dublin city council€¦ · the basement development conserves existing protected and heritage...
TRANSCRIPT
Dublin City Council
Basement Development
Guidance Document
Version 1.0
September 2019
DCC Basement Development Guidance Document Version 1.0
i
Contents 1. Introduction .................................................................................................................................... 4
1.1 Guidance Overview ................................................................................................................. 4
1.2 Basement Policy Objectives .................................................................................................... 4
1.3 Further DCC planning policies ................................................................................................. 6
1.4 Scope of Basement Guidance ................................................................................................. 7
1.5 Planning context ..................................................................................................................... 7
1.6 Disclaimer ................................................................................................................................ 8
2. Dublin City: Desk Study ................................................................................................................... 8
2.1 General Context ...................................................................................................................... 8
2.2 Dublin City Existing Environment; ........................................................................................... 9
3.0 Potential Impacts of Constructing Basements in Dublin City ....................................................... 11
3.1 Principal concerns relating to basement construction ......................................................... 11
3.2 Groundwater flow impacts ................................................................................................... 11
3.3 Land stability & ground movement impacts ......................................................................... 13
3.4 Surface flow and flooding impacts ........................................................................................ 16
3.5 Cumulative effects of basement construction ...................................................................... 17
3.6 Basement construction related impacts ............................................................................... 17
3.7 Other Potential Factors and Impacts .................................................................................... 18
3.8 Holistic Approach Required to Potential Impacts ................................................................. 19
4.0 Basement Development Specific Considerations ......................................................................... 19
4.1. Size and Extent of Basement Development .......................................................................... 19
4.2 Flood Levels ........................................................................................................................... 21
4.3 Sustainable Urban Drainage Systems (SUDS) ....................................................................... 21
4.4 Archaeological Impact ........................................................................................................... 21
4.5 Conservation areas and listed buildings ............................................................................... 22
4.6 Trees Landscape and Biodiversity ......................................................................................... 22
DCC Basement Development Guidance Document Version 1.0
ii
4.7 Internal Environment and Appearance of Basement ........................................................... 23
4.8 Lightwells .............................................................................................................................. 23
4.9 Railings, grilles and other lightwell treatment ...................................................................... 24
5.0 Basement Impact Assessment (BIA) Methodology ....................................................................... 24
5.1 Overview of Basement Impact Assessment (BIA Methodology ........................................... 24
5.2 Summary of tasks to be completed as part of BIA ................................................................ 25
5.3 Scoping .................................................................................................................................. 27
5.4 Continuous Site Investigation, Study and Monitoring .......................................................... 29
5.5 Impact Assessment and Mitigation Measures ...................................................................... 30
5.6 Qualifications and accreditation ........................................................................................... 36
6.0 Assessment of Basement Construction Potential Impacts ........................................................... 37
6.1 Introduction .......................................................................................................................... 37
6.2 Site investigation ................................................................................................................... 37
6.3 Extent of Basement and Site Dewatering & Recharge ......................................................... 41
6.4 Calculation Methods and Tools ............................................................................................ 41
6.5 Sources of Information ......................................................................................................... 42
6.6 Standards and Best Practice Guidance ................................................................................. 42
7.0 Planning Authority Assessment of BIA .......................................................................................... 43
7.1 Audit of information supplied ............................................................................................... 43
7.2 Basement Audit Categorisation ............................................................................................ 44
7.6 Updating the baseline ........................................................................................................... 45
7.7 Future Monitoring of Groundwater Levels to verify BIA Assumptions ................................ 45
8.0 Related DCC Corporate Policies .................................................................................................... 45
8.1 DCC Roads Requirement ....................................................................................................... 45
8.2 DCC Ground Anchor Installation Licence (GAIL) ................................................................... 45
8.3 DCC Pollution Control ........................................................................................................... 46
8.4 DCC Traffic Management ...................................................................................................... 46
DCC Basement Development Guidance Document Version 1.0
iii
8.5 DCC Waste Management ...................................................................................................... 46
8.6 DCC Drainage Planning ......................................................................................................... 47
8.7 Noise, Air Quality and Vibration ........................................................................................... 47
9.0 Glossary of Terms .......................................................................................................................... 48
10. Glossary of Impacts ....................................................................................................................... 51
11. References .................................................................................................................................... 52
Appendix A ............................................................................................................................................ 53
– Items to be submitted and reviewed as part of a Basement Impact Assessment............................. 53
Appendix B ............................................................................................................................................ 58
– Ground Anchor Installation Licence (GAIL) Application Form ........................................................... 58
Appendix C ............................................................................................................................................ 65
– Ground Anchor Installation Licence (GAIL) Guidance Notes ............................................................. 65
Appendix D ............................................................................................................................................ 70
– Cumulative Effects of Basement Construction .................................................................................. 70
Appendix E ............................................................................................................................................ 74
– Noise and Air Quality – “Construction and Demolition Good Practice Guide” ................................. 74
DCC Basement Development Guidance Document Version 1.0
4
1. Introduction
1.1 Guidance Overview
1.1.1 The “Basement Development Guidance Document” is intended to complement
both the DCC (Basement Development Policy Document) and the planning
guidance offered in the current Dublin City Development Plan (2016 – 2022). Both
the policy and guidance documents should be understood in the context of all
planning matters outlined in the Development Plan and other related planning
guidance. This guidance document aims to inform both planners and developers
about the potential for a variety of impacts on the city and the environment
arising from basement developments. It also outlines some practices which can
be utilised to identify and mitigate against these impacts at an early stage in the
application and design process.
1.1.2 The Dublin City Planning Authority now requires that all planning applications
containing an underground structure shall need to complete a Basement Impact
Assessment (BIA) as part of the overall planning application. This risk based
impact assessment is to be undertaken with regard to, amongst other potential
impacts, hydrology, hydrogeology and land stability and the consequence of
changes in these areas. Details of and guidance to complete a BIA are contained
herein.
1.1.3 This “Basement Development Guidance Document”, aswell as being of benefit to
Developers, shall also be utilised by the planning authority to ensure all aspects
of a Basement Impact Assessment (BIA) have been thoroughly investigated,
researched and reported upon.
1.1.4 The purpose of the DCC Basement Policy is to identify potential impacts (short-
term and long-term) as a result of basement construction. Owners, users and
developers of lands and property are advised to take account of this Guidance
Document (with reference to the associated “Basement Development Policy
Document”) when assessing the development potential of a particular site. No
assumptions should be made with regard to the development potential, or the
feasibility of constructing a basement, until a full analysis as outlined in this
document has been undertaken and the relevant approvals granted by the
Planning Authority.
1.1.5 DCC wish to acknowledge that the basement policy and guidance, contained
herein, was developed with reference to existing policies and guidance documents
already adopted by the London Borough of Camden.
1.2 Basement Policy Objectives
As is described in the “Basement Guidance Policy Document” a basement or underground
development is considered as being; an accessible area positioned below the existing
DCC Basement Development Guidance Document Version 1.0
5
street level or ground level and would include any works that will remain permanently in
the ground, such as embedded wall construction below the base of the accessible area.
The main principles for introducing a basement development policy are summarised in
this section. Each of these requirements should be addressed within the BIA submission.
The DCC basement policy requires Developers to ensure that basement development, as
evidenced in their BIA submission;
Protects and enhances where possible the groundwater quality, quantity
and classification (groundwater environment)
Provides evidence that the construction of basements shall not place the
groundwater at undue risk
Provides evidence that the structural stability of adjoining or neighbouring
buildings are not put at risk. The Developer should also identify the risk to
land stability of the site and adjacent areas and provides appropriate
mitigation, as required.
Provides an in-depth management plan for any demolition works and for the
construction of a basement. The Developer is required to adhere to this plan
(“Construction Management Plan”) if the application is deemed successful
Is in accordance with the proper development of the area with a high quality
design
Does not cause harm or undue nuisance to neighbourhoods and adjoining
buildings where development is to occur, during and after construction.
Ensures adequate consideration is given to traffic planning during
construction and thereafter.
Does not have an adverse effect on existing patterns of surface water
drainage, including infiltration into groundwater and is consistent with DCC’s
Policy on Sustainable Urban Drainage Systems (SUDS).
Does not increase groundwater infiltration into existing sewers and drains
beyond permitted restrictions.
Shall not significantly impact on groundwater or surface water flows to the
extent that this is likely to increase the risk of flooding. This flood risk is to
be evaluated, in accordance with the OPW 2009 Guidelines, during and post
construction with appropriate mitigation provided.
Does not include basement development for residential use, below the
estimated flood levels in flood zone areas Zone A or Zone B (see DCC
Development Plan for Zone locations).
Accounts for the impact of the future planting and mature development of
trees on site. A thickness of at least 1m of soil on the “roof” of a basement
is required to mitigate against and minimise surface water runoff, with
various SUDS measures incorporated.
Ensures that, all basement developments shall account for and
accommodate the existing groundwater contained within and flowing
through their site. As a minimum standard there is to be at least 0.5m wide
of clear space provided between the site/property boundary and the outer
DCC Basement Development Guidance Document Version 1.0
6
extent of a basement. This 0.5m wide space and shall extend over the full
height and around the perimeter of the basement and shall be filled with
suitable, highly permeable material (with appropriate wrapping).
Accounts for the characteristic of the site. In the case of a domestic
basement development to the rear of a property (garden) generally should
not exceed the footprint of the original building and be no deeper than one
full storey below ground level. Domestic basement development should
generally not extend to more than 50% of the amenity/garden space.
Provide appropriate evidence for larger schemes, including those consisting
of more than one storey in depth or extending beyond the footprint of the
above ground building, to demonstrate to the Planning Authority`s
satisfaction that the development does not harm the built and natural
environment or local amenity.
Takes account of the content of the “Dublin City Development Plan 2016 –
2022” for construction and development related matters. This policy is to be
read in conjunction with this document and all other current DCC policies.
Conserves and where possible enhances the biodiversity value of the site
Ensures appropriate handling and dealing with waste removal, including
contaminated/hazardous ground arising during construction – details to be
included in the “Construction Management Plan”.
Ensures that the impact of the proposed construction methodologies and
temporary works and ground anchors are fully assessed and any necessary
mitigation measures put in place.
Does not impact negatively on the surrounding areas, both private and
public.
All requirements, as accounted for in this policy document are to be evidenced in detail
within a BIA which is to be submitted as part of the planning application submission for
that particular development.
1.3 Further DCC planning policies
Whilst adhering to the policy requirements as outlined in Section 3.1, each of which are
to be addressed in the BIA submission, it does not preclude the applicant from meeting
other important and relevant DCC policy requirements, many of which are included in
the current “Dublin City Development Plan”. For example, when a basement
development is proposed, the Planning Authority shall also require as a minimum the
following items to be evidenced as part of the overall planning application submission;
The basement development conserves existing protected and heritage
buildings/sites, conservation areas, sites of archaeological interest etc.
The basement development provides an extensive structural stability and
conservation report in the case of listed buildings, or properties adjoining or
adjacent to listed buildings.
DCC Basement Development Guidance Document Version 1.0
7
The basement development provides a management plan for demolition
and/or construction where basement works are proposed in conservation
areas or adjacent to a listed building
The basement development does not harm the architectural character of
buildings and surrounding areas e.g. trees and gardens and character in such
areas are not to be harmed.
Ensures that adequate sunlight/daylight penetration is provided
Ensures that adequate ventilation is provided
Ensure that basements are provided with a means of escape allowing access
to a place of safety that provides access to the external ground level
These requirements are to be included within the Planning Application and their
examination is to be referenced accordingly within the BIA submission.
1.4 Scope of Basement Guidance
The scope of this document is to provide guidance on how to comply with the DCC
“Basement Development Policy Document”. In summary this guidance document is
intended to;
present guidance to assist Developers to identify potential impacts of
basement/subterranean infrastructure and other development
assist with the identification of hydrological, hydrogeological and other
geotechnical information that Developers are required to submit as part of
their planning application (and BIA), including a methodology which
Developers should follow to assess the impact of their development
Provide Guidance to Developers in relation to the BIA process.
1.5 Planning context
1.5.1 Principal Issues Concerning the Planning Authority
Specifically relating to basement construction the principal issues which concern
the Planning Authority are summarised in Section 1.2. These potential impacts as
a result of basement construction are described further in Section 3 of this
document.
1.5.2 Temporary Works
1.5.2.1 If temporary works are required to facilitate the construction of the
proposed basement the positioning of such temporary works is not
permitted within public lands/space without a Ground Anchor
Installation Licence (GAIL). The application (Appendix B), if required,
should form part of the development BIA submission and should be
completed in conjunction with the “Ground Anchor Installation (GAIL)
Guidance document” (Appendix C). Under no circumstances are the
temporary installations located within public lands to form part of the
permanent (long-term) structural stability of the development. All
ground anchors shall be temporary and shall not inhibit future
DCC Basement Development Guidance Document Version 1.0
8
infrastructure schemes. They shall be of a type which shall permit
effortless excavation, tunnelling etc. through the anchors. The relevant
details are contained in the “Ground Anchor Installation (GAIL) Guidance
document” (Appendix C).
1.5.2.2 Similarly the Developer is required to show that they have the necessary
permissions from the relevant land owner and/or authority for any
temporary works external to the applicant’s site required to assess
existing groundwater conditions or monitor the impact of dewatering
during basement construction.
1.6 Disclaimer
As stated in the DCC “Basement Development Policy Document” it is important to note
that, although prepared in consultation with industry experts this is a work in progress
document and it is based on best available data and guidance at the time of preparation.
Accordingly, all information in relation to basement development and construction is
provided for general policy and guidance only, and may be substantially altered in light
of future data and analysis, or future events etc. As a result, all landowners and
developers are advised that Dublin City Council and their agents can accept no
responsibility for losses or damages arising due to assessments indicating the suitability
of a site for basement construction e.g. vulnerability of their lands to flooding, the impact
of their proposed development on adjoining properties or amenities, cumulative effects
of basement construction, or the design and use of their proposed development.
Owners, users and developers are advised to take all reasonable measures to assess
potential issues (as outlined in this guidance document with reference also to the related
policy document) which may impact upon lands and buildings (including basements) in
which they have an interest, prior to making planning or development assumptions and
decisions.
The BIA Guidance and associated policy will be reviewed on an ongoing basis as is
required.
2. Dublin City: Desk Study
2.1 General Context
Dublin City in its entirety lies within the metropolitan area and the Regional Planning
Guidelines (RPG) give direction to Dublin City as the ‘gateway core’ for high-intensity
clusters, brownfield development, urban renewal and regeneration. The RPG settlement
strategy for the metropolitan area includes a strong policy emphasis on the need to gain
maximum benefit from existing assets, such as public transport and social infrastructure,
through the continuation of consolidation and increasing densities within the existing
built footprint of the city. A further key aspect is that future expansion, whether housing
or mixed uses, occur in tandem with high-quality rail-based public transport and on a
phased basis. The current DCC Development Plan incorporates these principles in a
settlement hierarchy which prioritises the inner city, Key District Centres (KDCs) and
DCC Basement Development Guidance Document Version 1.0
9
Strategic Development & Regeneration Areas (SDRA’s). The majority of SDRA’s relate to
a zoning objective which seeks the social, economic physical development or
rejuvenation of
Taking account of the development framework set out in higher level regional and
national plans, the proposed strategy for Dublin promotes the consolidation of the city,
maximising efficient use of land and integrating land use and transport, within the
context of an over-arching philosophy of sustainability and quality of life factors.
Dublin City Developers therefore are now looking to maximise the floor area for each new
development site. With the progress of building technology and available opportunities
the prospect of including a basement is becoming more attractive. This guidance
document aims to compliment the “Basement Development Policy Document” in the
assessment of such proposals on a case-by-case basis. Developers are advised to consult
this document and the DCC basement policy prior to making any development
assumptions or submitting an application for planning.
2.2 Dublin City Existing Environment;
2.2.1 Conservation Culture and Heritage;
As described in the “Dublin City Development Plan 2016-2021” Dublin City`s built
and natural heritage plays a pivotal role in the city`s character. It is a key objective
of the core strategy of Dublin City Council to protect and enhance the special
characteristics of the city`s built and natural heritage. The principle measures
enabling Dublin City Council to do this are the Record of Protected Structures and
the designation of Architectural Conservation Areas. The City Council has
identified priority areas of special historic and architectural interest and within
these areas will review the Record of Protected Structures, consider the
recommendations of the National Inventory of Architectural Heritage and, where
required, designate Architectural Conservation Areas.
In order to work towards such a plan Dublin City Council intends to increase the
sustainability of urban planning, new investment, infrastructure improvement
and regeneration by especially taking into account the existing built environment,
heritage, cultural diversity, socioeconomic and environmental values along with
community values.
Ensuring that new investment, regeneration and intervention acknowledges and
respects the significant archaeological and architectural heritage of the city is an
important issue for DCC. It is best achieved through appropriate objectives for
the protection, enhancement and management of the built heritage, while
encouraging regeneration and change.
2.2.2 Protected Structures;
The Record of Protected Structures presently comprises in excess of 8,500
structures. In respect of the process of managing the Record of Protected
DCC Basement Development Guidance Document Version 1.0
10
Structures, during the period from 2011– 2016, there were 51 structures added
and 242 structures deleted and on the basis of ongoing survey and monitoring,
the Record was clarified on a number of occasions.
Dublin City Council endeavours to protect the structures of special interest which
are included on the Record of Protected Structures and continues to review the
Record of Protected Structures within the context of future Architectural
Conservation Area designations and having regard to the recommendations of
the National Inventory of Architectural Heritage. The presence of such structures
shall need to be addressed in the BIA submission for any application in their
vicinity.
2.2.3 Architectural Conservation Areas;
There are presently 21 Architectural Conservation Areas in the city. In the period
2012–2015, Dublin City Council designated 9 Architectural Conservation Areas:
Mountjoy Square, Westmoreland Park, Sandymount, Temple Place, Colliers
Avenue, Elmpark Avenue and Elmwood Avenue, Ranelagh Avenue, Crumlin,
Belmont Avenue/Mount Eden Road, Phibsborough and Great Western Square.
