draft commissioning process for hvac systems · starting the commissioning process right at project...

144
Final Draft for public Comments - Comm Process for HVAC_19.02.2020 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Draft 17 Commissioning Process for 18 HVAC Systems 19 20 ISHRAE Standard - 10003-2020 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45

Upload: others

Post on 09-Jun-2020

37 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1

2 3 4

5 6 7 8 9

10 11 12 13

14 15 16

Draft 17

Commissioning Process for 18

HVAC Systems 19

20

ISHRAE Standard - 10003-2020 21

22 23

24

25 26 27 28

29 30 31 32

33 34 35

36 37 38 39 40

41 42 43 44

45

Page 2: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

46

47 48 49

50

ISHRAE Commissioning Standard Committee 51

52

53

S.No.

Name Organization Email ID

1 Mr. Ramachandran -

Chair

Eskayem Consultants Pvt

Ltd, Mumbai

[email protected]

2 Mr. Shankar Sapaliga -

Vice Chair

International Copper

Association India

[email protected]

3 Mr. Shiv Batra IBM India Pvt Ltd. [email protected]

4 Mr. Shankar Chatterjee In personal capacity [email protected]

5 Mr. Sandeep Dahiya In personal capacity [email protected]

6 Dr. Shivraj Dhaka Indian Green Building

Council (IGBC)

[email protected] ;

[email protected]

7 Mr. Rumi Engineer Godrej & Boyce Mfg. Co.

Ltd.

[email protected]

8 Mr. S.P. Garnaik Energy efficiency services

ltd

[email protected]

9 Mr. Prabhat Goel PK Goel Consulting

Engineers

[email protected]

10 Mr. Ravikumar P.

Gondkar

LEAD Consultancy And

Engineering Services (India)

Private Limited

[email protected]

11 Mr. Ajaj A Kazi Voltas Limited. [email protected]

12 Mr. Ravi Prakash

Kurkiya

Green Rating for Integrated

Habitat Assessment

[email protected]

13 Mr. Manjunath Underwriters Laboratories

Inc.

[email protected]

14 Dr. Jyotirmay Mathur Malaviya National Institute

of Technology, Jaipur

[email protected]

15 Mr. Suhas Mathur USGBC [email protected]

16 Mr. Ashish Rakheja AEON Integrated Buiding

Design Consultants LLP

[email protected]

17 Mr. M. Selvarasu LEAD Consultancy And

Engineering Services (India)

Private Limited

[email protected]

18 Mr. Sajay Seth Green Rating for Integrated

Habitat Assessment

[email protected]

19 Ms. Maija Virta Santrupti Engineers Private

Limited

[email protected]

54

55

56

Page 3: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

57

58 59 60

61 62

CONTENTS 63

64 65

Section Page No.

Forward

1. : Purpose

2. : Scope

3. : Exclusions

4. : Definitions

5. : Utilization

6. : Management of commissioning Process

6.1 : Initiating the process

6.2 : Owners Project Requirements

6.3 : Commissioning plan

6.4 : Basis of Design

6.5 : Commissioning Specifications

6.6 : Design Review

6.7 : Project submittals

6.8 : Observation and testing

6.9 : Issues resolution

6.10 : Systems manual

6.11 : Training of operating and maintenance

personnel

6.12 : Commissioning report

6.13 : Post occupancy operations

Informative Appendix A : Initiating the commissioning process

Informative Appendix B : Owners project requirements

Informative Appendix C : Developing a commissioning plan

Informative Appendix D : Establishing Basis of Design

Informative Appendix E : Developing commissioning specifications

Informative Appendix F : Design review report

Informative Appendix G : Review / Construction submittals

Informative Appendix H : Installation and Inspection

Informative Appendix HA1 : Unitary and packaged AC systems

Informative Appendix HA2 : VRF systems

Informative Appendix HA3 : Chillers

Informative Appendix HA4 : Cooling Towers

Informative Appendix HA5 : Pumps

Informative Appendix HA6 : Air Handling Units

Informative Appendix HA7 : Ducting systems

Informative Appendix HA8 : Variable air volume systems

Informative Appendix HA9 : Fans

Page 4: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Informative Appendix HA10 : Boilers and Hot water generators

Informative Appendix HA11 : Fan Coil Units

Informative Appendix HA12 : Meters and Gauges

Informative Appendix HB1 : Refrigerant piping

Informative Appendix HB2 : Water piping

Informative Appendix HB3 : Chilled water system

Informative Appendix HB4 : Condenser water system

Informative Appendix HB5 : Direct expansion system

Informative Appendix HB6 : Air Distribution System

Informative Appendix HB7 : Hot water system

Informative Appendix HB8 : Basement ventilation system

Informative Appendix HB9 : Kitchen ventilation system

Informative Appendix HB10 : Exhaust Systems

Informative Appendix HB11 : Pressurization system

Informative Appendix HB12 : Control Systems (HVAC)

Informative Appendix I : Resolution of issues

Informative Appendix J : Systems manual

Informative Appendix K : Training

Informative Appendix L : Commissioning report

Informative Appendix M : Reference

66 67 68

69 70

71 72

73 74

75 76 77 78

79 80 81 82

83 84 85

86 87 88 89 90

91 92 93 94

95

Page 5: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

96

FORWARD 97

98 99 100 (This forward does not form part of the standard) 101 102

ISHRAE has long felt the need to establish a standard for the commissioning process of HVAC 103 systems. Objective is to provide a structural methodology for implementing the process for 104 systems as well as for individual components with a view to obtain a fully functional and 105 properly balanced HVAC system with adequate documentation and trained operating and 106 maintenance staff. 107

108 The process begins at inception of the project and continues for the life of the facility. It ensures 109 through specified methodology that the design, construction, testing, documentation and 110

training meets the Owners Project Requirements. 111 112 By adopting this process, the project owner can ensure compliance with quality parameters 113 from the start of the project. By adhering to this standard, any need to modify the HVAC system 114

post facility occupancy can be considerably eliminated. 115 116

It is strongly suggested that the commissioning authority be part of the HVAC project process. 117 The commissioning authority shall represent the owner’s needs from the inception stage to post 118 occupancy and in fact, for the whole life of the project. 119

120

The commissioning authority can either be an employee of the owner or can be an independent 121 professional. He / She should be experienced in facility operation and maintenance, as well as 122 in design testing, balancing as well as in construction management and quality. 123

124 This standard is developed to help those who are implementing a quality based and cost 125

effective process. Starting the commissioning process right at project inception will achieve 126 maximum benefits. 127

128 Appendices are included to better understand each stage of the project. They are not mandatory 129 but are to be used to develop guidelines and documents which may define owner’s project 130

needs as well as other stages described in the standard. 131

132 The commissioning process, commencing at project inception, is a valuable tool for the owner 133 to control the project at each stage on a real time basis. 134

135 136

137

138 139

K RAMACHANDRAN 140 Chair – Commissioning Standard 141 Sub Committee – ISHRAE 142 143

144

145

Page 6: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1.0 Purpose 146 147

The purpose of this standard is to specify the process to be followed for 148 commissioning of Heating, Ventilating and Air Conditioning (HVAC) systems to 149 meet Owner’s Project Requirements (OPR) defined for Performance and 150

conformance to design intent approved by the owner. This standard provides input 151 for continuous improvement in the commissioning process. 152

153

2.0 Scope 154 155

This standard defines the process of commissioning, lists the parameters to be 156 measured, test methods, measuring and reporting method for all types of electrically 157 driven HVAC systems to enable the project to be accepted and put to beneficial use 158

by the project owner by conformance check as per agreed Owner’s Project 159 Requirement For new building or renovation. The standard is applicable for 160 complete HVAC system or only selected part of the system or only selected 161 equipment or only selected subassembly (ies). 162

163 164

3.0 Exclusions 165 166

This standard does not aim to define the system and equipment performance levels. 167 Also, this standard does not define safety conformance requirements of the 168 equipment and personnel. Wherever safety compliance requirements are defined by 169

local or national regulatory authorities, conformance to those regulations shall be 170

applicable. 171 172 HVAC Systems based on Vapour Absorption chillers, Evaporative Cooling 173

equipment and Passive Cooling systems are out of scope of this standard. 174 175

176

4.0 Definitions 177 178

4.1 Acceptance 179 180

A formal action taken by a person with appropriate authority to declare that aspect 181 under consideration of the project meets defined requirements, thus permitting 182

subsequent activities to proceed. 183 184 4.2 Accuracy 185 186

The closeness of agreement between a test result and the accepted reference value. 187

188 4.3 Back Check 189 190

A verification during the commissioning process that an agreed upon solution to a 191 design comment has been addressed. 192

193 194

195

Page 7: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

196

197 4.4 Balancing 198 199

The process of adjusting the flow rate of a fluid in a distribution system to achieve 200

the design flow rate. 201 202 4.5 Basis of Design 203 204

Basis of design details the design team’s approach to meet OPR and obtains owners 205

approval for critical design decisions. It shall include HVAC requirements of each 206 space consistent with the occupancy, activity to be carried out and desired quality 207 of indoor air. It shall satisfy applicable technical and code requirements. Basis of 208

design records the concepts, calculations, decisions and product selections to meet 209 the owners project requirements (OPR) and to satisfy applicable regulatory 210 requirements, standards and guidelines. 211 Note: Also known as Design Criteria. 212

213 4.6 Bench marking 214

215 Benchmarking is the complete process containing an objective establishment step, 216

a measurement step, a controlling step for the level of quality of the measurement 217 results, and a comparison step. In case of this standard benchmarking has been 218 referred to the comparison of energy usage of building under consideration to that 219

of other similar building. 220

221 4.7 Building 222 223

Construction works that has the provision of shelter for its occupants or contents as 224 one of its main purposes, usually partially or totally enclosed and designed to stand 225

permanently in one place. A roofed construction for which energy is used to 226 condition the indoor climate. 227

228

4.8 Calibration 229 230

Comparing an instrument of unknown accuracy with a standard of known accuracy 231 to detect or eliminate by adjustment any variation in the accuracy. 232

233 4.9 Commissionable system 234 235

A system designed and installed to specified requirements in such a manner as to 236 enable commissioning to be carried out. 237

238 4.10 Commissioning 239 240

Advancement of an installation from a state of static completion to full working 241 order meeting the specified requirements. 242

243 244

245

Page 8: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

246

4.11 Commissioning authority. 247 248

An owner appointed representative responsible for delivering the commissioning 249 process activities. Commissioning authority shall not be an employee of design and 250

construction companies involved in the project under consideration. 251 252 4.12 Commissioning process 253 254

A quality focussed process for enhancing the delivery of a project. 255

256 Is a process that defines the verification and conformance check method for all the 257 HVAC equipment under the scope of this standard are installed, tested, operated 258

and maintained to meet the OPR. 259 260

4.13 Commissioning process activities 261 262

The systematic activities performed for commissioning of the equipment to 263 conform to requirements of OPR. 264

265 266

4.14 Commissioning process report 267 268

A written document that details activities completed as part of the commissioning 269

process and significant findings from those activities. 270

271 Note: The report is continuously updated during the course of the project. 272

273 4.15 Commissioning agent 274 275

A person or team supporting the commissioning activity under the direction of 276 Commissioning Authority. 277

278

279 4.16 Commissioning check lists 280

281 A list of testing and inspection parameters to be verified to check the conformance 282

of HVAC equipment to OPR. 283

284 4.17 Commissioning issue 285 286

Any non-conformance to the OPR requirement defined for the HVAC system. 287

288 4.18 Commissioning plan 289 290

The commissioning plan is a written document describing the commissioning 291 activities and their schedule which ensures that the design, construction and 292

operation meet the OPR. The commissioning plan shall include the scope of the 293 process, resources required at each stage of the process as well as the agreed 294

timelines for each stage. 295

Page 9: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

296 4.19 Commissioning report 297 298

A document that records the activities and results of the commissioning process and 299 is developed from the commissioning plan. 300

301 4.20 Commissioning specifications 302 303

The contract documents that detail the objectives, scope and implementation of the 304 commissioning process as developed in the commissioning plan. 305

306 4.21 Commissioning team 307 308

Individuals and agencies who through co-ordinated actions are responsible for 309 implementing the commissioning process. 310

311 4.22 Commissioning check list 312

313 A form used by commissioning agent to verify conformance of equipment and 314

accessories through out process of commissioning including delivery of the 315 equipment, installation accessories at site and installation of the equipment as 316

defined by the equipment supplier to meet performance requirement defined in OPR 317

