    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 2 / 27

    INDEX

    INDEX ........................................................................................................................... 2AMENDMENTS AND REVISIONS .............................................................................. 41. INTRODUCTION .................................................................................................. 5

    1.1 PROJECT OVERVIEW ..............................................................................................51.2 PIPELINE SYSTEM DESCRIPTION ..........................................................................5

    2. DEFINITIONS AND ABBREVIATIONS .............................................................. 62.1 DEFINITIONS .............................................................................................................62.2 ABBREVIATIONS ......................................................................................................7

    3. REFERENCE RULES, CODES AND STANDARDS .......................................... 73.1 CODES AND STANDARDS .......................................................................................73.2 OWNER DOCUMENTS ..............................................................................................73.3 CONTRACTOR DOCUMENTS ..................................................................................7

    4. SCOPE OF DOCUMENT ..................................................................................... 85. RESPONSIBILITIES ............................................................................................ 86. PROCEDURE ...................................................................................................... 9

    6.1 ORGANIZATION OF PROJECT FILES ...................................................................106.2 HANDLING OF CORRESPONDENCE DOCUMENTS ............................................106.3 HANDLING OF TECHNICAL DOCUMENTS ...........................................................106.4 HANDLING OF INCOMING TECHNICAL DOCUMENTS ........................................12

    6.4.1 Logging of Technical Documents ....................................................................126.4.2 Deciding of the Distribution List and the Necessary Actions ...........................126.4.3 Distribution of Technical Documents ...............................................................126.4.4 Examination of Technical Documents ............................................................. 126.4.5 Contractors Evaluation of Comments on Technical Documents .................... 126.4.6 Updating of the MDR .......................................................................................136.4.7 Approval of the MDR .......................................................................................136.4.8 Handling of Master Documentation .................................................................13

    6.5 HANDLING OF OUTGOING TECHNICAL DOCUMENTS ......................................13

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    3/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 3 / 27

    6.6 TECHNICAL DOCUMENTS REFERENCES ...........................................................136.6.1 Technical Documents Template ......................................................................136.6.2 Technical Drawing Template ...........................................................................146.6.3 Technical Documents Checks .........................................................................146.6.4 Documents development phases ....................................................................14

    6.7 DOCUMENT NUMBERING ......................................................................................166.7.1 Codification for Technical Documents .............................................................166.7.2 Codification for Technical Specifications .........................................................176.7.3

    Codification for Drawings .................................................................................17

    6.7.4 ANNEX 1 Codes for Technical Documents and Technical Specifications

    Subject (D) .......................................................................................................196.7.5 ANNEX 2 Codes for Technical Document Category (E) ..............................206.7.6 Forms Records .............................................................................................206.7.7 ANNEX 3 Codes for Drawings Category ......................................................216.7.8 Sheet Number (Drawings) ...............................................................................216.7.9 Revision Number .............................................................................................22

    6.8 ELECTRONIC FILING OF DOCUMENTS................................................................226.9

    FINAL DOCUMENTATION ......................................................................................23

    7. ATTACHMENTS ................................................................................................ 24

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    4/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 4 / 27

    AMENDMENTS AND REVISIONS

    Amendmentand revision

    Date Page DescriptionProjectManager

    A1 16/12/11 All Issued for Comments/Approval

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    5/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 5 / 27

    1. INTRODUCTION

    1.1 PROJECT OVERVIEW

    Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore NaturalGas Pressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to EvviaIsland.

    The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag.

    Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated asAliveri landfall.

    The maximum water depth along the 20 Gas Pipeline route is approx. 70m (MSL).

    Figure 1-1 Natural Gas Pressure Pipeline Varnavas-Karavos route layout

    1.2 PIPELINE SYSTEM DESCRIPTION

    The offshore pipeline system consist of an 20 Natural Gas High Pressure Pipeline from the battery limitat Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new20 Natural Gas High Pressure Pipeline is about 14.2 km. The 20 Natural Gas High Pressure Pipeline

    will consist of the two offshore sections, joined together offshore by Above Water Tie In method.

    The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is70m.

    The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is31.2m.

    Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    6/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 6 / 27

    2. DEFINITIONS AND ABBREVIATIONS

    2.1 DEFINITIONS

    The following definitions will be applicable in this document:

    CONTRACTOR CONSORTIUM SAIPEM - ELTER

    OWNER DESFA HELLENIC GAS TRANSMISSION SYSTEM OPERATOR S.A.