Dublin City Council endeavours to protect the special character of the existing
designated Architectural Conservation Areas and Conservation Areas of Dublin
city and shall continue to identify other areas of special historic and architectural
interest and to designate these areas as Architectural Conservation Areas. If a
development is proposed for or close to one of these areas it shall need to be
addressed as part of the development BIA submission.
2.2.4 Importance of Green Infrastructure;
Dublin City Council has traditionally encouraged the utilisation of green
infrastructure systems in all new developments. This policy intends to
complement the existing green spaces of the city squares, historic gardens and
the canals and waterfront promenades. Green infrastructure in cities delivers
health-related benefits such as clean air and better water quality. The utilisation
of green infrastructure and Sustainable Urban Drainage Systems (SUDS) is also an
extremely effective method of managing surface water and provides a “total”
solution to rainwater management while traditional drainage can be considered
as only providing a “collection and disposal” approach. A site wholly covered by
hard impermeable surfaces intercepts all groundwater recharge resulting in
rainwater running off the site and into the surface drainage system.
2.2.5 Flood Risk in Dublin City;
Various projects have been completed in recent years to protect areas known to
be vulnerable to coastal flooding during extreme events. It is a requirement of all
planning applicants to complete a flood risk assessment to assess all forms of
potential flooding, in accordance with statutory flood risk management
guidelines. Such a flood risk assessment shall be referenced in a BIA.
DCC Basement Development Guidance Document Version 1.0
11
2.2.6 Construction Stage
Dublin is a vibrant city with considerable areas of mixed land use such as
residential, commercial and office spaces. Whilst the building and upgrade of
structures can be beneficial to a neighbourhood one must be conscious of the
impacts that construction works may have on a community and existing
buildings. The use of piling, deep excavations, change in groundwater levels etc.
and the impact of these on adjacent properties, assets and inhabitants need to
be accounted for. The need for pre and post construction surveys of surrounding
buildings should be considered.
Adequate control of noise, dust, traffic / truck movements, discharge of
groundwater into sewers or watercourses or through ground re-charge are all
elements of a BIA. The design of temporary works needs to be detailed and
investigated such that installation of future infrastructure to an area will be
possible in the future.
3.0 Potential Impacts of Constructing Basements in Dublin City
3.1 Principal concerns relating to basement construction
Some of the principal concerns relating to the excavation of new basements are
presented in this section after being summarised in Section 1.2. The range and variety of
the items illustrate the diverse but interconnected nature of the factors associated with
assessing proposals for basement/subterranean development within Dublin City.
There is a potential for impacts during both the construction phase and the long-
term/steady state phase of the project. Installation of temporary works may also result
in temporary impacts. Each of these impacts should be accounted for in the BIA
submission. Basement constructions impacts can be summarised under the flowing
headings;
Groundwater flow
Land stability and ground movement
Surface water flow and flooding
Cumulative effects
Construction stage impacts (incl. temporary works)
3.2 Groundwater flow impacts
3.2.1 As is referenced in Section 3.1 of the “Basement Development Policy Document”,
the Planning Authority will expect all basement development applications to
provide evidence that the construction of basements shall not place the
groundwater and surrounding environment at undue risk. Potential issues should
be investigated and highlighted in the scoping stage of the Basement Impact
Assessment (see Section 5). All groundwater investigations, assessments and
reports must be carried out by suitably qualified and experienced personnel.
3.2.2 If groundwater was forced to find an alternative flow route past an underground
obstruction such as a basement, it could cause the groundwater level to rise
DCC Basement Development Guidance Document Version 1.0
12
locally up gradient or adjacent to the new basement. If there is an existing cellar
that had not been suitably protected (“tanked”) against rising groundwater levels
or ingress, then dampness and/or seepage would likely have a significant impact.
3.2.3 Immediately upstream (up groundwater gradient) of the development the
groundwater level may rise, whilst immediately downstream the groundwater
level may fall. The magnitude of the change in water level will be dependent on
the nature of the natural groundwater flow system and the size and orientation
of the development. A narrow basement parallel to the direction of groundwater
flow will have less of an impact than a wider basement perpendicular to the
direction of flow since there is less blocking or deflection of the groundwater
from its original path. Structures which involve “corralling” shapes, such as an “L”
shaped structure with the convex corner in the line of groundwater flow, may
result in more pronounced effects.
3.2.4 For natural springs (or emergences of groundwater at the surface), the rate of
water flow from the spring might increase or decrease, depending on whether
the alternative route is diverting or increasing the flow to the point of the spring
source. If the flow is diverted from one spring, it may result in the groundwater
flow finding another location to issue from with new springs forming or old
springs being reactivated.
3.2.5 The level of the groundwater in the rock or overburden is commonly called the
“water table”. This level is the level below which all interconnected pores or
spaces in the subsurface are saturated at the particular time that the
measurement was made. The water table varies continuously and is not naturally
static. The level of the ‘water table at any moment in time represents the balance
between the inflows and outflows from the groundwater system. Groundwater
is continually draining under gravity out from the rock and the overburden.
Groundwater levels rise when the input of rainfall recharge exceeds the speed of
drainage from the system. Therefore, in the rise and fall of the water table is
dictated by seasonal changes in rainfall with spikes caused by extreme weather
events.
The level of groundwater and its natural fluctuations can have a significant impact
on the vitality of plants and trees on adjacent land or gardens. A significant and
rapid change in the previous fluctuation in groundwater levels can lead either to
water-logging and asphyxiation of deep plant roots or if the water level falls the
desiccation of shallow plant roots.
The groundwater level is also influenced by man-made drainage or groundwater
pumping and other factors such as pipe bursts and sewer leakage. Any
assessment of changes in ground water level that may be associated with a
specific subterranean development should therefore be viewed in the context of
site specific conditions and conditions under the area around the proposed
development.
3.2.6 Basement development may affect groundwater flows, even if the displaced
water can easily find a new course around the basement obstruction. This may
have other consequences for nearby properties, trees, etc. Given the nature of
DCC Basement Development Guidance Document Version 1.0
13
the geology in certain parts of Dublin City, or in locations where streams once
flowed, basement development may have the potential to divert or displace
groundwater which can cause a rise in groundwater and cause flooding of existing
basements or cellars, increased infiltration into sewers or increased pore water
pressure (heave), upstream of the development. Immediately downstream of the
obstructing basement the groundwater level may decline, which in extreme
circumstances, may affect wells, springs and ponds. It is possible that ground
subsidence downstream of the new development could also occur due to a
change in the groundwater levels, drop in pore water pressures (subsidence) and
flow patterns.
3.2.7 A larger basement (or a series of adjacent, contiguous basements) would have a
greater impact (cumulative effect) on the groundwater flow system (discussed in
Section 3.5). The shape of the resulting compound structure in relation to the
groundwater flow direction and soil strata should be considered to assess
whether any damming effect could arise.
3.2.8 The impact of a new basement should not be just assessed in the context of the
completed structure. Groundwater outside the boundary of the site is almost
always affected by dewatering in the site during construction. If there is
continuous dewatering of the excavation then it means that water is coming into
the excavation from below and outside the site. Therefore, the dewatering works
are either draining water underneath any cut off wall from adjacent sediments
outside the cut off wall, or water is flowing up through the floor of the excavation
from sediments or rock below the excavation. Dewatering, in effect, can transmit
an impact outside the boundary of the site. Dewatering could affect the yield and
drawdown in adjacent water supply pumping boreholes. It could lower the level
in ponds or wetlands down gradient of the site. It could draw in water from
adjacent streams. It could also draw in polluted or saline water from under
adjacent sites. Finally it could lower the pore water pressure in compressible
sediments (such as silts and clays) below the foundations of nearby historic
buildings, or below railway lines, canals, roads and sewers.
3.2.9 A simple example of groundwater flow and the relationship with one and more
basements can be seen in Appendix D. It should be noted that Appendix D is a
schematic that assumes a homogeneous aquifer with isotropic hydrogeological
properties. In most real-life scenarios Dublin City such simplified conditions shall
not be present.
3.3 Land stability & ground movement impacts
3.3.1 General
Whatever the ultimate cause of slope instability, one of the triggering factors
which can initiate ground movement is human activity. The act of constructing a
basement may result in instability affecting both that development and the land
surrounding it (Section 3.1 of the “Basement Development Policy Document”), for
example:
DCC Basement Development Guidance Document Version 1.0
14
Increases in water content due to alteration of drainage may
increase pore water pressures and decrease the strength of the soil
material.
Dewatering for basement construction may cause settlement.
Removal of vegetation (including tree felling) results in less water
extracted from a slope by plants and more water arriving on the
slope because of reduced interception of rainfall, which may initiate
ground movement through adverse changes in the pressure of water
within the soil pores.
Previous development, including landscaping works, may have also
increased the predisposition to land instability in the area, since the
soil and the surface topography are no longer in their natural state.
For example the presence on maps of areas marked as “worked
ground”, “old pits”, tanneries, “formerly dug”, “brickyard” should be
treated as triggers for further investigation. So too should a site
located near to a railway cutting or close to a cut-and-cover tunnel.
The preferential pathways to groundwater flow are mainly along the
interfaces or boundaries between different soil strata. It should be
noted that these boundaries are not clearly defined, and in an old
urban environment may be greatly influenced by historic building
and drainage works.
Any other local knowledge/guidance offered for slope stability
should be sought at design stage.
3.3.2 Structural damage beyond the site boundary
This section considers the potential effects of subterranean developments on
nearby structures and infrastructure. In the extreme case, an adjacent property
may directly adjoin another and the two buildings may share a common party
wall. In other situations, neighbouring buildings may not share a party wall, but
may still lie within the potential zone of influence of subterranean development
works at that building. Structural damage resulting from activities on a
neighbouring site may be due to changes caused to the geotechnical condition of
the ground but the actual nature and extent of the damage will be specific to the
affected structure.
Basements close to the public road affect both buried services/utilities and the
road/footway foundation and surface. The implications of damage induced by
ground movements, including the potential for legal proceedings arising from
damage to third-party property and structures can be significant.
The Planning Authority will expect all basement development applications to
provide evidence that the structural stability of adjoining or neighbouring
buildings is not put at risk (Section 3.1 of the “Basement Development Policy
Document” and Chapter 11 of “Dublin City Development Plan 2016 – 2022”).
Potential issues should be investigated and highlighted in the scoping stage of the
Basement Impact Assessment (see Section 5). An extensive analysis should occur
DCC Basement Development Guidance Document Version 1.0
15
in the case of listed buildings, or properties adjoining or adjacent to listed
buildings for which the Planning Authority shall require a structural stability
report as part of the BIA submission (Section 3.1 of the “Basement Development
Policy Document”). It is the developer’s responsibility to ensure adverse ground
movements and/or instability is guarded against through proper investigation
and design of mitigation measures at planning stage. The developer must then
satisfy the local authority that stability issues have been fully addressed. A pre-
condition survey (undertaken as part of the BIA) of all adjacent properties may
be sought by the Planning Authority. Therefore, DCC are likely to request that for
structures which are likely to be impacted by the proposed works a structural
survey is undertaken by a suitable professional and submitted as part of the BIA.
Issues identified by the survey can then be accounted for as part of the
Development design, temporary works etc. etc. The survey should also identify
whether the relevant buildings are “Protected” as per the current “Dublin City
Development Plan”.
3.3.3 Dewatering and Land Stability;
Where abstraction (dewatering) from an aquifer, as part of the temporary or
permanent works, is necessary to maintain dryness in the basement excavation, there
is the potential for subsidence. Dewatering lowers the groundwater table, reducing
pore water pressures, hence increasing effective stress. This causes the soil layer to
compress, leading to ground settlement. Dewatering can also induce settlement due
to loss of fines, if the groundwater lowering system continually pumps silt and sand
sized particles in the discharge water.
3.3.4 Land Stability key Issues to be assessed;
Instability brought about by basement construction should be guarded against by
ensuring proper investigation and design of mitigation measures is undertaken at
planning stage by the developer. This information should then be conveyed to the
local authority during the planning process to enable the local authority to be satisfied
that any instability has been taken into account.
Typically, through appropriate site investigations and geotechnical appraisal the key
issues for a developer are to determine whether;
the land is capable of supporting the loads to be imposed;
the development will be threatened by unstable slopes on or
adjacent to the site;
the development will initiate slope instability which may threaten
neighbouring structures and adjacent utilities;
the site could be affected by ground movements due to natural
cavities, underground streams/rivers
the site and adjoining structures could be affected by dewatering
processes or a change in groundwater levels over the
short/construction and longer term
DCC Basement Development Guidance Document Version 1.0
16
the site could be affected by ground movements due to past,
present or foreseeable future tunnelling or mining activities
3.4 Surface flow and flooding impacts
3.4.1 As per Section 3.1 of the “Basement Development Policy Document” basement
development shall not significantly impact on groundwater or surface water
flows to the extent that this is likely to increase the risk of flooding.
3.4.2 As with all proposed new development in Dublin City an SFRA (SFRA Dublin City
Development Plan 2016 -2022, Appendix 7) is to be undertaken and prepared in
accordance with The Planning System and Flood Risk Management - Guidelines
for Planning Authorities (Department of the Environment, Heritage and Local
Government and Office of Public Works, 2009) and Department of the
Environment, Community and Local Government Circular PL 2/2014. Flooding
from all sources should be considered (Section 3.1 of the “Basement
Development Policy Document”). In Dublin City some areas are known to be
susceptible to flooding. The guidance seeks to reduce the risk to the development
from flooding, as well as reducing current flood risk in the local area. Where
basement construction is proposed an SFRA is required to be undertaken. This
SFRA should account for the basement and included in the application
submission. The SFRA should be referenced accordingly within the BIA document.
3.4.3 The surface water and flooding elements of the Basement Impact Assessment
should be undertaken by a competent professional specialising in flood risk
management and surface water drainage.
3.4.5 In line with Section 16.10.15 of the Dublin City Development Plan, the Planning
Authority shall not permit “Development of all basements……. or any above
ground buildings for residential use below the estimated flood levels for flood
zone areas Zone A or Zone B…..”. The presence of a basement can provide a route
for flow from inundated sewers and drainage systems to enter into a building,
e.g. through the basement sanitary system. This type of flooding could be
guarded against through the use of non-return valves and anti-flooding devices.
Basements may also be at risk of flooding due to overland flow either from a
surface water course or a roadway and underlying surcharging sewers or from
intense roof run-off on site that exceeds the capacity of an on-site SUDs
infiltration system.
3.4.6 Alterations to the surface water regime are more likely when a basement extends
into areas of a plot which were previously vegetated (e.g. garden areas,
brownfield sites) or to the limits of the plot thus leaving insufficient corridors in
which to manage surface water e.g. constructing a basement under a garden will
reduce the infiltration capacity of the ground surface. As described in Section 3.1
of the “Basement Development Policy Document”, typically a thickness of at least
1m of soil must be placed on the “roof” of a basement to mitigate this. In the case
of a basement built under an existing structure, this situation does not arise, as
the existing building would already preclude rainwater infiltration into the
shallow soil strata.
DCC Basement Development Guidance Document Version 1.0
17
3.4.7 Constructing a basement, either beneath or adjacent to an existing building will
typically remove the permeable shallow ground that previously occupied the site
footprint. This reduces the capacity of the ground to allow rainfall to be stored in
the ground (in essence as a natural SUDS, or sustainable urban drainage system),
potentially leading to greater surface water run-off and greater risk of flooding.
The surface water runoff will flow down-gradient away from the developed
property if measures to manage the runoff have not been taken. Where adjoining
land or properties are at a lower elevation, there is the increased risk of surface
water flooding to that land or property. The reduction in rainfall absorption by
the ground will also reduce recharge to the underlying groundwater system.
3.4.8 If development were to result in an increase in surface runoff (or groundwater
discharge into the river systems) this could lead to an increased frequency of
flooding. The river system has a certain capacity to transport runoff. To assist
overflow areas can provide storage which in extreme rainfall events, when the
capacity of the channel would otherwise be exceeded, can retain a proportion of
the flow, to be released when the peak of the storm has passed i.e. the utilisation
of SUDS to reduce the potential for surface water run-off is an important aspect
to be considered as part of the BIA.
3.5 Cumulative effects of basement construction
A description of the potential for cumulative effects to occur as a result of basement
construction is described in Appendix D.
3.6 Basement construction related impacts
In addition to each of the potential impacts as a result of the basement design and
permanent presence a Developer shall need to be aware of and account for the potential
shorter term impacts as a of the basement construction. The construction of basements
has the potential to cause considerable nuisance to persons living and working close to a
development site.
The likely impacts at Construction Stage impacts include but are not limited to;
Temporary works and use of piling
Impact of deep excavations and piling on adjacent structures and assets and
utilities
Need for a pre and post construction survey
Noise, air quality (including dust) and vibration
o Site working hours
Traffic and heavy vehicular movements
Dewatering and impact on groundwater and adjacent structures
Discharge of groundwater into sewers or watercourses or through groundwater
recharge
Potential for hazardous/contaminated ground
The BIA needs to include an assessment of these impacts together with appropriate
mitigation measures.
DCC Basement Development Guidance Document Version 1.0
18
3.6.1 Temporary Works;
If a development requires temporary works e.g. ground anchors, to be installed
to support the basement excavation it should be noted that a Ground Anchor
Installation Licence (GAIL) is required to be completed and submitted as part of
the BIA. A GAIL is required when anchors (or similar) are proposed to be installed
external to the site. These anchors are required to be temporary in nature and
are to be cuttable in design to allow for the installation of future infrastructure.
A detailed survey of existing utilities and infrastructure is required to establish
locations and depths as part of the GAIL. Further details and the necessary
requirements are contained in the GAIL Guidance Document (Appendix C).
Note: Under no circumstances are ground anchors (or similar), installed beneath
public lands, permitted to form part of the proposed permanent structure.