318 4.23 Contract documents 319

320

The documents like design and construction contracts, price agreements, drawings, 321 specifications and data sheets but not limited to, for effective execution of 322 commissioning and to verify equipment meets performance requirement as defined 323

in OPR. 324

325 4.24 Data logging 326 327

Monitoring and recording of parameters such as temperature, flow, current etc. 328

(applicable to equipment) for a defined period and time interval using data 329 recorders. 330

331 4.25 Deficiency 332

333 Any condition that may adversely affect the commissionability, operability or 334 functionability of a system, equipment or component. 335

336 4.26 Design check list 337

338 A form developed by the commissioning team to verify that elements of the design 339 are in compliance with Owners Project Requirements. 340

341 4.27 Design professional 342

343 Architect or engineer of record for the project. 344

345

Page 10: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

346

347 4.28 Energy performance 348 349

Calculated or measured amount of energy needed to meet the energy demand 350

associated with typical use of the system. 351

352 4.29 Evaluation 353 354

Process by which performance of system or components thereof are measured and 355

confirmed with respect to the criteria required in Owners Project Requirements. 356 357 4.30 Functional Performance testing. 358

359 Testing performed to ensure that designated systems of the project meet the 360 requirements as per OPR. 361

362 4.31 Installation verification 363 364

Observations or inspections that confirm the system or component has been 365 installed in accordance with the contract documents and industry accepted best 366

practices. 367

368 4.32 Issue resolution 369

370

A formal and ongoing record of concerns and their resolution. 371

372 4.33 Maintainability 373

374 A design component or construction process that will allow a system or components 375

to be effectively maintained. 376

377 4.34 Monitoring 378

379 Observing, supervising, controlling or verifying the operations of a system. 380

381 4.35 Ongoing commissioning 382

383 A continuation of the commissioning process into post occupancy operation stage 384 to continually improve the operation and performance of the facility. 385

386 4.36 Operation and Maintenance manual 387

388 Set of documents detailing the design, method of operation and maintenance 389 requirements / procedures of the system. 390

391 4.37 Owner 392

393 A person or legal entity that will own the delivered facility. 394

395

Page 11: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

396

397 4.38 Owner’s Project Requirements. 398 399

A written document that details the requirements of a project and the expectations 400

of how it will be used and operated. 401

402 4.39 Performance test 403 404

The process of verifying that a material, product assembly or system meets defined 405

performance criteria. 406

407 4.40 Precision 408

409 Ability of an instrument to produce repeatable readings of the same quantity under 410 the same conditions. 411

412 4.41 Procedure 413 414

A defined approach that outlines the execution of a sequence of work or operation 415

416 4.42 Range 417 418

The upper and lower limits of an instrument’s ability to measure the value of a 419

quantity. 420

421 422 4.43 Recommissioning 423

424 Application of the commissioning process requirements to a project that has once 425

undergone the process. 426

427 4.44 Resolution (1) (Measurements) 428

429 Smallest change in a measured variable that an instrument can detect. 430

431 4.45 Resolution (2) 432

433 Implementation of actions that correct a tested or observed deficiency. 434

435 4.46 Regulation 436 437

Process of adjusting any one parameter in a system to obtain specified values. 438

439 4.47 Retro commissioning 440 441

Commissioning process applied to an existing facility that was not previously 442

commissioned. 443

444

445

Page 12: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

446

447 4.48 Site Observation Reports 448 449

Reports of site inspections and observations made by the commissioning authority. 450

451 4.49 Systems Manual 452 453

A system focused composite document that includes all information required for 454 the owners to operate the system. 455

456 4.50 Test Procedures 457 458

A written protocol that defines methods, personnel and expectations for tests 459 conducted on components, systems and interfaces between systems. 460 461

4.51 Testing 462

463 Measurement and recording of system parameters to assess conformance with 464

specifications. 465 466

4.52 Tolerance 467 468

Permissible range of variation acceptable from the design value of a measurable 469

characteristic. 470

471 4.53 Training Plan 472 473

A written document that detail expectations, schedule and deliverables of the 474 commissioning process activities for the benefit of users. 475

476 4.54 Validation 477 478

The process by which work is verified as complete and is operating correctly. 479 480

4.55 Verification 481 482

Process by which specific documents, components, systems and interface among 483 systems are confirmed to comply with the criteria discussed in owner’s project 484 requirements. 485 486

4.56 Continuous commissioning 487

488 Commissioning efforts executed after a project has been completed and accepted 489 by the Owner. 490 491 492

493 494

495

Page 13: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

496

5.0 Utilisation 497 498 5.1 General: 499 500

5.2 Essential activities for applying the commissioning process are covered in this 501 standard along with the sequence thereof. Deliverables and documentation at each 502 stage of the process are established. 503

504 5.3 Following are the commissioning process activities. 505

Page 14: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

506

Commissioning Process initiation (Cl. 6.1)

Define Owners Project Requirement (OPR) (Cl. 6.2)

Develop Commissioning plan (Cl. 6.3)

Establish basis of design (Cl. 6.4)

Develop commissioning specification (Cl. 6.5)

Review construction submittals (Cl. 6.7)

Resolve / owner approval for non

conformance (Cl. 6.9)Observe and test (Cl. 6.8)

Assemble systems Manual (Cl. 6.10)

Conduct training (Cl. 6.11)

Commissioning report (Cl. 6.12)

Post commissioning operation (Cl. 6.13)

Report NC & Resolution / Approval

from Owner

Conformance

Non conformance

Non Conformance

Conformance

Design review (Cl. 6.6)Report NC &

Resolution / Approval from Owner

Non conformance

Conformance

Page 15: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

507

5.4 Each step in the above process shall have an acceptance criteria which establishes 508 completion and acceptance by owner / client. 509

510 Note: The commissioning authority shall verify the conformance to OPR only 511

and shall not have authority to accept any revisions and project on behalf 512 of the owner. 513

514 515

6.0 Management of Commissioning Process. 516 517 6.1 Initiating the process 518 519

The owner shall be responsible for determining the scope of the commissioning 520 plan, selecting the commissioning authority, incorporating them into project team 521 and establishment of the commissioning budget. Owner shall direct the process, 522 review and accept each step of the process. 523

524 6.1.1 Owner shall include the commissioning activities as well as the commissioning plan 525

in the design and construction team’s contracts. 526 527

6.2 Owner along with the commissioning team shall develop the Owner’s Project 528 Requirement (OPR) document. The OPR shall define the equipment, systems and 529 assemblies covered in the scope of commissioning process. Any update to the OPR 530

made during project life shall be approved by owner. 531

532 6.3 The commissioning plan as defined in clause 4.18 shall be developed and approved 533

by the owner. 534

535 6.4 The Basis of design document as defined in clause 4.5 shall be prepared and owner 536

shall approve it. 537 538 6.5 Commissioning specifications shall be developed for all systems and assemblies 539

being commissioned. These shall be incorporated in all relevant contract 540 documents. Commissioning specifications shall include the roles and 541

responsibilities of each commissioning team member as well as the list of 542 equipment and systems to be evaluated with required check list formats and sample 543

test forms. 544 545 6.6 Design Review shall be conducted to verify conformance of the various systems 546

and assemblies in the design documents with the OPR. Design review shall be 547 completed before issue of construction documents. 548

549 Note: Commissioning Design review is not a “Peer Review”. 550

551 6.7 The HVAC system is installed, and put into operation during the Construction Phase 552

of the project. During this phase, Project submittals shall be reviewed for 553

conformance with OPR. Commissioning team shall be involved with the 554 construction, start-up, testing and balancing of all the components/ sub-assemblies 555

of the HVAC system. During this stage Operation and Maintenance team shall be 556

Page 16: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

trained as necessary. The team shall further ensure compliance with manufacturer’s 557

installation instructions. In addition to the components/ sub-assemblies of the 558 HVAC system, the Commissioning Team shall also check the conformance of 559 aspects of Construction such as receiving and unloading of equipment, on-site 560 storage, cleaning and closing of constructed duct work, pipe work etc as well as the 561

stipulated indoor air quality procedures during construction phase. Passivation of 562 installed pipes flushing and cleaning and pressure testing and leakage testing of duct 563 work and pipe work shall be witnessed by the Commissioning team for 564 conformance. 565

566

Regular meetings of the commissioning team shall take place for co-ordinating the 567 above activities and to identify and resolve any non-conformance. 568

569

Commissioning team shall maintain complete record of all Commissioning 570 submittals and reviews thereof and in case any of the submittals are not in 571 conformance with the OPR shall obtain owner’s approval before accepting the 572 concerned equipment or system. 573

574 6.8 Observation and testing shall be carried out to comply with OPR and contract 575

documents. For this, check lists, test procedures and report forms shall be developed 576 before installation. Person responsible shall carryout test protocols. Repeat testing 577

shall be carried out until all equipment, systems or assemblies pass the test. All 578 check lists and test procedure results shall be compiled into the final commissioning 579 report. The reports shall be presented in the relevant format as specified in the 580

annexures. 581

582 6.9 Any non-conformance identified during commissioning process shall be 583

documented and all unresolved non-conformance shall be presented to owner and 584

owner’s acceptance shall be included in final commissioning report. 585 586

6.10 The systems manual shall provide all information needed to operate and maintain 587 the buildings systems and assemblies and for training of personnel. The systems 588 manual shall be updated during the commissioning process with respect to design, 589

construction and operation. Owner shall approve the systems manual for use in 590 building operations. 591

592 6.11 Operating and maintenance personnel shall be trained on the commissioned 593

systems in accordance with a documented training plan as conformance with OPR 594 and is accepted by the owner. Evaluation of the training imparted and documented 595 feedback from participants shall be as per the OPR. 596

597 6.12 Commissioning report summarizes the entire commissioning process for the 598

benefit of the building owner and those who are entrusted with the responsibility of 599 operating and maintaining the systems installed. The Commissioning report shall 600 include all design and construction review reports and all unresolved issues along 601 with a resolution. Commissioning report shall be accepted and approved by owner. 602

603

6.13 Post occupancy operation commissioning shall include all delayed and seasonal 604 tests and warranty issues. This needs to be completed prior to warranty completion. 605

All unresolved issues identified and listed during the commissioning process shall 606

Page 17: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

be resolved during this stage and in case any of the issues are remaining to be 607

resolved it shall have the owner’s acceptance duly recorded. Any additional training 608 during the post occupancy period as included in the OPR document shall be 609 completed in this stage. At the end of the Post Occupancy Commissioning period 610 documents such as the Systems manual, unresolved issue statements, training 611

documentation and final commissioning report shall all be updated and furnished to 612 owner for his acceptance. 613

614 615

616 617 618 619

620 621 622 623

624 625 626

627 628 629

630 631

632 633

634 635

636 637 638 639

640 641 642 643

644 645 646

647 648 649 650 651

652 653 654 655

656

Page 18: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

657

658 659

ANNEXURE 660

661

Annexure A (Informative) 662 Initiating the Commissioning Process 663

664 665 1.0 The purpose of this annexure is to assist the commissioning team in successfully 666

using the commissioning process for various systems and assemblies that constitute 667 the HVAC system for the building. 668

669 1.1 HVAC Systems range from simple unitary systems to complex and large systems 670

employing water chilling units, pumps, water flow systems of closed hydronics for 671

chilled water, open water distribution for condenser water, cold air distribution 672 systems with fans, Air Handling Units, ducted air systems, several types of 673 ventilation and exhaust systems employing large fans as well as electric drives with 674 motors, starters, connecting cabling and wiring, control elements for control and 675

monitoring of various parameters. 676 677

1.1.1 While equipment like window air conditioners, split air conditioners, cooling 678 towers, pumps, fans, Air Handling Units etc. are well-engineered products tested 679 and certified at the factory / origin, subsystems such as water and air distribution 680

are engineered and assembled at the project site to meet specific design 681

requirements. 682 683 1.2 Procedures, methods and documentation requirements in this annexure describe the 684

application of the commissioning process for each project delivery phases from 685 Initiation through post commissioning operation phase. 686

687 1.3 This section of the annexure specifically deals with initiation of the Commissioning 688

Process 689 690 1.4 The project owner shall specify the role and responsibility of each team member 691

and the goals and objectives to be achieved. These shall be clearly defined in the 692

OPR. These should be updated periodically since the objectives may change as the 693 project progresses. 694

695

1.5 In case there are concerns which are unresolved between the project team, the owner 696 shall intervene and provide direction to the team to resolve the concerns. 697

698 1.6 Commissioning activities need to be incorporated within the project delivery 699

process and shall be part of the project scope, budget and time schedules. 700

701 702 703 704 705

706

Page 19: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

707

1.7 Commissioning scope shall specify the system to be commissioned and the purpose 708 for various contracts owner shall enter with: 709