    PROJECTDetailed Engineering, Procurement Of Materials & Construction Of TheOffshore Part Of The Stefani-Aliveri Natural Gas High Pressure Pipeline

    PROJECT MANAGERMeans, respectively, the entity and the person appointed by OWNER toprovide project management services

    SITE Means the lands, waters and other places on, under, in or through whichthe WORKS are to be performed including offshore installations, floatingconstruction equipment, vessels (including the area covered byapproved anchor patterns) design offices, workshops and places whereequipment, materials or supplies are being obtained, storied or used forthe purposes of the CONTRACT and any and all other places where thePERMANENT WORKS are to be executed and to which PLANT andMaterials are to be delivered and any other places as may be specifiedin the CONTRACT as forming part of the SITE.

    SUBCONTRACTOR Selected Sub-Contractor to perform the work described in this document

    SUPERVISING ENGINEER Means the company(ies) appointed by OWNER to carry out theConstruction Supervision duties, as well as the review of the detaileddesign issued by CONTRACTOR, as defined in Clause 2 hereof and inother CONTRACT DOCUMENTS

    WORKS Means all CONTRACTORs services and supplies to be rendered andPLANT furnished in accordance with the CONTRACT including bothTEMPORARY WORKS and PERMANENT WORKS. Without limitation toitems set out in the CONTRACT DOCUMENTS, the WORKS includeeverything of whatever nature that is required for the achievement of theobjective of the CONTRACT, except for any exclusion that arespecifically itemized in the CONTRACT DOCUMENTS

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    7/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 7 / 27

    2.2 ABBREVIATIONS

    DC Document Controller

    MDR Master Document Register

    PE Project Engineer

    CPM Contractor Project Manager

    CIM Contractor Installation Manager

    CEM Contractor Engineering ManagerPMT Project Management Team

    3. REFERENCE RULES, CODES AND STANDARDS

    3.1 CODES AND STANDARDS

    Ref Document Number Title

    /1/ ISO 9001:2000 Quality management system - Requirements

    3.2 OWNER DOCUMENTS

    Ref Document Number Title

    Specifications

    /2/ APENDIX F Contractor Documents Requirements

    /3/ DC-028Review/Approval of Contractors Technical Documentsusing Document Approval Form

    3.3 CONTRACTOR DOCUMENTS

    Ref Document Number Title

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    8/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 8 / 27

    Procedures

    /4/ WI-SMS-PCON-100-E Documentation Management

    /5/DSF-1101401-436-6300-QAC-MAN-0200

    Overall Quality Manual

    /6/DSF-1101401-436-6300-PRM-MAN-0100

    Project Overview Manual

    /7/ WI-SMS-INST-101-EOffshore Installation Engineering Documentsand Approval

    /8/ WI-SMS-OOFS-111-EWork Instruction Offshore AS BUILTdocumentation

    /9/ WI-SMS-INST-112-E Work Instruction Preparation of Drawings

    /10/ WI-SMS-INST-104-EWork Instruction Installation methods / designcontrol

    4. SCOPE OF DOCUMENT

    This procedure describes the system for handling the documents concerning the OFFSHORE PART OFTHE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE PIPELINE PROJECT.

    The objective is to guarantee the traceability, distribution, monitoring, disposal when necessary, and thesafekeeping of the Documents.

    5. RESPONSIBILITIES

    The DC is the focal point for the control of the Project Documentation during the whole project life.

    The mission of the DC is to insure the implementation of Project Document Control within the Project as

    follows:

    To make available the applicable project documentation to the project team (including Owner

    Subcontractors, Partners);

    To manage all project documentation flow (paper and electronic)

    The Document controller responsibilities include:

    Assigning on the request of the originator, a unique identification number for all project documents(including Subcontractors documents);

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    9/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 9 / 27

    Listing and controlling Project documents number within the project MDR;

    Only the duly endorsed documents (signed and approved by CONTRACTORs responsible persons)are sent to OWNER for review/approval;

    That all transmittals are duly indentified, numbered and filed ;

    Issuing Transmittals;

    Ensures that the MDR is updated and that transmittals and reports are issued embracing alldocuments generated in-house and by Vendor/Subcontractors or Third Parties during the ProjectLife (Engineering documents, Project Procedures, Queries, Vendor documents, OWNER) ;

