  • 7/25/2019 DRAWWING CHECK GUIDE.docx

    1/1

    SLAB

    DONUT= NAMING NEAR DONUT

    HATCH= SPLICE BAR AT DIFFERENT LEVELS

    MARK BAR SPACING WHEREVER LENGTH CHANGES

    BEAM

    HATCH AT DIFFERENT LEVELS IF BEAM LEVEL IS DIFFERENT ALONG WITH

    SLAB.

    DOTTEN LINES SHOULD BE USED FOR MARKING BEAMS WHERE SLAB I

    PRESENT, OR ELSE USE STRAIGHT LINE.

    SHOW BEAM CUTTING AT INTERSECTION WITH SUNSHADE ONLY IF THERE

    IS LEVEL DIFFERENCE.

    SHOW DIMENSIONS FROM COLUMNS TO ALL THE BEAMS IN BEAM LAYOUT

    FOR EASY IDENTIFICATION OF POSITION OF BEAM AT SITE.

    SHOW CROSS MARK FOR DUCTS

    WHERE SUNKEN SLAB IS PROVIDED , BEAM NEED NOT BE MARKED INDOTTED LINE,AS BEAM WILL BE ABOVE SLAB