Project Management Consultant (PMC) 710 Architect/ Civil Engineer 711

(Mechanical Electrical and Plumbing consultant (MEP) 712 Commissioning Authority (CA) 713 Suppliers of equipment and systems. 714 Installers/Contractors 715 Facility Management Agency (FMA) 716

717 1.8 Owner shall ensure that the project budget is sufficient to support the 718

commissioning activity and the construction schedule provides enough time to 719

complete the commissioning activities. 720

721 722 723

724 725 726

727 728 729

730 731

732 733

734 735

736 737 738 739

740 741 742 743

744 745 746

747 748 749 750 751

752 753 754 755

756

Page 20: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

757

758 ANNEXURE B (Informative) 759

760

Owners Project Requirements (OPR) 761 762 763 1.0 OPR document shall define the functional requirements of the project and the 764

expectations of the owner as regards the project’s use and operation. 765 766

2.0 Project owner shall provide the inputs which goes into OPR and the commissioning 767 authority shall assist the owner in identifying the facilities requirements. 768

769

3.0 OPR shall incorporate inputs from owner, design team, operation and maintenance 770 teams and also from the project users. All targets shall be verifiable and 771 measureable so that they can be used as benchmarks in the commissioning process. 772 The owner shall be responsible for updating the OPR from time to time till the end 773

of the commissioning process. 774 775

4.0 OPR to shall include the following information specifically required for HVAC 776 system. 777

778 1. HVAC system performance targets 779

a) Primary purpose of the building 780

b) Space programme 781

c) Number of occupants and usage profiles. 782 d) Flexibility to change floor layouts and use of spaces or the building. 783 e) Training required for operating and maintaining the building. 784

785 2. Targets for IEQ 786

a) Thermal comfort 787 b) Indoor air quality 788 c) Lighting 789

d) Acoustics 790 e) User satisfaction 791

792 3. Health and safety 793

a) Security 794 b) Water quality 795 c) Emergency lighting 796 d) Fire and smoke management 797 e) Accessibility and maintainability 798

799 4. Data / Communications 800

a) Phone connectivity 801 b) Wireless network 802 c) Wireless IOT data network. 803

804 805

806

Page 21: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

807

5. Environmental performance 808 d) Energy performance index 809 e) Primary energy consumption 810 f) Energy supply – Current & Future 811

g) Water use and reduction potential 812 h) Lifetime greenhouse gas emissions. 813 i) Operational greenhouse gas emissions. 814 j) Waste management. 815 k) Targets for ongoing commissioning and continuous monitoring. 816

817 Note: The OPR can include any additional requirements not limiting to the 818

above mentioned parameters. 819

820 5.0 OPR shall be part of the systems manual documentation. The document shall be 821

updated as decisions are made through during design, construction, occupancy, and 822 operations phases of the project. 823

824 6.0 OPR can be included as a part of Bid documents issued to vendors with a clear 825

stipulation that the document is only for information and shall not be used to 826 interrupt contract requirements. 827

828 829 830

831

832 833 834

835 836

837 838 839

840 841

842 843

844 845 846 847 848

849 850 851 852 853

854

855

856

Page 22: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

857

858 ANNEXURE – C (Informative) 859

860

Developing a commissioning Plan 861 862 863 1.0 Commissioning plan details the processes required for successful commissioning. 864

Based on the OPR the commissioning plan defines the scope and budget for the 865 commissioning process. 866

867 2.0 The commissioning plan shall contain the following information: 868 869

2.1 Commissioning process overview. 870 871 2.2 Roles and responsibilities of commissioning team. 872 873

2.3 Documentation requirements. 874 875

2.4 Detailed description of commissioning process activities during Pre-Design 876 phase, Design phase construction phase, occupancy and operation phases. 877

878 2.5 Design document verification procedures. 879 880

2.6 Steps to take where process verification indicates any deviation from OPR. 881

882 2.7 Verification for compliance with OPR at all project phases. 883

884

3.0 During design, construction and operation phases, concern and resolution log shall 885 be maintained. The log shall list all concerns which are at variance with the OPR 886

and also how each of them have been resolved. All outstanding concerns shall be 887 reviewed periodically. 888

889

4.0 Commissioning progress report shall be issued periodically and typically contains 890 the following information. 891

892 4.1 Process activities completed till date of report. 893

894 4.2 Any changes in the process schedule. 895 896 4.3 New issues, outstanding issues and planned activities to resolve outstanding 897

issues. 898

899 4.4 Process activities scheduled till next meeting. 900

901 902 903

904 905

906

Page 23: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

907

908 ANNEXURE – D (Informative) 909

910

Establishing Basis of Design 911 912 913 1.0 Basis of design shall be a written document and shall clearly specify the designer’s 914

approach to the OPR. OPR will provide the information requirements and the format of 915 the design document to the team. Design team shall formulate the basis of design and 916

shall submit it to the owner for review and approval. 917 918 2.0 Basis of design document shall be updated to reflect any changes to the design criteria 919

as the project moves forward along with the reasons for such changes. 920 921 3.0 Following contents shall constitute basis of design and which can be modified and used 922

for each project based on discussions and agreement between the owner, 923

commissioning team and the designer. 924 925

926

a) HVAC- Preliminary and Schematic Design 927 i. Space Use 928

ii. Redundancy 929 iii. Diversity 930

iv. Out door design criteria 931

v. Indoor design conditions 932 vi. Ventilation requirements. 933

vii. Zoning requirements 934

viii. Occupancy 935 ix. Permitted tolences on indoor conditions 936

x. Standards and Codes 937 xi. Green Building and Energy Code compliances 938

xii. Control systems 939

940 941

b) Integration with other Building Systems 942 i. Lighting and power 943

ii. Water management including cooling tower make up and heat 944

recovery systems 945

iii. Smoke management and Fire Safety 946

iv. Renewable energy 947

v. Sewage recycling and reuse. 948

vi. Any other systems as required by the OPR. 949

950 951

c) Design Development. 952 i. Energy modeling reports 953

ii. Ventilation calculations 954

iii. Heating/ Cooling load estimates 955

Page 24: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

iv. Equipment data sheets. 956

v. Control schematics 957 vi. Input/Output summary. 958

959

960 d) System performance parameters 961

i. Adaptability of mechanical systems. 962 ii. Maintainability 963

iii. Service and inspection access 964 iv. Reliability 965

v. Service life 966 vi. Replacement schedule 967

vii. Efficiency targets. 968

969 4.0 Commissioning team shall verify Basis of Design for HVAC system commissioning 970

and conformance that they are in line with owner’s project requirements. In terms of 971 user comfort and energy efficiency, it is important to simulate building operation and 972

typical spaces in the pre design phase. This will ensure that the selected technical 973 solutions fulfill the performance targets. 974

975 Note: CFD simulations will be helpful to simulate comfort conditions and air 976

movements with in the building. 977

978 979

980

981 982 983

984

985 986 987 988

989 990 991 992

993 994 995

996 997 998 999 1000

1001 1002 1003 1004

1005

Page 25: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1006

ANNEXURE – E (Informative) 1007 1008

Developing Commissioning Specifications 1009 1010

1011 1.0 Commissioning specifications shall include the commissioning process activities 1012

performed during construction stage and upto the post occupancy commissioning. 1013 1014 2.0 Administrative procedures for the commissioning process and how the construction 1015

team interacts with the commissioning team shall form part of the specifications. 1016 1017 3.0 Testing requirements for equipment, sub-assemblies and systems as well the 1018

construction teams involvement in the commissioning related testing needs to be clearly 1019 defined. 1020

1021 4.0 The commissioning team shall verify the construction team activities starting with 1022

installation, testing, and training of operating and maintenance personnel and 1023 preparation of systems manual (clause 6.10) to confirm that they conform to the OPR. 1024

1025 5.0 In case manufacturers authorised personnel is required at the time of start –up, same 1026

shall be specified. 1027 1028 6.0 Inclusion of commissioning process requirement and commissioning standard to be 1029

included as part of tender document 1030

1031 1032 1033

1034 1035

1036 1037 1038

1039 1040

1041 1042

1043 1044 1045 1046 1047

1048 1049 1050 1051 1052

1053 1054

1055

Page 26: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1056

1057 ANNEXURE – F (Informative) 1058

1059

Design Review Report 1060 1061 1062 1.0 This stage of the commissioning process involves review of design submissions. The 1063

commissioning team needs to ensure that the design submissions meet the OPR. 1064 1065

2.0 Design review shall include review of drawings as well as the specifications. 1066 1067 3.0 As a first step of the drawing review process the criteria on which the drawings will be 1068

reviewed shall be documented. 1069 1070 4.0 Drawings shall initially be reviewed on its general quality such as continuity, labelling, 1071

clarity legibility etc. 1072

1073 5.0 Second stage review of the drawings shall verify placement of equipment, its 1074

accessibility, possibility for maintenance and replacement, height requirements, 1075 sectional and elevational details, service connections etc. 1076

1077 6.0 A final drawing review shall involve sustainability requirements, conditions maintained 1078

with respect to OPR, BOD etc. 1079

1080

7.0 Any non-conformance in drawing review shall be documented and communicated to 1081 the originator of the drawing as well as the owner. 1082

1083

8.0 Review of specifications shall involve verification that they pertain to the project and 1084 is clear and concise. Similar to drawing review any non-conformance shall be 1085

documented and communicated to the originator as well as to the owner. 1086 1087 9.0 Design review report shall contain: 1088

1089 a) List of documents reviewed (Tile, issue date) 1090

b) Issues, comments and variable with OPR if any. 1091 c) Copy of drawings review. 1092

d) Review on systems and assemblies. 1093 e) Non-conformance report if any 1094

1095 1096 1097

1098 1099 1100 1101 1102

1103 1104

1105

Page 27: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1106

ANNEXURE – G (Informative) 1107 1108

Review / Construction Submittals 1109 1110

1111 1.0 In order to ensure that components procured fulfil the design requirements, contractor 1112

shall submit details of all major components to the commissioning authority who will 1113 check and confirm that they fulfil the operational requirements of the project. 1114 Commissioning authority shall provide the report to the owner as well as to the 1115

contractor. Commissioning authority shall also highlight any issues that may result in 1116 rework or change orders. 1117

1118

2.0 Following shall be reviewed: 1119 1120 2.1 Measurement of product data to specified standards. 1121 1122

2.2 Required safety requirements are fulfilled. 1123 1124

2.3 Where any changes are made technical performance of the system is not affected. 1125 1126

2.4 All selected components and materials which are selected have independent third party 1127 certification. 1128

1129

2.5 Products subject to energy and eco labelling meet the parameters specified. 1130

1131 2.6 All changes in components, materials and installation are updated in the documentation 1132

and non-conformance shall be reported. 1133

1134 1135

1136 1137 1138

1139 1140

1141 1142

1143 1144 1145 1146 1147

1148 1149 1150 1151 1152

1153 1154

1155

Page 28: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1156

ANNEURE – H (Informative) 1157 1158

Installation and Inspection 1159 1160

1161 1.0 This section of the guidelines specifically deals with inspection and testing of the 1162

systems / equipment for performance. 1163 1164 1.1 Observation helps to ensure that a particular component / material / sub assembly 1165

is received as it was specified, whether it was installed as specified in the OPR 1166 without damage and accessibility, maintainability and such other specified 1167 attributes are met. 1168

1169 1.2 Testing implies verification of the performance of the equipment or system and 1170

performance testing means altering some of the parameters to evaluate response of 1171 the system against expectations. 1172

1173 1.3 Testing shall cover physical properties of the system and assembly as well as 1174

performance parameters as well as logical or operational parameters. 1175 1176

1.4 Checklists are developed for testing which shall include criteria, process 1177 requirements and performance testing. Checklists shall not be considered to be 1178 exhaustive and shall be reviewed to ensure compliance with OPR and BOD. 1179

1180

1.5 Construction checklists shall be prepared for components and equipment that are 1181 delivered, installed and started up during construction. An individual checklist shall 1182 be prepared for each piece of component or piece of equipment. Similar 1183

construction checklists shall be prepared for systems and assemblies and for each 1184 test procedure, test data records shall be developed. 1185

1186 1.6 Test data records shall include the following: 1187 1188

1. Test number 1189 2. Date and Time 1190

3. System / Equipment identification. 1191 4. Testing conditions 1192

5. Expected performance 1193 6. Observed performance 1194 7. Test conclusion 1195 8. Dated signature of person conducting test. 1196

