DRAWINGS AND DOCUMENTS REQUIRED FROM MECON RMHS(Package-I, II & VI)Sl.No Package Description
A RMHS Package-06
B RMHS Package-01
C RMHS Package-02Civil & Structural Drawings of RMHS Package-02 from JH-09 to JH-16 Alternate route profile of Conveyors i.e from JH-11A to JH-11C
Civil & Structural Drawings of RMHS Package-06 ( Priority Circuit)comprising of Screening Building, Crushing Building, JH-16, JH-,19,20,21,21A,22,23,25,26,27,30& its associated conveyorsFor Balance Civil & Execution drawings of Non Priority Circuit of RMHS Package-06
Civil & Structural Drawinmgs of RMHS Package-01 ( Priority Circuit) from Track Hopper Area and Wagon tippler Area to JH-09
![Page 2: Drawings and documents to be recieved from MECON](https://reader036.vdocuments.us/reader036/viewer/2022082419/53f19109397c8a84718b46ca/html5/thumbnails/2.jpg)
DRAWINGS AND DOCUMENTS REQUIRED FROM MECON RMHS(Package-I, II & VI)Requirement from MECON
Nov-10
Dec-10
Dec-10
Dec-10Nov-10
![Page 3: Drawings and documents to be recieved from MECON](https://reader036.vdocuments.us/reader036/viewer/2022082419/53f19109397c8a84718b46ca/html5/thumbnails/3.jpg)
STATUS OF DRAWINGS AND DOCUMENTS FROM MECON RMHS(Package-I, II & VI)Date :- 02nd October, 2010
Sl. No. Description UOM
RMHS PACKAGE - 01A TRACK HOPPER AREA
Excavation Plan for track hopper cum 100000 100000 0
Civil
a) Track Hopper cum 10500 10500 0
b) Foundation for Shed of Track hopper cum 400 0 400 Pending from MECON's ENDc) Track Hopper Area (Inhaul Side and Outhaul Side) cum 4000 0 4000 Pending from MECON's ENDTotal Qty 14900 10500 4400Structural
a) Track Hopper Shed MT 300 300 0
Total Qty 300 300 0B WAGON TIPPLER AREA
Excavation Plan for Wagon tippler cum 50000 0 50000 Pending from MECON's ENDCivil Work
cum 12000 0 12000 Pending from MECON's ENDb) Foundation for Shed of Wagon tippler cum 250 0 250Total Qty 12250 0 12250Structural a) Complete Shed of Wagon Tippler MT 500 0 500 Pending from MECON's END
C STACKER RECLAIMER
cum 22500 22500 0
D RMHS Package-01Junction Houses & Conveyors
Civil
cum 15000 0 15000
Total Qty 15000 0 15000Structural
MT 8000 0 8000
Total Qty 8000 0 8000
QTY(Tentative)
Drwng Recieved
Qty
Balance Qty drawings to be received from MECON
Status of Drawings & Documents received from
MECON till date
Excavation Plan submitted by MECON dtd 26th March,2010
MECON submitted the Civil drawings of Track hopper dtd 03rd May, 2010 & 28th June,2010, Qty=10,000 cum
MECON submitted the GA and details of Track Hopper Shed on 26th March,2010, Qty=300 MT
a) Foundation for Wagon Tippler & Side Arm Charger (02 nos)
Civil Foundation Drawing for Stacker Reclaimer including the drain and Retaining Wall with rail fixing details
MECON submitted the foundation drawing for Stacker Reclaimer on 30th June,2010,
Civil Drawings for the Conveyors Trestle foundations and Junction Houses from JH-1 to JH-9 including the tunnel from the Unloading stationi.e Wagon tippler & Track Hopper Area to JH-1 & JH-2
MECON will start submitting the civil drawings by Dec 2010
Structural drawings for the Conveyor Trestles and Junction Houses for RMHS Package-01 from Unloading Station to the JH-9
MECON will start submitting the drawings by Dec 2010
![Page 4: Drawings and documents to be recieved from MECON](https://reader036.vdocuments.us/reader036/viewer/2022082419/53f19109397c8a84718b46ca/html5/thumbnails/4.jpg)
RMHS Package-02Civil
cum 12000 0 12000
Total Qty 12000 0 12000
Structural
MT 9000 0 9000
Total Qty 9000 0 9000
RMHS Package-06Civil
cum 80000 17000 63000
Total Qty 80000 17000 63000Structural
MT 20000 5000 15000
Total Qty 20000 5000 15000TS
TS for Electricals of RMHS Package-1
TS for Electricals of RMHS Package-1
TS for Utilities anfd Fire Fighting
Total Qty Drngs received
Civil Quantity cum 156650 50000 106650 Structural Qty MT 37800 5300 32500
Civil Drawings for the Conveyors Trestle foundations and Junction Houses from JH-9 to JH-16 also includfing the alternate route from JH-11A
assignment drawings of JH-10 & JH-11 released on 30th September 2010
Structural drawings for the Conveyor Trestles and Junction Houses for RMHS Package-01 from Unloading Station to the JH-9
MECON will start submitting the drawings by Dec, 2010
Civil Drawings for the Conveyors Trestle foundations and Junction Houses from JH-16 to JH-31 including the Screening and Crushing Building and Foundations for Shed of Yards and Portal Scrapper Reclaimer-1,2,3,4,5,6
1) MECON will start submitting the civil drawings for priority circuit particularly JH-16, JH 31 Screening & Crushing Building by Nov 2010 .2) Civil execution drawings for Crushed raw Coal Shed & Middling Shed expected from MECON by Nov 2010
Structural drawings for Junction Houses from JH-16 to JH-31, Shed for Yards (04 nos), Crushing and Screening Building, Conveyor Trestles , truck Tippling Station
1600 MT of detail engineering drawing of Clean Coal Shed received from MECON dtd 26.08.2010 and will submit the balance structural drawings for priority circuit by Nov,2010 including shed of Middling Coal & Crushed Coal
Received from MECON and is in the final stage of OrderingReceived from MECON and is in the final stage of Ordering
TS for Ventilation and Air Conditioning System & Dust Suppression System for RMHS Package-06
Received from MECON on 12.09.2010 and enquiry floated to Parties on 14.09.2010
TS for Ventilation and Air Conditioning System & Dust Suppressio System for RMHS Package-01 & 02.
To be received from MECON by Nov 2010
Balance to be received
![Page 5: Drawings and documents to be recieved from MECON](https://reader036.vdocuments.us/reader036/viewer/2022082419/53f19109397c8a84718b46ca/html5/thumbnails/5.jpg)
N.B :- The structural and civil quantities mentioned are tentative and can change during the detail design engineering of the system considering the workability of the system