.jpg)
Facilities: Reston Town Center Station
Precast: Complete Feb 2018
Steel Erection: Complete
Mechanical/Electrical/Plumbing rough-In: Jan 2017 - Fall 2018
Metal Decking: Complete
Roofing: Sep 2017 - Jun 2018
![Page 19: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/19.jpg)
Reston Town Center Station Pavilions
NORTH:
Concrete work: Complete
Precast erection: 90% Complete
Escalator setting: Upcoming
SOUTH:
Concrete work: Underway
Pavilion backfill: Upcoming
Below grade MEP Upcoming
![Page 20: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/20.jpg)
Reston Station Pedestrian Bridges
NORTH
PAVILION
2
1
4 3
SOUTH
PAVILION
5 6
NORTH: Spans 4 SOUTH: 2 Spans
# = Span Number
# = Span Installed
![Page 21: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/21.jpg)
Reston Station Pedestrian Bridges
NORTH:
4 Spans: 100% Erected
Deck Pours: Span 1 & 2 poured, 3 & 4
scheduled for Jan 2018
SOUTH:
2 Spans on site Assembly underway
![Page 22: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/22.jpg)
Loudoun Gateway Station
Cast-in-Place Concrete: Complete Feb 2017
Precast Erection: Start Feb 2018
![Page 23: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/23.jpg)
Loudoun Gateway Pavilion
NORTH:
Cast-in-place Concrete: Oct 2017 – Feb 2018
Precast Concrete: Start Feb 2018
![Page 24: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/24.jpg)
Loudoun Gateway Pedestrian Bridge
NORTH
PAVILION
2
1
4 3
NORTH: 4 Spans
# = Span Number
# = Span Installed
![Page 25: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/25.jpg)
Loudoun Gateway Pedestrian Bridge
NORTH:
Erection Dates: Span 1 – Jan 15, 2019 Span 2 – Dec 21, 2017
Span 3 – Dec 29, 2017 Span 4 – Dec 15, 2017
![Page 26: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/26.jpg)
Facilities: Ashburn Station Cast-in-Place Concrete: Jan 2017 – Feb 2018
Precast Erection: May 2017 – Feb 2018
Steel Erection: Dec 2017 – May 2018
Looking
East
Looking
West
![Page 27: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/27.jpg)
2
1 4
3
5
Ashburn Station Pedestrian Bridges
NORTH
PAVILION
SOUTH
PAVILION
NORTH: 3 Spans SOUTH: 2 Spans
# = Span Number
# = Span Installed
![Page 28: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/28.jpg)
Ashburn Station Pedestrian Bridges
SOUTH:
Span 4 and 5: 100% Erected
Deck Pours: Jan 2018
NORTH:
Span 1-3 to be erected Jan 2018
![Page 29: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/29.jpg)
Ashburn Station Pavilions
SOUTH: Cast-in-place: Completed Dec 2017
Frame and pour elevator hydraulic
shaft, strip elevated deck, complete
utility tie-ins, pour slab-on-grade: Upcoming
NORTH: Cast-in-Place: Complete Jan 2018
Precast: Start Feb 2018
Strip elevated deck, remove shoring
towers, elevator hydraulic trench: Upcoming
![Page 30: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/30.jpg)
Civil: Wayside Ductbank
Tie Breaker Stations (TBS)
TBS 8 & 11 Median: Complete after Track
Wall is installed Q1 2018
Traction Power Substations (TPSS)
TPSS 18 Wayside: Active
TPSS 20 Median: Active
![Page 31: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/31.jpg)
Civil:
34.5 kV Ductbank
61,705 feet of 61,705 foot ductbank installed (100% complete)
![Page 32: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/32.jpg)
Civil: Storm Drainage
Storm/Wet Utilities
66,150 of 86,400 LF Storm Pipe Installed (77%)
5,323 of 13,259 LF of Water Line Installed (40%)
3,709 of 9,140 LF of Sewer Line Installed (41%)
N08: DIAAH/DTR median storm: Q2 2018
Sunrise Valley storm: Q3 2018
N09: DIAAH/DTR median storm: Q3 2018
TBS 8 Median: Dec 2017
AP-2 Storm: Q1 2018
Innovation North Water: Q2 2018
N12: 772 North/South: Q2 2018
![Page 33: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/33.jpg)
Track Wall
Total Footer installed: 67,000 of 75,000 LF - 89% complete
Total Wall installed: 66,000 of 75,000 LF - 88% complete
East Segment: Close leave-outs
West Segment: Abutment B to Broad Run Bridge is active
Civil: Track Wall
![Page 34: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/34.jpg)
Civil: Grading/Excavation/Paving
East:
Turnover sub-ballast to Track at Reston & Herndon: Jan 2018
EB & WB DTR Road widening near Herndon Station: Underway
Herndon North Pavilion enabling work: Underway
Reston South JBG parking lot: Underway
West:
Active shoulder and sub-ballast from Abutment B-Broad Run Bridge: Q1 2018
![Page 35: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/35.jpg)
Track: Cable Trough
Precast Cable Trough Installed: 58,439 of 81,176 linear feet (72%)
Cast-in-Place Cable Trough Poured: 38,520 of 38,520 linear feet (100%)
![Page 36: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/36.jpg)
Direct Fixated Track Plinth: 36,726 of 37,595 TF poured (98%)
DF plinths were poured out in December
Track: Direct Fixated (DF)Plinths
![Page 37: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/37.jpg)
Contact Rail (aerial guideway segment): 24,842 of 40,750 LF installed (61%)
Track: Contact Rail
![Page 38: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/38.jpg)
Track: Ballasted
Ties set and rail clipped: 23,000 of 87,000 track feet (38%)
![Page 39: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/39.jpg)
Systems:
Wayside Facilities/Power
TPSS 13/14/15/17,19; TBS 6/7/9/10, and TCR N96/N97 are installed. 14 Comm. Room is installed.
