draft environmental assessment west carleton …draft environmental assessment west carleton...
TRANSCRIPT
Draft Environmental Assessment West Carleton Environmental Centre
6-32
chapter 6. detailed impact assessment of the undertaking
Figure 6-12 Final Operation Year – Preferred Leachate Management System Isopleths of the Maximum Predicted Odour Concentration – 10-Minute Average Period
Draft Environmental Assessment West Carleton Environmental Centre
6-33
chapter 6. detailed impact assessment of the undertaking
Figure 6-13 Final Operation Year – Contingency Leachate Management System Isopleths of the Maximum Predicted Odour Concentration – 10-Minute Average Period
Draft Environmental Assessment West Carleton Environmental Centre
6-34
chapter 6. detailed impact assessment of the undertaking
Although the maximum predicted odour concentrations at the property line are predicted to
exceed the 3 OU/m³ annoyance threshold from time to time, the MOE guidance document
indicates that odour concentrations need only be assessed at odour-sensitive receptor
locations, such as residences, commercial buildings, and outdoor parks and recreation areas.
Discrete Receptors
In the intermediate operation year, the maximum odour concentration resulting from the WCEC
operations was predicted to occur at Receptor R1, with a value of 4.2 OU/m³. The odour
concentration at Receptor R1 was predicted to exceed the detection threshold of 1 OU/m³
1.15% of the time and to exceed the annoyance threshold of 3 OU/m³ 0.15% of the time.
Predicted odours at the remaining sensitive receptors were less than the annoyance threshold.
Although predicted odours at some of the remaining sensitive receptors were predicted to
exceed the detection threshold, the frequency of exceedance of 1 OU/m³ at each of these
receptors was less that 0.5% of the time.
In the final operating year, the maximum odour concentration resulting from the WCEC
operations was predicted to occur at Receptor R3, with a value of 2.7 OU/m³. The odour
concentration at Receptor R3 was predicted to exceed the 1 OU/m³ detection threshold less
than 0.5% of the time and was not predicted to exceed the 3 OU/m³ annoyance threshold. The
predicted concentrations for all other sensitive receptors were predicted to exceed the 1 OU/m³
detection threshold less than 0.5% of the time.
Therefore, for the Preferred Leachate Management System, all sensitive receptor locations are
predicted to comply with the MOE’s current guidelines for odour, with the exception of R1 during
the intermediate operation year.
Contingency Leachate Management System results are similar to the results for the Preferred
Leachate Management System. This is consistent with the finding that the leachate evaporator
is not a main contributor to off-site odour impacts. Overall, the maximum predicted odour
concentrations for the Contingency Leachate Management System are the same as those
predicted for the Preferred Leachate Management System, while the predicted frequencies of
exceedance of the 1 OU/m³ detection threshold increased slightly at some sensitive receptor
locations.
Therefore, for the Contingency Leachate Management System, all sensitive receptor locations
are predicted to comply with the MOE’s current guidelines for odour, with the exception of R1
during the intermediate operation year.
Draft Environmental Assessment West Carleton Environmental Centre
6-35
chapter 6. detailed impact assessment of the undertaking
Potential Odour Effects
The impact of the expansion is evaluated based on the maximum predicted concentration and
frequency of time that the predicted concentration exceeds the odour detection threshold of
1 OU/m³ and the odour annoyance threshold of 3 OU/m³. The predicted odours at all of the
discrete receptors are in compliance with the MOE’s current guidelines in terms of both
predicted concentrations and frequency of predicted impacts, with the exception of Receptor 1,
with the implementation of the mitigation measures described in the following sub-section.
Predicted impacts at Receptor 1 exceed the 1 OU/m³ detection threshold 1.15% of the time and
exceed the 3 OU/m³ annoyance threshold 0.15% of the time. These predicted impacts are
slightly above the MOE guideline, which allows for predicted exceedances of the 1 OU/m³
detection threshold 0.5% percent of the time. Consequently, the impact of the expansion is
considered low at all discrete receptors for all future build scenarios, with the exception of
Receptor 1, where it is considered medium.
These results assume that the worst-case operations are occurring in the same locations for a
five-year period. In reality, the working face, which has been shown to be a dominant contributor
to off-site impacts, particularly at R1, will move to various locations within each landfill Stage
over the modelled period. The impact from the working face at a particular receptor will be
lessened as the distance between this source and the receptor increases. Therefore, the
frequencies of exceedance of the 1 OU/m³ and 3 OU/m³ thresholds at Receptor 1 may be
reduced relative to what was predicted by the dispersion modelling.
Mitigation and/or Compensation Measures for Odour
The odour assessment considered the following mitigation measures:
Development of an Odour Best Management Practices (BMP) Plan, which
will include all mitigation measures proposed, along with additional measures
determined during Detailed Design;
Progressive installation of the LFG collection system for the Preferred
Alternative Landfill Footprint;
Flaring or otherwise combusting all collected LFG;
Increase in stack height of the leachate evaporator to a minimum of 22 m
above grade;
Maintaining the leachate collection system under negative pressure and
sending the collected gas to the LFG collection system;
Minimizing the size of the working face; and,
Daily covering of the working face.
In addition to these mitigation measures, additional mitigation measures may be undertaken to
further reduce odour impacts and will be specified in the Odour BMP Plan.
Draft Environmental Assessment West Carleton Environmental Centre
6-36
chapter 6. detailed impact assessment of the undertaking
Odour Net Effects
The impact of the expansion is evaluated based on both the maximum predicted concentration
as well as the frequency of exceedance of the detection and annoyance thresholds for odour.
The maximum predicted impacts show increased odour levels relative to the baseline condition.
However, the only odour source included in the baseline scenario was the existing landfill under
final cover with full gas collection at an efficiency of 85%. The comparison indicates that the
proposed landfill expansion will result in increased detection of odours at the discrete receptors,
relative to baseline conditions; however, the detection frequencies are relatively low and are
within MOE guidelines for all receptors with the exception of Receptor R1.
6.7.1.4 Landfill Gas
The Landfill Gas Detailed Impact Assessment included the generic On-Site, Site-Vicinity, and
Regional study areas, as shown in Figure 6-3 and described below:
On-Site ............. the lands required for the Preferred Alternative Landfill Footprint;
Site-Vicinity ...... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions; and,
Regional ........... the lands within approximately 3 to 5 km of the Site and the
Preferred Alternative Landfill Footprint.
Landfill gas (LFG), although consisting mainly of methane and carbon dioxide, contains trace
amounts of volatile organic compounds (VOCs) and reduced sulphur compounds. Although
these contaminants account for less than 1% by volume of LFG escaping from the landfill, their
concentrations must be assessed because they can potentially result in health impacts at
residences or businesses that surround the landfill site. The type and concentration of
compounds within the LFG can vary greatly, depending on the composition of the decomposing
waste from which the LFG is created. Based on the Ministry of the Environment’s (MOE) Interim
Guideline to Assess Air Impacts from Landfills and the approved ToR, 24 contaminants of
interest in the LFG were reviewed. These compounds, which include 20 VOCs and 4 reduced
sulphur species, were assessed in the LFG study.
Contaminants emitted from the leachate management system were not previously assessed in
the LFG Baseline Conditions report. Contaminants emitted in common from the landfill and the
leachate management system were assessed (i.e., benzene and dichloromethane), as well as
ammonia, which is solely emitted from the leachate management system. Ammonia was
included in the LFG assessment because it is the typical contaminant of concern emitted from
leachate management systems.
Draft Environmental Assessment West Carleton Environmental Centre
6-37
chapter 6. detailed impact assessment of the undertaking
Vinyl chloride, benzene and hydrogen sulphide were selected as contaminants of particular
interest based on historical issues at the existing WCEC.
Predicted concentrations of VOCs, reduced sulphur compounds, and ammonia were compared
against Ontario Regulation 419/05 Air Pollution, Local Air Quality (O.Reg. 419) Point of
Impingement (POI) Standards.
The on-site sources of VOCs and reduced sulphur compounds include the existing landfill
mound under final cover, the Preferred Alternative Landfill Footprint and associated sources
(i.e., working face and contaminated soil stockpiles), the landfill gas-fired engines, the LFG
flares, and the leachate management system (preferred and contingency methods).
The evaluation considered the potential impacts from the Site sources including the Preferred
Alternative Landfill Footprint at 24 discrete receptor locations (refer to Figure 6-14),
representing receptors of interest in the Site-Vicinity and the Regional study areas. The discrete
receptor locations, considered in the dispersion model, include nearby residences, schools,
businesses, and other sensitive receptor locations. For all cases, humans were assumed to be
present at these receptors for 24 hours per day. Further details on LFG sources, receptors, and
dispersion modelling are found in the Atmospheric (Landfill Gas) Detailed Impact Assessment
Report in Supporting Document #5 – Detailed Impact Assessment.
