driiling sequencxxe costs
DESCRIPTION
xxxxTRANSCRIPT
![Page 1: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/1.jpg)
1
DRILLING SEQUENCE
�PETRONAS
�PETRONAS
I. TOP HOLE DRILLING
• REFERS TO THE SHALLOW SECTION OF THE WELL NORMALLY HAVING UNCONSOLIDATED FORMATIONS
• A BASE IS PREPARED• CELLAR FOR LAND OPERATIONS
• FIRST HOLE DRILLED AND CONDUCTOR CEMENTED OR FIRST CASING PILE DRIVEN FOR BOTH ONSHORE & OFFSHORE. [THIS STRING PROVIDES A BASE FOR THE DIVERTER]
• SURFACE HOLE IS DRILLED AND THE SURFACE CASING RUN AND CEMENTED [SURFACE CASING PROVIDES A BASE FOR THE BOP PACKAGE AND PROTECTION FOR POTABLE WATER ZONES].
�PETRONAS
�PETRONAS
![Page 2: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/2.jpg)
2
II. INTERMEDIATE & RESERVOIR SECTION.
• REFERS TO THE SECTION OF THE WELL BETWEEN SURFACE TO THE RESERVOIR SECTION(S)
• INTERMEDIATE CASING IS SET ABOVE RESERVOIR.
• PRODUCTION CASING IS SET ACROSS RESERVOIR SECTION
�PETRONAS
�PETRONAS
Drilling Operations - Making Holes
Typical Sequence of Operations :• Rig up
Sea level Conductordepth reference
Depth referencebelow derrick floor - bdfroller kelly bushing - rkb
�PETRONAS
�PETRONAS
![Page 3: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/3.jpg)
3
Install diverter
To diverter line
�PETRONAS
�PETRONAS
Surface Casing
Drilling Fluid
Drill 17 1/2”hole
�PETRONAS
�PETRONAS
![Page 4: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/4.jpg)
4
BOP Diverter(to be removed)
13 3/8” Casing(still suspended from the drill floor)
13 3/8” Casingcemented to surface
13 3/8” Casing
Prepare to remove the diverter and excess casing
�PETRONAS
�PETRONAS
13 3/8” Casing head
Fillet-Weld casing headto 13 3/8” casing
Side outlet valve
Install casing head housing
.
�PETRONAS
�PETRONAS
![Page 5: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/5.jpg)
5
BOP Stack
Ring joint flange connects BOP to
casing head
Mud Riser(allows drilling fluid
returns to mud system)
13-3/8” Casing
Install BOP stack and mud riser
�PETRONAS
�PETRONAS
Drilling Fluidreturning up
annulus
13-3/8” Casing Shoe
Drill 12 1/4”hole section
�PETRONAS
�PETRONAS
![Page 6: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/6.jpg)
6
Intermediate CasingDrilling Fluid
Cement slurrybehind casing
and in shoe track
9-5/8” Casing
Cement
9 5/8” casing
�PETRONAS
�PETRONAS
BOP Test Plug
Pressure test BOP stack
�PETRONAS
�PETRONAS
![Page 7: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/7.jpg)
7
8 1/2” Drilling assembly
9 5/8” Casing
Protection sleeve
Run 8 1/2”drilling assembly
�PETRONAS
�PETRONAS
9-5/8” Casing shoe
Drill through cap rock(impermeable formation) intoreservoir
Sandstoneor
LimestoneDrill into reservoir
Shale
Continue drilling into the reservoir
�PETRONAS
�PETRONAS
![Page 8: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/8.jpg)
8
Run electric log�
PETRONAS
�PETRONAS
Run and cement the production casing
Production casing
�PETRONAS
�PETRONAS
![Page 9: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/9.jpg)
9
Casing scraper
Bit
Run bit and casing scraper to clean out casing
Production casing
�PETRONAS
�PETRONAS
Perforate casing in selected production interval
Production casing
Perforations
�PETRONAS
�PETRONAS
![Page 10: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/10.jpg)
10
Install test string
Production casing
Production tubing
Production packer
Tail pipe