    That the MDR is updated on daily basis with the support of the PMT and available on the Projectdrive in the last revision;

    All documents are available to CONTRACTOR interested personnel, at any utilization point ;

    To upload all the issued documents on the FTP server that CONTRACTOR has set up in order toexchange the Project documentation with the OWNER, or to send all the documents and transmittalsby e-mail, and to send all the transmittals by fax;

    Information flow within the Project Team about documents status;

    Ensuring the collection of final AS BUILT and transmission to OWNER;

    To alert of any delays in pending documentation.

    ProjectTeam shall comply with this procedure and shall assist the DC in number assignment.

    6. PROCEDURE

    The project Document Control System includes:

    receipt;

    issuing;

    numbering

    logging;

    distribution;

    Document flowchart is shown in chapter 6.3.

    All incoming and outgoing transmittals and documents shall be transmitted at the following address:

    Mr. Giorgio Danieli

    Contractor Project Manager

    e-mail: [email protected]

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    10/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 10 / 27

    Mrs. Lorena Jerkovic

    Document Controller

    51000 Rijeka, A. Colonnella 2, Croatia

    Tel.: 00 385 51 651 908

    Fax: 00 385 51 651 940

    e-mail: [email protected]

    6.1 ORGANIZATION OF PROJECT FILES

    The CPM in collaboration with the DC shall establish the list of the incoming and outgoing files, and therelated logs:

    for the OWNER;

    On the basis of any other classifications the PM wishes to use.

    This system shall be kept active, and updated with any new items, for the entire duration of this project.

    The DC carries out the following activities:

    organises the file,

    labels the back of the file volumes, to facilitate consultation,

    Prepares the logs and keeps them updated.

    6.2 HANDLING OF CORRESPONDENCE DOCUMENTS

    All correspondence between CONTRACTOR and OWNER should be approved and signed by CPM, whodecides the distribution list and necessary actions.

    6.3 HANDLING OF TECHNICAL DOCUMENTS

    Management of CONTRACTORs project Technical documents should be carried out accordingly to itsQuality System and the following flow chart:

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    11/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 11 / 27

    Flow chartCoveringdocuments

    Consequent actions Action by

    IDC Form

    Discipline check

    Interdisciplinary check

    Archiving documents

    Updating MDR

    Contractor

    transmittal

    Sending / receiving documentsInsert OWNER comments

    Archiving transmittals

    Updating LOGs

    Contractor

    Documents review andcomment / approve

    Sending / receiving documents

    OWNER(when required)

    transmittal

    Sending documents

    Archiving documents

    Updating MDR

    Updating LOGs

    Contractor

    Implementation of documentsAll involved

    persons

    All documents issued for this project shall be signed by the Originator (Prepared), Checker (Verified) andCONTRACTORs Project Manager (Approved), in the absence of the CPM, all documents can be signed byCIM or CEM.

    All documents issued by SUBCONTRACTOR shall go through their document control and approval process

    before being sent to the CONTRACTOR.

    All transfers of documentation should be accompanied with established Transmittal form.

    Project documents shall be approved by OWNER.

    START

    Document issued forcomments/approval /reissued / revised by

    Contractor

    OWNERcomments

    NO

    YES

    Document issuedapproved forconstruction

    END

    Insert OWNERcomments

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    12/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 12 / 27

    6.4 HANDLING OF INCOMING TECHNICAL DOCUMENTS

    The handling of the incoming technical documents includes the following activities:

    Logging,

    Deciding the distribution list and necessary actions,

    Distribution.

    Archiving

    6.4.1 Logging of Technical Documents

    Logging of the technical documents is DC responsibilities and has to do the following actions:

    LOG the Document in MDR or other registers

    check the technical documents by the list of documents on the transmittal form;

    record the transmittal form and file the original, updating the Transmittal Log IN (FORM-DESFA-003 );

    return to the sender, when required, a copy of the transmittal form signed for receipt;

    The DC turns over all incoming technical documents to the CPM.

    6.4.2 Deciding of the Distributi on List and the Necessary Actions

    The CPM examines the incoming external documents and indicates the distribution list, specifying the action

    requested by Project Team members for each document if its necessary.