The potential air quality impacts that would result from the construction and operation of the
proposed Preferred Alternative Landfill Footprint were assessed at the worst case future build
stages and phases of development. The future build scenarios were assessed by determining
odour associated with the significant emission sources in each scenario and determining the
potential off-site impacts through dispersion modelling. The scenarios assessed include the
intermediate operation scenario (Year 2018) and final operation scenario (Year 2023). In
addition to the two operation scenarios, two proposed leachate management methods used to
treat the leachate were assessed: the preferred method (pre-treatment with discharge to City of
Ottawa sanitary sewer) and the contingency method (pre-treatment with leachate evaporator).
Landfill Gas Methodology/Additional Investigations
The LFG impacts from the existing landfill and the Preferred Alternative Landfill Footprint
conditions were determined using a dispersion model and reasonable worst-case emission
rates. Dispersion modelling was performed using the U.S. EPA’s AERMOD dispersion model
(AERMOD) to predict concentrations of LFG emitted from the WCEC preferred alternative
existing landfill at various receptors in the Study Area.
Draft Environmental Assessment West Carleton Environmental Centre
6-38
chapter 6. detailed impact assessment of the undertaking
Figure 6-14 Landfill Gas Detailed Impact Study Area and Receptor Locations
Draft Environmental Assessment West Carleton Environmental Centre
6-39
chapter 6. detailed impact assessment of the undertaking
Detailed Description of the Environment Potentially Affected by Landfill Gas
On-Site and Site-Vicinity
Maximum predicted concentrations did not exceed the applicable standards for any of the 24
contaminants of interest.
The maximum predicted off-site concentrations associated with the construction and operation
of the Preferred Alternative Landfill Footprint including the preferred leachate management
system is predicted to occur in 2018 scenario near the northeast corner of the facility. The vinyl
chloride concentrations are predicted to be the highest concentrations relative to the
corresponding limit. The maximum predicted 24-hour vinyl chloride concentration was
0.73 µg/m3, which represents 73% of the Schedule 3 Standard of 1 µg/m3. The predicted vinyl
chloride concentration was influenced by both emissions from the landfill mound as well as
emissions from the leachate treatment system (SBR).
Hydrogen sulphide was the only contaminant which had the calibration factor applied. The
maximum predicted calibrated hydrogen sulphide 24-hour concentration at any off-site location
in 2018 was 1.68 µg/m3, which represents 24% of the Schedule 3 Standard of 7 µg/m3.
The maximum predicted concentration of hydrogen sulphide in 2018 is influenced by the close
proximity of the most recently developed stage (Stage 1), to the property line. For conservative
purposes, it was assumed that the installation of the LFG collection system in Stage 1 in 2018 is
not complete and the gas collection efficiency is approximately 50% for this Stage. Landfill
sources with such reduced gas collection efficiency are generally the most dominant in causing
off-site impacts. Although the Preferred Alternative Landfill Footprint in the 2023 scenario
generates more LFG and also has an active stage (Stage 8) with a reduced gas collection, the
location Stage 8 is not as close in proximity to the property and therefore the 2023 scenario
concentration is not as influenced by this source as it is in the 2018 scenario. Consequently, the
maximum concentrations predicted throughout the future operating scenarios occurred in 2018.
Discrete Receptors
Predicted 24-hour vinyl chloride, benzene and hydrogen sulphide concentrations did not exceed
the POI limit or criteria at any of the receptors. The predicted 10-minute hydrogen sulphide
concentrations at the discrete receptors did not exceed the POI limit or criteria at any of the
receptors. The hydrogen sulphide concentrations were evaluated against the 10-minute
averaging standards only at the discrete receptors, in accordance with the MOE’s “Methodology
for Modelling Assessments of Contaminants with 10-Minute Average Standards and Guidelines
under O.Reg 419/05” Technical Bulletin.
Draft Environmental Assessment West Carleton Environmental Centre
6-40
chapter 6. detailed impact assessment of the undertaking
Maximum concentrations are predicted to occur at Receptor 2 (southeast corner of the WCEC
facility) for most of the time, with exception of the 10-minute hydrogen sulphide maximum
concentration which occurs at Receptor 3 (west of the WCEC facility) for all future build years.
Potential Landfill Gas Effects
For both the preferred leachate management system and the contingency leachate
management system, the maximum predicted concentrations are less than the applicable
standards or criteria at all receptors in the area, including both the discrete receptors and the
receptor grid. Consequently, the impact of the expansion is considered low at all discrete
receptors for all future build scenarios.
Mitigation and/or Compensation Measures for Landfill Gas
The LFG assessment considered several mitigation measures that are part of the design of the
preferred landfill alternative and include the following:
Development of an LFG BMP Plan which will include all mitigation measures
proposed, along with additional measures determined during Detailed Design;
Progressive installation of the LFG collection system for the Preferred
Alternative Landfill Footprint;
Flaring or otherwise combusting all collected LFG;
Increase in stack height of the leachate evaporator to a minimum of 22 m
above grade;
Maintaining the leachate collection system under negative pressure and
sending the collected gas to the LFG collection system;
Minimizing the size of the working face; and,
Daily covering of the working face.
In addition to these mitigation measures additional mitigation measures may be undertaken to
further reduce LFG impacts. These additional mitigation measures will be specified in the LFG
BMP Plan.
Landfill Gas Net Effects
The proposed landfill expansion will result in increased concentrations of the LFG compounds at
the discrete receptors, relative to baseline conditions; however, the maximum predicted
concentrations are within MOE guidelines for all receptors and all off-site locations. The
predicted concentrations at the discrete receptors and all other off-site locations do not exceed
the applicable standards or criteria under the preferred leachate management system or the
contingency leachate management system. Consequently, the impact of the expansion is
considered low at all discrete receptors for all future build scenarios.
Draft Environmental Assessment West Carleton Environmental Centre
6-41
chapter 6. detailed impact assessment of the undertaking
6.7.1.5 Noise
For the purposes of the Noise Detailed Impact Assessment, the On-Site Study Area includes
the lands owned or optioned by WM within the area enclosed by Highway 417, Richardson Side
Road, and Carp Road. The Site-Vicinity Study Area includes the area within 500 m of the On-
Site Study Area and the Regional Study Area stretches approximately 5 km from these lands
(refer to Figure 6-15).
Receptors of interest under MOE’s Noise Guidelines for Landfill Sites include noise-sensitive
land uses to be permanent or seasonal residence, hotels/motels, nursing/retirement homes,
rental residences, hospitals, camp grounds, as well as noise sensitive buildings such as schools
and places of worship.
As part of the undertaking WM will exercise property options within the On-Site Study Area. This
will result in current noise-sensitive receptors leaving the On-Site Study Area during the life of
the proposed undertaking. As a result, On-Site noise impacts have not been considered, as
there will be no noise-sensitive receptors within the Study Area.
The receptors considered within the Site-Vicinity include the following:
2-storey home on Richardson Side Road NNW (PR4);
2-storey home David Manchester Road (PR9);
1-storey home at 2485 Carp Road North (NR1);
2-storey home at 2166 Carp Road East (NR2);
2-storey home at 292 Moonstone Road South (NR4);
2-storey Terrace Youth Residential Services (NR8);
2-storey Sensitive Business Operation (NR9);
2-storey David Manchester Road Central (RR12);
2-storey at 607 William Mooney Road (RR14); and
2-storey Wilbert Cox Drive (RR15).
Draft Environmental Assessment West Carleton Environmental Centre
6-42
chapter 6. detailed impact assessment of the undertaking
Figure 6-15 Noise Detailed Impact Study Area and Receptor Locations
Draft Environmental Assessment West Carleton Environmental Centre
6-43
chapter 6. detailed impact assessment of the undertaking
Receptor NR1 is a single dwelling that is located on a single large parcel of land bounded by
Richardson Road to the north, Carp Road to the east, William Mooney Road to the west and the
proposed WCEC Landfill site boundary to the south. This parcel of land is designated Carp
Road Corridor Rural Employment Area in the City of Ottawa’s Official Plan and Light Industrial
within the Carp Road Corridor Community Design Plan. The zoning for this property is Rural
General Industrial. This parcel of land is currently non-conforming with future planned uses and
any future residential development in this parcel of land is not permitted. The noise assessment
therefore assumes any future use of this land would be commercial/industrial. Only the existing
single dwelling, located to the northeast of this parcel, has been used in the assessment and
identified as NR1.
Two site-vicinity residential receptors (PR4 and PR9) and one regional receptor (PR7) were
selected to account for the worst-case noise impacts from WCEC sources.
