Duane Phillips, MPMDirector of Project Management
![Page 2: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/2.jpg)
Understand what structure deflection is and the impacts to design & construction
Understand the mechanisms behind what drives structure deflection and its design implications
Discuss the construction impacts of structure deflection and construction considerations
![Page 3: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/3.jpg)
Deflection is the degree to which a structural element is displaced under a load.
Measure of the amount of movement from unloaded (resting) position
Components: pole top, arms
![Page 4: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/4.jpg)
Some deflection is inevitable in any structure materials
Manufacturing cost savings with a reduction in steel (significant)
Shifts further away from brittle fracture point (stress & strain resulting in failure)
![Page 5: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/5.jpg)
Reliability› Recurrence Interval/Return Period› Operational Contingencies
Safety› Construction› Operation› Maintenance
Existing Codes› 2012 NESC
![Page 6: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/6.jpg)
![Page 7: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/7.jpg)
Maximum un-factored loads
Should not cause damage to structure
Based upon the facility configuration & resulting loads
Maximum factored loads
Should not cause failure of structure
Based upon the ultimate strength of installed components
![Page 8: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/8.jpg)
Among Sub-Systems› Tangent Structures› Angle Structures› Dead End Structures› Conductor
Within Sub-Systems› Structure› Foundation› Hardware
Weakest
.
.
Strongest
Weakest
.
Strongest
![Page 9: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/9.jpg)
Types of Structures Monopole H-frame/Multi-pole Lattice
Deflection Points Structure Shaft (pole top - vertical) Arms (arm tip – vertical & transverse)
![Page 10: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/10.jpg)
Various loads act on structure simultaneously
Very unlikely that every load will reach ultimate load at once
For ultimate loads, design specifications provide factors for load magnification
![Page 11: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/11.jpg)
Conductor Point Loads› Wire Tension & Wind› Vertical Load Weight Span NESC Ice Load Local Utility – Extreme Ice
Pole Self-Weight Wind Acting on the Pole Hardware Construction
![Page 12: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/12.jpg)
Weight Span Concept
![Page 13: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/13.jpg)
Continental Winds› NESC Rule 250 C [Based on ASCE 7-05]
Not applicable if structure or attachments does not exceed 60 feet above ground
Load (lbs) = .00256*(Vmi/h)2*kz*GRF*I*Cf*A(ft2)
V → Basic Wind Speed kz → Velocity Pressure CoefficientGRF → Gust Response Factor I → Importance FactorCf → Shape Factor A → Projected Area
![Page 14: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/14.jpg)
Sag and tension are inversely proportional.As one increases, the other decreases.
Tension = span2 x weight/foot of wireSag x 8
![Page 15: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/15.jpg)
Transverse & Longitudinal Load due to Conductor Tension› Changes in Line Direction› Span Length Variation› Unbalanced Ice› Broken Wires› Dynamic Loads
![Page 16: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/16.jpg)
Based on total loads applied to structure & components
Comparison to design specification limits (allowable deflection)
Considers total load vs. vibration impacts› Some deflection is fine – too much is not
![Page 17: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/17.jpg)
Determine forces & associated stresses
Apply each load combination
Define critical demands
Max Load Demand ↔ Design Load Limits
![Page 18: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/18.jpg)
Used to optimize design (situational)
Operational or ultimate limits may govern specific feature
Should include both strength and fatigue design loading
![Page 19: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/19.jpg)
![Page 20: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/20.jpg)
![Page 21: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/21.jpg)
![Page 22: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/22.jpg)
![Page 23: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/23.jpg)
![Page 24: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/24.jpg)
![Page 25: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/25.jpg)
![Page 26: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/26.jpg)
![Page 27: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/27.jpg)
Clearances → additional sag › Other facilities & electrical ‘window’
Adjacent span sag/tension
Moment impacts to foundation
Constructability› Wire sag/tension specifications› Aesthetics
![Page 28: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/28.jpg)
Safety → understanding deflection & potential energy
Wire installation → properly sag/tension› Alternate means of sag verification› Shift installation sequence› Temporary guying deadends
![Page 29: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/29.jpg)
‘Up front’ discussion on means & methods of wire installation
Clear specification requirements
Review/approve wire installation methods
![Page 30: Duane Phillips, MPM Director of Project Management](https://reader031.vdocuments.us/reader031/viewer/2022012412/616bb45750cfec72b064ff44/html5/thumbnails/30.jpg)
Manufacturing cost reductions (quantity of steel)
Shift in field aesthetic perspective
Changes in means & methods of wire installation