    6.4.3 Distribut ion of Technical Documents

    The DC distributes the technical documents as per the distribution list so that they return to the CPM with theinformation requested.

    6.4.4 Examination of Technical Documents

    The persons indicated by the CPM examine received technical documents and carry out the requestedactions. Comments to the technical documents have to be written, using Comment sheet form.

    The documents, with the comments incorporated, have to be returned to the DC.

    6.4.5 Contractors Evaluation of Comments on Technical Documents

    The CPM, or person indicated by CPM, after evaluating the comments received on the technical documents,decides to:

    reject the documents, returning them with the comments to the originator for the preparation of anew revision;

    Approve them, upon approval document should be sent to OWNER for review/approval;

    Approve them, upon approval document should be issued for IFC (Issued for Construction) tothe OWNER.

    The OWNER evaluates the documents and returns them as R Reviewed, WC - reviewed with comments,

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    13/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 13 / 27

    orRWMC Reviewed with Minor Comments.

    6.4.6 Updating of the MDR

    The DC updates the MDR, on the basis of the CPMs instructions, throughout the life of the project, preparingeach time a new revision to be issued.

    6.4.7 Approval of the MDR

    The CPM approves the MDR, after the PE has checked the document.

    The DC arranges the distribution of the updated MDR to all Project Team members, and to any otherspecified by CPM, including the OWNER.

    MDR will be issued to OWNER on monthly basis.

    6.4.8 Handling of Master Documentation

    The DC organises, manages, and keeps the master documentation up to date replacing each document withthe latest revision. Prior revisions shall be stamped SUPERSEDED

    6.5 HANDLING OF OUTGOING TECHNICAL DOCUMENTS

    The DC handles all outgoing technical documentation, prepared according to this Procedure, and approvedby the CPM, in the following manner:

    files the document originals;

    prepares the Transmittal form (FORM-DESFA-001), which is to be sent to the receiver;

    updates the Transmittal Log OUT (FORM-DESFA-002) and MDR Take the different numbers and filing system for outgoing documentation to the OWNER, and

    the other one for outgoing documentation to the Subcontractors.

    6.6 TECHNICAL DOCUMENTS REFERENCES

    All Technical documents shall be written in the English and shall bear the Project references, as displayed onthe cover of this document and as described below in detail.

    6.6.1 Technical Documents Template

    A Technical document cover page and title block format, will display the following:

    Project Title OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGHPRESSURE PIPELINE

    Owner Logo, Main Contractor Logo, Contractor Logo;

    Title of Document

    Document Number;

    Issue Date and Revision number, Description of issue;

    Area for Originator, Checker and Engineering and OWNER approval sign-offs

    The Technical document Template is shown inAttachment 1 and it is prepared in Word format.

    Project Document, shall always include as minimum the following sections (drawings excluded):

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    14/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 14 / 27

    Each Technical Document shall contain the table Revision Status Log which shall be positioned after pagewith table of contents.

    6.6.2 Technical Drawing Template

    Technical Drawing Template used for the Drawings in this Project corresponds to the requirements ofCONTRACTORs document system.

    The CONTRACTOR Technical Drawing Template is shown inAttachment 2 and it is prepared in AutoCAD2004 (DWG) format. In case that newer AutoCAD is used, drawing will be always saved in 2004 format.

    Drawing identification table placed in the bottom right side of the template shall be filled according to thisprocedure.

    6.6.3 Technical Documents Checks

    Each Technical document prepared utilising the Technical document Template, shall be checked as follows.

    Self-Check Check made by the Originator on his own work.

    On completion of the document the Originator shall sign off the original document in order to confirmthe correctness of his work. One clean copy shall be forwarded at this stage to the respective LeadDiscipline Engineer for further processing.

    Discipline Check Check made by a Discipline Specialist (Checker).Discipline Check shall be carried out by the Discipline function. A qualified person, different form theoriginator, shall subject each design deliverable to a Discipline Check.

    Inter-discipline Check if required.Check regarding item(s) interfacing with other design disciplines, performed by the respectiveDiscipline Specialist.The PE shall be responsible for deciding which documents shall be subject to IDC and by whichdisciplines.