The receptors considered within the Regional Study Area include the following:
2-storey home at 2096 Carp Road South (PR7);
St. Stephen Catholic Elementary School (NR5);
Huntleigh United Cemetery (NR6);
Lloydalex Park (NR7);
2-storey Spruce Ridge Road Central (RR10);
2-storey David Manchester Road North (RR11);
2-storey David Manchester Road South (RR13);
2-storey Carp Road North (RR16);
2-storey Oak Creek Road (RR17);
2-storey West Carleton Industrial Park (RR18);
2-storey Timbermere (RR19);
2-storey Stittsville (RR20);
2-storey Jackson Trails (RR21);
2-storey Fairwinds (RR22);
2-storey Arcadia (RR23); and,
2-storey Kanata West (RR24).
Further details on noise sources, receptors, and dispersion modelling are found in the
Atmospheric (Noise) Detailed Impact Assessment Report in Supporting Document #5 –
Detailed Impact Assessment.
Draft Environmental Assessment West Carleton Environmental Centre
6-44
chapter 6. detailed impact assessment of the undertaking
Noise Methodology/Additional Investigations
The detailed assessment of environmental noise from the Preferred Alternative Landfill Footprint
focussed on landfill and construction operations as the major activities. The noise assessment
was completed by:
Reviewing available land use, traffic, and design data;
Determining the noise sources associated with the Preferred Alternative
Landfill Footprint landfill and construction operations;
Estimating sound emissions from sources using measured or theoretical
methods;
Establishing a three dimensional acoustic model of the project to predict
WCEC expansion noise levels;
Comparing predicted noise levels to the criteria contained in the MOE’s Noise
Guidelines for Landfill Sites; and
Assessing landfill noise levels cumulatively with background sound levels.
Noise impact modelling was completed using Cadna/A, a commercially available software
package implementing the ISO 9613 environmental noise propagation algorithms, and took into
account the following factors:
Source sound power level and directivity;
Distance attenuation;
Source-receptor geometry including heights and elevations;
Barrier effects of the facility, the surrounding buildings and surrounding
topography;
Duration of events;
Ground and air (atmospheric) attenuation;
Temperature and humidity effects on propagation; and,
Moderate downwind or inversion conditions (per the ISO 9613 standard,
where sound contributions at a receptor from multiple sources are calculated
under a downwind condition, regardless of spatial orientation).
The determination of change in environmental noise is rated based on both compliance with
applicable regulation, as well as the degree of change expected in the cumulative noise
environment. The criteria relevant to the WCEC EA are the MOE “Stationary Source” guidelines
for Class 2 (suburban) and Class 3 (rural) areas as set out in MOE Publication NPC-205 and
NPC-232, and the MOE Noise Guidelines for Landfill Sites.
Draft Environmental Assessment West Carleton Environmental Centre
6-45
chapter 6. detailed impact assessment of the undertaking
The criteria define the amount of noise that may be generated by activities on the Preferred
Alternative Landfill Footprint for the WCEC. Where the existing background noise levels exceed
these criteria, facility generated noise must not exceed the existing background level.
The MOE criteria establish the allowable noise contributions from the WCEC landfilling and
stationary source activities separately. To evaluate the amount of change in noise levels at
receptors, a cumulative approach is required. The changes in noise levels were determined by
comparing the existing environmental noise levels (including the Ottawa WMF, its gas collection
system and traffic) with the expected future noise levels due to the landfill expansion, gas
collection system, leachate treatment system and traffic. The definition of an effect will be based
on the “Just Noticeable Difference (JND)” of about 3 dBA. The JND is a defined value regarding
human response to sound. In cases where the change in sound level due to the WCEC is
greater than 3 dBA, mitigation/compensation is recommended to reduce the net effects.
Sound Level Increase[1]
(dB)
Qualitative Assessment of Change
1 to 3 Just Noticeable
3 to 6 Clearly Noticeable
6 to 9 Substantial Change
9 and over Very Substantial Change
Notes: [1 The increase in sound level at the receptor from the existing
condition to the proposed condition.
Detailed Description of the Noise Environment Potentially Affected
Existing noise levels within the environmental noise study area are influenced by traffic on
Richardson Side Road, Carp Road, Highway 417 and Highway 7. Natural sound also influences
the cumulative noise environment.
On-Site
The existing On-Site environment will include the LFG to energy facility and associated traffic.
Site-Vicinity
The sound levels surrounding the WCEC will be influenced primarily by road traffic noise from
along Richardson Side Road, Carp Road, Highway 7, and Highway 417. No existing noise
regulated industry surrounding the WCEC was identified or considered in this assessment as
discussed in consultation with the MOE. As such, only traffic noise impacts have been
considered for the assessment of the baseline noise conditions at Site-Vicinity receptors.
Draft Environmental Assessment West Carleton Environmental Centre
6-46
chapter 6. detailed impact assessment of the undertaking
Regional
The baseline noise levels in the Regional Study area are influenced by the existing sources on
the WCEC, surrounding light and heavy industrial activity, and traffic. However, only traffic noise
was considered in establishing baseline conditions on a regional scale.
Potential Noise Effects
The applicable guideline limit for steady-state sources may be exceeded by approximately
6 dBA at NR1. Similarly, predicted impulsive sound levels at receptors NR1, NR2, NR4, and
NR8 indicate the applicable guideline limit may be exceeded by 1 to 5 dBA. The potential
changes to noise levels are approximately 0.1 dBA with the addition of landfill traffic on public
roadways. Due to the large existing volumes of traffic, and the fact that most of the landfill traffic
will use Highway 417, the effects are considered negligible and are not carried into the net
effects assessment.
The potential effects of noise are the combined sound level contributions from the baseline
noise condition and all proposed WCEC landfill activities. The potential effects and sound level
increase from existing conditions are presented in Table 6-3. The results show that receptors in
the Site-Vicinity may experience changes in sound levels of up to 6 dBA in the daytime due to
landfilling. Regional receptors may experience potential change of up to 1 dBA, assuming
minimal influence from other local noise sources. This amount of change is not expected to be
noticeable, as background at these locations may have other local sources influencing noise
levels and the amount of change predicted is below 3 dBA.
Mitigation and/or Compensation Measures for Noise
Basic noise controls that were assumed to exist or be maintained at the WCEC were
incorporated into the noise modelling. These controls were either integral to the facility design or
assumed to be implemented. The specific controls considered include the following:
All WM trucks should use standard (factory) silencers and be kept in good
working order;
Stationary sources are enclosed in buildings where practical;
The existing landfill height of approximately 172 m will act as a berm for
receptors to the south;
The finished height of the preferred landfill footprint of approximately 156 m
will act as a berm for receptors to the north for sources travelling on the main
access road; and
Conduct construction and landfill operations between the hours of 7:00 am
and 7:00 pm to reduce the potential impacts.
Draft Environmental Assessment West Carleton Environmental Centre
6-47
chapter 6. detailed impact assessment of the undertaking
Table 6-3 Potential Increase in Sound Levels over Existing Conditions – Landfill Operations
Point of Reception
ID Point of Reception (PoR) Description
Resulting Landfill Guideline Limit
[1]
(dBA)
Cumulative Sound Level
[2]
(dBA)
Overall Increase in Sound Level
[3]
(dBA)
Sit
e V
icin
ity
Re
ce
pto
rs
PR4 2-storey home on Richardson Side Road NNW 56 58 2
PR9 2-storey home David Manchester Road 59 60 --
NR1 1-storey home at 2485 Carp Road North 55 61 6
NR2 2-storey home at 2166 Carp Road East 60 61 --
NR4 2-storey home at 292 Moonstone Road South 64 65 1
NR8 2-storey Terrace Youth Residential Services 57 59 1
NR9 2-storey Sensitive Business Operation 64 65 1
RR12 2-storey David Manchester Road Central 63 63 --
RR14 2-storey at 607 William Mooney Road 61 62 1
RR15 2-storey Wilbert Cox Drive 55 57 2
Reg
ion
al
Re
ce
pto
rs
PR7 2-storey home at 2096 Carp Road South 60 61 --
NR5 St. Stephen Catholic Elementary School 55 55 --
NR6 Huntleigh United Cemetery 55 56 1
NR7 Lloydalex Park 55 55 --
RR10 2-storey Spruce Ridge Road Central 55 55 --
RR11 2-storey David Manchester Road North 60 60 --
RR13 2-storey David Manchester Road South 55 55 --
RR16 2-storey Carp Road North 55 56 1
RR17 2-storey Oak Creek Road 61 62 --
RR18 2-storey West Carleton Industrial Park 55 56 1
RR19 2-storey Timbermere 55 55 --
RR20 2-storey Stittsville 55 55 --
RR21 2-storey Jackson Trails 55 55 --
RR22 2-storey Fairwinds 55 55 --
RR23 2-storey Arcadia 55 55 --
RR24 2-storey Kanata West 55 55 --
Notes: - All values shown are rounded to the nearest digit. Any apparent discrepancies are due to rounding.
