drying of pipelines prior to commissioning — ceps a.s

6
3/25/13 Drying of pipelines prior to commissioning — CEPS a.s. 1/6 www.ceps-as.cz/en/products/drying-of-pipelines.html english / česky all / products / projects / about the company / expert articles / contact product ON THIS PAGE Reasons for drying of gas pipelines after construction Sources of water inside pipelines Pipeline drying using deeply pre- dried air Vacuum drying GO TO THE RELATED ITEMS Products Information about Company Contacts DOWNLOADS Product catalogue PDF for screen (464 kB) Product catalogue PDF for print (1746 kB) DRYING OF PIPELINES PRIOR TO COMMISSIONING The water inside the operating pipeline is a source of many problems. The company CEPS can perfectly dry it—drying of pipelines it performs prior to putting it into operation by the extremely pre-dried air and also vacuum. Reasons for drying of gas pipelines after construction Water inside a gas pipeline in operation causes a number of problems. In medium-pressure gas pipelines, house pressure regulators tend to freeze in winter, which is very unpleasant both for the customer, who is suddenly deprived of heating and for the gas company because emergency crews need to go out to the field to repair this, which influences the economics of gas supplies. In high-pressure pipelines, complications with natural gas hydrates tend to form in addition to the problems with pressure regulating stations. The hydrates may clog even a large diameter pipe. In addition to this operational trouble, water in high- pressure pipelines primarily poses a direct risk of failure. Internal corrosion caused by free water has been already detected in many pipelines. However, it is only recently that a much more dangerous consequence of free water has been proved in gas pipelines transporting normally treated natural gas—internal stress corrosion cracking (SCC) which, in a relatively short time of operation (several Drying of pipelines prior to commissioning

Upload: im4uim4uim4uim4u

Post on 13-Aug-2015

40 views

Category:

Documents


0 download

DESCRIPTION

Drying of pipelines prior to commissioning

TRANSCRIPT

Page 1: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

1/6www.ceps-as.cz/en/products/drying-of-pipelines.html

english / česky

all / products / projects / about the company /

expert articles / contact

product

ON THIS PAGE

Reasons for drying of gas pipelines

after construction

Sources of water inside pipelines

Pipeline drying using deeply pre-

dried air

Vacuum drying

GO TO THE RELATED ITEMS

Products

Information about Company

Contacts

DOWNLOADS

Product catalogue

PDF for screen (464 kB)

Product catalogue

PDF for print (1746 kB)

DRYING OF PIPELINES PRIOR TO

COMMISSIONING

The water inside the operating pipeline is a source of many problems. The

company CEPS can perfectly dry it—drying of pipelines it performs prior to

putting it into operation by the extremely pre-dried air and also vacuum.

Reasons for drying of gas pipelines after construction

Water inside a gas pipeline in operation causes a number of problems.

In medium-pressure gas pipelines, house pressure regulators tend to freeze in

winter, which is very unpleasant both for the customer, who is suddenly deprived of

heating and for the gas company because emergency crews need to go out to the

field to repair this, which influences the economics of gas supplies.

In high-pressure pipelines, complications with natural gas hydrates tend to form in

addition to the problems with pressure regulating stations. The hydrates may clog

even a large diameter pipe. In addition to this operational trouble, water in high-

pressure pipelines primarily poses a direct risk of failure. Internal corrosion caused

by free water has been already detected in many pipelines.

However, it is only recently that a much more dangerous consequence of free water

has been proved in gas pipelines transporting normally treated natural gas—internal

stress corrosion cracking (SCC) which, in a relatively short time of operation (several

Drying of pipelines prior

to commissioning

Page 2: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

2/6www.ceps-as.cz/en/products/drying-of-pipelines.html

years), may cause a complete failure of extensive stretches of the line. At the same

time there is no reliable method at present to detect the creation and beginnings of

SCC development on the inside of the pipe wall.

Sources of water inside pipelines

Water enters a pipeline before putting into operation usually due to lack of

discipline at work during construction. In some cases, the reason may be the

construction technology itself, for example where underground river crossings are

laid which requires that the pipe is flooded with water.

Hydrotests or stresstests are another stage of construction when water enters a pipe.

This is evident when the tests are carried out using water but we should not ignore

tightness-tests using air when water contained in air condenses in the pipe after the

air is compressed.

Although some of the water is removed from the pipeline when it is cleaned, a

significant proportion of water cannot be removed from the pipeline even when

repeatedly applying mechanical cleaning techniques using water-absorbing cleaning

pigs because the water adheres to the pipe walls due to capillary forces. This water

can only be removed by special drying techniques.

CEPS carries out pipe drying before commissioning, using both methods that are

currently used throughout the world—deeply pre-dried air and vacuum drying.

Both of these technologies can also be deployed for drying other pipelines facilities

(metering stations, interconnecting nodes, etc.) or even pieces of equipment

requiring a high level of dryness (chemical apparatuses, high-performance steam

turbines, etc.).