3.7 Other Potential Factors and Impacts
3.7.1 Quality of design and workmanship:
Extending downwards beneath an existing building, especially old, masonry-built
properties that were not designed to contemporary engineering standards and
modern Building Regulations, is a challenging and potentially hazardous
undertaking. The work involved in forming a basement under an existing
structure is not trivial and it merits input from experienced professional
engineers and contractors, including underpinning specialists. A check as to
whether buildings under review are “Protected Structures” should be undertaken
– refer to the current “Dublin City Development Plan” and Section 4.5 of this
document.
3.7.2 Archaeology:
Most basement schemes involve removal of the shallow strata, (e.g. “made
ground”) which, in general, have the highest archaeological potential. Many
archaeological discoveries in Dublin City have been as a result of construction
works: subterranean developments therefore represent a means of increasing
knowledge and understanding of the archaeology in the city. The Developer
should consider this in their application – (Chapter 11 of “Dublin City
Development Plan 2016 - 2022”). A review of Section 16.10.20 of the “Dublin City
Development Plan” is recommended……“New basement development at
medieval sites shall be omitted where it is deemed that undue damage to
archaeology deposits shall occur”.
3.7.3 Uses of created subterranean space:
The principal potential uses of new underground spaces beneath private
residences typically include car parking, leisure (swimming pools and gyms) and
increasing the habitable space of the house, although not usually through
provision of bedrooms or garden flats. New underground spaces could therefore
potentially increase parking facilities within Dublin City, but may also increase car
usage and water consumption, both of which would have adverse effects on
DCC Basement Development Guidance Document Version 1.0
19
sustainability and environmental footprint. Depending on the location of the
proposed basement various restrictions may be placed on the basement end use.
3.7.4 Environment – waste to landfill and carbon emissions:
The process of extending a property by digging downwards to form a basement
will produce a considerably greater volume of spoil and require a greater volume
of construction materials (notably concrete, which has a relatively high carbon
dioxide emission rating) than would be typical in an above ground extension to a
residential property, such as a loft conversion or conservatory. The excavated
material taken from the basement space could be “made ground” rather than
natural soil, and it would have to be removed from the site (by lorry) and disposed
of at a suitable landfill site as, typically, non-inert waste. As a rough estimate, a
basement of 150m3 (for example 10m length by 5m width by 3m depth) would
generate in the order of twenty lorry loads, assuming a lorry is carrying one 8
cubic metre per load. The environmental “footprint” of a basement project is
therefore not trivial, and should be viewed with Dublin City Council`s
environmental and sustainability policies in mind. A brief description of DCC
Waste Management Department requirements is outlined in Section 8.5.
3.8 Holistic Approach Required to Potential Impacts
It can be observed in Section 3.3, 3.4 and 3.5 that groundwater, surface water, soil
stability, drainage and SUDs must be assessed by an experienced team. These issues
along with many other potential factors must be analysed and reviewed in an integrated
and holistic manner i.e. each of these potential impacts and factors should not be
assessed in isolation.
4.0 Basement Development Specific Considerations
When considering applications for basement developments, the Planning Authority shall have
regard to the following;
4.1. Size and Extent of Basement Development
4.1.1 Larger basement developments, such as those of more than one storey in depth
or which extend outside of the footprint of the above ground building, are likely
to have a greater impact than smaller schemes. Larger basement developments
require more extensive excavation resulting in longer construction periods, and
greater numbers of vehicle movements to remove the spoil. These extended
construction impacts can have a significant impact on adjoining neighbours
through disturbance through noise, vibration, dust, and traffic and parking issues.
Larger basements also can have a greater impact on the water environment by
reducing the area for water to runoff or soak away and impacting on
groundwater. Basement development that extends below garden space can also
reduce the ability of that garden to support trees and other vegetation leading
to poorer quality gardens and a loss in amenity and the character of the area.
DCC Basement Development Guidance Document Version 1.0
20
4.1.2 The Planning Authority recognises that in the case of larger buildings in Dublin
and on large comprehensively planned sites (for example on large sites that
occupy an urban block) the impacts of basements will differ to basement
schemes in primarily residential neighbourhoods and in such circumstances
larger basements are likely to be more appropriate.
4.1.3 In areas of existing large scale commercial/office development, in certain
instances and if ground conditions allow, a basement may be permitted to cover
a considerable proportion of the site. The feasibility of such proposals shall need
to be validated and highlighted in the submitted BIA with respect to all potential
impact as outlined in this document.
As described in Section 3.1 of the “Basement Development Policy Document” all
basement developments shall account for and accommodate the existing
groundwater contained within and flowing through their site. As a minimum
standard there is to be at least 0.5m wide of clear space provided between the
site/property boundary and the outer extent of a basement. This 0.5m wide
space and shall extend over the full height and around the perimeter of the
basement and shall be filled with suitable, highly permeable material (with
appropriate wrapping).
4.1.4 As per Section 16.10.15 of the “Dublin City Development Plan” and Section 3.1 of
the “Basement Development Policy Document” the permissible size of a
basement development to the rear of a domestic property will be guided by the
characteristic of the site. In the case of large sites a basement development to
the rear of a property generally should not exceed the footprint of the original
building and be no deeper than one full storey below ground level. Domestic
basement development should generally not extend to more than 50% of the
amenity/garden space.
4.1.5 The extent and design of a proposed basement should take account of the
requirements outlined in this document to undertake adequate site investigation
and continuous monitoring (boreholes etc.) before, during and after the
construction phase. Provision for de-watering of the excavation during the
construction phase needs to be accounted for and as such a location for recharge
of groundwater needs to be incorporated within the site boundary. The
location(s) of a groundwater recharge point(s) should be accounted for at the
basement design stage and the location should be included as part of the
construction methodology section of the BIA submission, taking into account and
with reference to the local site geology, hydrogeology, ground conditions etc.
Calculations should be provided as part of the BIA demonstrating the expected
level of groundwater discharge and expected recharge capacity back to the
groundwater (within the site boundary). Where recharge is not possible,
calculations and an analysis of groundwater discharge to sewer should be
included in the BIA for review by the Planning Authority and DCC Pollution
Control department.
4.1.6 The internal environment of the development should be fit for the intended
purpose, and there should be no impact on any trees on or adjoining the site, or
DCC Basement Development Guidance Document Version 1.0
21
to the water environment or land stability (as outlined elsewhere in this
document). As per Section 3.1 of the “Basement Development Policy Document”,
larger schemes, including those consisting of more than one storey in depth or
extending beyond the footprint of the above ground building, will be expected to
provide appropriate evidence within the BIA to demonstrate to the Planning
Authority`s satisfaction that the development does not harm the built and
natural environment or local amenity.
4.1.7 Often with basement development, the only visual features are lightwells and
skylights, with the bulk of the development concealed wholly underground, away
from public view. However, just as overly large extensions above the ground level
can dominate a building, contributing to the over-development of a site, an
extension below ground can be of an inappropriate scale. There may be more
flexibility with the scale of a development when it is proposed underground, but
there are a number of factors that would mean basement development could
result in overdevelopment.
4.2 Flood Levels
As per Appendix 7 of “Dublin City Development Plan 2016 -2022” a Strategic Flood Risk
Assessment (SFRA) will provide an area-wide assessment of all types of significant flood
risk to inform strategic land use planning decisions. A site specific is to be undertaken and
prepared in accordance with The Planning System and Flood Risk Management -
Guidelines for Planning Authorities (Department of the Environment, Heritage and Local
Government and Office of Public Works, 2009) and Department of the Environment,
Community and Local Government Circular PL 2/2014 and is to be referenced within the
BIA submission.
4.3 Sustainable Urban Drainage Systems (SUDS)
The use of SUDS as a requirement for new development has been a feature of DCC
Planning requirements for many years. Taking account of this policy a basement
development should provide an appropriate proportion of soft landscaping and planted
material to compensate for any reduction in the natural storm water infiltration capacity
of the site, in accordance with DCC’s preferences on Sustainable Urban Drainage (refer
to DCC Development Plan for further detail). As detailed in Section 3.4.6 the basement
“roof” should be covered with an adequate depth of soil (not less than 1m) and an
associated drainage membrane to allow the soft landscaping extend over the basement
area. The impact of SUDs proposal should be assessed in the context of groundwater flow
and levels and consequential impacts (see section 3.4.8).
When designing SUDS systems account should also be taken of Section 3.4 (Surface flow
and flooding) and Section 4.1.3 and 4.1.4.
4.4 Archaeological Impact
As described in Section 3.7.2 Archaeology discoveries are deemed to be extremely
important to the city as a whole. Chapter 11 and Section 16.10.10 of the Dublin City
DCC Basement Development Guidance Document Version 1.0
22
Development Plan outlines DCC policy requirements and guidance with respect to
development on archaeological sites in zones of archaeological interest.
4.5 Conservation areas and listed buildings
4.5.1 As described in Section 3.1 of the “Basement Development Policy Document” and
Chapter 11 of the “Dublin City Council Development Plan 2016 - 2022” an
extensive structural stability and conservation report is required in the case of
listed buildings, or properties adjoining or adjacent to listed buildings. A record
of protected structures is contained in Volume 4 of the “Dublin City Council
Development Plan 2016 – 2022”.
4.5.2 As with all development schemes, the Planning Authority shall need to be
satisfied that effective measures will be taken during demolition and construction
works to ensure that damage is not caused to the listed building and any buildings
it directly adjoins (e.g. Chapter 11 of Dublin City Development Plan 2016 – 2022).
Poor demolition and construction methods can put neighbouring properties at
risk and so can have considerable effects on the character and appearance of
heritage buildings and conservation areas.
4.5.3 As per Section 3.1 of the “Basement Development Policy Document”, the Planning
Authority (as part of the BIA) requires the submission of a management plan for
demolition and/or construction where basement works are proposed particularly
in conservation areas or adjacent to a listed building. All relevant details and
references should be contained in the overall “Construction Management Plan”
(see Section 5.5) to be submitted as part of the BIA.
4.5.4 Each of the reports mention in this section should be referenced accordingly
within the BIA.
4.6 Trees Landscape and Biodiversity
4.6.1 As per Section 16.10.15 of the “Dublin City Development Plan 2016 - 2022” the
basement development should provide an appropriate proportion of planted
material to allow for rain water to be absorbed and/or to compensate for the loss
of biodiversity caused by the development. This will usually consist of a green
roof or detention pond on the top of the underground structure. As per Section
3.1 of the “Basement Development Policy Document” it will be expected that a
minimum of 1 metre of soil be provided above basement development that
extends beyond the footprint of the building, to enable garden planting and to
mitigate the effect on infiltration capacity. The use of SUDS is sought in all
basement developments that extend beyond the footprint of the original
building.
4.6.2 Again as per Section 16.10.15 of the “Dublin City Development Plan 2016 - 2022”
consideration should be given to the existence of trees on or adjacent to the site,
including street trees and the required root protection zone of these trees.
Existing trees and shrubs shall be surveyed by qualified professionals and
retained or replaced to maintain the street environmental character. Any plants
or animals of scientific interest shall be reported to the appropriate authority and
DCC Basement Development Guidance Document Version 1.0
23
any guidance from this authority followed. Restrictions on tree cutting periods
shall be followed.
ROOT PROTECTION ZONE The area around the base or roots of the tree that
needs to be protected from development and compaction during construction to
ensure the survival of the tree.
4.7 Internal Environment and Appearance of Basement
Where basement accommodation is to provide living space, the Planning Authority in line
with Section 16.10.15 of the “Dublin City Development Plan 2016 – 2022” will take
cognisance of the development standards relating to (but not limited to);
space,
amenity and
natural light
Ventilation
Means of escape
4.8 Lightwells
4.8.1 Adequate sunlight/daylight penetration will be required which will be influenced
by site orientation and the size of site and any lightwell/courtyard; the planning
authority may require a daylight analysis to be submitted as part of a planning
application.
4.8.2 The building stock in Dublin is varied. Some areas contain basements
developments that include front lightwells taking up part, or all, of the front
garden. Other areas do not have basements or lightwells that are visible from the
street. The presence or absence of lightwells helps define and reinforce the
prevailing character of a neighbourhood.
4.8.3 Where basements and visible lightwells are not part of the prevailing character
of a street, new lightwells should be discreet and not harm the architectural
character of the building, or the character and appearance of the surrounding
area, or the relationship between the building and the street. In situations where
lightwells are not part of the established street character, the characteristics of
the front garden or forecourt will help to determine the suitability of lightwells.
4.8.4 In plots where the depth of a front garden is quite long, basement lightwells are
more easily concealed by landscaping and boundary treatments and a substantial
garden area can be retained providing a visual buffer from the street. In these
situations new lightwells that are sensitively designed to maintain the integrity of
the existing building may be acceptable, subject to other design requirements
and environmental considerations.
4.8.5 In plots where the front garden is quite shallow, a lightwell is likely to consume
much, or all, of the garden area. This may not be unacceptable in streets where
lightwells are not part of the established character and where the front gardens
have an important role in the local townscape.
4.8.6 Excessively large lightwells may not be permitted in any garden space.
DCC Basement Development Guidance Document Version 1.0
24
4.8.7 A lightwell to the side or rear of a property is often the most appropriate way to
provide a means of providing light to a new or extended basement development,
and can often provide a link to the rear garden. Lightwells to the side or rear of a
property should be set away from the boundary to a neighbouring property.
4.9 Railings, grilles and other lightwell treatment
4.9.1 Light wells should be secured by either a railing (1.1m high) or a grille. In gardens
that front a street, railings can cause a cluttered appearance to the front of the
property and can compete with the appearance of the front boundary wall, or
obscure front windows. This is particularly the case in shallow gardens. Where
front light wells are proposed, they should be secured by a grille which sits flush
with the natural ground level, rather than railings. In certain publicly accessible
locations grilles should be lockable.
4.9.2 Railings will be considered acceptable where they form part of the established
street scene, or would not cause harm to the appearance of the building.
4.9.3 The lowering of the natural ground level to the rear of the property should be
minimised as much as is practicable. It is recommended that the rear garden
should be graded rather than secured by railings.
4.9.4 Where a basement extension under part of the front or rear garden is considered
acceptable, the inclusion of skylights designed within the landscaping of a garden
will not usually be acceptable, as illumination and light spill from a skylight can
harm the appearance of a garden setting and cause light pollution.
5.0 Basement Impact Assessment (BIA) Methodology
5.1 Overview of Basement Impact Assessment (BIA Methodology
5.1.1 A BIA is intended to provide sufficient and accurate information which the
Planning Authority can utilise to determine whether or not to grant planning
consent. This information is also used by affected parties to evaluate the
acceptability of the development and its impacts.
5.1.2 It should be noted that other factors relating to Planning Policy may have equal
or overriding importance than the content of a BIA when it comes to the Planning
Authority reaching a decision on the application.
5.1.3 The proposed BIA methodology is derived from the Environmental Impact
Assessment (EIA) model which is a well-established and widely-utilised process
of identifying, predicting, evaluating and mitigating relevant environmental
effects of development proposals prior to decisions being taken.
5.1.4 The Dublin City Council Basement Policy states that the Planning Authority will
only permit basements and other underground development that does not cause
harm to the built and natural environment and local amenity and does not result
in an increased risk of flooding both above ground or of basements and cellars in
nearby properties or ground instability. Developers are required to demonstrate
by methodologies which are appropriate to the particular site ensuring that;
DCC Basement Development Guidance Document Version 1.0
25
The structural stability of the building and neighbouring properties are
maintained
The water environment shall not be adversely affected and
groundwater flow, drainage and/or run-off shall also not be negatively
impacted
Avoid cumulative impacts upon structural stability or the water
environment
Take account of overland surface and underground water flows
5.1.5 The information which is to submitted to the Planning Authority to support a
planning application for a basement development will need to address, amongst
others, the issues above in order to enable the Planning Officer to determine an
application.
Unless agreed differently with DCC Planning Department the methodology used
to assess the impact of a proposed basement with regard to the matters
described above, takes the form of an impact assessment. The Basement Impact
Assessment (BIA) process takes the form of the well-established EIA process.
5.1.6 A BIA is critically dependent on the expertise, experience, independence and
objectivity of water, soils, environmental and structural specialists. It is the
responsibility of the Developer`s Specialists to understand the proposed
development sufficiently so that likely significant adverse impacts can be
anticipated and mitigated where possible. The Specialists are required to
characterise the existing environment and then predict how the receiving
environment will interact with the proposed environment (physical and
ecological). If the Specialist anticipates significant adverse impacts they will need
to work with the Developer and Design Team to devise measures to eliminate or
mitigate such impacts. The suitably qualified Specialist who prepares each section
should be identified in the report.
5.1.7 The BIA process requires disclosure of information and commitments to
mitigation. These are the responsibilities of the Developer. Prior to
commencement of a BIA a Developer should be aware of the requirements
arising from the BIA planning assessment (Section 1.2).
5.1.8 The BIA shall identify potential impacts during the construction of the
development (incl. temporary works) and in the longer term (steady state) when
the building is constructed. Reference to the baseline condition (pre-
development) should be referenced throughout the BIA.
5.2 Summary of tasks to be completed as part of BIA
5.2.1 The tasks which are to be incorporated and detailed within a BIA to be submitted
to the Planning Authority are summarised as;
Scoping
o Scoping is the process of identifying significant issues which should
be addressed as part of the BIA.
o Informal review with Planning Authority utilising pre-planning queries
during the BIA compilation and drafting process
DCC Basement Development Guidance Document Version 1.0
26
Continuous Site Investigation, Study and Monitoring
o Site Investigation works and analysis will be required as part of the
scoping stages of a BIA and in order to establish the baseline site
conditions. Additional and continuous site investigation and/or
monitoring, specific to the particular site and particular development
is likely to be required pre-planning, pre-construction, during
construction and post construction.