[1] The higher of MOE Landfill guideline limit or background sound level (see Table C3.1). This is also referred to as the “baseline
noise condition”.
[2] Cumulative sound levels include contributions from the baseline noise conditions, total landfill activities and total ancillary
facilities.
[3] Change from baseline noise condition.
Draft Environmental Assessment West Carleton Environmental Centre
6-48
chapter 6. detailed impact assessment of the undertaking
Investigation of potential mitigation measures indicates that placement of temporary berms at
the active working faces could sufficiently control noise levels at NR1. In the worst-case
scenario, 7 m berms (i.e., blocking line of sight and 4 m above the equipment) placed at both
the construction and landfilling working faces for operations occurring at grade in cells 1 and 3
(north-eastern cells) would result in a daytime noise level of approximately 55 dBA at NR1,
which complies with the MOE landfill criteria. The berm heights at the working faces can
gradually decline with increase in separation distance from the receptor as the activities migrate
west and south. At a minimum, the berms should block line of sight and be 1 m above the
equipment in north-western cells (cells 5 and 7). The progression of landfilling from north to
south allows the use of the landfill itself as a berm to further reduce noise impacts. Therefore,
berms are not required for landfilling or construction activities in the southern cells. In addition,
aligning the initial site preparation activities with quarry operations east of Carp (i.e., during
summer months) would account for elevated background sound levels.
Mitigation for the potential exceedance of applicable criteria for impulsive sources may be
problematic. Impulsive sources that show potential to exceed the criteria are propane cannons.
Propane cannons are a directional noise source. The current predictions assume no advantage
due to directionality. The degree of potential exceedance for these sources is 5 dBA or less, so
careful placement of the cannons in a manner that they are pointed away from the residences is
expected to mitigate any effects. This should be verified through measurement during
operations.
The use of trained raptors, such as falcons, and other visual deterrent techniques should be
considered as a bird control alternative.
Noise mitigation needs will vary over the life of activity in the Preferred Alternative Landfill
Footprint depending on the spatial arrangement of equipment in the landfill, including the landfill
height.
Noise Net Effects
The modelling results indicate that landfill activity located on the Preferred Alternative Landfill
Footprint will generate noise at some of the receptors in the Site Vicinity but is expected to
comply with MOE requirements once mitigation is applied. Noise levels at some of the
representative receptors may be affected by landfill activity, but the amount of change is not
expected to be noticeable.
Draft Environmental Assessment West Carleton Environmental Centre
6-49
chapter 6. detailed impact assessment of the undertaking
6.7.2 Geology and Hydrogeology
The specific On-Site, Site-Vicinity, and Regional study areas for the Geology and Hydrogeology
Detailed Impact Assessment are shown in Figure 6-16 and described as follows:
On-Site .............. the lands required for the Preferred Alternative Landfill
Footprint and includes the area immediately north of the
existing landfill footprint and extends west to William Mooney
Road, east to Carp Road and north to the northern boundary of
lands under option to Waste Management;
Site-Vicinity ....... the lands in the vicinity of the Preferred Alternative Landfill
Footprint, extending about 500 m in all directions, including the
licensed area of the existing WM Ottawa WMF landfill and the
Contaminant Attenuation Zones (CAZs); and,
Regional ............ the lands within natural hydrogeologic boundaries, including
Huntley Creek to the north, Feedmill Creek to the south, and
extending to Carp River in the east. The upgradient boundary
of the Regional Study Area coincides with the boundary of the
Site-Vicinity Study Area.
6.7.2.1 Geology and Hydrogeology Methodology/Additional Investigations
The environmental characteristics of the Study Area were reviewed based on the FCR to verify
the accuracy of the assessment of net effects from the Preferred Alternative Landfill Footprint.
From this review, it was determined that the SWM ponds identified in the preliminary landfill
design could have potential effects on groundwater flow and contaminant transport within the
On-Site and Site-Vicinity Study Areas. Consequently, a detailed groundwater modelling
investigation was conducted in order to assess the potential effects on the Geology and
Hydrogeology discipline from the preliminary landfill design.
The results from the initial modelling exercise to identify potential effects led to the development
of additional mitigative measures that are predicted to achieve acceptable net effects from the
Preferred Alternative Landfill Footprint.
The predicted potential effects, mitigation measures and net effects are described in the
following subsections.
Draft Environmental Assessment West Carleton Environmental Centre
6-50
chapter 6. detailed impact assessment of the undertaking
Figure 6-16 Geology and Hydrogeology Detailed Impact Assessment Study Area
Draft Environmental Assessment West Carleton Environmental Centre
6-51
chapter 6. detailed impact assessment of the undertaking
6.7.2.2 Detailed Description of the Geology and Hydrogeology Environment Potentially
Affected
On-Site Study Area
Topography and Drainage
The On-Site Study Area consists of well-drained sandy areas, representing the upland side of a
post-glacial beach ridge. The topography is flat-lying on the western half of the property with an
elevation of approximately 125 mASL, and slopes downward toward the eastern edge of the
ridge, reaching approximately 120 mASL. The land surface has been modified by former
aggregate extraction activities and landfill operations on the south half of the On-Site Study Area.
Surface drainage on the southern half of the On-Site Study Area is controlled by ditches and a
SWM pond. Surface flow is from the southwest to northeast across the south half of the
property, and the majority of surface water flow in this area collects in shallow ponded areas. On
the north half of the On-Site Study Area, surface water flow follows the land contours and
agricultural ditches in a northerly orientation. Surface drainage collects in Huntley Creek, which
ultimately flows into the Carp River.
Geology
Overburden deposits were found to be relatively homogeneous, grading from sand-gravel in the
eastern portion along the post-glacial beach ridge, to fine sand further west, away from the edge
of the ridge. The overburden thickness ranges from approximately 4 to 16 m. The bedrock
surface slopes toward the north and northeast.
The bedrock consists of light to medium grey, fine to medium-grained fossiliferous limestone
with some shaly and sandy interbeds. The bedrock is classified as the Bobcaygeon Formation,
which is described regionally as a limestone with shaly partings and intermittent sandstone. The
bedrock is generally most fractured in the upper few metres, although at the western end of the
On-Site Study Area, relatively high fracture frequencies are observed for 5 to 10 m below the
bedrock surface.
Hydrogeology
Shallow groundwater flow generally follows the trend in bedrock surface topography.
Groundwater flows in a northerly orientation on the western half of the On-Site Study Area, and
gradually becomes northeasterly across the eastern portion. In the northwest corner of the
existing landfill, there is localized groundwater mounding which results in a small component of
Draft Environmental Assessment West Carleton Environmental Centre
6-52
chapter 6. detailed impact assessment of the undertaking
flow to the northwest in the immediate vicinity of the landfill mound; however, the natural
hydraulic gradient, which is oriented north-northeast, controls the direction of flow further away
from the landfill mound.
The groundwater elevations in the deep bedrock are similar to the trend in overburden-shallow
bedrock, with the regional groundwater flow in the deep bedrock being toward the northeast.
With few exceptions, the water quality parameters from monitoring wells screened in the
overburden-shallow bedrock on the western side of the On-Site Study Area are within the
expected range of background concentrations.
The southern boundary of the On-Site Study Area lies along the northern edge of the existing
landfill. Groundwater monitoring completed as part of the regular environmental monitoring
program for the operating landfill site has shown that leachate-impacted groundwater is moving
northward away from the landfill, in a direction consistent with the local groundwater flow.
Elevated concentrations of dissolved parameters are also seen downgradient of the SWM pond,
in a former area of biosolids storage.
Site-Vicinity Study Area
Topography and Drainage
Within the Site-Vicinity Study Area, the natural topography, which has been modified by
extraction and waste disposal activities, ranges from an elevation of approximately 131 mASL
southwest of the landfill site to less than 110 mASL on the Huntley Quarry property, located east
of Carp Road.
North and west of the existing landfill site, surface drainage flows within the Huntley Creek
subwatershed. Tributaries of Huntley Creek generally flow northward to Richardson Side Road,
and then eastward past Carp Road. Huntley Creek discharges to Carp River east of Huntmar
Road.
From within the boundaries of the existing landfill property, there is minimal direct off-site
discharge of surface water. Surface water drainage is primarily contained within the landfill
property and is directed to on-site ponds. The exceptions to this are the external slopes of the
vegetated site perimeter berms along the east and south boundaries of the landfill property;
however, this amount of surface runoff is very minor and is not in contact with operational
activities at the landfill. Runoff from the vegetated berms flows into the Carp Road and Highway
417 drainage systems. There is also a small area of drainage from the extreme western end of
Draft Environmental Assessment West Carleton Environmental Centre
6-53
chapter 6. detailed impact assessment of the undertaking
the site, north of the service entrance, which flows into the ditch along William Mooney Road,
and then northward into a tributary of Huntley Creek.