�PETRONAS
�PETRONAS
Typical Casing Configurations
Conductor
Surfacecasing
Intermediatecasing
Production casing
Production liner
Functions1. Conductor (20”-30”) to protect loose, near
surface formations and enables circulation of drilling fluid
2. Surface casing (13-3/8”- 20”) to provide blowout protection and prevent loss circulation
3. Intermediate casing (9-5/8” - 16”) to isolate unstable hole section and loss circulation, low pressure and production zones (often set in the transition between normal to abnormal zone)
4. Production (4-1/2”-9-5/8”) to isolate production zone and contains formation pressure in the event of tubing leaks
5. Liner (4-1/2” - 13-3/8”) to improve hydraulic performance during deep drilling and to allow the use of larger tubing above the liner top
6. Tieback string to provide additional pressure integrity from the liner top to the wellhead
Tieback string
�PETRONAS
�PETRONAS
![Page 11: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/11.jpg)
11
TYPICAL SEQUENCE OF DRILLING OPERATIONS
Development Well - Jack-up or Tender Assisted• Position rig• Skid rig over slot• Clean out conductor• Set cement plug• Drill top hole (pilot hole if first well)• Set surface casing• Install & test BOP• Drill intermediate hole• Set intermediate casing• Install & test BOP• Drill production hole• Run logs• Set production casing• Complete well• Skid rig
�PETRONAS
�PETRONAS
DATE OF COMPLETION : CASING :RIG : T-6 ( Tender Assisted) :TUBING : :X-MAS TREE :
PACKER FLUID : PBTD :RTE TO TBG HANGER :MAXIMUM DEVIATION :
FLOW COUPLINGSCSSV- TRSVFLOW COUPLING
X NIPPLE
FLOW COUPLINGSSDFLOW COUPLING
FLOW COUPLINGSSDFLOW COUPLING
BLAST JOINT
LOCATOR9-5/8" BWS PERM. PACKER
SBESEAL ASSYXN NIPPLECONICAL MULESHOE
EOT
3.000 3.920
SPM ( Dummy)
SPM ( Dummy)
SPM ( Dummy)
SPM ( Dummy)
14.1m ( RKB:33.9mMDDF )65.87. DEG @ mMDDF
EQUIPMENT
scavenger per 100bbls f iltered brine
CAMERON, DUAL 3-1/8" X 3-1/8" X 11", 5000PSINaCl treated w ith 4 gals DIOCIDE + 2 drums of C303 + 2 drums of Oxygen
SHORT STRING LONG STRING3-1/2", 9.2PPF, 9Cr-1Mo, AMS28 3-1/2", 9.2PPF, 9Cr-1Mo, AMS28
XN NIPPLLEPOP c/w CATCHER SUBEOT
9-5/8" BHD RET. PACKER
X NIPPLE
SPM ( Dummy)
SPM ( Dummy)
SPM ( Dummy)
SPM ( Dummy)
SCSSV - TRSVFLOW COUPLING
X NIPPLE
TYPICAL PCSB CONVENTIONAL DUAL OIL PRODUCER
FLOW COUPLING
9-5/8" 43.5PPF, N-80 @ 3422 mMDDF13-3/8" 54.5PPF,K-55 @ 1500 mMDDF26" DRIVE PIPE @ 185 mMDDF
~3422mMDDF
DEPTH
3-1/2", 9.2PPF, Carbon Steel, AMX28
mMMDF mMMDFDEPTH
MAX ODMIN IDIN IN
EQUIPMENT MAX ODIN
MIN IDIN
150.0
600.0
OP
OP/WI
160.0
600.0
3.9205.0303.920
3.960
5.310
5.310
5.310
5.310
3.960
8.457
3.9603.960
2.9002.8132.900
2.813
2.867
2.867
2.867
2.867
2.813
2.880
2.6902.964
2.9002.8132.900
2.813
2.867
2.867
2.867
2.867
2.9002.8132.900
2.9002.8132.900
2.900
2.8804.000
4.0002.8802.690
3.9205.0303.920
3.960
5.310
5.310
5.310
5.310
3.9204.4503.920
3.9204.4503.920
4.000
4.2508.120
5.0624.0003.960
I-35
HANGER
I-68
�PETRONAS
�PETRONAS
![Page 12: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/12.jpg)
12
Where thereWhere there’’s oil theres oil there’’s always Alligatorss always Alligators�
PETRONAS
�PETRONAS
DRILLING PROBLEMSa) Stuck pipe :-
Differential sticking.
Clay swelling.
Under gauge hole.
Well bore instability.
Key seating.
b) Lost circulations.
c) Equipment problems such as failures.
d) Presence of shallow gas.