    6.6.4 Documents development phases

    Phases of document development shall be defined, as it is described bellow:

    PHASE PROGRESS

    Start Date of the document 0%

    Issued for Internal Review 10%

    Issued for Comments / Approval (IFA) 60%

    Issued for Construction (IFC) 100%

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    15/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 15 / 27

    NOTE: Documents issued for Information (I1) shall be issued to OWNER after Internal Review cycle and willhave 100% progress.

    Engineering documents shall be issued with status clearly indicated in the description column of title block asfollows:

    Issued (or Re-issued in case of any further rev ) for Internal Review

    Issued (or Re-issued in case of any further rev ) for comments / approval

    Issued (or Re-issued in case of any further rev ) for construction

    OWNER will review and comment on the document within maximum of 10 calendar days. Urgent documents

    may require shorter review period, but it shall never be less than two working days.

    Documents / drawings returned by OWNER with comments shall be reviewed by relevant Originator.

    Whenever these comments can be incorporated without further questions the document / drawing shall berevised by the Originator, rechecked by the Checker approved by CPM and issued as Issued forconstruction.

    Upon document issue in new revision, the previous one shall be stamped SUPERSEDED.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    16/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 16 / 27

    6.7 DOCUMENT NUMBERING

    Control of issued documents is established through the Master Document register (MDR).

    Each technical document (drawings, specifications, calculations, technical reports) originated for this Projectby CONTRACTOR and by its SUBCONTRACTORS shall be assigned with an unequivocal OWNERsidentification number as per the scheme as follows:

    6.7.1 Codification for Technical Documents

    Document code as per the following structure:

    A B C D E - F

    (A) Project Code: DSF-1101401

    (B) Contract No.: 436

    (C) Unit No.: 6300

    (D) Document subject according to Annex 1

    (E) Document category according to Annex 2

    (F) Document Serial Number

    Example:

    DSF-1101401-436-6300-CNV-STU-001

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    17/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 17 / 27

    6.7.2 Codification for Technical Specifi cations

    Specification code as per the following structure:

    A B C D E

    (A) Project Code: DSF-1101401

    (B) Contract No.: 436

    (C) Specification Code: SPC

    (D) Specification subject according to Annex 1

    (E) Specification Serial Number:

    1XX for Material Technical Specifications

    2XX for Job Technical Specifications

    Example:

    DSF-1101401-436-SPC-CON-201

    6.7.3 Codification for Drawings

    Drawing code as per the following structure:

    A B C D E - F

    (A) Project Code: DSF-1101401

    (B) Contract No.: 436

    (C) Unit Code: 6300

    Note: In case of Issue of Standard Drawings the above Unit Number shall be replaced by the code STD.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    18/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 18 / 27

    (D) XXX/ZZ

    The first part XXX designates this drawing Category according to the Annex 3 and the second part ZZdesignates the Drawing Subject and is valid only for the category 55 (pipeline plans and longitudinalsections) as follows:

    01 for recording plans

    02 for longitudinal sections

    (E) Drawing Size:

    0 for drawing standard size A0

    1 for drawing standard size A1

    2 for drawing standard size A2

    3 for drawing standard size A3

    4 for drawing standard size A4

    N for non-standard size drawings

    (F) Drawing Serial Number:

    a.) For the Drawings category 03 (Annex 3) as follows:

    001, 002 etc. for Engineering Flow Diagrams

    101, 102 etc. for Process Flow, Utility Balance, Block Flow Diagrams

    201, 202 etc. for Materials of Construction diagrams

    301, 302 etc. for Design Pressure / Temperature Diagrams

    401, 402 etc. for packaged Unit Diagrams

    b.) For all other drawings: Serial Number

    Example:

    DSF-1101401-436-6300-93-2-001

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    19/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 19 / 27

    6.7.4 ANNEX 1 Codes for Technical Documents and Technical Specifications Subject(D)

    The following are the letters for the types of technical documents (3) to be used in the documentsidentification code:

    D

    ADM Administration

    COA Coating

    CON Construction

    CPR Cathodic Protection

    DCC Document Control

    ENV Environmental

    GEO Geological

    GET Geotechnical

    NAV Naval

    NDT Non Destructive Testing

    PCO Project Control

    PLN Pipeline (Natural Gas Service)

    POS Positioning

    PRC Procurement

    PRJ Project Engineering

    PRM Project Management

    QAC Quality Assurance / Control

    SAF Safety

    SEI Seismic

    STA Stress Analysis

    STR Structural (Steel Structures)