The Highway 417 drainage system controls surface water flow immediately south of the existing
landfill property. Surface water drainage south of the landfill property is controlled by ditches,
catch basins and culverts along Highway 417 and generally flows from west to east, eventually
reaching Feedmill Creek and ultimately Carp River.
Surface water drainage on the quarry property on the east side of Carp Road is influenced by a
series of excavated ponds that are used as a recirculation system for on-site aggregate washing
and dust control.
Geology
The surficial geology across the Site-Vicinity Study Area reflects the glacial history of the Ottawa
region. The unconsolidated deposits observed during subsurface investigations consist
principally of sand, silt, gravel and glacial till, and range in thickness from approximately 3 to
17 m. The surficial deposits are interpreted to be ice-contact stratified drift sediments, consisting
of a mixture of poorly to well-sorted, stratified gravels and sands, interbedded with a silty sand-
gravel till. The deposits are interpreted to have been submerged during the Champlain Sea
encroachment, and therefore show indications of re-working in a subaqueous environment.
The bedrock surface generally slopes toward the northeast across the Site-Vicinity Study Area,
ranging between elevations of 125 mASL and 108 mASL. The bedrock surface features two
apparent topographic highs: one located near the southwest extremity of the study area, and the
other in the western portion of the existing landfill site.
Bedrock consists of light to medium grey, fine to medium-grained fossiliferous limestone with
some shaly and sandy interbeds. The bedrock is classified as the Bobcaygeon Formation which
is described regionally as a limestone with shaly partings and intermittent sandstone. The
bedrock is generally most fractured in its upper few metres, while the frequency of fractures in
the bedrock decreases starting at depths of approximately 6 to 8 m below the bedrock surface.
Hydrogeology
In the higher topographic elevations along Carp Road, the water table in the unconsolidated
deposits (i.e., sand, silty sand and silty sand-gravel till) is generally found at over 10 m depth,
indicating that the majority of the unconsolidated deposits are unsaturated. The saturated
thickness of these deposits, which represents the water table aquifer, is generally limited to 5 m
or less. In areas where the bedrock is closer to the surface or where the topographic elevations
Draft Environmental Assessment West Carleton Environmental Centre
6-54
chapter 6. detailed impact assessment of the undertaking
decline, the depth to the water table decreases, however, the saturated thickness remains
limited. Groundwater is also found in the weathered bedrock at the overburden-bedrock
interface. This part of the unit extends to a depth of approximately 6 to 8 m below the bedrock
surface.
Shallow groundwater flow within the Site-Vicinity Study Area generally follows the bedrock
topography, with a water table elevation varying from 128 to 129 mASL in the southwest portion
of the landfill property to less than 112 mASL east of Carp Road. The direction of groundwater
flow within the overburden-shallow bedrock in the southwest portion of the study area is towards
the north-northeast. In the northwest corner of the existing landfill site, the topographic high
present in the bedrock appears to influence shallow groundwater flow and induces an area of
localized northwesterly flow toward the northwest corner of the site. Across the majority of the
study area, the direction of groundwater flow in the overburden-shallow bedrock is towards the
northeast.
The regional direction of groundwater flow in the deep bedrock is interpreted to be toward the
northeast. Groundwater flow in the deep bedrock is interpreted to be influenced by isolated
fracture zones, which do not appear to be well-connected across most of the Site-Vicinity Study
Area. However, across the western portion of the Site-Vicinity Study Area, where the bedrock is
found at shallower depths, the hydraulic heads in the deep bedrock zone are generally more
consistent with those in the overburden-shallow bedrock zone than they are on the eastern
portion of the study area. This indicates that there may be more hydraulic connectivity between
the shallow and deep hydrostratigraphic units in this area.
The groundwater quality within the Site-Vicinity Study Area is highly variable due to influences
on natural groundwater quality from the existing landfill, major transportation corridors,
aggregate processing, and local agricultural/commercial/industrial practices.
Regional Study Area
Topography and Drainage
The Regional Study Area consists of sandy upland areas in the northwest and west to poorly
drained swampy areas, clay plains and the Carp River floodplain toward the northeast. The
primary natural topographic feature in the area is a northwest-southeast trending sand and
gravel ridge, which has historically been exploited for aggregate extraction.
Within the area, the natural topography, which has been modified by extraction and waste
disposal activities, ranges from an elevation of approximately 131 mASL southwest of the
existing landfill site to less than 100 mASL along Carp River. The dominant man-made
Draft Environmental Assessment West Carleton Environmental Centre
6-55
chapter 6. detailed impact assessment of the undertaking
topographic features in the study area are the WM Ottawa Landfill, which extends to an
elevation of approximately 172 mASL, and the Huntley Quarry, which has been mined to a floor
elevation of less than 75 mASL.
The Regional Study Area is situated within the Carp River watershed. The watershed drains
approximately 306 km2 of land in the northwestern portion of the City of Ottawa. Carp River is
located approximately 4 km northeast of the existing landfill and discharges to the Ottawa River
at Fitzroy Harbour, approximately 20 km northwest of the landfill property. Surface drainage
within the Regional Study Area is controlled by the ground surface topography and small
tributaries of Carp River, as modified by the surrounding quarry and landfill operations and the
Highway 417 drainage system.
Geology
The surficial deposits in the Regional Study Area consist of glacial and related materials from
the late Wisconsian glaciation. During this glacial period, thick sequences of sand and gravel
were deposited along the Ottawa River valley, followed by deposits of silt and clay during
encroachment of the Champlain Sea.
The materials observed in the vicinity of the WM Ottawa Landfill are interpreted to be ice-
contact stratified drift sediments, consisting of a mixture of poorly to well-sorted, stratified
gravels and sands, interbedded with lenses of silty sand-gravel till. The deposits are interpreted
to have been submerged during the Champlain Sea encroachment, and therefore show
indications of re-working in a nearshore, subaqueous environment. Closer to Carp River, thick
deposits of silt, clay and organic materials (peat and muck) have been deposited in a lower
energy, offshore marine environment consistent with the deeper waters of the Champlain Sea.
Organic deposits are found on the southeastern portion of the quarry property, east of Carp
Road.
The Regional Study Area is underlain by several carbonate rock-types. Throughout the majority of
the portion of the Regional Study Area that also encompasses the Site-Vicinity and On-Site,
bedrock consists of grey, fine to medium-grained fossiliferous limestone with some shaly or sandy
interbeds of the Bobcaygeon Formation, a member of the Middle Ordovician-aged Ottawa Group.
Within the Regional Study Area, the Bobcaygeon Formation is in contact with interbedded silty
dolostone, limestone, shale and sandstone of the underlying (older) Gull River Formation and
overlying (younger) Verulam Formation, which are classified as limestone with shale interbeds.
Both formations are also members of the Middle Ordovician-aged Ottawa Group.
The bedrock surface generally slopes at less than 1 degree in a northeasterly direction under
the Regional Study Area.
Draft Environmental Assessment West Carleton Environmental Centre
6-56
chapter 6. detailed impact assessment of the undertaking
The Paleozoic formations in the Ottawa area are transected by steeply dipping normal faults,
three of which are found within the Regional Study Area oriented from northwest to southeast.
Carp River follows the orientation of the Hazeldean Fault, which separates the Paleozoic
bedrock found within the Regional Study Area from the much older Precambrian rocks that
compose the Carp Ridge northeast of the study area. A second line of faults separates the
Bobcaygeon and Verulam Formations east of the Huntley Quarry. A third fault has been
mapped west of the existing landfill, separating the Gull River and the Bobcaygeon Formations.
Hydrogeology
Groundwater occurs within the unconsolidated overburden units and the Paleozoic bedrock
fracture systems found within the Regional Study Area. The general direction of regional
groundwater flow is northeast toward Carp River. Water table elevations range from
approximately 135 m southwest of the existing landfill to between 92 and 105 m along Carp
River.
Locally, groundwater recharge occurs along the sand and gravel ridge and upland areas
extending north and south of the existing landfill. Overall, the western portion of the Regional
Study Area is interpreted as having strong to weak downward gradients, indicating that these
areas are considered recharge zones. Closer to Carp River, groundwater discharge zones
occur, with upward hydraulic gradients becoming more pronounced in proximity to the river.