Generator of very dry air JUV 3600 allows to dry up to 3600 m³ of air per hour—

pipeline DN 1000 with a length of 10 to 15 km can be dried in one to two days

pipeline drying using

deeply pre-dried air

Pipeline drying using deeply pre-dried air

This technique is suitable for pipes made of steel and plastic materials, and also for

process equipment. At first step the air is dried to a temperature of water dew point

below −80 °C in a special unit based on a molecular sieve, and then blown into the

pipeline for being dried. The water, which is present in the line evaporates into the

pre-dried air, and in this air is carried to outside the pipeline.

CEPS has two big units available. Each unit has a drying capacity of one cubic metre

Page 3: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

3/6www.ceps-as.cz/en/products/drying-of-pipelines.html

of air per second, i.e. 3,600 cu. m/hour. This is sufficient capacity to dry a pipeline

having a nominal diameter DN 1000 (40 in.) and a length of 10 to 15 km in one or two

days. In case of need (particularly to speed up the drying process) both units can be

connected in parallel. Both units are housed in containers and are transported on

off-road vehicles capable to manage the navigation throughout the difficult terrain,

and therefore can be transported over the construction strip (r.o.w).

The third one, smaller unit has a capacity of drying 650 cubic metre of air per hour

and is used for drying of low profile pipelines.

Very dry air generator JUV 650

The units’ operating pressure of 4 to 8 bar is strong enough to push porous cleaning

pigs through the pipe during the drying process, which helps to achieve the high rate

of drying. At forked/branched pipelines or those whose dimension changes

significantly, or in process equipment, i.e. wherever the porous elements cannot be

pushed through the equipment, the drying takes a proportionately longer time. The

drying of a complex pipeline node, after the hydrotest or stresstest water has been

simply released, would take several days.

Pipes are dried to the standard level of the temperature of water dew point in

the pipe of minus 20 °C. However, in case of need, particularly for process

equipment, up to minus 70 °C can be achieved.

vacuum drying Vacuum drying

Vacuum drying is based on a generally known physical phenomenon—as the

pressure drops, also the boiling point of liquids drops. At an absolute pressure of

about 2 kPa, water boils at the temperature of the soil that surrounds the pipe.

Page 4: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

4/6www.ceps-as.cz/en/products/drying-of-pipelines.html

The drying process by this method should be very carefully followed because at too

high pumping speed of the out coming air, pipeline is not sufficient to complement

the evaporative heat of water supply through the wall of pipe, but instead the

evaporative heat is taken from the water inside the pipe, which causes its cooling.

This phenomenon consequently does not lead to the evaporation of water but water

inside pipe freezes. The pipeline then apparently acts as dry, but after putting into

operation ice gradually melts and the problems with water appears again. Therefore

it is necessary follow carefully process of drying, including control dead time. This

dwell time when pumping is stopped, which is repeated according to pipeline

diameter prevents water freezing. These dwell times the other hand significantly

prolong the drying time.

Vacuum drying is also suitable for a complicated internal piping

The vacuum drying is suitable particularly for branched steel pipes and pipeline

facilities. For pipes having a nominal diameter of more than DN 500 (20 in.), the

geometric stability of the pipes under deep vacuum always needs to be assessed.

This technique now cannot be employed with plastic pipes—application of method

for this purpose requires to perform the certification tests that are currently carried

out.

In comparison with drying based on deeply predried air supported by porous pigs

pushed through the pipe, vacuum drying is slower. However, where the porous

elements cannot be used, vacuum drying may even be faster for more complex

pipeline nodes.

CEPS operates several vacuum units, each one with the capacity of up to

200 cu. m/hour. In case of need, the units can work in parallel.

Vacuum drying is very appropriate for drying complexly shaped distribution network

pipes, because in addition to the drying itself, it also makes the first gas admittance

into the pipes much easier. The gas is flowing into vacuum and therefore there is no

risk of forming an explosive mixture in the pipe, and the pipe does not need to be

deaerated.

Both technologies of pipeline drying used by CEPS, meet the requirements of

TPG 702 13.

related products

Together with this product are usually

Cleaning and gauging

of pipelines

Stresstests and hydrotests

of high-pressure pipelines

Page 5: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

5/6www.ceps-as.cz/en/products/drying-of-pipelines.html

provided the following products and

services

all products

High-pressure steel pipelines

rehabilitation after long-time

of operation

Decontamination of pipelines

transporting petroleum liquids

before repairs or shutdowns

Products and services

show all products and

services

related documents

More documents and other

information, see the section about

the company CEPS

all about company

ISO 9001:2008

ISO 14001:2004

OHSAS 18001:2007

ISO 3834-2:2005

About CEPS company

show everything about the

company CEPS

contact

If you have any questions, do not

hesitate to contact technical experts

and business persons of CEPS

Contact us

Ing. Aleš Brynych

executive director

phone +420 241 021 547

[email protected]

Ing. Bc. Aleš Crha

commercial director

and welding engineer

phone +420 241 021 549

[email protected]

Head office of CEPS a.s.

phone +420 241 021 511

fax +420 241 021 512

Page 6: Drying of pipelines prior to commissioning — CEPS a.s

3/25/13 Drying of pipelines prior to commissioning — CEPS a.s.

6/6www.ceps-as.cz/en/products/drying-of-pipelines.html

e-mail [email protected]

all contacts and maps

© 2013 CEPS a.s. / RSS / Genera l terms and conditions CZ / Technica l speci fications CZ /

Contacts

back to top