    SUR Survey

    TOP Topographical

    WEL Welding

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    20/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 20 / 27

    6.7.5 ANNEX 2 Codes for Technical Document Category (E)

    The following are the letters for the types of technical documents (3) to be used in the documentsidentification code:

    E

    CHT Chart

    CLC Calculation

    DAB Data Book

    DAT Data Sheet

    IND IndexLST List

    MAN Manual

    MST Method Statement

    MTO Material Take Off

    PHL Philosophy

    PLN Plan

    PRC Procedure

    REG Register

    REP Report

    REQ RequisitionSCH Schedule

    SHT Sheet

    SOW Scope of Work

    SPE Specification

    STU Study

    GEN General Document

    6.7.6 Forms Records

    Forms Records shall be numbered as follows:

    DESFA FORM-xxx

    xxx progressive number

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    21/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 21 / 27

    6.7.7 ANNEX 3 Codes for Drawings Category

    D

    01 Plot Plan and elevations

    46 Steel Structures

    55 Pipeline plans & Longitudinal sections

    59 Pipe Supports

    78 Cathodic Protection

    89 Pre-commissioning (heads, layouts,)

    90 Rigging Laouyts

    91 Survey dwgs Scale 1:1000

    92 Survey dwgs Details

    93 Survey dwgs Scale 1:5000

    94 Survey dwgs Scale 1:50000

    95 Survey maps

    96 Anchor Patterns

    97 Vessels Equipment, Layouts

    98 Pipeline installation aids (heads, clamps,)

    99 Installation sequence drawings (story boards)

    6.7.8 Sheet Number (Drawings)

    Each drawing issued regarding this procedure shall contain sheet number. Sheet number shall consist of twonumerical digit starting from "01".

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    22/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 22 / 27

    6.7.9 Revision Number

    Documents circulated internally for review / comments can be assigned with revision number 0 (zero) (textin the description of revision shall be Issued for Internal Review).

    Document ready to be submitted to the OWNER for comments / approval, it shall be assigned with revisionnumberA1 (text in the description of revision shall be Issued for Comments / Approval). In case of re-submission of a document following the OWNER comments subsequent numbers (i.e. A2, A3.,) shall beassigned until the document is finally approved.

    Once the document has been approved by the OWNER, it shall be re-issued with revision code C1 (text inthe description of revision shall be Approved for Construction). In case of re-submission of a documentfollowing the OWNER comments subsequent numbers (i.e. C2, C3.) shall be assigned until the document isfinally approved.

    Document ready to be submitted to the OWNER for Info, it shall be assigned with revision numberI1 (textin the description of revision shall be Issued for Information). CONTRACTOR does not expect commentson such documents, but in case of required changes document will be issued in next revision (I2, I3, etc.).

    6.8 ELECTRONIC FILING OF DOCUMENTS

    All documents shall be stored in the computer system, in the OFFSHORE PART OF THE STEFANI-ALIVERINATURAL GAS HIGH PRESSURE PIPELINE Project dedicated area.

    The document number together with the revision number shall constitute the name of the electronic file ofeach document, for example:

    DSF-1101401-436-6300-SAF-MAN-0400_A1.doc

    All drawings shall be stored in AutoCAD 2004 version. The drawing number together with the sheet numberand revision number shall constitute the name of the electronic file of each drawing, for example:

    DSF-1101401-436-6300-5501-3-0700_A1.dwg

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    23/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 23 / 27

    6.9 FINAL DOCUMENTATION

    Prior to issue the final As-Built document/drawings CONTRACTOR shall submit to OWNER forreview/comments As-Built documents/drawings.

    The final As-Built drawings must fully conform to the final arrangement. The final As-Built drawings shall bebased on the drawings issued for construction but shall include modifications, alterations, corrections orremarks concerning changes effected during construction.

    Documents to be included in the Asbuilt shall be defined by issuing As built Dossier Index (Doc. No. DSF-1101401-436-6300-PCO-IND-0303) and shall be sent to OWNER for approval.

    Subcontractor shall submit to CONTRACTOR a proposed Index of As-Built Documentation for approval priorcommencement of the Supply of the Work.