Groundwater quality within the Carp River watershed is generally acceptable for potable usage,
and is free from recognizable regional-scale groundwater impacts. Non-health related water
quality parameters, such as total dissolved solids, hardness, iron, sulphate and chloride
commonly exceeded the Ontario Drinking Water Standards, although the concentrations in the
groundwater tend to vary considerably with the type of bedrock formation. In general, the
regional groundwater quality reflects the characteristics of the limestone bedrock, being
dominated by calcium carbonate (hardness) and also containing iron and sulphur compounds
(sulphate, hydrogen sulphide) from the shaley interbeds.
6.7.2.3 Future Baseline Geology and Hydrogeology Conditions
Computer modelling simulations were used to predict future conditions for groundwater flow and
quality in the On-Site and Site Vicinity areas. The simulations were run using chloride as an
indicator of contaminant movement, because of its conservative nature in dissolved phase
transport. Whether chloride is appropriate to be used as a monitoring indicator and compliance
trigger for the site will be determined during the detailed design phase of the landfill and the
development of an Environmental Monitoring Plan.
Draft Environmental Assessment West Carleton Environmental Centre
6-57
chapter 6. detailed impact assessment of the undertaking
Groundwater Flow
The future baseline conditions for groundwater flow are predicted to be consistent with the
observed conditions seen at the landfill. The full extent of the landfill footprint and site
infrastructure have been established, and the site conditions at the time of the groundwater flow
model development and calibration are not expected to change significantly in the future. The
future baseline groundwater head contours for the Regional Study Area and the Site-Vicinity
Study Area are shown on Figures 6-17 and Figures 6-18, respectively.
Groundwater Quality
The western two-thirds of the existing landfill footprint is unlined, and leachate generated from
the waste can come into contact with the underlying groundwater. The direction of groundwater
flow from this area is toward the northeast. The concentrations of leachate indicator parameters
immediately adjacent to the unlined landfill are elevated above background and indicate
migration of leachate away from the toe of the landfill. It is expected that this movement of
elevated concentrations of dissolved parameters will continue in future, following the direction of
groundwater flow.
The existing purge well system installed along Carp Road to the east of the existing landfill
footprint and the closed south cell will continue to be operated in the future. The system
provides containment of leachate-impacted groundwater east of the site. As long as the purge
wells are operating, groundwater impacts on the Contaminant Attenuation Zone (CAZ)
properties are expected to gradually decrease over time.
In order to predict the future orientation and extent of leachate-impacted groundwater from the
unlined landfill footprint, computer-based numerical modelling of groundwater flow and
dissolved phase transport was completed. The groundwater flow model was calibrated to the
observed water levels on the landfill site and to water levels reported in the MOE’s Water Well
Information System (WWIS). The groundwater flow model simulates the flow system in the
study area and is used as the basis for establishing the direction that leachate impacts are
expected to migrate away from the landfill. To simulate movement of the leachate-impacted
groundwater, source concentration profiles were estimated for the landfill footprint based on
observed leachate concentrations, and by fitting an exponential decay curve post-closure. The
source concentrations were input to the groundwater flow system model, and allowed to migrate
with the groundwater flow according to the principles of advective-diffusive contaminant
transport. As noted previously, chloride was used as a modelling parameter to examine plume
orientations and trends. This is because of its conservative nature and elevated source
concentrations.
Draft Environmental Assessment West Carleton Environmental Centre
6-58
chapter 6. detailed impact assessment of the undertaking
Figure 6-17 Modelled Groundwater Heads in the Regional Area, Future Baseline Conditions
Draft Environmental Assessment West Carleton Environmental Centre
6-59
chapter 6. detailed impact assessment of the undertaking
Figure 6-18 Modelled Groundwater Head Contours in the Site-Vicinity, Future Baseline Conditions
Draft Environmental Assessment West Carleton Environmental Centre
6-60
chapter 6. detailed impact assessment of the undertaking
The results from the future baseline transport modelling indicate that leachate-impacted
groundwater is expected to continue to migrate away from the unlined landfill footprint. Figure
6-19 illustrates the simulated progression of impacted groundwater. The figure shows the
approximate orientation and extent of chloride concentrations that are predicted to exceed
130 mg/L (the Reasonable Use Limit for an aquifer with a background chloride concentration of
10 mg/L). It is seen that the impacted groundwater is predicted to eventually extend beyond the
current boundaries of the CAZ properties. This is because the orientation of groundwater flow
takes the dissolved constituents north of the existing purge well system, beyond its zone of
influence. Measures to control and abate the predicted extent of leachate impacts from the
existing unlined landfill are expected to be required.
It should be noted that the computer modelling simulations are not considered sufficiently
accurate to predict actual groundwater concentrations at specific locations and/or times.
Instead, the simulations are used to provide a reasonable projection of future contaminant
orientations and trends. Field observations (groundwater elevations and concentration trends)
will be necessary to measure actual leachate impacts at specific monitoring well locations.
6.7.2.4 Potential Geology and Hydrogeology Effects
Groundwater Flow
The potential effects on Groundwater Flow from the Preferred Alternative Landfill Footprint
(including the SWM ponds) are as follows:
1. Recharge to the groundwater is expected to be reduced within the area of
the new landfill footprint. This will have the effect of lowering the
groundwater elevations immediately below the landfill, but is predicted to
have minimal effects away from the footprint. The local and regional
groundwater flow directions are not expected to be impacted.
2. Infiltration from the SWM ponds is predicted to cause the groundwater
levels to rise under the unlined pond stages. The effects of this
groundwater mounding diminish with increased distance from the ponds.
The groundwater flow will be radially away from the ponds, which is
predicted to affect the orientation of the local flow regime and influence
groundwater quality in the vicinity.
The predicted groundwater head contours in the Site-Vicinity Study Area from the development
of the new landfill and the SWM ponds are shown on Figure 6-20.
Draft Environmental Assessment West Carleton Environmental Centre
6-61
chapter 6. detailed impact assessment of the undertaking
Figure 6-19 Predicted Chloride Concentrations under Future Baseline Conditions
Draft Environmental Assessment West Carleton Environmental Centre
6-62
chapter 6. detailed impact assessment of the undertaking
Figure 6-20 Modelled Groundwater Head Contours in the Site-Vicinity, Assuming Operation of the New Landfill Footprint and Stormwater Management Ponds
Draft Environmental Assessment West Carleton Environmental Centre
6-63
chapter 6. detailed impact assessment of the undertaking
Groundwater Quality
The proposed development of the new landfill footprint and the SWM ponds is expected to have
the following potential effects on the future baseline conditions for Groundwater Quality:
1. Surface water that infiltrates to the groundwater table from the SWM ponds
may contain elevated concentrations of contaminants from surface runoff,
traffic and landfill operations. These contaminants may migrate with the
groundwater flow toward the downgradient property boundary, which is
situated approximately 200 m to the east of the ponds.
2. Radial groundwater flow predicted to occur around the SWM ponds is
expected to intercept the movement of leachate-impacted groundwater
from the existing unlined landfill. This is expected to have the effect of re-
orienting leachate-impacted groundwater further northward across the On-
Site Study Area and extending beyond the northern property boundary. A
southern arm of leachate-impacted groundwater is expected to migrate
eastward onto the existing CAZ; however, because of the reduced mass of
contaminants being transported in this direction, the impacts may not
extend as far east as the future baseline scenarios, and may potentially
remain within the CAZ boundaries.
The potential effects from the SWM ponds and from the migration of leachate-impacted
groundwater from the existing unlined landfill are shown on Figure 6-21. Figure 6-21(a) shows
the maximum predicted extent of chloride concentrations greater than 130 mg/L from the SWM
ponds. Note that the maximum source concentration of chloride infiltrating from the ponds that
was used in the modelling simulations was set at 165 mg/L during landfill operations. This
effluent concentration limit restricts the mass of contaminant that is available for transport, as
will be discussed in the Geology and Hydrogeology Mitigation and/or Compensation Measures
subsection. Once the landfill site is closed, final cover will be applied and operations traffic
reduced. In the simulations, the projected source concentration was linearly reduced to 0 mg/L
over five years of post-closure.
Figure 6-21(b) shows the predicted maximum extent of leachate-impacted groundwater from
the existing unlined landfill, as influenced by the new landfill footprint and SWM ponds. From the
results of the simulations, it is apparent that the leachate-impacted groundwater would be
transported further northward than the future baseline scenarios. With no mitigation measures in
place, it is predicted that the potential effects to groundwater quality would extend off-site to the
north.
Draft Environmental Assessment West Carleton Environmental Centre
6-64
chapter 6. detailed impact assessment of the undertaking
Figure 6-21 Predicted Chloride Concentrations, Assuming Operation of the New Landfill Footprint and Stormwater Management Ponds
Draft Environmental Assessment West Carleton Environmental Centre
6-65
chapter 6. detailed impact assessment of the undertaking
The predicted contaminant flux through the double-composite liner of the new landfill footprint is
described in Supporting Document #4 – Facility Characteristics Report. The chloride
concentrations predicted to discharge through the base of the attenuation layer of the new
landfill were used as source concentration inputs to the groundwater model. Since the mass flux
of contaminant through the double-composite liner is very small (transport through the low
permeability liner components is dominated by diffusion rather than by advection), the changes
in chloride concentrations in the groundwater at the base of the attenuation layer are negligible.