Impact Assessment and Mitigation Measures
o Impact assessment is completed in order to establish the impact of
the proposed basement on the baseline conditions (during
construction and longer term post construction). Any proposed
mitigation measures are to be accounted for and the residual impacts
reviewed
Review and Decision making
o This step is to be undertaken by the DCC Planning Department. An
audit of the suitability and content of the BIA is undertaken. The
significance of each of the impacts and proposed mitigation measures
for a particular development is then analysed and a decision taken.
5.2.2 The BIA process will be developer-led, with Dublin City Council providing
guidance in the initial scoping stages, followed by review of the resulting impact
assessment by the Planning Authority. The BIA process should be undertaken for
all proposed basement developments that are subject to planning, regardless of
size, location or proposed use. The scale and content of the BIA will, however,
differ for each proposal and should be appropriate to the proposed development
and the scale of the potential impacts identified during the scoping and site
investigation stages. Further details with regard to the categorisation of
basement development is outlined in Section 7.2.
5.2.3 The following sections outline the methodology that has been devised for
specifying and undertaking a BIA in the Dublin City administrative area.
5.2.4 Developers need to ensure that they allocate a realistic period to allow for the
research, investigation and the compilation of data such that a BIA can be
adequately prepared. The length of time involved very much depends on the
objective of the work being undertaken or the sensitivity of the receiving
environment. For example, groundwater and/or ecological baselines may require
observations and monitoring on either a seasonal basis or over a hydrological
year, from October through to the following September.
5.2.5 A non-technical summary of the evidence that applicants shall have gathered at
each stage of the BIA is required to be submitted in a format which can be fully
understood by those with limited technical knowledge.
5.2.6 Forms and checklists to be completed by the Planning Applicant and included
within the BIA submission are included in Appendix A (Section 1 and Section 2).
Submitted BIA review sheets, to be utilised by the Planning Authority, are also
included for reference in Appendix A, Section 3.
DCC Basement Development Guidance Document Version 1.0
27
5.3 Scoping
5.3.1 A BIA is required for all developments which include the construction of a
Basement (as per Section 3.2 of “Basement Development Guidance Document”).
Scoping is the activity of defining in further detail the matters to be investigated
as part of the BIA process.
5.3.2 Scoping must be focused on issues and impacts which are;
Scientifically based
Likely to occur
Significant and adverse
5.3.3 The BIA scoping stage aims to define the scope of investigation required in order
to provide the information necessary to make an assessment of the impact of the
issues identified. The defined scope should be specific to the site and proposed
development.
5.3.4 A conceptual ground model is often a useful tool to assist in the carrying out the
scoping stage as it can include the known and suspected features on, below and
adjacent to a proposed site (see Section 5.3.11).
Scoping process
5.3.5 For a BIA, it is proposed that the scoping stage requires the developer to identify
the potential impacts for each of the matters of concern. Some of the main
potential impacts of basement development in Dublin City are described in
Section 3 of this document.
5.3.6 In practice, identifying the potential impacts is facilitated if a conceptual ground
model is developed for the proposed site. A conceptual ground model includes
the flow of groundwater through the site and the known and suspected features
on, below and adjacent to a proposed site, including geotechnical details. Such a
model will assist in identifying the likely implications of the ground, groundwater
or surface water for a proposed basement development. It is helpful to portray
the conceptual ground model as a three-dimensional block model showing
adjacent buildings, trees, gardens, and buried infrastructure that allows the scale
of the features, in relation to the size of the development, to be appreciated.
5.3.7 To undertake the scoping stage of the BIA process, a developer would need to
have some information on the specific project as well as the site. This may involve
some preliminary data collection and field work. It is the applicant’s responsibility
to obtain appropriate information proportionate to the potential impacts of the
proposed basement. Information likely to be required for scoping for a BIA
includes, but not limited to:
Characteristics of the Project
o Brief description of the proposed development.
o A plan showing the boundary of the development including any
land required temporarily during construction.
DCC Basement Development Guidance Document Version 1.0
28
o An assessment and description of the ground conditions
groundwater levels and as history of previous built infrastructure
on the site of the proposed excavation.
o The physical form of the development (layout, dimensions,
construction materials, etc.).
o A work programme for construction, operation and
commissioning phases, and restoration and after-use where
appropriate.
o Construction methods – incl. any temporary/permanent works
o Information about mitigation measures being considered.
o Details of any other permits required for the project (T2, GAIL,
waste, discharge, etc.).
Location of the Project
o Maps and photographs showing the location of the project
relative to surrounding buildings, topography, protected
structures, natural and man-made features.
Characteristics of the Potential Impact
Impacts on soils, land use, water quality and hydrology.
Nature and scale of the impacts (i.e. short, medium and long-term,
permanent and temporary, positive and negative).
Extent of the impacted area.
Mitigation incorporated into the project design to reduce, avoid or offset
significant adverse impacts.
5.3.8 The potential impacts identified at this stage will be used by a developer to devise
a study and an investigation to obtain information which will answer the
questions posed. The aim should be to ensure as far as possible that the scope of
the BIA includes such considerations as the incremental effect of the proposed
basement upon the cumulative impact of basements in the area. The maps
included in this report should assist the Planning Authority in recognizing where
potential impacts beyond those which a developer might, unbidden, take into
account in his assessment.
5.3.9 The scoping should identify the matters which should be covered in the technical
information submitted by the developer to the Planning Authority in the BIA, in
particular, to identify the matters which are of most importance so that these can
be addressed in most detail. It is not necessary for the scoping activity to produce
a detailed schedule or specification for the study, but it should define the nature
of the matters to be investigated in sufficient terms that a specification can be
produced at the next stage of the BIA process.
5.3.10 Consultation with local residents; Parallel to the scoping stage of the BIA, a
developer may wish to enter pre-consultation and/or set-up a working group
with local residents who may be impacted by a proposed basement. The purpose
of community involvement would be to understand and address in the BIA
process local residents concerns with regard to the proposed development.
DCC Basement Development Guidance Document Version 1.0
29
This is not a formal stage or requirement within the BIA methodology and should
be viewed solely as a recommendation for developers to assist in identifying
potential matters of concern. It should supplement the scoping stages of the BIA
methodology. Local residents may also have some knowledge of the flooding
history.
5.3.11 The Conceptual Ground Model; This is an integrated subsurface and surface
conceptual model. The translation of an identified possible impact into the scope
for an investigation involves deciding what should be measured, where, and at
what scale. In order to do that, an understanding is needed of the relevant
physical processes in operation, including the scale and speed at which they
operate. This requires a conceptual ground model to be developed.
A ground model contains all the known geological (in the broadest sense
encompassing hydrological and hydrogeological and geotechnical as well as
stratigraphic) information about the site and the physical processes which affect
it. In other words, the ground model should be an explanation of how the site
works. The ground model may initially be quite generalised, and would be revised
as new information is obtained.
5.4 Continuous Site Investigation, Study and Monitoring
5.4.1 Site investigation, study and monitoring will be required to adequately complete
all stages of a BIA, pre-planning, pre-construction, during construction and post
construction. Site investigation is to be designed and undertaken such that it is
specifically appropriate and relevant to the proposed development.
5.4.2 The site investigation required for a BIA should identify the conditions which may
affect a particular development and to arrive at an understanding of the site and
immediate surroundings which will allow safe and economic development. The
“conditions” are understood to include the ground conditions (i.e. the soil and
rocks) and also the surface water and groundwater regime, any contamination
and the effects of previous uses of the site and its environs. The degree of
investigation will vary depending upon the matters of concern identified in the
scoping stage, and therefore will be dependent on the location of the proposed
basement within the city, it`s size and setting in relation to the existing
development on the site and its relationship to adjacent properties and nearby
features of importance.
5.4.3 The BIA site investigation comprises several stages including:
desk study, including site walkover
field investigation, including intrusive investigation
establishment of a baseline condition
monitoring (before, during and post construction phase)
reporting
interpretation
comparison to baseline condition post-construction (seasonal
monitoring required)
DCC Basement Development Guidance Document Version 1.0
30
5.4.4 The field investigation stage is likely to include intrusive investigation within the
boundary of the site. The field investigation might, however, also include surveys,
intrusive investigations and measurements which extend beyond the site
boundary. Monitoring for both a short and an extended period is required both
within and beyond the site boundary.
5.4.5 The data and information collected in the site investigation will be analysed and
interpreted by the developer or his specialist adviser/consultant, to provide
baseline data which, in the next stage of the BIA, can be used in order to make
an assessment of the potential impacts identified through the scoping exercise.
5.4.6 It should be noted that variations in groundwater level can be caused by seasonal,
tidal, fluvial changes as well as storm events. Site investigation measures/stages,
as per Section 6.2.3 shall need to be undertaken to observe and record these
changes and fluctuations such that a comprehensive baseline reference and
understanding is available as part of the BIA submission for the specific site.
Dependent on the location and nature of the development this may require
extensive monitoring over a hydrological cycle (hydrological year) before, during
and post construction such that a reasonable comparison to the baseline post-
construction can be assessed and fluctuation limits established for the
construction and post-construction phases. Such details are to included in the
BIA.
5.4.7 Specific site investigation should account for and report upon the suitability of
the temporary works required to construct the proposed basement. The site
investigation works should reference the proposed temporary works design and
be sufficiently adequate to inform the Ground Anchor Installation Licence (GAIL)
process, where Developers wish to apply for permission to install ground anchors
or similar in a public space e.g. location of existing utilities and infrastructure,
suitability of ground conditions etc. (Appendix B and Appendix C).
5.4.8 As further issues may arise during investigations these too should be scoped and
addressed as part of the BIA submission.
5.5 Impact Assessment and Mitigation Measures
Impact Assessment for a basement development may be defined as the process of
evaluating the direct and indirect geo-environmental implications of the proposed
project. It should be a flexible process and can make use of a number of evaluation
methods and techniques. Guidance in undertaking an impact assessment is provided in
the following section.
5.5.1 In simple terms, a BIA describes the impacts of the project on the environment
by comparing the present situation (the baseline) with the situation as it would
be with the basement in place i.e. constructed. The approach is similar to an
economic analysis or an EIA.
5.5.2 A systematic approach is required, and the BIA should describe, quantify, and
then aggregate the effects of the development on those attributes or features of
the hydrogeological and hydrological environment which have been identified (in
the scoping stage) as being potentially affected.
DCC Basement Development Guidance Document Version 1.0
31
5.5.3 Whenever possible, impacts should be described by reference to an existing
acknowledged standard or criteria for the topic. The criteria on which the
terminology is based should be clearly defined for each discipline. Where this is
not possible then it is recommended that impacts should be described by
reference to the “glossary of impacts” (Section 10).
5.5.4 The generic review of attributes is summarised as below (but is not limited to):
Surface (hydrological) flow
Rate of runoff
Direction of overland flow
Stream hydrograph
Soil moisture
Frequency of surface flooding
Sediment transport (erosion and siltation)
Subsurface (groundwater) flow
Groundwater levels and existing natural fluctuations
Groundwater chemistry and bacteriology
Spring hydrographs
Soil moisture
Water quality
Slope stability
Slope angle
Moisture content
Porewater pressure
Stiffness
Compressibility
Bearing capacity (strength)
Atterberg limits
5.5.5 The BIA should evaluate the attributes with and without the development and
consider the possibility of alternatives. For example, what are the groundwater
levels (including range of seasonal fluctuation) by hydrogeological calculation,
beneath the site, before development and the predicted levels, post
development? The impacts should be measured in terms of the “nett” changes
in the attribute at a given point in time. For example the nett change may be the
rise upstream and the lowering downstream of groundwater levels due to a
basement.
5.5.6 As part of the BIA an assessment should be taken of the potential impacts during
construction if/when dewatering is required to facilitate construction. There may
be a risk to adjoining structures etc. Similarly, when dewatering ceases and the
water-table is allowed return to the natural levels there is again a potential for
land and structure stability issues. This scenario shall also need to be assessed by
a suitably competent person(s) and accounted for in the BIA.
DCC Basement Development Guidance Document Version 1.0
32
5.5.7 Monitoring of groundwater levels and other applicable parameters should be
undertaken during and post development to permit a comparison with the
baseline levels and to establish threshold limits for dewatering etc.
5.5.8 The consequences of changes in attributes determine the amount of change from
baseline conditions which may be accepted. Thus, a predicted rise in
groundwater level upstream of a proposed basement may have consequences in
terms of an increased likelihood of groundwater flooding, or a risk of damage to
the foundations of a neighbouring building, both of which would be
unacceptable.
5.5.9 The baseline would incorporate the presence of existing basements, so that the
additive effect of another basement would be the assessed change. Nearby and
adjacent basements should be accounted for and highlighted within the report.
5.5.10 If the consequences are not acceptable, mitigation should be incorporated into
the proposed scheme and the changes in attributes re-evaluated and the new
nett consequences determined. Any mitigation measures incorporated into the
proposed scheme should be described in the BIA report with details of how they
reduce and/or alter the impact of the proposed basement on the surrounding
environment.
5.5.11 Mitigation measures which may be included in basement development proposals
include (but are not limited to):
Controlled or adequate drainage
High permeability corridors
Underpinning of neighbouring structures
Setting the basement in from property boundaries
Etc.
5.5.12 The baseline conditions (pre-construction) should be established and the
relevant mitigation measures and residual impacts should be accounted for and
demonstrated separately for the subsequent two stages of the development;
i. Construction stage
ii. Steady state (long-term post construction)
It is imperative that these mitigation measures and residual impacts are
accounted for and highlighted in the BIA. The construction stage impacts and
mitigation measures should be included within the “Construction Management
Plan” (Section 5.5). The steady state scenario (impacts and mitigation measures)
are to be recorded and should form part of the as-built drawings of the structure
and included as part of the scheme Safety File, to be made available at future
request for interested parties.
5.5.13 Alternative options should be examined and considered during design and
consultation to ensure that options that are of interest to all parties are
evaluated.
5.5.14 Consequences will differ from one location to another, but their assessment
should be based on the concept of identified targets. The susceptibility of the
targets, which might be watercourses, utilities, existing buildings, roads or
DCC Basement Development Guidance Document Version 1.0
33
structures in close proximity to the proposed basement, possibly even trees,
should be evaluated using appropriate methods.
5.5.15 In the case of susceptibility of buildings to damage resulting from ground
subsidence, there are established methods in geotechnics. Where the target is a
groundwater supported feature such as a spring or wetland the methods may be
more subjective even when the impact of the development on the relevant
attribute (groundwater seepage) can be reasonably quantified.
5.5.16 The Geotechnical Design Report for the project, as required in IS EN 1997, should
address the issues relevant to the BIA.
5.5.17 Special attention is to be given to protected and heritage structures. These
structures and measures are to be highlighted with the BIA with the relevant
planning guidelines followed.
5.5.18 All design measures are the responsibility of the Applicant`s design/specialist
team.
Cumulative impacts of basement development
5.5.18 The cumulative effect of the incremental development of basements in close
proximity, particularly when these are large, can potentially create a significant
impact. Therefore, Basement Impact Assessments must identify neighbouring
basements (both existing and those with planning approval or already in the
planning process) and make the assessment considering all such nearby
basements. Basement Impact Assessments must respond to the issues of
cumulative impacts and account for/undertake appropriate mitigation measures.
5.5.19 In order to avoid cumulative effects and in an effort to be as fair and equitable as
possible to all development proposals, all basement developments shall account
for and accommodate the existing groundwater contained within and flowing
through their site. Any scheme with a proposed basement shall ensure that the
ability of groundwater to exit and/or to pass through the site shall remain
unchanged post construction. Groundwater levels upstream or downstream of
the development are not to be altered as a result of the development i.e. each
basement development shall implement measures to ensure that the volume of
groundwater, within and passing through the site pre-development shall be
unchanged post-development and there should be no impact upon groundwater
levels up-stream or down-stream of the groundwater gradient.
5.5.21 Further to the point made above, in an effort to be as fair and as equitable as
possible, as a minimum standard, all basement development is required to
provide at least 0.5m wide of clear space between the site/property boundary
and the outer extent of a basement. This 0.5m wide space shall extend over the
full height and around the perimeter of the basement and shall be filled with a
suitable, highly permeable material (with appropriate wrapping), thus reducing
the potential for cumulative effects if further basements are to be constructed
nearby.
DCC Basement Development Guidance Document Version 1.0
34
In providing the highly permeable 0.5m wide space between the site boundary
and the basement structure the design team should ensure that erosion and
undermining beneath the adjoining site/property would not be possible.
5.5.22 If the required 0.5m wide high permeable space is regarded by the developer`s
design team as being inadequate to account for the volume of groundwater
observed within a particular site the Developer is required to identify more
robust measures in order to meet the requirements described in Section 5.5.19.
Construction Management Plans
5.5.23 The Planning Authority shall require a construction management plan for all
underground basement developments to manage and mitigate the construction
impacts of these schemes. Construction management shall be particularly
important on constrained sites, in conservation areas, for listed buildings and at
sites located adjacent to listed buildings amongst others. The level of content of
the Construction Management Plan should be proportional to the scale and
complexity of the proposed development. The Developer is required to adhere
to this “Construction Management Plan” if the application is deemed successful.
5.5.24 A basement construction plan sets out detailed information to demonstrate how
the design and construction of the basement has been prepared in order to
minimise the impacts on neighbouring properties, public lands and the water
environment. The basement construction plan should provide a programme of
measures to be undertaken whereby the Developer shall minimise and mitigate
against any potential impact on the structural integrity of neighbouring
properties and sensitive structures e.g. the public road infrastructure.
5.5.20 A basement “Construction Management Plan” should plan should contain (as a
minimum);
Provision for phasing of the works
Provision for site management, safety and supervision
A method statement detailing the proposed method of ensuring the
safety and stability of neighbouring properties and land throughout
the construction phase, including temporary works sequence
drawings
Provision to monitor movement of structures and land (details to be
provided)
Provision to monitor groundwater levels and alerts to be raised as
required (details to be provided). Appropriate limits of groundwater
fluctuation to be accounted for and detailed. Critical groundwater
threshold levels are to be identified such that alarm set-points can be
established. Appropriate mitigation measures to be detailed if these
limits are reached or exceeded e.g. to prevent occurrence of ground
movement
Proposed site working hours
Management of noise, vibration and dust
DCC Basement Development Guidance Document Version 1.0
35
Construction & Demolition Waste Management Plan – reference to
soil conditions, contaminants, hazardous waste etc.