    CONTRACTOR shall also submit to OWNER the final As-built drawings and documents in digital file formin CD-ROMs. The drawings shall be submitted in standard DXF or DWG format for AutoCAD latest release.All other final Technical Documentation (reports, tables, lists, etc) shall be also submitted in MicrosoftOffice Word/Excel files.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    24/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT CONTROL PROCEDURE

    DSF-1101401-436-6300-DCC-PRC-0302

    REV. A1 Page 24 / 27

    7. ATTACHMENTS

    Attachment 1 Technical Document Template - Word format for technical documents consisting more than 1page (pages 7)

    Attachment 2 Technical Drawing Template AutoCAD format (pages 1/1)

    Attachment 3 Transmittal Form (page 1)

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    25/36

    Attachment 1 Technical document Template

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    26/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 1 / 7

    DOCUMENT TITLE

    Rev Date Descripti on of Revision Prepared Checked Approved Owner

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    27/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 2 / 7

    INDEX

    1. INTRODUCTION ...................................................................................................................... 41.1 PROJECT OVERVIEW ..................................................................................................... 41.2 PIPELINE SYSTEM DESCRIPTION ................................................................................. 4

    2. DEFINITIONS AND ABBREVIATIONS .................................................................................... 52.1 DEFINITIONS ................................................................................................................... 52.2 ABBREVIATIONS ............................................................................................................. 62.3 REFERENCES .................................................................................................................. 6

    3. RESPONSIBILITIES AND OBLIGATIONS ............................................................................... 64. SCOPE OF DOCUMENT ......................................................................................................... 65. HEADING 01 (PROCEDURE DESCRIPTION) ........................................................................ 7

    5.1 HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT) ............................................... 75.1.1. TITLE 03 (STYLE HEADING 03, FONT: ARIAL 10PT) .............................................. 7

    6. ATTACHMENTS ....................................................................................................................... 7

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    28/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 3 / 7

    AMENDMENTS AND REVISIONS

    Amendmentand revision

    Date Page Description

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    29/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 4 / 7

    1. INTRODUCTION

    1.1 PROJECT OVERVIEW

    Public Natural Gas System Operator (DESFA) of Greece plans to install an N.G.T.S. Offshore Natural GasPressure Pipeline Varnavas-Karavos (Aliveri) whose purpose will be to supply natural gas to Evvia island.

    The southern landfall in Attiki is named Varnavas while the previous names used for this landfall are Ag.Apostoli or Grammatiko. The northern landfall in Evvia is named Karavos which is also indicated as Aliverilandfall.

    The maximum water depth along the 20 Gas Pipeline route is approx. 70m (MSL).

    Figure 1-1 Natural Gas Pressure Pipeline Varnavas-Karavos route layout

    1.2 PIPELINE SYSTEM DESCRIPTION

    The offshore pipeline system consist of an 20 Natural Gas High Pressure Pipeline from the battery limitat Varnavas landfall, Attiki to the battery limit at Karavos landfall at Evvia island. The length of the new20 Natural Gas High Pressure Pipeline is about 14.2 km. The 20 Natural Gas High Pressure Pipelinewill consist of the two offshore sections, joined together offshore by Above Water Tie In method.

    The Varnavas side offshore pipeline section commences at the KP -0.020 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is

    70m.

    The Karavos side offshore pipeline section commences at the KP 14.205 and finishes at AWTI Targetpoint at KP 13.360 in water depth of 31.2m. Along the pipeline section route, maximum water depth is31.2m.

    Both pipeline sections will be manufactured from carbon steel with internal corrosion coating.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    30/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 5 / 7

    2. DEFINITIONS AND ABBREVIATIONS

    2.1 DEFINITIONS

    The following definitions will be applicable in this document:

    CONTRACTOR CONSORTIUM SAIPEM - ELTER

    OWNER

    DESFA HELLENIC GAS TRANSMISSION SYSTEM OPERATOR

    S.A.

    PROJECTDetailed Engineering, Procurement Of Materials & Construction Of TheOffshore Part Of The Stefani-Aliveri Natural Gas High PressurePipeline

    PROJECT MANAGERMeans, respectively, the entity and the person appointed by OWNER toprovide project management services

    SITE Means the lands, waters and other places on, under, in or trhoughwhich the WORKS are to be performed including offshore installations,floating construction equipment, vessels (including the area covered byapproved anchor patterns) design offices, workshops and places whereequipment, materials or supplies are being obtained, storied or used forthe purposes of the CONTRACT and any and all other places where

    the PERMANENT WORKS are to be executed and to which PLANTand Materials are to be delivered and any other places as may bespecified in the CONTRACT as forming part of the SITE.