This is consistent with the regulatory definition of the GII liner system, which is designed to
provide protection to groundwater quality without reliance on attenuation in the landfill buffer
area.
6.7.2.5 Geology and Hydrogeology Mitigation and/or Compensation Measures
Mitigation measures will be required to reduce the potential effects of the Preferred Alternative
Landfill Footprint on Groundwater Quality to acceptable levels. The proposed mitigation
measures are design-based and operational in nature, related to the movement of leachate-
impacted groundwater from the existing landfill and effluent from the SWM ponds, respectively.
Within the context of the EA, the proposed mitigation measures have been developed to a
conceptual design level, using computer-based numerical modelling simulations. This is
considered reasonable and sufficient in order to evaluate general trends in flow orientation and
contaminant concentrations, and to assess the conceptual feasibility of the proposed measures.
A detailed design of the mitigation measures, including additional modelling simulations and
field testing, would need to be completed at such time as actual contaminant transport dictates.
Purge Wells
The potential effects of the Preferred Alternative Landfill Footprint and associated operations
relative to the future baseline conditions are that contaminant concentrations from leachate-
impacted groundwater exceeding acceptable levels (as defined by the Reasonable Use Limits1
and as modelled using chloride as an indicator parameter) are predicted to extend beyond the
northern boundary of the site. The source of the leachate-impacted groundwater is the existing
unlined (closed) landfill footprint.
Purge wells are an effective method for controlling leachate migration from landfills in
permeable geologic environments. The existing purge wells on the site control the eastward
movement of impacted groundwater. A proposed mitigation measure to reduce the potential
1. The Reasonable Use Policy is aimed at ensuring that a proponent’s undertaking does not impair the ‘reasonable
use’ of ground water on neighbouring properties. It sets limits to the level of ground water impact that can occur at the proponent’s site property boundaries.
Draft Environmental Assessment West Carleton Environmental Centre
6-66
chapter 6. detailed impact assessment of the undertaking
effects of the Preferred Alternative Landfill Footprint is to install a series of purge wells along the
northern toe of the existing landfill, between the landfill and the new footprint. The existing
geologic conditions in the area consist of sand to sand-gravel overburden, underlain by
fractured limestone bedrock of the Bobcaygeon Formation. The average hydraulic conductivity
in the overburden-shallow bedrock zone is on the order of 1.5x10-4 m/s, which is considered a
permeable formation with favourable conditions for hydraulic capture via purge wells. The purge
wells would target the saturated overburden and the upper 6 to 8 m of fractured limestone as
the primary pathway for leachate migration.
The concept of purge wells installed as a mitigation measure was simulated using the numerical
model of groundwater flow and contaminant transport. The results of the modelling simulations
indicate that sufficient capture could be achieved by installing nine purge wells spaced evenly
along the toe of the existing landfill, completed in the overburden-shallow bedrock zone. The
predicted maximum extent of leachate-impacted groundwater with chloride concentrations
greater than 130 mg/L with the operation of the new purge wells is shown in Figure 6-22. Each
purge well was simulated to pump 45 m3/day (31.3 L/min), which is considered to be a
reasonable pumping rate for this type of aquifer, and is less than the average pumping rate for
the existing purge wells.
Under this modelling scenario, the predicted distribution of leachate-impacted groundwater
exceeding Reasonable Use Limits would not extend beyond the property boundaries of the
Preferred Alternative Landfill Footprint. In addition, although there would be drawdown of
groundwater levels in the vicinity of the purge wells and changes to the localized groundwater
flow directions, it is not expected that there would be any impacts to groundwater levels or flow
directions beyond the property boundaries.
The actual number and spacing of purge wells required and the design pumping rates will be
determined during the detailed design of the mitigation measures, when required. However, for
conceptual design purposes, the proposed mitigation measure is considered to provide a
reasonable method of reducing the potential effects on groundwater quality to acceptable levels.
Operational Controls on Stormwater Management Pond Effluent
The SWM ponds have the potential effect of allowing elevated concentrations of contaminants
to infiltrate to the groundwater table. The ponds are designed with two stages: surface runoff
first flows into a lined stage and then overflows to an unlined stage. Effluent in the lined stage
can be contained in case of a spill or other emergency.
The SWM ponds are located relatively close to the downgradient property boundary and beyond
the zones of influence of the existing purge well system and the proposed northern purge wells
Draft Environmental Assessment West Carleton Environmental Centre
6-67
chapter 6. detailed impact assessment of the undertaking
Figure 6-22 Predicted Chloride Concentrations, Assuming Operation of the New Landfill Footprint and Stormwater Management Ponds, and with Mitigation Measures In-Place
Draft Environmental Assessment West Carleton Environmental Centre
6-68
chapter 6. detailed impact assessment of the undertaking
described in the previous section. Because of the pond locations and the types of underlying
geologic formations, once in the groundwater there is limited attenuation capacity available to
further reduce the effluent concentrations. Therefore, the potential effects on groundwater
quality from the operation of the SWM ponds should be controlled by establishing limits on the
concentration of effluent in the unlined pond stages. These operational effluent limits would
restrict the concentrations of dissolved constituents entering the groundwater system such that
groundwater quality at the property boundaries would continue to meet acceptable levels.
Several predictive analyses of groundwater quality were completed using maximum effluent
concentrations from the ponds ranging from 50 to 300 mg/L. The results of the simulations
indicate that a chloride concentration of approximately 165 mg/L would reduce the potential
effects from the ponds to acceptable levels. Figure 6-22 shows the predicted maximum extent
of impacted groundwater with chloride concentrations greater than 130 mg/L, using a maximum
effluent concentration of 165 mg/L from the SWM ponds. The impacted groundwater in this
scenario (i.e., groundwater with chloride concentrations greater than 130 mg/L) does not extend
beyond the property boundaries.
Based on this conceptual assessment, the proposed mitigation measure for the potential effects
from the SWM ponds is to establish concentration limits on the effluent infiltrating to the
groundwater from the unlined pond stages. Further evaluation to confirm the final recommended
chloride effluent concentration and to determine whether other parameter limits should be
established will be completed during the detailed design phase for the landfill.
6.7.2.6 Geology and Hydrogeology Net Effects
The mitigation measures proposed for Groundwater Flow are sufficient to reduce the potential
effects from the Preferred Alternative Landfill Footprint to acceptable levels.
Implementation of the mitigation measures proposed for Groundwater Quality also result in net
effects that are considered acceptable.
6.7.3 Surface Water
The study area for the Surface Water environmental component is shown in Figure 6-23 and
described as follows:
On-Site .............. the lands owned or optioned by WM bounded by Highway 417,
Richardson Side Road, and Carp Road;
Site-Vicinity ....... the lands within 500 m of the On-Site Study Area; and
Regional ............ Huntley Creek subwatershed
Draft Environmental Assessment West Carleton Environmental Centre
6-69
chapter 6. detailed impact assessment of the undertaking
Figure 6-23 Surface Water Detailed Impact Assessment Study Area
Draft Environmental Assessment West Carleton Environmental Centre
6-70
chapter 6. detailed impact assessment of the undertaking
6.7.3.1 Detailed Description of the Surface Water Environment Potentially Affected
The existing landfill site and proposed landfill expansion area are situated adjacent to the south
tributary of the Huntley Creek subwatershed of Carp River. The subwatershed area is relatively
flat with a significant amount of wetland and scattered agricultural use as well as ongoing
estate-lot residential development.
The south tributary has a limited drainage area with a headwater area generally defined to the
west and south by Highway 417, to the north by Cavanmore Road, and to the east by Carp
Road. Local drainage patterns are somewhat undefined and are characterized by large wetland
areas that have significant storage potential, especially in the vicinity of the landfill site.
Depending on the magnitude of rainfall and the storage-discharge characteristics of the various
wetland areas, flow from these locations may or may not be realized on adjacent lands and at
the new landfill site. However, flow estimates were developed that reflected minimal storage to
provide a conservative estimate of peak flows.
A portion of the existing landfill site was a former gravel pit and has relatively permeable, silty-
sandy soils. Municipal water supply in adjacent built-up areas to the south (Ottawa – Stittsville)
and east (Ottawa - Kanata) is from the Ottawa River at the Britannia intake, while water supply
for the built up area to the north (Ottawa-Carp) is from local municipal wells. Water supply for
the rural areas is from private wells.