Management of construction traffic and parking incl. traffic
movements/routes to and from site
Details demonstrating that the basement has been designed using
evidence of local factors including ground conditions, the local water
environment and the structural condition of neighbouring properties,
in order to minimise the impact on them.
The Construction Management Plan should contain the
structural/geotechnical design submissions (as required in IS EN
1997).
Appropriate monitoring including details of risk assessment
thresholds and contingency measures e.g. for ground movement,
groundwater levels, surface water flooding etc.
The location(s) of a groundwater recharge point(s) should be
accounted, taking into account and with reference to the local site
geology, hydrogeology, ground conditions, development extent and
site boundary etc.
If discharge is proposed to a local sewer details related to the
anticipated pumped volumes and discharge quality is to be detailed
The locations of a minimum of 4no. groundwater monitoring points
facilitating monitoring during pre-planning, pre-construction phase,
construction phase and post construction phase, taking into account
and with reference to the local site geology, hydrogeology, ground
conditions, development extent and site boundary etc. (coordinates
provided and to be accessible and maintained post-construction
where possible).
Details as to whether temporary or permanent works are to extend
outside the site boundary, e.g.
o Boreholes required to monitor groundwater? – permissions
required
o Ground anchors/soil nails for which a Ground Anchor
Installation Licence (GAIL) shall be required (Appendix B) –
see also Ground Anchor Installation Licence guidance
document (Appendix C).
Provision to retain at the property throughout the construction phase
a suitably qualified engineer and supported as required by a
hydrogeologist from a recognised relevant professional body
(including dewatering phase) to monitor impacts, adjust pumping
rates, inspect dewatering arrangement, review and apply the
threshold groundwater levels (pumping controls) and approve the
permanent and temporary basement construction works.
DCC Basement Development Guidance Document Version 1.0
36
Measures to ensure the ongoing maintenance and upkeep of the
basement.
5.5.21 The “Construction Management Plan” should ensure that:
Suitably qualified and experienced engineers and hydrogeologists
have agreed the design, construction process and monitoring and
mitigation protocols.
The modelling of ground conditions and water environment is
appropriately conservative; and
Permission has been sought from the Local Authority or third parties
if temporary/permanent works are to extend beyond the site
boundary e.g. GAIL application to be submitted.
Best endeavours are undertaken to prevent any impact on the
structural integrity of the neighbouring properties
The construction methodologies and proposals are in accordance with
the Design Team proposals and requirements and that each design
element has been accounted for. All requirements to construct the
building as per design is required to be included in the “Construction
Management Plan” and scoped accordingly e.g. structural stability of
adjoining building requirements has been incorporated, sequencing
of works as per design requirements etc. etc.
5.5.22 Prior to final submission to the Planning Authority for approval, Basement
Construction Management plans will need to be certified by a suitably qualified
and experienced engineer and/or a hydrogeologist who is independent of the
design team. The certification will need to be funded by the applicant.
5.5.23 Construction Management Plans should take into consideration other
developments taking place in the local area with a view to minimising the
combined effects of these construction works. The Planning Authority
encourages applicants to inform and engage with affected neighbours at an early
stage.
5.5.24 If successful the Construction Management Plan submitted in the BIA shall form
a material consideration in the conditioning of a planning application
5.6 Qualifications and accreditation
5.6.1 At each stage in the process, the person/s undertaking to complete the BIA
process on behalf of the developer should hold qualifications relevant to the
matters being considered. Details of these qualifications/accreditation should be
submitted as part of the BIA.
DCC Basement Development Guidance Document Version 1.0
37
6.0 Assessment of Basement Construction Potential Impacts
6.1 Introduction
The BIA toolkit gives further guidance with regard to the site investigation stage of the
BIA. This section comprises the following set of methods and techniques to be used for
the site investigation and study;
calculation methods and tools,
reference literature
information sources
applicable standards and best practice guidance
A competent consultant or site investigation contractor should be well aware of these as
well as being experienced and knowledgeable in their use. The following sections draw
attention to particular issues which should be borne in mind by a developer when
specifying an investigation and by DCC when reviewing the output from an investigation.
6.2 Site investigation
Site investigation required for a BIA may include several parts, including desk study,
intrusive investigation, monitoring, reporting and interpretation. This section outlines
further guidance to Section 5.4 with regard to completing the different parts of a site
investigation.
6.2.1 Desk Study;
Phase 1 of a site investigation is usually a desk study, which is the collation and
review of information already available about the site. The desk study need not
be restricted to the site boundary; indeed the desk study is the right place to
present information on the wider interaction between the development and its
environs.
The desk study does not involve site works, but will usually include a visual
inspection or walkover of the site and its surrounding area. Some sources of
hydrogeological information for a desk study are listed in Section 6.5. Some of
the desk study information may have already been gathered at the screening and
scoping stage.
6.2.2 Intrusive testing (boreholes and trial pits);
The next phase(s) of site investigation involves subsurface inspection of the
ground to determine the soil types and soil properties at the site and entails
drilling boreholes and/or excavation of trial pits. The driver for carrying out an
intrusive investigation is usually the developer’s or client’s civil or structural
engineer, and the information collected may be no more than what the engineer
needs for the structural design of the building in accordance with the relevant
Building Regulations. In recent years the scope of a standard site investigation
has been enlarged to include inspection for contamination and also the
acquisition of information to support drainage design, but it remains substantially
focused on the needs of the building designer. This section is intended to provide
DCC Basement Development Guidance Document Version 1.0
38
guidance on expanding the extent of an intrusive investigation to ensure that the
data collected will be appropriate to later allow the impacts of the basement to
be determined with respect to the matters of concern identified in this study.
The intrusive part of a site investigation is usually carried out only within the
boundaries of the proposed development, because that is all the developer or his
client has access to. However, groundwater conditions and environmental factors
outside the site boundaries can have a significant effect on conditions inside the
boundaries. Also, a development can have a potentially significant effect beyond
the site boundary. A standard investigation carried out for geotechnical and
structural design purposes does not necessarily address these collateral factors.
Intrusive testing beyond the site boundary is only possible with the consent of
adjacent landowners. Where permission is given to investigate beyond the site
boundary, the investigation should be extended accordingly and appropriate
testing of the ground should be undertaken to address the identified relevant
matters of concern. Where permission is not given to investigate beyond the site
boundary, the undetermined ground conditions beyond the site boundary should
be identified as a risk in the impact assessment and mitigated against accordingly.
Any site investigation works, and any subsequent basement construction, should
undertake a duty of care to prevent any damage to neighbouring properties,
infrastructure, ponds etc.
The detailed scope of the intrusive testing phase(s) (the “ground investigation”)
of a site investigation will depend upon the nature of the proposed development
and the particular site conditions. Guidance can be found in many readily-
accessed publications. Many of the problems which may be encountered in
attempting to interpret the results of a site investigation have quite simple and
avoidable causes; advice on some of the most common is given below:
For basements beneath existing houses and those in gardens, intrusive
investigation may be required.
Boreholes or trial pits should extend to a depth at least 3 metres below
that of the proposed basement and foundation excavations and typically
further into the rock if possible, to assess the underlying soil that may
affect or be affected by, for example, the loads from the building.
Construction design and methods for boreholes and trial pits should be
specified to ensure that information can be obtained to assess the
matters of concern described in the scoping stage of the BIA. All borehole
drilling and trial pits will be supervised, directed and logged by suitably
qualified professionals to obtain the best relevant information. These
professionals on site can adjust the drilling methodology and focus of
attention in the light of the findings as they emerge, in order to obtain
the appropriate samples and information with detail extent to reflect the
scale of the development.
For proposed basements beneath an existing house, it may be necessary
to position boreholes / trial pits beyond the footprint of the proposed
basement.
DCC Basement Development Guidance Document Version 1.0
39
The location of site investigation boreholes adopted for groundwater
monitoring, groundwater dewatering boreholes and groundwater
recharge boreholes should be such that monitoring can continue both
during and after construction works have taken place. Groundwater
monitoring shall be required before, during and after construction for a
duration determined by the findings of the BIA and the conditions of a
planning permission.
A minimum of four boreholes or trial pits (converted to groundwater
monitoring boreholes) is usually required in order to determine the
groundwater flow direction. For larger plots more locations will be
needed.
The direction of flow of groundwater can be determined from
measurement of the elevation of the water surface at four points;
The water table rises and falls seasonally. Broadly speaking, it will be
highest (closest to the surface) from December to April, and lowest at the
end of September to middle of October.
All data should be referenced to a common geographic coordinate
system, and the reference given to an appropriate level of resolution. A
six-digit OS grid reference is only accurate to 100m which is not sufficient
when an individual dwelling plot is being considered, and in that case the
location of features should be quoted to eight digits or better. Maps at
scales of larger than 1:10,000 are of little use for site assessment and
1:1,250 plans should be used.
Elevation data (including water levels, the observed increased inflows of
water during drilling and soil and lithological changes in boreholes and
trial pits) should be quoted with reference to Malin Head Ordnance
Datum. This allows sub-surface data to be correlated with topographic
data, which is related to OD.
Borehole numbering can be a source of confusion. A unique numbering
scheme should allow the inclusion of extra boreholes; it should be as
informative as reasonably possible. Most importantly, the numbering
scheme should not be changed or boreholes re-numbered.
6.2.3 Monitoring;
Hydrogeological processes are subject to seasonal and longer-term cyclical
influences. Measurements taken at one particular time may not indicate how
conditions might be in a month or six months from that time. The effect of a
change in conditions, such as the construction of a basement, may be marked at
first but reduce with time as the effect of the disturbance dissipates – or the
reverse might occur, with a gradual increase in cumulative effects. Monitoring of
groundwater levels over a period of time is therefore necessary. The frequency
of measurement and duration of monitoring must be chosen with reference to
the specific effect which is being investigated. For example, if the matter of
concern is the potential for groundwater flooding, measurement is best taken
during the period of the year when groundwater levels are naturally at their
DCC Basement Development Guidance Document Version 1.0
40
highest (March or April). If the impact being considered is related to increased
disposal of rainfall to the ground, a measurement should be taken frequently, e.g.
daily, during periods of contrasting rainfall intensity.
Rainfall and tide fluctuations should be monitored for comparison with
groundwater levels. This may be through on-site monitoring and/or acquisition
of external third-party weather station data (if a nearby weather station
representative of the site conditions is available). Further information on data
sources is included in Section 6.5.
It may take some time, hours or several days, for water levels in newly installed
boreholes to stabilise and reach equilibrium with the surrounding groundwater
system. Appropriate efforts to accurately record groundwater levels and
groundwater movement should be undertaken, recorded in the BIA and
incorporated into the building design and the “Construction Management Plan”.
Dependent on the location, extent and nature of the proposed development,
recording and monitoring of groundwater flow/level for a full “hydrological year”,
in order to establish an accurate seasonal baseline, may be required.
If the applicant is successful and construction works commence, groundwater
monitoring is required to continue throughout the construction phase of a
project and for a minimum of one full hydrological year following completion or
such time as approved by DCC and/or as specified in the planning decision. This
is to be undertaken by the Developer to demonstrate and quantify the impacts
associated with a proposed development. All associated costs with groundwater
monitoring throughout the different phases are to be covered by the
Applicant/Developer.
6.2.4 Site investigation report
The Site Investigation Report will consist of a factual description of the work
carried out and an interpretation of this information.
Intrusive site investigation techniques are used to characterise the
hydrogeological and engineering properties of the subsurface below the site for
the purposes of engineering design. The results of the site investigation are
compiled into the first part of the site investigation report, by suitably qualified
personnel.
Details of the ground conditions, driller’s logs, geology and groundwater
conditions will be provided in the factual report. The report will contain details
and results of tests undertaken during the work and the results of laboratory
analyses of soil, rock and water.
A factual report will contain no interpretation and as such will generally
necessitate specialist knowledge to interpret the data contained in the report.
6.2.5 Interpretative report;
The interpretative part of the Site Investigation report will comprise three parts:
an interpretation of the detailed site soils and geology
an interpretation of the geotechnical properties of the ground
DCC Basement Development Guidance Document Version 1.0
41
an engineering and hydrogeological interpretation of the
implications of the ground conditions for the development project.
The interpretative part of the report will bring together the data from the desk
study and the findings of the site investigation. Production of a conceptual
ground model at the site along with expected geotechnical and hydrogeological
properties for each layer, lens or zone will be included with the interpretative
report.
The interpretations will assess the significance of the interpreted ground
conditions and any geological or other hazards identified in relation to the
proposed development. The level of interpretation will be related to the type and
size of the development however it may include a discussion on the type of
foundations, the need for ground treatment or piling, likely settlements,
groundwater control and expedients necessary to deal with the site problems.
For large construction projects additional reports may be necessary including
detailed geotechnical design based on the interpretive report however these
reports would normally form part of the design process as part of the project.
6.3 Extent of Basement and Site Dewatering & Recharge
The extent and design of a proposed basement should take account of the DCC Basement
Policy requirements to undertake adequate site investigation and continuous monitoring
(boreholes etc.) throughout construction and post the construction phase. Provision for
de-watering of the excavation during the construction phase is likely to be required and
as such a location for recharge of groundwater needs to be incorporated within the site
boundary. The location(s) of a groundwater recharge point(s) should be accounted for at
the basement design stage and the location should be included as part of the construction
methodology section of the BIA submission, taking into account and with reference to
the local site geology, hydrogeology, ground conditions, development extent and site
boundary etc. Calculations should be provided as part of the BIA demonstrating the
expected level of groundwater discharge and expected recharge capacity to back to the
groundwater (within the site boundary) if this is necessary or possible.
As outlined in Section 5.5.6 an impact assessment of the effect of dewatering and then
ceasing dewatering and the water-table returning to its natural level needs to be
assessed, understood and included as part of the BIA. Such water-table fluctuations may
have a negative impact on the stability of adjacent lands or structures.
6.4 Calculation Methods and Tools
It may be necessary to perform calculations on the data collected during intrusive
investigation and monitoring phases of site investigation in order to derive parameters,
for example hydraulic conductivity, or to estimate ground responses to certain effects,
for example groundwater level response to dewatering.
Appropriate methods should be used in the derivation of technical parameters. Any
method used should be referenced, and a source given. Calculations should be checked
and approved.
DCC Basement Development Guidance Document Version 1.0
42
Standard calculation methods should be used where possible. Some methods of
calculation are given in Construction Industry Research and Information Association
(CIRIA) guides and in BS and EN standards. However, when using these guides and
standards, account should be taken should of fracture controlled groundwater flow found
in the limestone bedrock below Dublin City.
6.5 Sources of Information
In addition to published literature available from libraries and via the internet, statutory
authorities and agencies hold information which is relevant to the hydrogeology and
hydrology of the Dublin area. Some of the principal sources are listed below. Developers
and their consultants should consult these sources when preparing their BIA`s;
Irish Geological Survey
o Bedrock Geology map Sheet 16
o Geotechnical database site and borehole Records
o Previous site investigation reports
o Groundwater Well records
The Ordnance Survey Map
Water Framework Directive (2000/60/EC). The Water Framework
Directive (WFD) establishes a framework for the protection,
improvement and sustainable use of all water environments;
The Construction Industry Research and Information Association
(CIRIA) Environmental Good Practice on Site (C502) (1999). C502
provides guidance on how to avoid causing environmental damage
when on a construction site
CIRIA Control of Water Pollution from Construction Sites (C532)
(2001). C532 provides guidance on how to plan and manage
construction projects to control water pollution.
• The Environment Protection Agency (EPA)
o Licensed abstractions
o River flow data
o Statutorily protected sites of ecological interest
o Surface water quality data
• Meteorological Office (Met Office) & Dublin City Council
o Rainfall data
o River/Estuary Levels
6.6 Standards and Best Practice Guidance
Site investigation consultants, specialists and contractors are expected to operate quality
management systems, preferably integrating health, safety, quality and environment
systems which are accredited to recognised European or Irish Standards. It is particularly
important that soil and water testing laboratories are INAB accredited to provide
assurance of the validity of test results.
DCC Basement Development Guidance Document Version 1.0
43
The site investigation should be specified and supervised by suitable qualified person/s
(see Section and 5.6 and Section 6.2). The person/s (the contractor) undertaking the site
investigation should be experienced and competent in the works being undertaken.
Intrusive ground testing (e.g. boreholes and trial pits) should be specified in accordance
with Site Investigation best practice. Guidance on geotechnical desk studies is available
from the Geotechnical Society of Ireland. Guidance on groundwater and borehole design
and construction can be found in the Institute of Geologists of Ireland Water Well
Guidelines (2007).
Specific advice can also be found in publications from British Standards (BS5930 and
BS10175), AGS (2000), Eurocode 7 [50], Ciria C515, and in geotechnical texts (such as
Simons et al, 2002). Guidance on good practice and procedures in Environmental Impact
Assessment are also relevant to the planning and execution of a BIA.
7.0 Planning Authority Assessment of BIA
7.1 Audit of information supplied
The BIA should be submitted with the planning application so that the Planning Authority
has all the information necessary to support decision making.
The assessment by DCC Planning Authority of the information submitted in a BIA is
essentially a process of auditing the submission against the criteria given in Section 6 to
ensure the Development achieves the policy requirements as outlined in Section1.2. The
objective of the process should be that the developer will have been required, under the
powers enshrined in DCC Basement Policy, to consider such factors as the incremental
contribution of the proposed scheme to the cumulative impact of all basement
developments in the relevant locality. The adequacy of the information provided and
assessed within BIA should be assured through proper scoping and the professional
competence of the contractor/consultant.
The audit stage of the process, as with the earlier stages, has much in common with the
corresponding step in the EIA process.