1197

1.7 Test reports shall cover the following stages. 1198 1199

1. Delivery check lists 1200 2. Pre installation checks 1201 3. Installation check lists. 1202

4. Performance data. 1203 1204

1205

Page 29: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1206

1.8 Preparation for tests shall include the following: 1207 1208

1. Certification that all systems and equipments are installed and are operating 1209 as per the requirements of contract documents. 1210

2. Certification that testing, adjusting and balancing procedures have been 1211 completed and approved. 1212

3. Systems and equipment shall be put in operation mode. 1213 4. Safety cutouts, alarms and interlocks shall be verified. 1214 5. Required measuring / logging instruments shall be installed. 1215

1216 1.9 Scope of testing shall include the following: 1217 1218

A. Equipment 1219 A.1 Unitary and Package Systems 1220 A.2 VRF Systems 1221 A.3 Chillers 1222

A.4 Cooling Towers 1223 A.5 Pumps 1224

A.6 Air Handling Units 1225 A.7 Ducting systems 1226

A.8 Variable Air Volume Systems 1227 A.9 Fans 1228 A.10 Hot Water generators 1229

A.11 Fan Coil Units 1230

A.12 Meters and gauges. 1231 1232 B. Sub Systems 1233

1234 B.1 Refrigerant Piping 1235

B.2 Water piping 1236 B.3 Chilled water system 1237 B.4 Condenser water system 1238

B.5 Direct Expansion system 1239 B.6 Air Distribution System 1240

B.7 Hot Water system 1241 B.8 Basement Ventilation System 1242

B.9 Kitchen ventilation system 1243 B.10 Exhaust system 1244 B.11 Pressurisation System 1245 B.12 Control System (HVAC) 1246

1247

1.10 Scope of testing shall include measuring capacities and also effectiveness of 1248 operational and control functions. Whenever possible, tests shall be performed at 1249 design conditions. When required, simulated conditions may be produced using 1250 artificial load. 1251

1252

1.11 Sample test reports are given in attachments HA.1 to HA.12 in respect of equipment 1253 and HB1 to HB12 in respect of sub Systems. 1254

1255

Page 30: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1256

1257 ANNEXURE – H1 (Informative) 1258

1259

Test measurements and testing instruments 1260 1261 1262 1.0 The following is a non comprehensive listing of measurements which should be 1263

taken while testing of HVAC systems. 1264 1265

2.0 The system / Equipment under test shall be operated to determine proper 1266 functioning of all components as well as instruments. All measurements and 1267 readings are to be taken only after the system / equipment has been operated and 1268

steady state conditions are established. After establishing steady state, the 1269 measurements are taken for period of 30 minutes and shall be minimum 3 sets of 1270 readings taken during the test period at equally timed intervals. 1271

1272

All parameters are shall be calculated from the average of measurement data 1273 obtained at the end of the test period. 1274

1275 3.0 The measurement instruments shall meet measurement accuracy requirements as 1276

below. 1277 1278 3.1 Dry bulb temperature (DBT) and wet bulb temperatures (WBT) ≤ ± 0.1°C and 1279

temperature differentials. 1280

1281 3.2 Pressure or pressure differential ≤ ± 2% of the numerical value of measured 1282

quantity. 1283

1284 3.3 Flow measurements ≤ ± 2% of the flow rate measured. 1285

1286 4.0 All test instruments shall be calibrated and recalibrated on a regular schedule that 1287

is appropriate for the instrument and calibration records shall be maintained. 1288

1289 5.0 Test instrumentation 1290

1291 5.1 Air side measurements: 1292

1293 5.1.1. Rotating Vane Anemometer 1294 1295

The mechanical propeller or revolving vane anemometer consists of a light, wind-1296 driven wheel connected through a gear train to a set of recording dials that read the 1297

linear feet (meters) of air passing through the wheel in a measured length of time. 1298 The instrument is made in various sizes, but 3, 4, and 5 in. (75, 100, and 125 mm) 1299 are the most common. Each instrument requires individual calibration. The required 1300 instrument accuracy of calibration is 1%–3% of scale (using a corrective chart). 1301

1302

Recommended Uses 1303 1304

Page 31: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

a. Use to measure supply, return, and exhaust air quantities at registers and 1305

grilles. 1306 b. Use to measure air quantities at the faces of return air dampers or 1307

openings, total air across the filter or coil face areas, etc. 1308 Limitations 1309

a. Each reading from this instrument must be corrected by its calibration 1310 chart. 1311

b. The air terminal manufacturer’s specified Ak (effective area) factor for 1312 the terminal must be used in computing air quantities. 1313

c. Total inlet area of the instrument must be in the measured airstream. 1314

d. It is not suitable for measurement in ducts. 1315 e. It is fragile and cannot be used in dusty or corrosive air. 1316 f. Since the instrument has a turbine wheel of very low inertia, caution is 1317

advised as to reliability of readings in non-uniform, turbulent, or 1318 stratified airstreams. This is likely to occur downstream of dampers, face 1319 and bypass coils, or any device that causes turbulence in the airstream 1320 being measured. 1321

g. The instrument is not direct reading and, therefore, must be timed 1322 manually. 1323

h. At low velocities, the friction drag of the mechanism is considerable. In 1324 order to compensate for this, a gear is commonly used. For this reason, 1325

the correction is additive at the lower range and subtractive at the upper 1326 range, with the least correction in the middle of the range. Most of these 1327 instruments are not sensitive enough for use below 1.0 m/s (200 fpm) , 1328

although ball-bearing models claim ranges down to 0.15 m/s (30 fpm) . 1329

The useful range is from 1.0 to 10.0 m/s (200 to 2000 fpm) . 1330 1331 5.1.2. Direct Reading Digital Type- Vane Anemometer 1332

1333 This instrument is the same as the mechanical type in most respects, except that it 1334

uses a powered electronic circuit to convert a pulse generated by the rotating vane 1335 into a small electric current to give a meter reading calibrated directly in air velocity 1336 units. Generally, these instruments have microprocessor software to compensate for 1337

any nonlinearity 1338 1339

Recommended Uses 1340 1341

a. Use to measure supply, return, and exhaust air quantities at registers and 1342 grilles. 1343

b. Use to measure air quantities at the faces of return air dampers or 1344 openings or of total air across the filter or coil face areas, etc. 1345

1346

Limitations 1347 1348

a. The air terminal manufacturer’s specified Ak factor (effective area) for 1349 the terminal must be used in computing air quantities. 1350

b. The total inlet area of the instrument must be placed in the measured 1351

airstream. 1352 c. It is not suitable for measurement in ducts. 1353

d. It is fragile and cannot be used in dusty or corrosive air. 1354

Page 32: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

e. Since the instrument has a turbine wheel of very low inertia, caution is 1355

advised as to reliability of readings in non-uniform, turbulent, or 1356 stratified airstreams. This is likely to occur downstream of dampers, face 1357 and bypass coils, or any device that causes turbulence in the airstream 1358 being measured. 1359

f. At low velocities, the friction drag of the mechanism is commonly used. 1360 For this reason, the correction is additive considerable. In order to 1361 compensate for this, a gear is at the lower range and subtractive at the 1362 upper range, with the least correction in the middle of the range. Most 1363 of these instruments are not sensitive enough for use below 1.0 m/s (200 1364

fpm), although ball-bearing models claim ranges down to 0.15 m/s (30 1365 fpm). The useful range is from 0.51 to 25.4 m/s (100 to 5000 fpm). 1366

1367

5.1.3 U Tube Manometer/ Pitot Tube 1368 1369

The manometer is a simple and useful means of measuring partial vacuum and 1370 pressure, both for air and hydronic systems. In its simplest form, the manometer 1371

consists of a U-shaped glass tube partially filled with liquid. A difference in height 1372 of the two fluid columns denotes a difference in pressure in the two legs. 1373

1374 Recommended Uses 1375

1376 a. Use to measure pressure changes through coils, heat exchangers, and 1377

orifices. 1378

b. Use to measure pressure changes across water circulators. 1379

c. Use to measuring gas pressures. 1380 1381

Limitations 1382

1383 a. Manometer tubes shall be cleaned to ensure accuracy and shall be filled 1384

with the correct fluid. 1385 b. Use collecting safety reservoirs on each side of a mercury manometer to 1386

prevent blowing out mercury into the water system, which can cause 1387

rapid deterioration of any copper it touches in the system. 1388 1389

5.1.4 Pitot Tube 1390 1391

Construction: A Pitot static tube, used in conjunction with a manometer, provides a 1392 basic method of determining the air velocity within a duct. The typical Pitot static 1393 tube is of a double concentric tube construction, consisting of a 3.2 mm (1/8 inch). 1394 O.D. inner tube that is concentrically located inside a 7.9 mm (5/16 inch). O.D. 1395 outer tube. The outer static tube has eight equally spaced 1.02 mm (0.04 inch). 1396

diameter holes around the circumference of the outer tube, located 63.5 mm (2.5 1397 inch) () back from the nose or open end of the Pitot tube tip. At the base end, or 1398 tube-connection end, the inner tube is open ended, as is the head. The outer tube has 1399 a side outlet tube connector perpendicular to the outer tube, directly parallel with 1400 and in the same direction as the head end of the Pitot static tube 1401

1402 Recommended Uses 1403

1404

Page 33: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

a. Use to measure airstream “total pressure” by connecting the inner tube 1405

outlet connector to one side of a manometer or draft gauge. 1406 b. Use to measure airstream “static pressure” by connecting the outer tube 1407

side outlet connector to one side of a manometer or draft gauge. 1408 c. Use to measure airstream “velocity pressure” by connecting both the 1409

inner and outer tube connectors to opposite sides of a manometer or 1410 draft gauge. 1411

d. This instrument, when used with a manometer or micro manometer, is a 1412 reliable and rugged instrument. Its use is preferred over any other 1413 method for the field measurement of air velocity, system total air, 1414

outdoor air, return air quantities, fan static pressure, fan total pressure, 1415 and fan outlet velocity pressures, where such measured quantities may 1416 be required. 1417

1418 5.1.4. Flow Measurement hood/ matrix 1419 1420 Construction: This is a conical or pyramid shaped hood used to collect all the 1421

airflow from a terminal and guide it over a flow-measuring system, which reads 1422 directly in cfm (L/s). The instrument can be a swinging vane anemometer, a 1423

differential-pressure air gauge (diaphragm type), a manometer, or a thermal 1424 anemometer. The balancing cone should be tailored for the particular job. The large 1425

end of the cone should be sized to fit over the complete air-terminal unit and should 1426 have a seal to eliminate air leakage. The cone should terminate in a straight section 1427 with factory-designed and calibrated pressure grids, straighteners, and instruments 1428

1429

Recommended Uses. 1430 1431

Use to proportion air distribution devices directly in L/s (cfm). 1432

1433 Limitations 1434

1435 a. Shall not be used where discharge velocities exceed 10 m/s (2000 fpm ) 1436 b. It shall be recognized that the device generally redirects the normal 1437

pattern of air discharge and that it contributes an artificially imposed 1438 pressure drop in the branch of the air terminal being measured. These 1439

will result in a decrease in the delivered airflow of the outlet. 1440 c. The air-terminal manufacturer should be contacted for details in using 1441

this instrument with the manufacturer’s terminals. 1442 d. The instrument must be calibrated for the method of use intended. For 1443

use with supply distribution devices, the instrument shall be calibrated 1444 in the supply mode. For use with return distribution devices, the 1445 instrument shall be calibrated in the return mode. 1446

1447 5.1.5 Digital Thermometer 1448 1449

Construction: There are four basic types of electronic thermometers: thermocouple, 1450 thermistor, RTD (resistance temperature detector), and diode sensors. They consist 1451

of a portable, hand-held, battery-powered, digital thermometer connected by a short 1452 cable to a variety of interchangeable probes. The probes are designed for sensing 1453

the temperature of air or other gases, of liquids by immersion in liquids, or of the 1454

Page 34: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

surfaces of solids by contact with a solid surface. Some instruments offsets 1455

introduced by mechanical shocks, ambient temperature variations, or component 1456 drift. Some instruments have F/C switching and 0.1/1.0 resolution switching. 1457 Response times are 1 to 10 s for liquids and solids, and 5 to 50 s for gases. 1458 Instrument accuracy shall be ±0.3°C (±0.5°F) where the temperature is below 1459

350°C (700°F ) and ±0.8°C (±1.5°F) for temperatures of 350°C (700°F ) and above. 1460 The lower range instruments shall be used for all measurements within their range. 1461