6.7.3.2 Potential Effects on Surface Water
Without mitigation, flow would outlet to South Huntley Creek upstream of Carp Road either by
flow north to South Huntley Creek in an existing swale across private lands or west to the Carp
Road westside ditch.
Construction
With no permanent mitigation during construction, surface water runoff from the landfill would
have to be contained by in-line or offline temporary SWM ponds to ensure that water quality
impacts from construction-related equipment and vehicles would be minimised and any
sediments from erosion would be contained.
Operation
From a water quality perspective, operation of the new landfill has the potential to impact water
quality due to accidental leachate seeps to the surface and/or increases in Total Suspended
Solids (TSS) concentration due to runoff from the landfill side slopes and the internal gravelled
access roadways.
Draft Environmental Assessment West Carleton Environmental Centre
6-71
chapter 6. detailed impact assessment of the undertaking
From a water quantity perspective, two main potential impacts are possible. The first is the
effect on local drainage patterns as surface water runoff from the landfill would likely have to be
diverted away from private lands to the north, and the swale that runs through it conveying
surface water north to South Huntley Creek. This diversion would:
Reduce flows to the swale, which would then be maintained only by adjacent
surface and groundwater flow. This impact would not be mitigated.
Reduce flows (by less than 5%) to South Huntley Creek tributary along
Richardson Side Road. This impact would not be mitigated.
Increase flows along the west ditch of Carp Road. This could be mitigated.
Require the re-location of existing SWM Facility (SWMF) #1 as a new two
stage SWMF to the east.
The second potential impact is a change in local topography provided by the relatively steep-
sloped (from a hydrologic perspective) landfill configuration and a resulting reduction in travel
time (as a result of increased flow velocities) that would create increased peak flows with
potential to increase downstream water levels and flood damage.
6.7.3.3 Surface Water Mitigation and/or Compensation Measures
Construction
SWM ponds managing all of the surface water runoff from the expanded site would be
constructed first and, as such, would provide the necessary quantity and quality control during
the remaining construction period and the operational lifetime of the site.
Other items for consideration during construction should include:
Implement appropriate BMPs (to be drafted at the Detail Design stage) for
protecting aquatic habitat and for limiting soil mobilization and trapping
sediment as close to the source as possible. The sedimentation and erosion
protection measures are to reflect these principles: minimize the duration of soil
exposure, retain existing vegetation where feasible, encourage re-vegetation,
divert runoff away from exposed soil, and keep runoff velocities low.
Maintain the integrity of all sediment trapping devices through regular
monitoring. In the event that it is determined that that controls are
unacceptable, WM shall cease those operations. Such structures should be
removed only after the soils from the construction areas have been stabilized
and then only after the trapped sediments have been removed.
Draft Environmental Assessment West Carleton Environmental Centre
6-72
chapter 6. detailed impact assessment of the undertaking
Direct runoff and overland flow away from working areas and areas of
exposed soils and maximize length of overland flow through to points where
stormwater is collected.
Swales and culverts will be installed, as required, to allow for surface flow to
pass under the on-site roads.
Any accidents or malfunctions (i.e., spills to surface water) will be limited in
their spatial and temporal extent, such that they will not result in the loss of
any component of the aquatic system.
A sediment control plan has been developed to mitigate effects associated with construction of
the project to prevent suspended sediment, mud, debris, fill, rock dust, etc., from entering
adjacent lands and the stormwater system. The following activities will be incorporated as part
of the sediment and erosion control plan:
Limit the zone of construction impacts to minimize disturbance of existing
vegetated areas where grading is required;
Minimize exposure time for un-vegetated soils;
Store and stabilize any stockpiled materials away from open water through
the installation of sediment and erosion control fencing such as silt
fences/curtains, sediment traps and check dams as appropriate;
Install silt fences, blankets, and/or berms around construction areas,
including the laydown area, and across sloping terrain/areas to prevent
surface runoff from carrying sediment off-site;
Properly site and contain all materials and equipment used for site
preparation and completion of work to prevent any deleterious substance
from entering the water;
Conduct refuelling and handling of potential hazardous substances away
from the SWM system;
Leave sediment and erosion control measures in place until all disturbed
areas have been stabilized;
Implement vehicle and timely equipment cleaning procedures of tracked mud,
dirt and debris along the access routes and areas outside of the immediate
work area where sediment and control measures are not in place;
Suspend work if excessive flows of sediment discharge occur and capture
and adequately filter drainage from any unstabilized surface to reduce
sediment loading;
Draft Environmental Assessment West Carleton Environmental Centre
6-73
chapter 6. detailed impact assessment of the undertaking
Install temporary security fence to surround and secure the site prior to
commencement of any site excavation, filling or grading works and maintain
on regular basis prior to and after runoff events. Clean out any accumulated
materials during maintenance and prior to removal;
Restoration of all disturbed areas on land to natural conditions and re-
vegetation as soon as conditions allow to prevent erosion and restore habitat
functions; and
Land based measures will not be removed until vegetation has been re-
established to a sufficient degree (or surface soils stabilized using other
measures) so as to provide adequate erosion protection to disturbed work
areas.
Operation
Water quality impacts would be mitigated by a two-staged SWMF to remove larger particle size
TSS loading and provide for emergency leachate/spill containment in a Stage 1 sediment
forebay with a Stage 2 providing extended control for additional TSS removal. SWMF outflow
would be as groundwater discharge (infiltration), with the SWMF incorporating existing local
excavation as previously practised at the existing site.
The water quantity impacts would be mitigated by Stage 1 and Stage 2 of the SWMF providing
attenuation of post-development flows to pre-development levels. SWMF outflow would be as
groundwater discharge (infiltration), with the SWMF incorporating existing local excavation that
would contain the 1:100 year runoff.
In more detail, SWM for the expanded site will be achieved through integration of the existing
and proposed system of ditches, culverts, stormsewers and SWM ponds that have been
designed to mitigate the impacts of stormwater runoff on water quantity and water quality before
discharge to South Huntley Creek. The SWM criteria, as identified by the MOE in Ontario
Regulation 232/98 and related Landfill Standards Guidelines (1998), include:
ditching designed to accommodate runoff from a 1:25 year rainfall event;
detention of runoff from a 4-hour 25 mm rainfall event; and
attenuation of peak flows to pre-development levels for all rainfall events up
to and including the 1:100 year Return Period event.
The existing site and proposed new landfill footprint area is founded on relatively permeable
soils and there is currently no direct discharge to South Huntley Creek from the landfill proper or
its servicing roads and operational areas. Rather, discharge is to three defined recharge areas,
Draft Environmental Assessment West Carleton Environmental Centre
6-74
chapter 6. detailed impact assessment of the undertaking
two of which have sedimentation forebays, the recharge areas eventually discharging through
groundwater, to South Huntley Creek. The proposed SWM system for the expansion is planned
in a similar manner and will account for the relocation of one of the existing recharge areas that
will be removed to accommodate the new landfill footprint.
The three proposed SWM ponds, including the relocated facility, are located in Figure 6-24 with
one pond to the southwest accommodating flow from the access road; one to the Southeast,
replacing existing SWMF #1 and Depression #3; and one to the north accommodating flow from
the proposed landfill and perimeter access road.
The three new SWM ponds are designed as two-stage facilities with an emergency flow control
system in-between the two stages. A typical two-stage facility is illustrated in cross-section in
Figure 6-25.
The first stage will function not only as a sedimentation cell but also as an emergency response
cell where runoff can be stored in case of surface water contamination by leachate or on-site
spills. Discharge can be shut-off in case of an emergency in which leachate has been found to
be contaminating the surface water runoff. There will be regular inflow monitoring of indicator
parameters (possibly including Oil and Grease, Conductivity, pH and TDS) to trigger a shutdown
response using either a control valve or gate. This pond will be lined and designed to retain
runoff from the 1:100 year rainfall until appropriate treatment can be applied and the runoff
either treated and discharged to the second stage or pumped and hauled for treatment
elsewhere.
The second stage will be an unlined pond for recharge purposes and is sized to accommodate
the volume from the 1:100 year runoff from respective catchment areas. Other design features
will include:
First stage invert higher than the invert of the second stage and likely higher
than the design water level to ensure positive drainage.
Design water level for the volume of runoff from the 1:100 year rainfall event
since the SWMF would likely have no natural positive outlet given the
adjacent topography.
Design water levels not higher than adjacent service roads.
Emergency overflow routes to be defined once the facility characteristics are
more clearly understood. With no positive outflow, the recharge rate governs
the rate of water level reduction and available capacity for the next rainfall
event.
Draft Environmental Assessment West Carleton Environmental Centre
6-75
chapter 6. detailed impact assessment of the undertaking
Figure 6-24 Proposed Stormwater Management Ponds