The process will be based on reviewing the BIA approach undertaken by the Developer.
It shall follow the approach recommended in this report and should include the following:
Check qualifications / credentials of author
Thorough review of scoping undertaken in the BIA
Does the description of the proposed development include all aspects
of temporary and permanent works which might impact upon
geology, hydrogeology and hydrology?
Have the appropriate issues been investigated? This includes
assessment of impacts with respect to the DCC Basement Policy
including land stability, hydrology, hydrogeology etc.?
Is the scale of any included maps appropriate? That is, does the map
show the whole of the relevant area of study and does it show
sufficient detail inside and outside the site?
DCC Basement Development Guidance Document Version 1.0
44
Have the issues been investigated using EIA methodology? (Section 5)
Has the need for mitigation been considered and are appropriate
mitigation methods incorporated in the scheme? (Section 5)
Has the need for monitoring been addressed and is the proposed
monitoring and analysis of data before, during and after construction
sufficient and adequate? (Section 6.2.3)
Have the residual (after mitigation) impacts been clearly identified?
Is there a proposal for continuous monitoring of impacts been
included?
Where the information listed above, and any other pertinent details relating to the
development, is not provided to an adequate standard within an application, the Planning
Authority may not validate the application, or may refuse applications due to lack of
information, or may require further information to finalise its assessment.
The Planning Applicant is required to review and submit all items required in the BIA
Policy and Guidance Documents which are briefly summarised as per the BIA checklist,
included in Appendix A.
7.2 Basement Audit Categorisation
The size, scale and nature of basement development are to be split into three categories,
A, B and C. The level of detail contained within a BIA for a particular development shall
be dependent on which category the development fits into. The assigned/referenced
category for a development should be appropriate to the proposed development and the
scale of the potential impacts identified during the scoping and site investigation stages.
Category A
Residential or commercial development with single storey basement where the Scoping
Stage of the Basement Impact Assessment indicates no matters of concern which need
further investigation.
Submitted BIA anticipates no significant impact relating to:
land stability or impacts, buildings or infrastructure;
groundwater flow or surface water flooding and underground tunnels
Category B
Residential single basement or commercial development with single or double basement
where the Scoping Stage of the Basement Impact Assessment identifies matters of
concern which need further investigation.
Submitted BIA anticipates potential impact:
to a listed building;
on land stability;
on groundwater flow;
on potential for surface water flooding ;
on underground tunnels or infrastructure; and
cumulative impact on ground stability and the water environment
DCC Basement Development Guidance Document Version 1.0
45
Category C
Exceptional development (in terms of geometry, area, depth, location/position or
complexity) which may be a single or double basement with potential complications.
Submitted BIA anticipates potential for significant impact:
to a listed building;
on other buildings and or with land stability issues;
to groundwater flow and potential for surface water flooding ;
underground tunnels or infrastructure; cumulative basement
impacts;
relating to significant technical issues raised by third parties.
7.6 Updating the baseline
If the scheme is granted planning consent, and if it proceeds to construction, the baseline
will have changed for potential future applications. The Developer is required to submit
a copy of their basement as-built drawings to DCC for future reference.
7.7 Future Monitoring of Groundwater Levels to verify BIA Assumptions
It is imperative that the Developer continues to monitor groundwater levels and other
environmental parameters to ensure that the as-constructed development reflects the
residual impacts identified in the BIA.
8.0 Related DCC Corporate Policies
In addition to the requirements outlined earlier in this document Developers of basement
structures are required to take account of other existing DCC policies where appropriate.
Some of the existing polices which are likely to be applicable to basement construction are
briefly referenced in this Section. It shall be the responsibility of the Developer to identify and
comply with these and any other relevant DCC/statutory policies.
8.1 DCC Roads Requirement
The Planning Applicant should take account of the existing DCC Roadworks Control and
DCC Road Maintenance requirements where works in public spaces (roads, footpath etc.)
are required.
8.2 DCC Ground Anchor Installation Licence (GAIL)
If as part of the proposed development it is intended to install ground anchors (or similar)
beneath a public space the applicant is required to complete a Ground Anchor Installation
Licence (GAIL) application. This application is required to be submitted as part of the BIA.
DCC Basement Development Guidance Document Version 1.0
46
8.3 DCC Pollution Control
No discharge of trade effluent (groundwater discharged during construction) shall take
place unless under and in accordance with a licence to be issued by the relevant
Sanitary Authority.
8.4 DCC Traffic Management
As part of a BIA submission the Planning Authority shall require a “Transport
Assessment”. A “Transport Assessment” is a comprehensive review of all the potential
transport impacts of a proposed development. In the case of developments with
significant vehicular trip generation potential and attraction rates, applicants will be
required to submit a detailed assessment of the transportation systems provided and the
impact of the proposed development on the surrounding environment and
transportation network through the submission of a Transport Assessment. Details of the
requirements for a Traffic Assessment can be seen in the Dublin City Development Plan.
Details relating to the construction phase of the proposed development is an extremely
important element of the “Traffic Assessment” and should be included as part of the BIA
submission.”
8.5 DCC Waste Management
The following conditions will be considered by DCC Waste Regulations Section for
inclusion into a Construction & Demolition Waste Management Plan when a submission
is requested by the Planning Office. The conditions to be inserted in individual planning
permissions may vary for each. A developer should make themselves aware of all
potential conditions and plan for the environmental sound management of any wastes
that may be generated by the proposed development.
8.5.1 Provide a detailed account of potential wastes arising on site including waste
description, quantities and corresponding List of Waste (LoW) code, previously
known as the EWC code.
8.5.2 A full list of authorised waste collection permit holders and their NWCPO
numbers, including any sub-contractors to be used to transport waste off site.
8.5.3 A full list of destination waste facilities that the authorised waste collection
holders intend to use.
8.5.4 Provide letters on headed paper signed by a relevant competent person from
the destination waste facilities confirming acceptance of material and agreed
tonnages to be received.
8.5.5 Contact details for the site manager (email and mobile phone number).
8.5.6 Ensure, and confirm, that the waste dockets used are specific to
the authorised waste collector collecting each waste load, subcontractors cannot
move waste under another waste carries documentation.
8.5.7 Please be aware that crushing concrete onsite is classified as a waste activity
requiring authorisation under the Waste Management (Facility Permit and
Registration) Regulations 2007 as amended. Any mobile plant brought onto the
site for any waste activity must be covered by a valid Waste Facility Permit
(WFP)/Certificate of Registration (COR). The developer and/or site owner is liable
DCC Basement Development Guidance Document Version 1.0
47
to ensure the necessary WFP/COR authorisations are in place. Where an
application for a WFP/COR will be required, a minimum of 6 weeks should be
allowed. In addition, the waste activity must be outlined in the planning decision.
8.5.8 Laboratory testing of any soil to be removed off site will be required prior to its
removal. A waste characterisation report and laboratory results will be required
in advance of a planning decision.
8.5.9 An Invasive Species survey will be required, if any invasive plant species are
identified on the site, an Invasive Species Management plan will be required.
8.5.10 An Asbestos Survey must be carried out prior to demolition works taking place. If
asbestos is identified, an Asbestos Management Plan will be required.
8.5.11 A live log of all waste movements must be available in digital format for
inspection by Dublin City Council personnel upon request.
8.5.10 Where it is intended to reuse material on another site, a notification must be
submitted to the Environmental Protection Agency (EPA) in accordance with
Article 27 of the European Communities (Waste Directive) Regulations 2011. The
EPA determination should be obtained prior to the commencement of any works.
8.5.11 Each site owner is responsible for identifying their environmental liabilities in
accordance with the Environmental Liabilities Regulations 2008. The developer
and site owner will remain liable throughout the storage, transport and
disposal/recovery for the environmentally sound management of any wastes
produced during the development works.
8.6 DCC Drainage Planning
The DCC Drainage Department shall review each application bearing in mind proposals
for some important surface water drainage design aspects in relation to (amongst
others);
Sustainable Urban Drainage Systems (SUDS)
Reference to Greater Dublin Strategic Drainage Study (GDSDS)
Greater Dublin Regional Code of Practice for Drainage Works
DCC Strategic Flood Risk Assessment (SFRA)
8.7 Noise, Air Quality and Vibration
In order to regulate noise, air quality and vibration DCC have developed a “Construction
and Demolition Good Practice Guide” (Appendix E). The developer is requested to adhere
to these guidelines with proposals reflected in the project Construction Management
Plan, to be submitted as part of the BIA.
Although it is conceivable for ground-borne vibration from construction projects to
cause building damage, the vibration from construction activities is almost never of
sufficient amplitude to cause even minor cosmetic damage to buildings. The primary
concern is that the vibration can be intrusive and annoying to building occupants. Most
construction vibration is in the mid- to upper- frequency range, and therefore has a
lower potential for structural damage.
DCC Basement Development Guidance Document Version 1.0
48
DCC has guidelines for vibration levels from construction related to their activities, and
recommends that the maximum peak-particle-velocity levels remain below 1 mm per
second at the nearest structures.
9.0 Glossary of Terms
Aquifer
A body of permeable rock or overburden, or impermeable rock with open interconnected
fractures or conduits, that is capable of storing and transmitting water.
Archaeology
The study of past societies of any period through the material remains left by those societies
and the evidence of their environment. The material things (objects, monuments, sites,
features, deposits) which archaeology uses to study past societies are referred to as
‘archaeological heritage’.
Baseline Survey
A description of the existing environment against which future changes can be measured.
Ecology
The study of the relationships between living organisms and between organisms and their
environment (especially animal and plant communities), their energy flows and their
interactions with their surroundings.
Effluent
Any liquid discharged from a source into the environment.
Environmental Impact Assessment – EIA
The process of examining the environmental effects of development - from consideration of
environmental aspects at design stage through to preparation of an Environmental Impact
Statement, evaluation of the EIS by a competent authority and the subsequent decision as to
whether the development should be permitted to proceed, also encompassing public response
to that decision.
Emission
a) An emission into the atmosphere of a pollutant within the meaning of the Air
Pollution Act 1987.
b) A discharge of polluting matter, sewage effluent or trade effluent within the
meaning of the Local Government (Water Pollution) Act 1977 to waters or sewers
within the meaning of that Act.
c) Disposal of waste, or
d) Noise.
EPA (see section EPA)
The Environmental Protection Agency.
DCC Basement Development Guidance Document Version 1.0
49
Geology
The science of the earth, including the composition, structure and origin of its rocks.
Habitat
The area in which an organism or group of organisms live.
Hydrology and Hydrogeology
These applied sciences are concerned with the occurrence and circulation of water in all its
phases and modes, and the relationship of these to man. Hydrology particularly relates to
surface water, and Hydrogeology particularly relates to subsurface water.
Impact
The degree of change in an environment resulting from a development.
Impact Anticipation
Using knowledge of both the development and the receiving environment to predict the likely
effects and consequences.
Impact Avoidance
The modification of project decisions (about site location or design for example) having regard
to predictions about potentially adverse environmental effects.
Infrastructure
The basic structure, framework or system which supports the operation of a development
project for example, installations such as roads and sewers which are necessary to support
development projects.
Land-use
The activities which take place within a given area of space.
"Likely Effects / Impacts"
The effects that are proposed to take place - based on an understanding of the interaction of
the proposed development and the receiving environment".
Methodology
The specific approach or techniques used to analyse impacts or describe environments.
Mitigation
Measures designed to avoid, reduce, remedy or compensate for impacts.
Mitigation by Remedy
Impact Avoidance When no change is caused.
Impact Reduction
Where the significance of adverse impacts is lessened.
Impact Remedy
When an adverse effect is replaced with a more acceptable effect.
DCC Basement Development Guidance Document Version 1.0
50
Mitigation Measures
The means by which decisions about a proposed development are modified to avoid, reduce or
remedy the adverse environmental effects that are identified.
Monitoring
The repetitive and continued observation, measurement, analysis and evaluation of
environmental data to follow changes over a period of time, to assess natural conditions, the
impact of activities and the efficiency of control measures.
Pollution
Any release to the environment which has a subsequent adverse effect on the environment or
man.
Precautionary Principle
The theory that the absence of complete information should not preclude precautionary action
to mitigate the risk of significant harm to the environment.
Reasonably Foreseen
A working assumption about the future that assumes that a project will be developed as
planned and used within a receiving environment that will change in accordance with currently
evident trends. It will include a consideration of the likelihood and consequences of abnormal
occurrences - such as accidents.
Receptor
Any element in the environment which is subject to impacts.
Residual impacts
Those impacts that remain following the implementation of the mitigation measures proposed
Risk Assessment
An analytical study of the probabilities and magnitude of harm to human health or the
environment associated with a physical or chemical agent, activity or occurrence.
Scoping
The process of identifying the significant issues which should be addressed by a particular
Environmental Impact Assessment.
Screening
The process of assessing the requirement of a project to be subject to Environmental Impact
Assessment based on project type and scale and on the significance or environmental sensitivity
of the receiving environment.
Sensitivity
The potential of a receptor to be significantly changed.
Significance
The sensitivity of a receiving environment to change or the consequence of change for the
receiving environment.
DCC Basement Development Guidance Document Version 1.0
51
Sustainable Development
Defined by the Brundtland Commission 1987 "Development that meets the needs of the
present without comprising the ability of the future generation to meet their own needs".
Threshold
The magnitude of a project which, if exceeded, will trigger the requirement for an
Environmental Impact Assessment to be carried out.
10. Glossary of Impacts
Quality of Impacts
Positive Impact
A change which improves the quality of the environment (for example, by increasing species
diversity; or the improving reproductive capacity of an ecosystem, or removing nuisances or
improving amenities).
Neutral Impact
A change which does not affect the quality of the environment.
Negative Impact
A change which reduces the quality of the environment (for example, lessening species diversity
or diminishing the reproductive capacity of an ecosystem; or damaging health or property or by
causing nuisance).
Significance of Impacts
Imperceptible Impact
An impact capable of measurement but without noticeable consequences.
Slight Impact
An impact which causes noticeable changes in the character of the environment without
affecting its sensitivities.
Moderate Impact
An impact that alters the character of the environment in a manner that is consistent with
existing and emerging trends.
Significant Impact
An impact which, by its character, magnitude, duration or intensity alters a sensitive aspect of
the environment.
Profound Impact
An impact which obliterates sensitive characteristics.
Duration of Impacts
Short-term Impact
Impact lasting one to seven years.
DCC Basement Development Guidance Document Version 1.0
52
Medium-term Impact
Impact lasting seven to fifteen years.
Long-term Impact
Impact lasting fifteen to sixty years.
Permanent Impact
Impact lasting over sixty years.
Temporary Impact
Impact lasting for one year or less.
Types of Impacts
Cumulative Impact
The addition of many small impacts to create one larger, more significant, impact.
‘Do Nothing Impact’
The environment as it would be in the future should no development of any kind be carried out.
Indeterminable Impact
When the full consequences of a change in the environment cannot be described.
Irreversible Impact
When the character, distinctiveness, diversity or reproductive capacity of an environment is
permanently lost.
Residual Impact
The degree of environmental change that will occur after the proposed mitigation measures
have taken effect.
Synergistic Impact
Where the resultant impact is of greater significance than the sum of its constituents.
`Worst case’ Impact
The impacts arising from a development in the case where mitigation measures substantially
fail.
11. References
Environmental Protection Agency, Guidelines on the information to be contained in
environmental impact statements, 2002.
London Borough of Camden, Camden Planning Guidance, Basements and Lightwells, July 2015
London Borough of Camden (Ove Arup & Partners Ltd), Camden geological, hydrogeological and
hydrological study, Guidance for subterranean development, November 2010
DCC Basement Development Guidance Document Version 1.0
53
Appendix A
– Items to be submitted and reviewed as part of a Basement Impact Assessment
DCC Basement Development Guidance Document Version 1.0
54
SECTION 1 – Basement Impact Assessment (BIA) Applicant and BIA Author Details – completed by Applicant
Before completing this form, please read the accompanying documents, “DCC Basement Development
Policy document" and the “DCC Basement Development Guidance document”.
This form is to be completed in BLOCK LETTERS:
Planning Ref. for Development: _____________________________________________
Development Address: _____________________________________________
Development Description: _____________________________________________
_____________________________________________
Applicant Name: _________________________________________________
Applicant Address: _________________________________________________
Applicant Contact Name: _________________________________________________
Applicant Contact Phone Number: Mobile; ________________________________
Office; _________________________________
Applicant Contact E-Mail: _________________________________________________
BIA Author Company: _______________________________________________
BIA Author Contact Name: _________________________________________________
BIA Author Contact Ph. No: Mobile; ________________________________
Office; _________________________________
BIA Author E-Mail: _________________________________________________
Note: Basement Impact Assessments are required to adhere to the “DCC Basement Development
Policy document” and are to be undertaken in accordance with the “DCC Basement Development
Guidance document”.
DCC Basement Development Guidance Document Version 1.0
55
SECTION 2 – Basement Impact Assessment (BIA) Submission Check Sheet - completed by Applicant:
Items provided for Basement Impact Assessment (BIA)1
Item provided Yes, No or N/A2
Name of BIA document/appendix in which information is contained and/or comment
1 Description of proposed development. Choose an item.
2
Plan showing boundary of development
including any land required temporarily
during construction.
Choose an item.
3
Plans, maps and or photographs to show
location of basement relative to
surrounding structures.
Choose an item.
4
Plans, maps and or photographs to show
topography of surrounding area with any
nearby watercourses/waterbodies
including consideration of the relevant
maps in the FRA
Choose an item.
5 Plans and sections to show foundation
details of adjacent structures.
Choose an item.
6 Plans and sections to show layout and
dimensions of proposed basement.
Choose an item.
7 Programme for enabling works,
construction and restoration.
Choose an item.
8
Identification of potential risks to land
stability (including surrounding structures
and infrastructure), and surface and
groundwater flooding.
Choose an item.
DCC Basement Development Guidance Document Version 1.0
56
9
Assessment of impact of potential risks on
neighbouring properties and surface and
groundwater.