�PETRONAS
�PETRONAS
![Page 13: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/13.jpg)
13
�PETRONAS
�PETRONAS
Development of a Key Seat
�PETRONAS
�PETRONAS
![Page 14: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/14.jpg)
14
FISHING
• Fish is an object left in the well bore during drilling or work over that must be recovered before work can proceed.
• Eg. of fish – parted drill pipe, lost bit cones
�PETRONAS
�PETRONAS
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
TIME, COSTAND
CONTRACTS
![Page 15: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/15.jpg)
15
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
1111
2 3 4
56 7 8
910 11 1212
13 1414 151515 161616 1718 19192020
0 4 8 12 16 20 24 28 32 36 40 44 48 52 56 60
DAYS
0
1000
2000
3000
MEA
SUR
ED D
EPTH
(m-R
KB)
Plan
DEPTH VS DAYREHMAT-3
ATTACHMENT 4
No Activity Planned Days PlannedCumm Days Plan Depth
1 Rig up. 0.30 0.30 0.00
2 Drill 26" hole to section TD. 1.09 1.39 150.00
3 Run & cemet 20" csg. Install casing head 1.13 2.52 150.00
4 N/U Diverter System. 0.50 3.02 150.00
5 Drill 17-1/2" hole (take LOT) to section TD. 10.02 13.04 1550.00
6 Run logs 0.25 13.29 1550.00
7 Run & cemet 13-3/8" csg. 1.00 14.29 1550.00
8 N/D Diverter. N/U casing head. N/U BOP. 1.00 15.29 1550.00
9 Drill 12-1/4" hole (take LOT) to section TD. 11.59 26.88 3000.00
10 Run logs 0.30 27.18 3000.00
11 Run & cemet 9-5/8" csg. 1.33 28.51 3000.00
12 N/D BOP. N/U Casing head. N/U BOP. 1.00 29.51 3000.00
13 Drill 8-1/2" hole (take LOT) to section TD. 6.64 36.14 3600.00
14 Run logging tool+wiper trip+MDT/RFT 3.00 39.14 3600.00
15 Run & cemet 7" liner / casing 1.33 40.47 3600.00
16 P/U 3-1/2" DP. 1.00 41.47 3600.00
17 Clean well & displace well to brine 1.50 42.97 3600.00
18 R/U Schlumberger. Run CBL/VDL/CCL/GR logs. 0.50 43.47 3600.00
19 Perforate zones & Complete well & gravel pack 12.00 55.47 3600.00
20 N/D BOP & N/U X-mas tree & test 0.50 55.97 3600.00
Total Days 55.11 55.97
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
DRILLING CHART
-3000
-2500
-2000
-1500
-1000
-500
00 5 10 15 20 25 30
TIME (DAYS)
DEP
TH (
M)
Mob
Drill 17 1/2”hole
Run & Cement 13 3/8”casing Drill 12 1/4” hole
Run & Cement 9 5/8”casing
Drill 8 1/2” hole
E-Log
Run & Cement 7”casing
Production Test
P&A
Demob
![Page 16: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/16.jpg)
16
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
• Actual well cost are divided into.Tangibles – casing, tubing, wellhead & x-mas tree, completion, etc.
Supplies – Drilling Fluid, cement, bit, fuel, etc.
Contracted – Rig, directional, e-log, mud log, stimulations, etc.
Allocation – salaries, transport, supply base, etc.
• This cost is further divided into Drilling, Completion, Formation Evaluation, rig operations, logistic, management and others.
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Cos
t (%
)
Misc. 5%
Logistics 10%
Rig Operations 25%
Form. Evaluation 15%
Testing 20%
Drilling 25%
COST BREAKDOWN -EXPLORATION WELLS
![Page 17: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/17.jpg)
17
COST BREAKDOWN -EXPLORATION WELLS
Cost Breakdown for a Development Well
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
CONTRACTS
VARIOUS CONTRACTS FORM NORMALLY USED IN DRILLING:-
1. Unit (Day/monthly/piece) rate contract.2. Footage contract.3. Turnkey contract.4. Incentive contract.5. Partnering & Alliancing.
![Page 18: Driiling Sequencxxe Costs](https://reader034.vdocuments.us/reader034/viewer/2022042814/552ce8e255034614108b4587/html5/thumbnails/18.jpg)
18
PETROLEUM ENGINEERING SKG-10
E & P CORE PROGRAM �PETRONAS
�PETRONAS
Where thereWhere there’’s oil theres oil there’’s always Alligatorss always Alligators
THAT’S ALL
FOLKS