    SUBCONTRACTORSelected Sub-Contractor to perform the work described in thisdocument

    SUPERVISING ENGINEER

    Means the company(ies) appointed by OWNER to carry out theConstruction Supervision duties, as well as the review of the detaileddesign issued by CONTRACTOR, as defined in Clause 2 hereof and inother CONTRACT DOCUMENTS.

    WORKS

    Means all CONTRACTORs services and supplies to be rendered andPLANT furnished in accordance with the CONTRACT including bothTEMPORARY WORKS and PERMANENT WORKS. Without limitationto items set out in the CONTRACT DOCUMENTS, the WORKS include

    everything of whatever nature that is required for the achievement ofthe objective of the CONTRACT, except for any exclusions that arespecifically itemized in the CONTRACT DOCUMENTS.

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    31/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 6 / 7

    2.2 ABBREVIATIONS

    The following abbreviations will be applicable in this document:

    CPM Contractor Project Manager

    2.3 REFERENCES

    Ref. Document No. Document Title

    1

    2

    3

    4

    5

    6

    7

    8

    9

    3. RESPONSIBILITIES AND OBLIGATIONS

    Text (Style P1, Font: Arial 10 pt)

    Bullet (Style P1, Font: Arial 10pt)

    Text (Style P1, Font: Arial 10pt)

    4. SCOPE OF DOCUMENT

    Text (Style P1, Font: Arial 10 pt)

    Bullet (Style P1, Font: Arial 10pt)

    Text (Style P1, Font: Arial 10pt)

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    32/36

    OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH

    PRESSURE PIPELINEContract No. 436/11

    DOCUMENT TITLE

    DSF-1101401-436-6300-xxx-xxx-xxxx

    REV. X Page 7 / 7

    5. HEADING 01 (PROCEDURE DESCRIPTION)

    Text (Style P1, Font: Arial 10 pt)

    Bullet (Style P1, Font: Arial 10pt)

    Text (Style P1, Font: Arial 10pt)

    5.1 HEADING02 (STYLE HEADING 02, FONT: ARIAL 10PT)

    Text (Style P1, Font: Arial 10 pt)

    Bullet (Style P1, Font: Arial 10pt)

    Text (Style P1, Font: Arial 10pt)

    5.1.1. Title 03 (Style Heading 03, Font: ARIAL 10pt)

    Text (Style P1, Font: Arial 10 pt)

    Bullet (Style P1, Font: Arial 10pt)

    Text (Style P1, Font: Arial 10pt)

    6. ATTACHMENTS

    Attachment 1 - Text (Style P1, Font: Arial 10pt)

    Attachment 2 - Text (Style P1, Font: Arial 10pt)

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    33/36

    Attachment 2 Technical Drawing Template

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    34/36

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    35/36

    Attachment 3 Transmittal Form

  • 7/29/2019 DSF 1101401 436 6300 DCC PRC 0302_A1 Document Control Procedure

    36/36

    Date:

    4= For Bid

    No.off Rev. Acti on Co de Resp. Cod e

    1

    Transmitted by:

    Date:

    Received by:

    Date:

    Project No.: DSF-1101401

    Distribution

    Correspondence number:

    PROJECT NAME: OFFSHORE PART OF THE STEFANI-ALIVERI NATURAL GAS HIGH PRESSURE

    PIPELINE

    CONTRACT No.: 436/11

    To:

    Address:

    TRANSMITTAL FORM

    Form no.: FORM-DESFA-0001

    Rev. 01 DatE: 17.11.2011

    Pag. 1 of 1

    Title / Description

    B = Approved on condition

    CLIENT: DESFA- HELLENIC GAS TRANSMISSION

    SYSTEM OPERATOR S.A.

    Ref.No.:

    Subject:

    Quantity:

    From: SAIPEM

    PLESE SIGN AND RETURN COPY

    RESPONSE CODE:

    Document No.

    D= No comment - For info

    only

    ACTION CODE:

    1 = For Approval

    2 = For Comment

    3 = For Information

    5= For Construction

    6= For Design

    A = Approved C= Unnaceptable