Choose an item.
10 Identification of significant adverse
impacts.
Choose an item.
11 Evidence of consultation with neighbours. Choose an item.
12
Ground Investigation Report and
Conceptual Site Model including
- Desktop study
- exploratory hole records
- results from monitoring the local groundwater regime
- confirmation of baseline conditions
- factual site investigation report
Choose an item.
13 Ground Movement Assessment (GMA). Choose an item.
14 Plans, drawings, reports to show extent of
affected area.
Choose an item.
15
Specific mitigation measures to reduce,
avoid or offset significant adverse
impacts.
Choose an item.
16
Construction Sequence Methodology
(CSM) referring to site investigation and
containing basement, floor and roof
plans, sections (all views), sequence of
construction and temporary works.
Choose an item.
17 Proposals for monitoring during
construction.
Choose an item.
18
Confirmatory and reasoned statement
identifying likely damage to nearby
properties according to Burland Scale
Choose an item.
19
Confirmatory and reasoned statement
with supporting evidence that the
structural stability of the building and
neighbouring properties will be
Choose an item.
DCC Basement Development Guidance Document Version 1.0
57
maintained (by reference to BIA, Ground
Movement Assessment and Construction
Sequence Methodology), including
consideration of cumulative effects.
20
Confirmatory and reasoned statement
with supporting evidence that there will
be no adverse effects on drainage or run-
off and no damage to the water
environment (by reference to ground
investigation, BIA and CSM), including
consideration of cumulative effects.
Choose an item.
21 Identification of areas that require further
investigation.
Choose an item.
22 Non-technical summary for each stage of
BIA.
Choose an item.
Additional BIA components (added during
Review/Audit)
Item
provided
Yes , No or N/A2 Comment
Notes:
1 It is assumed that consideration of architectural character, impacts on archaeology, amenity and
other matters which are not covered by this checklist shall be incorporated elsewhere within the
applicant`s submission.
2 Where response is ‘no’ or ‘N/A’, an explanation is required in the Comment section.
DCC Basement Development Guidance Document Version 1.0
58
Appendix B
– Ground Anchor Installation Licence (GAIL) Application Form
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
59
SECTION 1 – Ground Anchor Installation Licence Application Form Applicant Details
Before completing this form, please read the accompanying document "Ground Anchor Installation
Licence – Guidance Document"
This form is to be completed in BLOCK LETTERS:
Applicant Name: Click or tap here to enter text.
Applicant Address: Click or tap here to enter text.
Applicant Contact Name: Click or tap here to enter text.
Applicant Contact Phone Number: Mobile; Click or tap here to enter text.
Office; Click or tap here to enter text.
Applicant Contact E-Mail: Click or tap here to enter text.
Location of Anchor Installation: Click or tap here to enter text.
(Road / Street & Building Number)
Planning Ref. for Development: Click or tap here to enter text.
Ground Anchor/Structural Designer: Click or tap here to enter text.
Ground Anchor Designer Contact: Click or tap here to enter text.
Ground Anchor Designer Contact Ph. No: Click or tap here to enter text.
Ground Anchor Designer E-Mail: Click or tap here to enter text.
Number of Anchors to be installed: Click or tap here to enter text.
Period for which Licence is required: Click or tap here to enter text.
Public Liability Insurer & Policy No.: Click or tap here to enter text.
Minimum cover of €6.5 million, with specific indemnity to Dublin City Council
Note: The installation of a ground anchor into/beneath a public road/path without a Ground Anchor
Installation Licence is not permitted. Under Section 13 of the Roads Act (1993), any person to do so
shall be guilty of an offence.
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
60
SECTION 2 – Ground Anchor Installation Licence Application Form Application Check Sheet
What must be submitted with a Ground Anchor Installation Licence Application Form?
The following items are required to be included as part of the GAIL application. An incomplete
application will result in delays. Please include and tick as appropriate. The Applicant is referred
throughout to a more detailed list of requirements as included in the "Ground Anchor Installation
Licence – Guidance Document".
Application Procedure for Installation of Ground Anchors: Submitted by
Applicant
Completed GAIL Application form (Section 1 & 2), with fee included and signed DECLARATION (as
per para. 3.1 & 3.2 of GAIL Guidance Document)
Choose an
item.
Details of anchor type, materials proposed, length of time required, detailed anchor drawings in plan
and section etc. (as per para. 3.3 & 3.4 of GAIL Guidance Document)
Choose an
item.
Detailed Section & Plan with location of anchors and existing utilities identified (as per para. 3.5 of
GAIL Guidance Document)
Choose an
item.
Anchor designer’s Risk Assessment Choose an
item.
Certification provided by Anchor Designer identifying available utility corridor (as per para. 3.6 of
GAIL Guidance Document)
Choose an
item.
Baseline survey and proposed monitoring system throughout “anchor support period” (as per para.
3.7 of GAIL Guidance Document)
Choose an
item.
Utilities have been contacted by the Applicant in advance (as per para. 3.8 of GAIL Guidance
Document)
Choose an
item.
Safety Statement and MS submitted, which incorporates the proposed anchor installation works and
which complies with all relevant Health & Safety Legislation (as per para. 3.10 & 3.11 of GAIL
Guidance Document)
Choose an
item.
Bond enclosed (rate per anchor, as per para. 3.13 of GAIL Guidance Document) Choose an
item.
Application only relates to installation of anchors in public domain only (as per para. 3.14 of GAIL
Guidance Document)
Choose an
item.
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
61
All relevant statutory utilities to be advised 7 days in advance of any anchor installation taking place
(as per para. 4.1 of GAIL Guidance Document)
Choose an
item.
Proof of DCC indemnity submitted by Applicant (period from start of works through until one year
after end of “anchor support period” (as per para. 4.2 of GAIL Guidance Document)
Choose an
item.
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
62
SECTION 3 – Ground Anchor Installation Licence Application Form End of Anchor Support Period – Check Sheet
What Must be Submitted at Expiry of “Anchor Support” Period?
At the end of the licensed “anchor support” period (decommissioning of anchors) the following
documentation and submission confirmation is to be submitted to the DCC Road Maintenance
Department. The Applicant is referred to a more detailed list of requirements as included in the
"Ground Anchor Installation Licence – Guidance Document".
Expiry of GAIL Licence (end of “Anchor Support Period): Submitted by
Applicant
Confirmation that DCC Roads Maintenance have been informed of date for
decommissioning of anchors (as per para. 5.2 of GAIL Guidance Document)
Choose an item.
Design Certificate submitted by anchor Designer and signed by Chartered Engineer
confirming that for all anchors installed the entire anchor length is no longer
structurally required and has been de-commissioned and de-stressed (if applicable).
The anchor headblock securely capped or buried
Choose an item.
As constructed detailed drawings are to be provided to DCC Roads Maintenance
Department showing the location and details of installed anchors in plan and in section
with additional information provided for all materials used (as per para. 5.4 of GAIL
Guidance Document)
Choose an item.
Final monitoring survey submitted (as per para. 5.5 of GAIL Guidance Document) Choose an item.
Signature of Applicant: __________________________________ Date: ___________
Print Name of Applicant: ___________________________________
Signature of Anchor Designer: __________________________________ Date: ___________
Print Name of Anchor Designer: ___________________________________
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
63
SECTION 4 – Declaration
I hereby apply for approval for a Ground Anchor Installation Licence (GAIL) and agree to be bound by
the conditions as listed in the "Ground Anchor Installation Licence – Guidance Document", the “GAIL
Application Form” and any specific conditions imposed by Dublin City Council.
I agree to comply with the provisions of the submitted, anchor design, installation methodology and
proposed materials, end of “anchor support period” requirements and submit all documentation, as
per Section 1, 2 & 3 of this application, to the satisfaction of DCC.
This licence pertains only to the installation of ground anchors. Separate discussions requiring the
opening and reinstatement of the public road / footpath / Park Area etc. must be held with and
permissions obtained from the relevant departments of Dublin City Council.
For clarity Section 1, 2 and 4 of this application along with the relevant documentation are to be
submitted 8 weeks prior to the issuing of the Commencement Notice or the commencement of
construction, whichever is the earlier. Section 3 of this form is to be submitted along with the relevant
documentation at the end of the “anchor support period”.
In addition to complying with the requirements of the DCC published “Ground Anchor Installation
Licence – Guidance Document” I also hereby agree to:
Liaise with Dublin City Council’s Roadworks Control Unit in the planning and execution of the
works and to fully comply with the "Directions for the Control and Management of Roadworks
in Dublin City" as issued by them.
Maintain the roadway and/or footpath to the specification of Dublin City Council’s Roads
Maintenance Services all of which is included in the Directions for the Control and
Management of Roadworks in Dublin City.
Lodge the required Licence Fee payable to Dublin City Council with Roads Maintenance
Services, Floor 4, Block 2, Civic Offices, Dublin 8, with the licence application. The licence fee
incorporates both the cost of inspection of anchor installation, removal and associated
administration costs.
Apply for a Road Opening Licence if excavation in the public domain if required.
The GAIL only becomes effective when approved by a representative from DCC Roads
Maintenance Services.
Indemnify and save harmless the Council (with minimum indemnity of €6,500,000.00 for any
one claim in respect of all claims, proceedings, liabilities, losses or expenses of whatever
nature, howsoever arriving in connection with the activities covered by this application.) The
period of cover shall be from the start of the works through until taking back in charge by DCC.
Roads Maintenance Services,
Floor 4, Block 2,
Civic Offices,
Wood Quay, Dublin 8.
Ph. (01) 222 2255
64
Take charge of the defence of any proceedings as aforesaid at the request of the Council.
The applicant must give written notification to the Area Engineer on completion of the works,
at which point an inspection of the works will be carried out and items as per Section 3 of the
GAIL Application are submitted.
Signature of Applicant: __________________________________ Date: ___________
Print Name of Applicant: ___________________________________
Signature of Anchor Designer: __________________________________ Date: ___________
Print Name of Anchor Designer: ___________________________________
For Office Use Only
Total Fee Received: ______________________
Approved: _____________________________ Date: _______________________________
65
Appendix C
– Ground Anchor Installation Licence (GAIL) Guidance Notes
66
Ground Anchor Installation Licence (GAIL) – Guidance Notes:
1. Introduction
Dublin City Council acting in its statutory role as the Roads Authority has decided to establish
standards, protocols and procedures to cover the issuing of licences to third parties who wish to install
ground anchors or similar structural support devices under or within areas, lands, roads, public domain
etc. under the ownership or control of DCC.
These standards, protocols and procedures have been adopted by Order of the City Engineer and are
available to view in full on the Dublin City Council website, together with details of how to apply for
the requisite licence.
2. Standards Specified by Roads Authority
In order to preserve the availability of space under roads for maintenance or installation of existing or
future services the DCC Environment & Transportation (E & T) Department will only consider
applications for the installation of temporary ground anchors (referred to as ‘ground anchors’ in this
guidance document) under areas/lands in its charge. The anchors shall be designed and constructed
as a temporary structural support and only be required to have a structural role for a clearly defined
period (the “anchor support period”). This “anchor support period” is limited to a point in time where
the permanent works are constructed and the structural support provided by ground anchors is no
longer required.
Ground anchors must be capable of being easily broken/cut if required in the future e.g. a Glass Fibre
Reinforced Plastic (GFRP) anchor.
Ground anchors shall be constructed and such measures taken following construction as are required
so that, immediately following the conclusion of the “anchor support period”, normal excavations,
whether by open cut trenches, tunnelling or directional drilling or any other method of excavation can
be carried out safely and without any obstruction or additional risk or cost arising from the presence
of the ground anchors.
3. Application Procedure for Installation of Ground Anchors:
3.1 All applications for a Ground Anchor Installation Licence (GAIL) must be made by the Developer
of the site in whose name the Planning Permission has been granted or their Agent (the
Applicant).
3.2 All Applicants must complete a GAIL Application Form. A minimum fee of €500 is payable with
each application. A separate application must be made for each road affected. If it is proposed
to excavate the road surface a Road Opening Licence Application must be submitted to DCC.
The GAIL application form must be submitted to DCC Roads Maintenance Department 8 weeks
67
prior to the issuing by the Developer of the Commencement Notice or the commencement of
construction, whichever is the earlier.
3.3 Full details of the type of anchor proposed, materials to be used etc., and the length of time the
anchors are required as a structural support are to be submitted as part of the application. If
steel couplers are required to be installed within the anchor bond length the coupler location
should be staggered.
3.4 Accurate and detailed drawings are to be provided showing location of proposed anchors in
plan and in section with XYZ Coordinates of the anchor head, toe, coupling location, top and
base of bonded length and type of bonded length provided.
3.5 Detailed cross section and plan, showing proposed anchors and clearances to existing services
are to be submitted showing:
Location, levels and diameter of all existing services (when required these cross-
sections should be verified on site by trial holes and witnessed by relevant
statutory utility staff. A Road Opening Licence is required for excavation of trial
holes.)
Location and angle of installation of proposed ground anchors and clearances
horizontal and vertical relative to existing services.
Cross sectional area and longitudinal extent, with XYZ coordinates, indicating an
available corridor within the road-space which may be excavated/tunnelled
through if necessary during the period when the anchors are structurally required.
3.6 The Application shall be accompanied by a Certificate, signed by a Chartered Structural Engineer
or Chartered Geotechnical Engineer or appropriately qualified person, stating that the corridor
identified in para. 3.5, above, is available for use by a third party for excavation/tunnelling
purposes during the anchor support period. The Certificate shall confirm that excavation within
this corridor can take place without any impact on the required performance of the anchor.
Contact details of the anchor designer should be provided as part of the application for which
any correspondence relating to a proposed excavation of a public area where anchors are
installed and still structurally required can be directed.
3.7 The applicant is to develop a baseline topographic survey encompassing the public area where
the anchors are proposed to be installed. Subsequent and in addition to the approved baseline
survey the applicant is required to establish a suitable monitoring system which is to be
maintained throughout the course of the “anchor support period”. The survey and monitoring
proposals are required to be submitted to DCC in advance as part of the application process.
3.8 Confirmation by the Applicant that all the relevant Utilities have been contacted and agreement
reached regarding the proposal in advance of license application. Please note that Utility
Providers may have detailed requirements in this regard including submission of a bond and/or
indemnities, supervision of works, etc.
68
3.9 DCC does not accept any responsibility for establishing/verifying the ground conditions in the
public domain. All design information relating to ground conditions located in the public domain
are the responsibility of the Applicant.
3.10 The Applicant is to confirm that that there is a valid Safety Statement in place, which
incorporates the proposed anchor installation works and which complies with all relevant
Health & Safety Legislation. The Safety Statement should identify the relevant parties, their
registered offices and it should be signed by an authorised person, with their name and position
within the company identified.
3.11 A detailed method statement should be submitted demonstrating that an appropriate system
is proposed for installation of the anchors which ensures that there is no negative impact or
disturbance to existing infrastructure / structures / property etc.
3.12 Notwithstanding the submission of details as requested, an application for a Ground Anchor
Installation Licence (GAIL) may be refused, where, in the view of the E&T Department the
installation of ground anchors may have an adverse impact in terms of safety and /or cost on
the maintenance or installation of existing or future services in the road.
3.13 A fee of €1,000 per anchor must be lodged with the DCC Road Maintenance Services as part of
the GAIL application prior to works commencing.
3.14 The Ground Anchor Installation Licence relates only to the public domain and lands/areas under
the ownership or control of DCC. The GAIL does not provide or imply permission to install
ground anchors in any other property.
4. Applicant Requirements during GAIL Period (“anchor support period”):
4.1 All relevant statutory utilities (i.e. services which have been identified as per para. 3.5) are to
be advised 7 days in advance of any anchor installation taking place.
4.2 The Applicant shall Indemnify and save harmless the Roads Authority (with minimum
indemnity of €6,500,000 for any one claim in respect of all claims, proceedings, liabilities, loses
or expenses of whatever nature, howsoever arriving in connection with the activities covered
by this application). The period of cover shall be from the start of the ground anchor installation
works through until one year after Applicant has fully completed installation and
decommissioning of all ground anchors (i.e. one year after expiry of “anchor support period”).
4.3 Any persons wishing to excavate a road where anchors have already been installed and remain
structurally required (as per approved GAIL details) shall be referred by DCC Road Maintenance
Services to the anchor Design Engineer (whose details are submitted as part of the GAIL
application). The anchor Design Engineer is required to assess the risk in undertaking the
proposed excavation works and provide guidance and direction to the relevant party, with no
fee required. This assessment should also be provided to DCC Road Maintenance Services so
that they are aware of the anchor designer`s review of the proposed works.
69
4.4 Drilling logs and anchor design drawings shall be made available to the DCC Road Maintenance
Services upon request. These logs are to include full details in respect of anchors installed
including, installation time, date, location, length, volume of grout used etc. (as per relevant
guidance documents and standards).
4.5 The applicant is required to monitor, record and report to DCC Roads Maintenance Services (or
other relevant DCC department) any ground movement and /or disturbances to the public road
where anchors have been installed. A baseline grid survey should be established in advance of
works taking place, as outlined in para. 3.7. Routine and regular checks of the grid should be
undertaken thereafter, particularly during and directly after drilling has taken place, as per para.
3.7. The installation of an inclinometer may be applicable in certain cases (as advised with
guidance from the anchor Design Engineer or to be installed as required on instruction by Road
Maintenance Services).
5. Expiry of GAIL (end of “anchor support period”):
5.1 Any extension of the Licence is at the discretion of the Roads Authority and will be subject to
an additional application process.
5.2 At the end of the “anchor support period” (strands and/or bars) are to be decommissioned and
de-stressed (if applicable). The DCC Roads Maintenance Department shall be informed 1 week
in advance so that they can attend and witness the process. A Design Certificate is to be
submitted by the Applicant’s anchor Designer confirming that, for all anchors installed, the
entire anchor length is no longer structurally required and has been fully decommissioned and
de-stressed (if applicable). This certificate must be signed by a Chartered Structural Engineer
or Chartered Geotechnical Engineer and submitted to DCC Roads Maintenance.