1462 Recommended Uses. 1463

1464

Suitable for all TAB temperature measurements, including air and other gases, 1465 liquids, and surfaces of pipes and other components with the appropriate probe. The 1466 manufacturers’ directions must be followed regarding proper use of probe and 1467

maximum allowable temperature for the probe and/or thermometer. Equipment is 1468 available to measure from –230°C to 1230°C (–380°F to 2250°F ). Common ranges 1469 used are –10°C to 120°C (+14°F to +248°F). 1470

1471

Limitations 1472 1473

a. The power source – battery shall be charged or replaced for good 1474 operation level. 1475

b. In piping applications, it should be remembered that the surface 1476 temperature of the pipe is not equal to the fluid temperature and that a 1477 relative comparison is more reliable than an absolute reliance on 1478

readings at a single circuit or terminal unit. 1479

c. Measurement must be taken at least as long as the response time. 1480 1481 5.1.6 Sling Psychrometer 1482

1483 Construction: The sling psychrometer consists of a matched pair of mercury-filled 1484

glass-tube thermometers, one of which has a cloth wick or sock around its bulb. The 1485 two thermometers are mounted side-by-side on a frame fitted with a handle by 1486 which the device can be whirled with a steady motion through the surrounding air. 1487

The whirling motion is periodically stopped to take readings of the wet-bulb and 1488 dry-bulb thermometers (in that order) until such time as consecutive readings 1489

become steady. Due to evaporation, the wet-bulb thermometer will indicate a lower 1490 temperature than the dry-bulb thermometer, and the difference is known as the wet-1491

bulb depression. The required instrument test accuracy is ±0.5°C (±1°F ) 1492 1493

Recommended Uses. 1494 1495

The sling psychrometer can be used in determining the psychrometric properties of 1496

conditioned spaces, return air, outdoor air, mixed air, and conditioned supply air. 1497 The readings taken from the sling psychrometer can be plotted on a standard 1498 psychometric chart air can be determined. 1499

1500 Limitations 1501

1502

Page 35: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

a. Accurate wet-bulb readings require an air velocity of between 5.0 and 1503

7.5 m/s (1000 and 1500 fpm) across the wick, or a correction shall be 1504 made. 1505

b. Distilled water only must be used and the wick should be replaced for 1506 every measurement. 1507

c. For an instrument with 450 mm (18 inch) radius, it shall be whirled at 1508 a rate of at least two revolutions per second. 1509

d. Evaporation must reach equilibrium to be accurate. 1510 1511 5,1,7 Humidity Measuring Devices 1512

1513 Construction: In addition to the sling psychrometer, there are variety of instruments 1514 available to measure the moisture in air that can be more accurate and do not require 1515

the swinging of a manually wetted wick. These instruments include the following: 1516 1517 a. Battery-powered hygrometer 1518 b. Powered dew-point indicator 1519

c. Powered psychrometer with built in pump and fan 1520 d. Digital psychrometer with built in reservoir and fan 1521

1522 Recommended Uses. These instruments do not require hand swinging and, thus, 1523

may be more convenient to use. The hygrometers give direct, rapid RH readings, 1524 and the digital psychrometer gives dry-bulb and wet-bulb depression in about 30 1525 seconds. 1526

1527

5.1.8 Electronic Differential Pressure Gauge /Meter 1528 1529 This instrument is a hand-held (or belt-worn) device that measures differential 1530

pressure and gives a digital readout directly in pressure or velocity. Some 1531 instruments are available with adapters and probes to measure flow and 1532

temperature. Typical ranges reach 0 to 25 kPa (0 to 100 inch water column) for low 1533 density fluids, and 0 to 0 to 600 kPa (200 ft water column ) or 0 to 700 kPa (0 to 1534 100 psi ) for high density fluids. Temperatures can be measured from –48°C to 1535

120°C (–55°F to 250°F)). 1536 1537

Recommended Uses. Use with a Pitot static tube, static probe, flow grid, orifice 1538 plate, or special balancing valve. Some instruments can also be combined with a 1539

flow measuring hood. Many instruments have memories, averaging capabilities, 1540 and printers. 1541

1542 Limitations 1543 1544

a. These instruments are battery powered and require checking batteries 1545 and replacing or recharging them. 1546

1547 5.1.9 Electronic Tachometer 1548 1549

The stroboscope has a controlled high-speed electronic flashing light. The 1550 frequency of the flashing light is electronically controlled and adjustable. When the 1551

frequency of the flashing light is adjusted to equal the frequency of the rotating 1552

Page 36: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

machine, the machine will appear to stand still. This unit need not be in contact with 1553

the machine when it is being used. The instrument accuracy is generally within 1554 1.5% of the indicated value and within 1% if a magnetic pickup is used. The solid-1555 state photoelectric tachometer is an optional instrument that is pointed at the device 1556 to be measured and the rpm is directly read on the dial face. A reflective paint or 1557

material must be spotted on the rotating device, which is actually counted 1558 electronically integrated over time to give an instantaneous rpm reading. The 1559 instruments usually have several ranges, and no electrical or physical contact with 1560 the device is necessary. Accuracy is within ±1% of the dial scale reading when 1561 properly calibrated. 1562

1563 Recommended Uses. Use to measure rotational speeds when instrument contact 1564 with the rotating equipment is not feasible. 1565

1566 Limitations. Care must be taken to avoid reading multiples of the actual rpm when 1567 using the stroboscope. Readings must be started at the lower end of the scale. 1568

1569

5.1.10 Clamp-On AC Power Meter (Wattmeter) 1570 1571

The clamp-on type power meter has trigger-operated, clamp-on transformer jaws 1572 like the voltammeter. The instrument will measure true rms voltage and current, in 1573

addition to power, in single-phase or balanced three-phase circuits. Compared with 1574 mean-value measurement, true rms measurement is especially valuable for distorted 1575 waves, such as noise and multiplexed signals Typical ranges are 20 to 600 V rms, 1576

2 to 200 A rms, and 2 to 200 KW; or 20 to 600 V rms, 0.2 to 20 A rms, and 0.2 to 1577

20 KW. 1578 1579

Recommended Uses. The instrument will measure single-phase, split-phase, and 1580

three-phase power sources. Given the motor efficiency and power factor, power 1581 draw can be related to motor brake horsepower as related on a fan or pump curve 1582

and, thus, the operating point can be determined. 1583 1584

Limitations. Caution is required, particularly when taking measurements under 1585

confined conditions. Readings below 10% of input range are not recommended. 1586 Batteries must be checked before use. 1587

1588 5.1.11 Digital Sound level meter 1589

1590 This is used to measure sound pressure level. The most basic sound level meters 1591 measure overall sound pressure level and have up to three weighted scales that 1592 provide limited filtering capability. The instrument is useful in assessing outdoor 1593 noise levels in certain situations and can provide limited information on the low-1594

frequency content of overall noise levels. 1595 1596 5.1.12 Vibration analyser 1597 1598

Sound-level meters and computer-driven sound-measuring systems are the most 1599

useful instruments for measuring and evaluating vibration. Usually, they are fitted 1600 with accelerometers or vibration pickups for a full range of vibration measurement 1601

Page 37: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

and analysis. Other instruments used for testing vibration in the field are described 1602

as follows. 1603 1604

Reed micrometers are relatively inexpensive and are often used for testing 1605 vibration, but their relative inaccuracy limits their usefulness 1606

1607 Vibrometers are moderately priced and measure vibration amplitude by means of a 1608 light beam projected on a graduated scale. 1609

1610 Vibrographs are moderately priced mechanical instruments that measure both 1611

amplitude and frequency. They provide a chart recording amplitude, frequency, and 1612 actual wave form of vibration. They can be used for simple, accurate determination 1613 of the natural frequency of shafts, components, and systems by a bump test. Reed 1614

vibrometers, vibrometers, and vibrographs have largely been supplanted by 1615 electronic meters that are more accurate and have become much more affordable. 1616

1617 Vibration meters are moderately priced, relatively simple-touse modern electronic 1618

instruments that measure the vibration amplitude. They provide a single broadband 1619 (summation of all frequencies) number identifying the magnitude of the vibration 1620

level. Both analog and digital readouts are common. 1621 1622

Vibration analyzers are relatively expensive electronic instruments that measure 1623 amplitude and frequency, usually incorporating a variable filter. 1624 Strobe lights are often used with many of the other instruments for analyzing and 1625

balancing rotating equipment. 1626

1627 Stethoscopes are available as inexpensive mechanic’s type (basically, a standard 1628 stethoscope with a probe attachment), relatively inexpensive models incorporating 1629

a tunable filter, and moderately priced powered types that electronically amplify 1630 sound and provide some type of meter and/or chart recording. 1631

. 1632 The choice of instruments depends on the test. Vibrometers and vibration meters 1633 can be used to measure vibration amplitude as an acceptance check. Because they 1634

cannot measure frequency, they cannot be used for analysis and primarily function 1635 as a go/no-go instrument. The best acceptance criteria consider both amplitude and 1636

frequency. Anyone seriously concerned with vibration testing should use an 1637 instrument that can determine frequency as well as amplitude, such as a vibrograph 1638

or vibration analyzer. 1639 1640

Vibration measurement instruments (both meters and analyzers) made specifically 1641 for measuring machinery vibration typically use moving coil velocity transducers, 1642 which are sizable and rugged These are typically limited to a lower frequency of 1643

500 cycles per minute (cpm) [8.33 Hz] with normal calibration. If measuring very-1644 low-speed machinery such as large fans, cooling towers, or compressors operating 1645 below this limit, use an adjustment factor provided by the instrument manufacturer 1646 or use an instrument with a lower low-frequency limit, which typically uses a 1647 smaller accelerometer as the vibration pickup transducer. 1648

1649 1650

1651

Page 38: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1652

1653 1654 1655 5.2 Water Side 1656

1657 5.2.1 Ultrasonic flow meter 1658 1659

This is a device that, by the use of acoustic signals, determines the flow directly in 1660 design units (gpm, L/s, etc.) The ultrasonic flow metering station will either be an 1661

integral part of the piping system or a strap-on meter. In either case, there is no 1662 intrusion into the pipe or liquid flow to generate a pressure drop. There are no 1663 moving parts in the flow to maintain or service. There are two distinct types of 1664

ultrasonic flowmeters: a transit-time device for HVAC or clear water measurement 1665 and a Doppler-effect device for flows containing a required volume of particulate 1666 in the liquid. 1667

1668

Recommended Uses. Use to measure flow in full pipes. Excellent when low or zero 1669 pressure drop is a requirement. They are best fitted for larger pipes and most 1670

manufacturers’ specifications are based on flows of 1 fps or greater. 1671 1672

Limitations 1673 1674

a. Doppler Flowmeters: The liquid must contain particulate or gas bubbles. 1675

b. Transit-time Flowmeters: The liquid must be acoustically transparent 1676

(i.e., of low particulate content, such as typical lake or river water, or 1677 cleaner). 1678

c. Strap-on (Portable) Flowmeters: Pipe parameters (pipe diameter, wall 1679

thickness, and material of construction) must be known or determinable. 1680 The pipe must be acoustically transparent (concrete or lined pipe is not). 1681

1682 5.2.2 Mercury Thermometer 1683 1684

Description. Mercury-filled glass-tube thermometers have a useful temperature 1685 range of –36°C to 510°C (–38°F to 950°F) . They are available in a variety of 1686

temperature ranges, scale graduations, and lengths. The required instrument test 1687 accuracy minimum must be within a scale division mark. 1688

1689 Recommended Uses 1690

1691 a. The complete-stem-immersion calibrated thermometer must be used 1692

with the stem completely immersed in the fluid in which the temperature 1693

is to be measured. 1694 b. Thermometers calibrated for partial stem immersion are more 1695

commonly used. They are used in conjunction with thermometer test 1696 wells specifically designed to receive them. No emergent stem 1697 correction is required for the partial-stem-immersion type. 1698

1699 Limitations 1700

1701

Page 39: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

a. Radiation effects—When the temperature of the surrounding surfaces 1702

are substantially different from the measured fluid, there is a 1703 considerable radiation effect upon the thermometer reading if the 1704 thermometer is left unshielded or otherwise unprotected. Proper 1705 shielding or aspiration of the thermometer bulb and stem can minimize 1706

these radiation effects. 1707 b. Time is required for the thermometer to reach the temperature of the 1708

fluid being measured. 1709 c. Mercury may separate in the tube. 1710 1711

5.2.3 Calibrated Pressure Gauge 1712 1713

Test gauge shall be of a minimum “Grade A” quality and have Bourdon tube 1714

assemblies made of stainless steel, alloy steel, monel, or bronze, and a nonreflecting 1715 white face with black letter graduations conforming to ANSI/ASME Standard 1716 B40.1-1985, Gauges: Pressure Indicating Dial Type-Elastic Element.1 Test gauges 1717 are usually 3.5 to 6 in. (90 to 150 mm) in diameter with bottom or back connections. 1718