Dominion Energy Vista Switch Yard installations complete at TPSS’s 13/14/15/16/17/18/19.
80% of all 34.5kV cable has been installed, spliced, and terminated Project-wide.
Permanent 34.5kV Power available to TPSS’s 13/14/15/16/17, TBS’s 6/7/10, Innovation Station, and
Herndon Station.
![Page 40: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/40.jpg)
Start-up/Commissioning/Turnover
19
15
9
10
17
7
14
13 6
AIRPORT SEGMENT
EAST SEGMENT
WEST SEGMENT
Stations: Switchgear Testing begins January; Communications Installation Begun at Dulles
Guideway: Turnover completed for N96, N97, N99E and part of N98A (~30%)
Waysides: 64% of Buildings Set (TBS 6, 7, 9, 10; TPSS 13, 14, 15, 17, 19); Fit-out Ongoing
Overall: Finalizing management plans and procedures for Project Acceptance by Stakeholder.
TES Building Set
ATC/TES Work
Underway
Trackwork
Civil
![Page 41: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/41.jpg)
Manpower Hours September 2017 – November 2017
Manpower Hours Sep 2017 Oct 2017 Nov 2017
Professional Staff 46,530 41,809 39,040
Craft Labor – CRC &
Subcontractors 150,116 151,361 91,883
![Page 42: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/42.jpg)
Labor by Race/Ethnicity September 2013 to December 12, 2017
African
American
Asian
Caucasian
Hispanic
Other
Total Hires # % # % # % # % # %
6758 991 15 72 1 2490 37 3056 45 149 2
![Page 43: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/43.jpg)
Labor by State September 2013 – December 12, 2017
Virginia
Maryland
District of
Columbia
Other
% % % %
September 2013 –
December 12, 2017 58% 26% 3% 13%
![Page 44: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/44.jpg)
DBE Status: November 2017 Base Contract Only
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
$180,000,000
DBE ProjectGoal
DBECommitted
Value AgainstAwardedContracts
Remaining toBuy
ProjectedFinish
DBE Status $164,888,780.00 $167,212,580.00 $- $169,046,913.62
Do
lla
rs P
roc
ure
d t
o D
BE
0
$0
14.35%
0%
14.20% 14%
![Page 45: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/45.jpg)
Local Employment Outreach Program
Sep – Dec 2017:
09/08/17: Building Futures Program, DC
09/27/17: Greater Washington Urban League
![Page 46: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/46.jpg)
Environmental Erosion and Sediment Control
• In Compliance - No reportable infractions for
this project.
• November Virginia Department of
Environmental Quality Semi-Annual
Inspection went very well. Minor findings
have been addressed.
Spills/Releases
• In Compliance - No releases to surface
water for this quarter or since the inception
of this project.
![Page 47: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/47.jpg)
Environmental
Waste Management
• In Compliance: No infractions regarding
our waste handling/disposal procedures.
Project Close Out
• Waste: Currently prepping waste
handling/disposal protocols for project
demobilization.
• Documentation: In 100% compliance at
this time. Continue to ensure all open
deliverables are provided.
![Page 48: Dulles Corridor Metrorail Project Phase 2, Package A ... · Dulles Corridor Metrorail Project Phase 2, Package A Capital Rail Constructors: Quarterly Update to MWAA Board of Directors](https://reader033.vdocuments.us/reader033/viewer/2022060601/6055cb705bde1a2c3e6c7fdf/html5/thumbnails/48.jpg)