5.3 Once the cuttable anchor has been decommissioned and any remaining steel strand removed,
the headblock shall be immediately securely capped or buried within the completed structure.
This is to ensure that the redundant anchor pre-stressed free length cannot remove itself in the
event the anchor is cut at a later date. The presence of the headblock is to be confirmed by the
Anchor Designer as part of the Design Certificate.
5.4 As constructed detailed drawings are to be provided to the DCC Roads Maintenance
Department (or other relevant DCC department) showing the location and details of installed
anchors in plan and in section with additional information provided for all materials used.
5.5 Once the anchors have been decommissioned and removed from service a final survey is to be
undertaken (similar to that as detailed in para. 3.7) and submitted to DCC Road Maintenance
Services. This survey is to be submitted within 2 months of the end of the anchor support
period.
5.6 The deposit fee of €1,000 per anchor will only be refunded when all items outlined in this
document have been submitted and are deemed satisfactory to DCC Road Maintenance
Services.
70
Appendix D
– Cumulative Effects of Basement Construction
71
Cumulative Effects of Basement Construction;
The cumulative effect - if any - of several underground developments in a given street could potentially
differ from the impact of the initial single basement. It is therefore appropriate for the Planning
Authority to consider the layout and proximity of existing basements and/or where multiple
basements are proposed. It should again be noted that Appendix D1 is a schematic that assumes a
homogeneous aquifer with isotropic hydrogeological properties;
The shape of the structure in relation to the groundwater flow direction and soil strata
should be considered to assess whether any damming effect could potentially arise.
If the basement is to be constructed perpendicular to the flow of groundwater it shall
have the greatest impact.
Appendix D1 (Scenario B1, B2 and B3) illustrates the principle of groundwater flow
around a single basement structure. The diversion of flow paths around the basement
structure leads to an increase in groundwater levels upstream, and a similar reduction
in groundwater levels downstream.
Appendix D1 (Scenario C1, C2 and C3) demonstrates the effect of several basements
acting cumulatively. Scenario C provides a notional example where a one house width
gap is always present between adjacent basements. Groundwater flows through the
gaps between basement structures and is prevented from passing beneath the houses
with new basements. The effect is an increase in groundwater levels upstream of the
structures, and a decrease downstream.
For hydraulic cut-off structures such as sheet piles, the purpose of which is to form a
barrier to groundwater flow. In the notional case shown in Appendix D1 (Scenario C1,
C2 and C3) the space remaining open between buildings, as a proportion of the
original flow channel, is approximately 40%. The flow velocity through the narrowed
channel will be higher than before, which might conceivably result in piping and
subsurface erosion of loose sandy material if this is present, but the greater impact
will be to the groundwater levels. The higher flow velocity is due to the increased
hydraulic gradient resulting from the rise in water levels upstream, and lowering
downstream of the row of basements.
The change in water levels could be assumed to be in proportion to the increase in
the length of the flow path. In the case of a site measuring 10m in the direction of
groundwater flow, the natural difference in groundwater level might be one or two
centimetres. Introducing a basement of dimension 10m by 10m will increase the flow
path from 10m before to approximately 20m.
Where several basements effectively act as a single barrier to groundwater flow such
as in Appendix D1 (Scenario D1,D2 and D3) the impact will be larger. In this case the
water will be forced to follow a longer flow path, with greater energy loss as a
consequence, and therefore the changes in groundwater levels upstream and
downstream will be greater.
The extent to which the cumulative effects of basements may impact groundwater
flow and levels is likely to depend on the properties of the aquifer materials. In highly
permeable formations groundwater flow can easily be diverted around basements,
and will not ultimately lead to a groundwater level rise upstream of the basement.
72
Therefore, a single basement in extensive sand and gravel deposits is unlikely to have
a significant impact, whereas a single basement blocking a narrow linear gravel
deposit with clay in either side, will have a very significant impact.
Detail of groundwater flows due to cumulative effects shall need to be accounted for
in the basement design. In order to make basement construction fair and equitable
for all parties the Planning Authority shall require a Hydrogeological Assessment of
the site to determine the extent of existing groundwater passing through the site pre-
development (relative to depths etc.). Each development shall then be required to
account for the groundwater flows and volumes of groundwater below and through
their own site ensuring that there shall be minimal change to the groundwater flows,
levels and volumes post-completion of the works when compared to the pre-
development scenario. These proposals should be described in detail within the BIA.
Details of the required seasonal monitoring and site investigation required to record
the required relevant data is detailed further later in this document.
73
Appendix D1 – Cumulative effects of basement construction
74
Appendix E
– Noise and Air Quality – “Construction and Demolition Good Practice Guide”
75
Air Quality Monitoring and Noise
Control Unit’s Good Practice Guide
for Construction and Demolition
Prior to the commencement of work on the site a construction and demolition plan must be
developed. When developing the construction and demolition plan reference must be made
to the requirements of the Air Quality Monitoring and Noise Control Unit’s Good
Practice Guide for Construction and Demolition.
This Guide has been produced with reference to the London Good Practice Guide:
Noise and Vibration Control for Demolition and Construction produced by the London
Authorities Noise Action Forum, July 2016.
76
In order to ensure that demolition and construction work does not have an adverse impact
on those living and working nearby, the following best practice guidance has been
developed. All construction and demolition work has the potential to have adverse
environmental impacts no matter what the scale. The following best practice guide sets out
the measures which all developers should consider prior to commencement of work and
provides further recommendations for the control of noise, vibration and air pollution.
A risk based approached is to be used taking into account the locality, nature of the work
and the expected duration of the work.
Risk Assessment A – Locality/Site Information
The site should be assessed in relation to the duration of the work, distance to sensitive
receptors, ambient noise levels and working hours. Tick the field most likely to apply and add
up the number of ticks in each column.
Risk Assessment B - Work Information
Tick the field that is most likely to represent the works in each category, add up the total
number of ticks in each column.
Total Risk Assessment
The table ‘total risk assessment’ contains the sub-total numbers from ‘Risk Assessment A
and B. The column in total risk assessment with the most ticks indicates the risk category
that should be employed for the site.
If two risk categories have an equal number of ticks, the higher category of the two shall
apply. Once the risk category is known the ‘good practice measures’ outlined in this code of
practice shall be employed.
77
1. Locality
Identify those who may be affected by noise, including particularly sensitive locations
(hospitals/schools) and determine ambient noise levels (noise maps or noise
monitoring)
Low Medium High
Expected duration of work
Less than 6 months
6 months to 12 months
Over 12 months
Proximity of nearest sensitive receptors
Greater than 50 metres from site
Between 25m and 50m
Less than 25 metres
Hospital or school within 100 metres
Day time ambient noise levels
High ambient noise levels (>65dB(A))
Medium ambient noise levels (55-65dB(A)
Low ambient noise levels (<55dB(A)
Working Hours
7am – 6pm Mon-Fri; 8am-1pm Sat
Some extended evening or weekend work
Some night time working, including likelihood of concrete power floating at night
SUBTOTAL A
78
2. Work information
Low Medium High
Location of works
Majority within existing building
Majority External
External Demolition
Limited to two weeks
Between 2 weeks and 3 months
Over three months
Ground Works
Basement level planned
Non-percussive methods only
Percussive methods for less than 3 months
Percussive methods for more than 3
months
Piling
Limited to one week
Bored Piling Only
Impact or vibratory piling
Vibration generating activities
Limited to less than 1 week
Between 1 week and 1 month
Greater than 1 month
SUBTOTAL B
79
Low Medium High
Risk Assessment A
Risk Assessment B
Total
The column in total risk assessment with the most ticks indicates the risk category that
should be employed for the site.
80
1. General Considerations
All site staff shall be briefed on noise mitigation
measures and the application of best
practicable means to be employed to control
noise.
All sites
Good Quality site hoarding should be erected to
maximise the reduction in noise levels
Medium and High risk sites
The contact details of the contractor and site
manager shall be displayed to the public,
together with the permitted operating hours,
including any special permissions given for out
of hours work
Medium and High risk sites
The site entrance shall be located to minimise
disturbance to noise sensitive receptors
Medium and High risk sites
Internal haul routes shall be maintained and
steep gradients shall be avoided
Medium and High risk sites
Material and plant loading and unloading shall
only take place during normal working hours
unless the requirement for extended hours is for
traffic management(i.e road closure) or health
and reasons(application must be made to DCC
a minimum of 4 days prior to proposed works)
All sites
Use rubber linings in chutes, dumpers and
hoppers to reduce impact noise
High risk sites
Minimise opening and shutting of gates through
good coordination of deliveries and vehicle
movements
Medium and High risk sites
No materials shall be burned on site All sites
Adequate dust/debris screening should be in
place at the site boundary to contain and
minimise the amount of windblown dust. This
must be maintained in good condition at all
times.
Medium and High Risk sites
All consignments containing material with the
potential to cause air pollution being transported
by skips, lorries, trucks or tippers must be
covered during transit on and off site.
All sites
81
The site shall be dampened down as necessary
to minimise windblown dust when necessary or
during periods of dry weather.
All sites
Dust suppression equipment must be used
when point source emissions are likely.
All sites
The entry and exit points to the site should be
constructed of hard standing which is regularly
dampened to minimise dust emissions.
Medium and High Risk Sites
2. Plant
Ensure that each item of plant and equipment
complies with the noise limits quoted in the
relevant European Commission Directive
2000/14/EC
All sites
Fit all plant and equipment with appropriate
mufflers or silencers of the type recommended
by the manufacturer
All sites
Use all plant and equipment only for the tasks
for which it has been designed
All Sites
Shut down all plant and equipment in
intermittent use in the intervening periods
between work or throttle down to a minimum
All sites
Power all plant by mains electricity where
possible rather than generators
Medium and High Risk Sites
Maximise screening from existing features or
structures and employ the use of partial or full
enclosures for fixed plant
Medium and High Risk Sites
Locate movable plant away from noise sensitive
receptors
All sites
3. Vehicle activity
Ensure all vehicle movements (on site) occur
within normal working hours. (other than where
extension of work requiring such movements has
All sites
82
been granted in cases of required road closures
or for health and safety reasons )
Plan deliveries and vehicle movements so that
vehicles are not waiting or queuing on the public
roads. If unavoidable engines should be turned
off.
Medium and High Risk Sites
Minimise the opening and closing of the site
access through good coordination of deliveries
and vehicle movements
Medium and High Risk Sites
Plan the site layout to ensure that reversing is
kept to a minimum
Medium and High Risk Sites
Where reversing is required use broadband
reverse sirens or where it is safe to do so
disengage all sirens and use banks-men
Medium and High Risk Sites
Rubber/neoprene or similar non-metal lining
material matting to line the inside of material
transportation vehicles to avoid first drop high
noise levels.
Medium and High Risk Sites
Wheel washing of vehicles prior to exiting the site
shall take place to ensure that adjoining roads
are kept clean of dirt and debris. Regular
washing of adjoining streets should also be
carried out by the developer, as required by
mechanical road sweepers
Medium and High Risk Sites
4. Demolition Phase
Employ the use of acoustic screening; this can
include planning the demolition sequence to
utilise screening afforded by buildings to be
demolished.
Medium and High Risk Sites
If working out of hours for Health and Safety
reasons (following approval by DCC) limit
demolition activities to low level noise activity
unless absolutely unavoidable)
All sites
83
Use low impact demolition methods such as
non-percussive plant where practicable
Medium and High Risk Sites
Use rotary drills and ‘bursters’ activated by
hydraulic or electrical power or chemically
based expansion compounds to facilitate
fragmentation and excavation of hard material.
High Risk sites
Avoid the transfer of noise and vibration from
demolition activities to adjoining occupied
buildings through cutting any vibration
transmission path or by structural separation of
buildings
Medium and High Risk Sites
Consider the removal of larger sections by lifting
them out and breaking them down either in an
area away from sensitive receptors or off site.
High Risk Sites
5. Ground Works and Piling Phase
The following hierarchy of groundwork/piling
methods should be used if ground conditions,
design and safety allows:
pressed in methods, e.g., hydraulic jacking
Auger/bored piling
Diaphragm walling
Vibratory piling or vibro-replacement
Driven Piling or dynamic consolidation
Medium and High Risk Sites
The location and layout of the piling plant should
be designed to minimise potential noise impact of
generators and motors
Medium and High Risk Sites
Where impact piling is the only option utilise a non-
metallic dolly between the hammer and driving
helmet or enclose the hammer and helmet with an
acoustic shroud
Medium and High Risk Sites
Consider concrete pour sizes and pump locations.
Plan the start of concrete pours as early as
possible to avoid overruns
Medium and High Risk Sites
Where obstructions are encountered, work should
be stopped and a review undertaken to ensure that
work methods that minimise noise are used.
Medium and High Risk Sites
84
When using an auger piling rig do not dislodge
material from the auger by rotating it back and
forth. Use alternate methods where safe to do so.
Medium and High Risk Sites
Prepare pile caps using methods which minimise
the use of breakers, e.g., use hydraulic splitters to
crack the top of the pile.
Medium and High Risk Sites
6. Monitoring
Establish pre-existing levels of ambient noise by
baseline monitoring or use of the noise maps.
Medium and High Risk Sites
Carry out regular on site observation monitoring
and checks/audits to ensure that BPM is being
used at all times. Such checks shall include;
Hours of work
Presence of mitigation measures
Number and type of plant
Construction methods
Site reviews must be recorded and made available
for inspection
High Risk Sites
Monitor noise and vibration continuously during
demolition, piling, excavation and sub and
superstructure works at agreed locations and
report to DCC at agreed intervals and in an agreed
format.
To comply with this the following must take place.
The monitoring locations for existing sites as
agreed with officers of Dublin City Council must
remain in situ. If additional monitoring is required
this will be provided and the new locations will be
agreed with Dublin City Council. For all new sites
the monitoring locations must be agreed with
Dublin City Council.
High Risk Sites
85
The results of the monitoring must be forwarded to
officers of the Air Quality Monitoring and Noise
Control Unit every two weeks in the following
format:
Provide the construction noise level as defined in British Standard 5228 and the peak particle velocity readings for the hours of operation of the site. This will include the construction noise level for any overtime period worked outside of normal working hours. Provide a report detailing and discussing the noise and vibration levels over the reporting period. If a breach is recorded the follow up action that took place to prevent any further breaches must be included in the report.
This information must be provided in electronic format If results are required owing to complaints the results will be provided as soon as possible by the contractor to Dublin City Council.
Appraise and review working methods, processes
and procedures on a regular basis to ensure
continuous development of BPM
Medium and High Risk Sites
The ‘ABC’ Method detailed in Paragraph E.3.2 of
BS 5228-1:2009 shall be used to determine
acceptable noise levels for day, evening and night
time work.
Medium and High Risk Sites
Vibration levels must be kept below 1.0 mm/sec
(PPV) where possible. Where levels are expected
to exceed this value residents must be warned and
an explanation given.
Medium and High Risk Sites
Appropriate dust suppression must be employed to
prevent fugitive emissions affecting those
occupying neighbouring properties or pathways
All sites
Street and footpath cleaning must be undertaken
during the demolition and ground works phase to
minimise dust emissions
Medium and High Risk Sites
Continuous dust monitoring along the site
boundary should be undertaken during any
demolition or ground works
High Risk Sites
7. Communication and Liaison
86
A Community Liaison Plan should be developed by
the developer in consultation with local
residents/businesses and a single point of contact
nominated to engage with Dublin City Council and
the residents/businesses and to handle complaints
and communication of site information. A copy of
this plan must be sent to Dublin City Council
Planning Department as a matter of urgency in the
case of sites where development has already
commenced and 14 days in advance of
commencement of works for any other site
Medium and High Risk Sites
Contact details for the site manager and liaison
officer should be displayed prominently on the site
hoarding
Medium and High Risk Sites
All staff should be briefed on the complaints
procedure and the mitigation requirement and their
responsibilities to register and escalate complaints
received.
Medium and High Risk Sites
Send regular updates at appropriate intervals to all
indentified affected neighbours/ businesses via a
newsletter and post relevant information on the site
hoarding. Also make the information available via
email/website including weekly noise monitoring
reports
Medium and High Risk Sites
Arrange regular community liaison meetings at
appropriate intervals including prior to
commencement of the project.
High Risk Sites
Meet regularly with neighbouring construction sites
to ensure activities are coordinated to minimise
any potential cumulative issues.
High Risk Sites
Extensions of Working Hours in exceptional circumstances
Ensure at least 4 days notice is given to Dublin
City Council Planning Department when applying
for extensions to normal working hours. Do not
undertake out of hours work unless permission to
do so has been granted.
All sites
87
The applicant must demonstrate in writing that
the works required cannot be carried out during
normal working hours. The documentation sent
in must be accompanied by a detailed
engineering or/and traffic management or/and
safety case as to why the works are required
outside normal hours.
Power floating after 6pm is the only activity that
will be permitted during the extensions where
they relate to required large concrete pours. All
reasonable and appropriate measures to
minimise noise associated with these works must
be put in place and no works other than those
approved may be carried out during extended
working hours.
The Developer/his agent must give the times and
dates of the proposed work, and the mitigation
measures that are to be used to minimise
noise/disturbance
All sites
Advise neighbours about requirement for and
duration of any permitted works outside of
normal working hours, and associated
environmental mitigation measures being put in
place during the course of the extended works,
following receipt of approval from DCC
All sites
All complaints will be referred directly to the site
liaison person and a reply must issue to the
complaint within 3 hours of receipt of the
complaint.
All sites
A log of all complaints and a summary of how
they were dealt with should be kept and be made
available to DCC, as required
All sites
Any breaches of permitted working hours or
permitted extended working hours or developers
or subcontractors not carrying out their
requirements under this protocol may lead to
enforcement action and may also result in the
withdrawal of any extension of hours of works for
a period that will be at the discretion of Dublin
City Council.
All sites