Many dials are available with pressure, vacuum, or compound ranges. Instrument 1719 minimum accuracy shall be within 1% of full scale. 1720

1721 Recommended Uses. 1722

1723 Use primarily for checking pump pressures, coil, chiller, and condenser pressure 1724 drops and pressure drops across orifice plates, venturis, and other flow-calibrated 1725

devices.” 1726

1727 Limitations 1728

1729

a. Pressure ranges shall be such that the anticipated working pressure range 1730 is in the middle two-thirds of the scale range, and the gauge shall not be 1731

exposed to pressures greater than the maximum dial reading. Similarly, 1732 where there is exposure to vacuum, use a compound gauge. 1733

b. Reduce or eliminate pressure pulsations by installing a snubber or needle 1734

valve in the water line. 1735 c. Eliminate vibration by avoiding mounting on vibrating equipment or 1736

piping. Wall mounting is preferred. Another alternative is to install 1737 pressure/temperature test ports that can be used with a portable stem 1738

probe and gauge (or thermometer) through an elastic, durable, self-1739 sealing material. The test port shall be capped when not in use for 1740 additional sealing security 1741

1742 5.2.4 Fluid System Digital Electronic Differential Pressure Meters 1743

1744 This instrument measures the differential pressure across an element in a system 1745 when flow is present. The digital reading can be in a pressure range of 0.3 to 50 ft 1746 wc (1 to 150 kPa). Some instruments provide a temperature probe for a range of 1747 32°F to 248°F (0°C to 120°C), hoses with snap-on fittings, and automatic air 1748

purging. A computer is available for calculating the flow in a range of 0.2 to 4750 1749 gpm (0.01 to 300 L/s) and computing the hand wheel setting of compatible valves 1750

Page 40: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

by proportional balancing procedures. Maximum working pressures can be up to 1751

300 psig (2060 kPa). 1752 1753

Recommended Uses. Use to measure fluid flow, temperature, and differential 1754 pressure; for computing the setting of compatible valves by proportional balancing 1755

procedures. 1756 1757

Limitations. The computing feature is limited to compatible valves. 1758 1759 1760

6.0 Test Methods 1761 1762 6.1 Air volumetric Measurement 1763

1764 6.1.1 Digital Vane Anemometer 1765 1766

Procedures. To obtain the air velocity from the readings of an air-velocity meter, 1767

Refer to the test procedure section 7- of this standard. 1768 1769

Location of Instrument. If the opening is covered with filters, grille, the instrument 1770 should touch the grille face and shall be 1 to 2 inches away for the filter section but 1771

should not be pushed in between its bars. For a free opening without a grille, guide 1772 wires should be stretched across the plane of the opening and the instrument held 1773 in such a manner that the airflow through the instrument is in the same direction as 1774

was used for calibration (usually from the back toward the dial face). An instrument 1775

should be held in place by means of a thin handle; the hands and body of the 1776 observer should be entirely outside the area of flow. 1777

1778

Correction Factor. The correction factor is the factor by which the average velocity 1779 for the instrument is to be multiplied to obtain the true average velocity. 1780

1781 Average Velocity for Instrument 1782

1783

Average Velocity × Designated Area = True Flow Rate 1784 1785

Accuracy. The general conclusions from Sauer and Howell were that the rotating 1786 vane anemometer can be relied upon for air volume measurements with an accuracy 1787

+5% if the measurements are made at a free-open intake (with flange) or at a free-1788 open discharge from a long duct. When the opening is covered with a grille or 1789 screen, the results are not as reliable, but an accuracy of 5% could be expected, both 1790 for flanged intakes and for discharge or supply openings that have an approach duct 1791 at least 2 diameters in length. The instrument factor is little affected by the area or 1792

the shape of the opening, by the instrument size, or by the air velocity above 500 1793 fpm (2.5 m/s). For comparative measurements, the anemometer is highly accurate, 1794 within 2% or less. 1795

1796 1797

1798 1799

1800

Page 41: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1801

1802 1803 1804 6.1.2 Pitot Tube & U Tube Manometer(Duct Traverse method) 1805

1806 General. It is assumed that an HVAC system will contain airways (ducts) suitable 1807 for flow measurement. Research and state-of-the-art practices allow the traversing 1808 of ducts as a field method for fan or system-performance measurement 1809

1810

Flow rate is determined by using the area and the average velocity at a traverse 1811 plane, as in the following equation: 1812

1813

𝑄 = 𝑉 × 𝐴 1814 where 1815 Q = flow rate in m3/s (cfm) 1816 A = cross sectional area at the traverse plane in m2 (ft2 ) 1817

V = average velocity in m/s (fpm) 1818 1819 6.1.2.1 Flow in Ducts 1820

1821 Instruments. The instruments recommended for use in measuring velocity pressure 1822 include a Pitot static tube and electronic instruments of comparable accuracy. These 1823

are described in Section 5 - Test equipment description. 1824 1825

Location of Traverse Plane. The qualifications for a Pitot traverse plane that is 1826 considered suitable for the measurements used in determining flow rate are as 1827

follows 1828 1829

The angle of the flow stream in any specific location is indicated by the orientation 1830 of the nose of the Pitot static tube that produces the maximum-velocity pressure 1831 reading. However, when making a duct traverse, the nose of the Pitot tube is held 1832 parallel to the side walls of the duct and pointing into the airflow. 1833

1834 The cross-sectional shape of the duct in which the traverse plane is located should 1835 not be irregular. Proper distribution of traverse points and accurate determination 1836 of the area of the traverse plane are difficult to achieve when the airway in which 1837

the traverse plane is located does not conform closely to a regular shape (round, 1838 oval, or rectangular). 1839

1840

The cross-sectional shape and area of the duct should be uniform throughout the 1841 length of the duct in the vicinity of the traverse plane. In instances where the 1842 divergence or convergence of the duct is irregular or more than moderate in degree, 1843 significantly non uniform flow conditions may exist. 1844

1845

The traverse plane should be located to minimize the effects of leaks in the portion 1846 of the system that is located between the traverse plane and the fan. 1847

1848 A location in a long, straight run of duct of uniform cross section will usually 1849

provide acceptable conditions for the Pitot traverse plane. In locating the traverse 1850

Page 42: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

plane close to a fan, as is often done to minimize the effect of leakage, flow 1851

conditions upstream of the fan are usually more suitable. In some installations, more 1852 than one traverse plane may be required in order to account for the total flow. Also, 1853 more than one traverse location per system may be used to substantiate the accuracy 1854 of the system performance. 1855

1856 In any installation in which a field test is anticipated, particularly when the 1857 requirement for a field test is an item in the specifications, provision should be 1858 included in the system for a suitable traverse plane location 1859

1860

In any instance in which the fan is ducted on the outlet side and the traverse plane 1861 is to be located downstream from the fan, the traverse plane should be situated a 1862 sufficient distance downstream from the fan to allow the flow to diffuse to a more 1863

uniform velocity distribution and to allow the conversion of velocity pressure to 1864 static pressure. The information presented in figure below provides guidance for the 1865 location of the traverse plane in these cases (see Figures D-2 and D-3). The location 1866 of the traverse plane on the inlet side of the fan should be more than 0.5 equivalent 1867

diameters from the fan inlet. In any case in which the traverse plane must be located 1868 within an inlet box, the plane should be located a minimum of 0.3 m . (12 inch) 1869

downstream from the leaving edges of the damper blades and more than 0.5 1870 equivalent diameters upstream from the edge of the inlet cone. 1871

1872

1873 1874

Page 43: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1875 1876

1877 Regions immediately downstream from elbows, obstructions, and abrupt changes 1878 in airway area are not suitable traverse plane locations. Regions where unacceptable 1879

levels of swirl are usually present should be avoided, such as the region downstream 1880

from an axial flow fan that is not equipped with straightening vanes. 1881 1882

On occasion, an undesirable traverse plane location may not be avoidable, or each 1883

of a limited number of prospective locations may lack one or more desirable 1884 qualities. In such cases, the alternatives are as follows: 1885

1886 a. Accept the most suitable location and evaluate the effects of the 1887

undesirable aspects of the location on the accuracy of the test results. 1888 1889 b. Provide a suitable location by modifying the system. The modifications 1890

may be temporary or permanent, minor or extensive, depending on the 1891

specific conditions encountered. Once a suitable location for the traverse 1892 plane has been established, the area of the traverse plane must be 1893 accurately determined. Measurement should be made by probing for the 1894

inside duct dimensions, and special care should be used when measuring 1895 lined duct. It is important to note, particularly in any case in which it is 1896 necessary to locate the traverse plane in a converging or diverging 1897 airway, that the traverse plane is located at the tip of the Pitot static tube. 1898

1899

The Traverse. To determine the velocity in the traverse plane, a straight average of 1900 individual point velocities will give satisfactory results when point velocities are 1901 determined by the following rules: 1902

1903

The Equal Area Rule is shown in Figure D-5A for traverses in a rectangular duct. 1904

Page 44: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1905

1906 1907

The Log-Tchebycheff Rule (from ISO 3966)10 is shown in Figure D-5B. 1908 1909

Figure D-6A, shows the measuring points for a circular duct traverse using the Log-1910 Linear Rule and three symmetrically disposed diameters. Points on two 1911

perpendicular diameters may be used where access is limited. 1912

Page 45: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1913 Figure D-6B, shows the measuring points for a commonly accepted flat-oval duct 1914

traverse. 1915

1916

Page 46: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1917 1918

Since field-measured airflows are rarely steady and uniform, accuracy can be 1919 improved by increasing the number of measuring points. When velocities at a 1920

traverse plane are fluctuating, the basis. Two traverse readings in short succession 1921 will also help to average out velocity variations that occur with time. If negative-1922 velocity pressure readings are encountered, they are considered a measurement 1923 value of “zero” and calculated into the average velocity pressure. 1924

1925

1926 1927 1928 1929

1930

Page 47: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1931

1932 6.1.2 Flow measuring hood/ matrix 1933 1934

The flow-measuring hood is a direct reading flow measurement device. It is 1935

designed with a fabric “sock” that covers the terminal air outlet device being 1936 measured. The conical or pyramid shaped hood collects all of the air entering or 1937 leaving an air outlet and guides the airflow over the flow measuring 1938 instrumentation. Hoods generally are constructed so that the outlet tapers down to 1939 the metering section. A velocity measuring grid and calibrated differential pressure 1940

manometer in the hood will display the airflow in cfm (l/s) directly. 1941 1942

Velocity Matrix. 1943

A velocity matrix provides a larger measurement area, reducing the total number of 1944 samples resulting in quicker measurements. The velocity matrix can be used on a 1945 supply opening with no grill or louvers and on the filters at the AHU room, but may 1946 not be the best choice if there are turbulent air flows. They can cause some turbulent 1947

air patterns which could affect the averaging function of the grid pressures. 1948 1949

Location of Instrument 1950 Capture hoods are popular instruments to use for measuring flow rates from supply 1951

grilles. Since they obtain measurements quickly, provide a direct air volume 1952 reading, are easy to use, and come with a variety of hood sizes to match various 1953 grilles, capture hoods are often the tool of choice (when measuring supply). 1954

1955

1956 ASHRAE standard 111 recommends performing a duct traverse to determine if a 1957 correction factor is needed for air capture hood measurements. Different diffuser 1958 styles, elbows attached directly to the diffuser, and dampers located just upstream 1959

of the diffuser can impair the uniformity of the flow patterns coming out of the 1960 diffuser and affect the hood reading. Be sure to choose the hood size that most 1961 closely matches the outlet size being measured 1962

1963 1964

1965

1966

Page 48: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

1967

Capture Hood Flow Resistance 1968 1969

All capture hoods cause flow resistance on the air handling system. Just as different 1970 diffuser styles have their own characteristic flow resistance, so do capture hoods. 1971

This added resistance reduces the actual volume of air exiting the diffuser. In the 1972 majority of cases, this error is less than or equal to the accuracy of the instrument. 1973 Proportional balancing techniques will also assist in making these effects 1974 negligible. 1975

1976

To determine if flow resistance effects are important, perform duct traverses* to 1977 determine the volume rate exiting a diffuser both with and without the capture hood 1978 in place. The difference between the volume rate with and without the capture hood 1979

in place is the flow resistance effect for that diffuser. 1980 1981

To determine a correction factor for flow resistance that can be used on similar 1982 diffusers and duct configurations, use the volume rates as determined from the duct 1983

traverses when performed with and without the hood applied to the diffuser or grill 1984 as follows. 1985

1986

𝐶𝑓 =𝑉𝑛𝑜 ℎ𝑜𝑜𝑑

𝑉ℎ𝑜𝑜𝑑⁄ 1987

1988 Where: 1989

𝑉 ℎ𝑜𝑜𝑑= Flow rate with the hood in place on the diffuser 1990

𝑉𝑛𝑜 ℎ𝑜𝑜𝑑 = Flow rate without the hood in place on the diffuser 1991

𝐶𝑓 = Correction factor 1992

1993

𝑉𝑐𝑜𝑟𝑟𝑒𝑐𝑡𝑒𝑑 = 𝐶𝑓 × 𝑉𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑 1994

1995 Where: 1996

𝑉𝑚𝑒𝑎𝑠𝑢𝑟𝑒𝑑 = Volume rate as displayed by the capture hood 1997

𝑉𝑐𝑜𝑟𝑟𝑒𝑐𝑡𝑒𝑑 = Volume rate corrected for the flow resistance of the capture hood 1998

1999 *Be sure to traverse the duct connected to the diffuser being tested. Also verify that 2000

there are no leaks in the duct between the traverse location and the diffuser or in the 2001

duct to diffuser connection. 2002

2003 Characterizing a Capture Hood to an Outlet Using a Correction Factor 2004 Capture hoods are to be calibrated on a wind tunnel with a 610 mm × 610 mm (2 ft 2005

× 2 ft) diffuser for supply and exhaust. To minimize recirculation regions (non-2006 laminar flows on one side of the hood), hood sizes should match the diffuser being 2007 measured as closely as possible. 2008

2009 Large recirculation regions will affect volume flow readings. Different diffuser 2010

sizes cannot be directly compared. On a 610 mm × 610 mm (2 ft × 2 ft) diffuser 2011 using a 610 mm × 610 mm (2 ft × 2 ft) hood, there are no recirculation regions. 2012

2013 If the capture hood is used on a small diffuser, the recirculation regions will create 2014

turbulence and the accuracy will be impaired. 2015

Page 49: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2016

2017 2018

2019 Characterizing the hood to the outlet being measured is accomplished by 2020

performing a duct traverse of the branch leading to the outlet and comparing it to 2021

the hood reading. Divide the duct traverse reading by the hood reading to come up 2022

with a correction factor to be applied to the hood readout. This correction factor can 2023 then be used on similar outlet and duct configurations 2024 To determine a correction factor for the hood to match a duct traverse, use the 2025 following formula: 2026

2027

𝐶𝑓 =𝐷𝑡𝑟

𝐻𝑟⁄ 2028

CF = Dtr / Hr 2029 2030

Where: 2031

𝐶𝑓= Correction Factor 2032

𝐶𝑓= Duct Traverse Reading 2033

𝐻𝑟 = Hood Reading 2034

Page 50: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2035

To apply the correction factor to the hood readout, use the following formula: 2036

𝐻𝑐 = 𝐻𝑟 × 𝐶𝑓 2037

2038

Where: 2039

𝐻𝑐 = Corrected Hood Reading 2040

𝐻𝑟 = Hood Reading 2041

𝐶𝑓 = Correction Factor 2042

2043 6.1.4 Water flow Measurement 2044 2045

Instruments 2046

The instruments shall conform to the requirements of “Section-5 Test equipment 2047 description” 2048

2049 6.1.4.1 Clamp on Ultrasonic flow meter 2050 2051

The flow measurements are made by penetrating the pipe with ultrasound. Time 2052

differences, frequency variations or phase shifts of the ultrasonic signals caused by 2053 the flowing liquid are subsequently evaluated. 2054

The measurement of flow is based on the principle that sound waves traveling in 2055 the direction of flow of the fluid require less time than when traveling in the 2056 opposite direction. The difference in transit times of the ultrasonic signals is an 2057

indication for the flow rate of the fluid. 2058

Since ultrasonic signals can also penetrate solid materials, the transducers can be 2059

mounted onto the outside of the pipe. 2060 2061

Transit-time principle 2062 2063

Transit-time flow meters utilize two transducers, which function as both ultrasonic 2064

transmitters and receivers. The transducers are clamped to the outside of a closed 2065

pipe at a specific distance from each other. 2066 2067

2068 Reflection Mode Diagonal Mode 2069

2070 The transducers can be mounted in reflection or in diagonal mode. This selection is 2071

based on pipe and liquid characteristics. 2072 2073 6.1.4.2 Doppler Ultrasonic Flow meters 2074 2075

Doppler ultrasonic flow meters measure the frequency change (doppler effect) of a 2076

signal sent into the flowing liquid stream across the pipe. The injected signal 2077 bounces off of bubbles or particles in the stream and this echo is returned to the 2078 transducer (Figure ). The frequency of the signal is shifted lower in case of flow 2079

moving away from the sensor. The device compares the frequency shift to the 2080

Page 51: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

original signal and computes the flow velocity. For accurate flow measurement with 2081

the doppler-type ultrasonic flow meter, the fluid should contain sufficient 2082 concentration of particles and/or bubbles to reflect the signal adequately. Doppler 2083 ultrasonic flowmeters work well with suspension flows where particle 2084 concentration is more than 100 parts per million and particle size is larger than 100 2085

micrometers, but less than 15 percent in concentration. Thus, these flowmeters are 2086 not recommended for use in clean water. Doppler flowmeters typically have just 2087 one transducer, therefore setup for measuring may be easier than the transit-time 2088 flowmeters. 2089

2090

2091 Selecting Portable Ultrasonic Flowmeters 2092 2093 There are a number of important factors to consider when choosing a good portable 2094

ultrasonic flowmeter. One factor is the sediment properties of the water in terms of 2095 quantity and size. Generally, when water to be measured has sediment particles 2096 more than 100 parts per million and larger than 100 micrometers (the numbers may 2097

be different for different manufacturers), the doppler type should be considered. On 2098 the other hand, in the case of clear and clean water without sufficient sediments, the 2099

transit-type works better. The desired level of accuracy should be considered when 2100 selecting the best portable ultrasonic flow meter for the job. 2101

2102 Measurement procedure 2103

2104 a. To ensure well-conditioned water flowing past the measuring location, a sufficient 2105

length of straight, unobstructed pipe is required from the meter location. It is sug-2106

gested placing flowmeters at a distance of at least 10 times the diameters of straight 2107 pipe (in Inches) downstream of pipe fixtures. 2108

b. Figure shows the straight pipe length requirements for some of the pipe fittings and 2109 configurations to ensure accurate flow measurement. The lengths (L) are in pipe 2110 diameter (D) multiples. For example, a 6-inch pipe with “10 D” recommendation is 2111

saying the meter should be at least 60 inches (5 feet) from the disturbance. Note, 2112 the lengths are from the fixture to the center of the ultrasonic meter. 2113

c. In case of the shorter straight length of the pipe, in which case correction factors 2114 may need to be employed. Correction factors for an ultrasonic meter can be derived 2115

from laboratory calibrations of manufacturer. 2116 d. Clean the surface of the pipe intended for measurement and area shall be smooth 2117

section of pipe free of defects . 2118

Page 52: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2119 e. Apply the acoustic gel between the transducer and the pipe. Like gels used for 2120

medical sonograms, this material makes a continuous path for the sound signal to 2121 pass through. 2122

f. Applying the gel requires caution to ensure it does not dry out or air bubbles are not 2123

introduced from excessive spreading. Bubbles in the gel can cause signal echoes. 2124 The gel should be applied in a bead that will spread evenly along the transducer 2125 base and allow for full contact with the pipe wall when the transducer is pressed 2126 onto the pipe. 2127

g. The transducers must be mounted exactly parallel to the liquid flow in the pipe. 2128 h. Input the pipe wall thickness into the ultrasonic flow meter as per the pipe technical 2129

data sheet. 2130

i. The transit-time flowmeter transducer pairs shall be mounted as per the 2131

arrangements . The three main configurations are the direct transmission (Z-2132 method), the single reflection (V-method), and the multiple reflection (W-method). 2133

The first two configurations are most common. The direct method where 2134 transducers are mounted on the opposite sides are more commonly used in larger 2135 diameter pipes whereas the reflection methods, where the transducers are mounted 2136

on the same side, are normally applied for small diameter pipes 2137

2138 2139 2140 2141

2142

Page 53: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2143

j. Measure and record the water flow. 2144 2145 e. Temperature Measurement: Air side & Water side 2146 2147

6.2 Air Side 2148 2149

Air temperatures consist of the dry-bulb temperature (DBT) and the wet-bulb 2150 temperature (WBT). These temperatures are required to determine density/specific 2151 volume of air, humidity (moisture content), and the heat content of the air handled 2152

by the system 2153 2154

Instruments 2155

2156 Mercury thermometer 2157 Electric resistance thermometer, including thermistors. 2158

2159

The instruments shall conform to the requirements of “Section-5 Test equipment 2160 description” 2161

2162 6.2.1 Dry-Bulb Measurements 2163

2164 The following shall be considered to ensure that temperature measurements are 2165 representative of the airstream being tested at the plane of interest: 2166

If temperature stratification exists, a sufficient number of readings shall be obtained 2167

to ensure that the average value represents the true value. 2168 2169

When determining wet-bulb depression, the two temperature- measuring devices 2170

shall be calibrated against each other to obtain better accuracy. When DBT and 2171 WBT are being obtained simultaneously, the DB measuring device shall be 2172

upstream from the WB measuring device to ensure that the DBT reading is not 2173 influenced by the effects that the WB device may have on that portion of the 2174 airstream that flows over the DB device. 2175

2176 There shall be no “liquid” moisture in the airstream at the point where the DB 2177

reading is obtained 2178 2179

The sensor shall be shielded if thermal radiation is a factor that could influence the 2180 reading. 2181

2182 Consideration shall be given to appropriate immersion of the sensing device into 2183 the airstream and correction factors applied if necessary. 2184

2185 Temperature measurements shall be made over a sufficient length of time to ensure 2186 that a steady-state value is being recorded or, if there are oscillations in the values, 2187 that representative average values can be determined. 2188

2189

2190 2191

2192

Page 54: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2193

6.2.2 Wet-Bulb Measurements 2194 2195

The considerations noted in Section above also apply to wet-bulb temperature 2196 measurements, as do the following: 2197

2198 Distilled water shall be used to wet the wick of the wet bulb sensing device. 2199

2200 The wick covering the sensor shall be clean and remain wet while the measurement 2201 is being made. 2202

2203 The time over which the measurement is made shall be sufficient for equilibrium to 2204 be achieved. 2205

2206 The air velocity across the sensor shall be between 3.5 and 10 m/s (700 and 2000 2207 fpm) for minimum error. 2208

2209

The sling psychrometer is recommended for obtaining wet-bulb temperatures of 2210 ambient air. 2211

2212 System Conditions. System conditions can produce effects that cause temperature-2213

measurement errors. The following are the most commonly encountered. 2214 2215

Stratification 2216

Velocity 2217

Temperature 2218 Contamination 2219 Dust (Wet Bulb) 2220

Contaminated H2O (Wet Bulb) 2221 Free moisture (Dry Bulb) 2222

2223 6.3 Water Side 2224 2225

Temperatures of fluids, such as water, oil, antifreeze solutions, heat-transfer fluids, 2226 etc., will be used to determine the intensity of the heat content using either the 2227

Fahrenheit (°F) scale or the Celsius (°C) scale. For HVAC work, the normal 2228 operating range is from 5°C (40°F ) to 99°C (210°F). 2229

2230 The quantity or amount of heat in a fluid is measured in British Thermal Units (Btu) 2231 or in kilojoules (kJ). Heat flow is measured in Btu per hour (btu/h) or watts (W). 2232

2233 2234

Instruments 2235 2236 6.3.1 Temperature measurements of fluid shall be made using the following instruments: 2237

Mercury thermometer 2238 Electric resistance thermometer 2239

2240 2241

2242

Page 55: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2243

6.3.1a Fluid Immersion 2244 2245

Thermometer test wells installed at the desired locations permit accurate readings 2246 without removal or loss of the system fluid. A good heat transfer fluid ( Glycerene) 2247

or mastic should be used to ensure a good thermal contact between the thermometer 2248 and the test well. 2249

2250 Radiation Effects. When the temperatures of the surrounding surfaces are 2251 substantially different from the measured fluid, there is considerable radiation effect 2252

upon the thermometer reading if the thermometer is left unprotected. Proper 2253 shielding or aspiration of the thermometer bulb and stem can minimize these 2254 radiation effects. 2255

2256 Emergent Stem Correction. The complete stem- immersion type of calibrated 2257 thermometer must be used with the stem completely immersed in the fluid in which 2258 the temperature is to be measured. If complete immersion of the thermometer stem 2259

is not possible or practical, then a correction must be made for the amount of 2260 emergent liquid column. 2261

2262 The correct equation is: 2263

2264

𝑆𝑡𝑒𝑚 𝑐𝑜𝑟𝑟𝑒𝑐𝑡𝑖𝑜𝑛 = 𝑘𝑛 × (𝑡𝑏 − 𝑡𝑠) 2265 2266 where 2267

k (Hg), °C = 1.00016 2268 k (Hg), °F = 1.00009 2269

n = number of degrees of emergent liquid column 2270

𝑡𝑏 = temperature of bath 2271

𝑡𝑠 = temperature of stem 2272 2273

Thermometers calibrated for partial-stem immersion are more commonly used. 2274 They are used in conjunction with thermometer test wells designed to receive them. 2275

No emergent stem correction is required for the partial-stem-immersion type 2276 2277 6.4 Pressure Measurement: Air side & Water side 2278

2279

6.4.1. Air Side 2280

2281 The pressures involved with air measurements are static pressure, velocity pressure, 2282

total pressure, and differential pressure. One or more of these pressures is required 2283 to determine air density, airflow rate, and resistance to airflow of system 2284 components and to make certain system component adjustments 2285

2286 Experience must be used in selecting a pressure measurement plane. Even the best 2287

location available in the field must be evaluated for system effects that can influence 2288 the accuracy of the measurement. An example is the measurement of fan total 2289 pressure. Rarely, if ever, can the fan pressure be measured in strict accordance with 2290 AMCA-specified methods. Therefore, even experienced engineers should use this 2291

field-measurement method as a guide only. 2292

Page 56: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2293

Instruments. 2294 2295

Instruments used refer to Section 5- Test Equipment Description for details. 2296 2297

Static Pressure 2298 2299

When testing, adjusting, and otherwise evaluating a system, all values of static 2300 pressure (design values and test values) must be referenced to the same value of 2301 atmospheric (barometric) pressure. (Static pressure measurements can be either 2302

positive or negative. Positive values are those greater than atmospheric pressure. 2303 Negative values are those less than atmospheric pressure.) 2304

2305

A Pitot static tube with a manometer or pressure taps with a manometer shall be 2306 used to measure static pressure. It is important that the inner duct surface /plenum 2307 be smooth and free from irregularities and that the velocity of the gas stream does 2308 not influence the pressure measurements. 2309

2310 A straight run of duct upstream of the measurement plane usually results in 2311

acceptable conditions at the plane. Regions immediately downstream from elbows 2312 or regions where there are obstructions and abrupt changes in airway area are 2313

generally unsuitable locations. Regions where unacceptable airflow irregularities 2314 are present shall be avoided. Refer to Section 5 Test Equipment description for 2315 details. 2316

2317

In any fan system installation, if the prospective locations for static pressure 2318 measurement are not stable, the alternative is to accept the best-qualified locations 2319 and evaluate the effects of the undesirable aspects of the conditions on the accuracy 2320

of the test results. 2321 2322

Special consideration should be given to measuring static pressures for use in 2323 determining fan static. It is recommended that the measurements be made at 2324 locations near the fan inlet and near the fan outlet and that the duct between the 2325

measurement plane and the plane of interest be straight and without change in a 2326 cross-sectional area. In this situation, the duct friction loss between the 2327

measurement plane and the plane of interest is usually insignificant and 2328 considerations of velocity pressure conversions and calculations of pressure losses 2329

for duct fitting and other system components can be avoided. 2330 2331

Fan total pressure (𝑃𝑡𝑓) is the algebraic difference between the fan-outlet total 2332

pressure (𝑃𝑡2) and the fan inlet total pressure (𝑃𝑡1). It is the measure of the total 2333 mechanical energy added to the air by the fan 2334

2335

𝑃𝑡𝑓 = 𝑃𝑡2 − 𝑃𝑡1 2336

2337

Fan velocity pressure (𝑃𝑣𝑓) is the velocity pressure corresponding to the average 2338

velocity through the fan outlet. It is the kinetic energy per unit volume of air exiting 2339 the fan. 2340

2341

Page 57: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Differential fan static pressure (𝑃𝑠𝑓) is the algebraic difference between the 2342

discharge fan static pressure (𝑃𝑠𝑓1) and the suction static pressure of the fan (𝑃𝑠𝑓2). 2343

2344

𝑃𝑠𝑓 = 𝐹𝑎𝑛 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑆𝑡𝑎𝑡𝑖𝑐 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 (𝑃𝑠𝑓1) - 2345

𝐹𝑎𝑛 𝑠𝑢𝑐𝑡𝑖𝑜𝑛 𝑠𝑡𝑎𝑡𝑖𝑐 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 (𝑃𝑠𝑓2) 2346

2347 In the event the fan is ducted on the outlet side, the static pressure- measurement 2348

plane downstream of the fan shall not be less than one equivalent diameter from the 2349 fan. 2350

2351 The location of the static-pressure-measurement plane upstream of the fan should 2352 not be less than 0.5 equivalent diameters from the fan inlet. 2353

2354 In the event that static pressure measurements must be obtained in an inlet box, the 2355 measurement plane should be located as indicated in Figure. In the case of double 2356

inlet fans, static pressure measurements must be made in both inlet boxes in order 2357 to determine the average static pressure on the inlet side of the fan. 2358

2359 2360 6.4.2 Filters Static pressure drop 2361

2362 Measuring the pressure drop across a filter is effective method for verifying filter 2363 and system performance. An air filter should be changed when the filter fills up 2364

with debris and creates an excessive pressure drop, resulting in reduced airflow 2365

Page 58: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

through the filter. Periodic visual inspections and monitoring the pressure drop 2366

across the filter with a mechanical or digital manometer is a simple solution for 2367 general ventilation system maintenance. 2368

2369

Differential filter static pressure (𝑃𝑠𝑓) is the algebraic difference between the 2370

discharge filter static pressure 2371 2372

(𝑃𝑠𝑓1) and the suction static pressure at the filter (𝑃𝑠𝑓2). 2373

2374

𝑃𝑠𝑓 = 𝐹𝑖𝑙𝑡𝑒𝑟 𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑠𝑡𝑎𝑡𝑖𝑐 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑃𝑠𝑓12375

− 𝐹𝑖𝑙𝑡𝑒𝑟 𝑠𝑢𝑐𝑡𝑖𝑜𝑛 𝑠𝑡𝑎𝑡𝑖𝑐 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒 𝑃𝑠𝑓2 2376

2377

6.5 Water Side 2378 2379

Instruments 2380

2381 Pressure and/or vacuum measurements of fluids shall be made using the instruments 2382 referred in the section 5 Test Equipment description 2383

Gauge/Absolute Pressure. The pressure of most hydronic systems is measured in 2384 terms of pounds per square inch (psi [kPa]) or feet of water (ft wg [Pa]). This 2385 indicated pressure is known as the gauge pressure (psig), and for gauge pressure, 2386

the measuring device should indicate a zero reading when not connected. 2387 2388

For HVAC work, atmospheric pressure can be assumed to be 101.3 kPa (14.7 psi ) 2389

at sea level, even though barometric conditions constantly change. Absolute 2390

pressure (psia) equals the gauge pressure plus the 101.3 kPa (14.7 psi ) of 2391 atmospheric pressure. 2392

2393 Differential pressure: The pressure difference existing between two measured 2394 pressures. If possible, the same gauge should be used to take both readings. 2395

2396

6.6. Sound pressure Measurement with respect to AHU operation. 2397 2398

Present technology does not test whether equipment is operating with desired sound 2399 levels; field tests can only determine sound pressure levels, and equipment ratings 2400 are almost always in terms of sound power levels. Until new techniques are 2401

developed, the testing engineer can only determine (1) whether sound pressure 2402 levels are within desired limits and (2) which equipment, systems, or components 2403

are the source of excessive or disturbing transmission 2404 2405

Sound-Measuring Instruments. 2406 Instruments used for sound pressure level. Refer to Section 5- Test Equipment 2407 Description for details. 2408

2409 The precision sound level meter is used to measure sound pressure level. The most 2410

basic sound level meters measure overall sound pressure level and have up to three 2411 weighted scales that provide limited filtering capability. The instrument is useful in 2412 assessing outdoor noise levels in certain situations and can provide limited 2413

information on the low-frequency content of overall noise levels, but it provides 2414 insufficient information for problem diagnosis and solution. Its usefulness in 2415

Page 59: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

evaluating indoor VAC sound sources is thus limited. Proper evaluation of HVAC 2416

sound sources requires a sound level meter capable of filtering overall sound levels 2417 into frequency increments of one octave or less. 2418

2419 Sound analyzers provide detailed information about sound pressure levels at various 2420

frequencies through filtering networks. The most popular sound analyzers are the 2421 octave band and center frequency, which break the sound into the eight octave 2422 bands of audible sound. Instruments are also available for 0.33, 0.1, and narrower 2423 spectrum analysis; however, these are primarily for laboratory and research 2424 applications. Sound analyzers (octave midband or center frequency) are required 2425

where specifications are based on noise criteria (NC) and room criteria (RC) curves 2426 or similar frequency criteria and for problem jobs where a knowledge of frequency 2427 is necessary to determine proper corrective action. 2428

2429 Sound Level Criteria. Without specified values, the testing engineer must determine 2430 whether sound levels are within acceptable limits (Refer ASHRAE HVAC 2431 Application 2011-Chapter 47). Note that complete absence of noise is seldom a 2432

design criterion, except for certain critical locations such as sound and recording 2433 studios. In most locations, a certain amount of noise is desirable to mask other 2434

noises and provide speech privacy; it also provides an acoustically pleasing 2435 environment, because few people can function effectively in extreme quiet. Table 2436

1 in Chapter 8 of the 2009 ASHRAE Handbook—Fundamentals lists typical sound 2437 pressure levels. In determining allowable HVAC equipment noise, it is as 2438 inappropriate to demand 30 dB for a factory where the normal noise level is 75 dB 2439

as it is to specify 60 dB for a private office where the normal noise level might be 2440

35 dB. Most field sound-measuring instruments and techniques yield an accuracy 2441 of ±3 dB, the smallest difference in sound pressure level that the average person can 2442 discern. A reasonable tolerance for sound criteria is 5 dB; if 35 dBA is considered 2443

the maximum allowable noise, the design engineer should specify 30 dBA. The 2444 measured sound level of any location is a combination of all sound sources present, 2445

including sound generated by HVAC equipment as well as sound from other 2446 sources such as plumbing systems and fixtures, elevators, light ballasts, and outdoor 2447 noises. In testing for sound, all sources from other than HVAC equipment are 2448

considered background or ambient noise. Background sound measurements 2449 generally have to be made 2450

(1) when the specification requires that the sound levels from HVAC equipment 2451 only, as opposed to the sound level in a space, not exceed a certain specified level; 2452

(2) when the sound level in the space exceeds a desirable level, in which case the 2453 noise contributed by the HVAC system must be determined; and 2454 (3) in residential locations where little significant background noise is generated 2455 during the evening hours and where generally low allowable noise levels are 2456 specified or desired. Because background noise from outdoor sources such as 2457

vehicular traffic can fluctuate widely, sound measurements for residential locations 2458 are best made in the normally quiet evening hours. Procedures for residential sound 2459 measurements can be found in ASTM Standard E1574, Measurement of Sound in 2460 Residential Spaces. 2461

2462

2463 2464

2465

Page 60: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2466

2467 6.7 Vibration analysis 2468 2469

Instruments 2470

Refer to the section5 Test Equipment description. 2471 2472

Vibration testing is necessary to ensure that 2473 (1) equipment is operating within satisfactory vibration levels and 2474 (2) objectionable 2475

Vibration and noise are not transmitted to the building structure. Although these 2476 two factors are interrelated, they are not necessarily interdependent. A different 2477 solution is required for each, and it is essential to test both the isolation and vibration 2478

levels of equipment. 2479 General Procedure. 2480 Make a visual check of all equipment for obvious errors that must be corrected 2481 immediately. 2482

2483 Make sure all isolation is free-floating and not short-circuited by obstruction 2484

between equipment or equipment base and building structure. 2485 2486

Turn on the system for an aural check of any obviously rough operation. Checking 2487 bearings with vibration measurement instrumentation is especially important 2488 because bearings can become defective in transit and/or if equipment was not 2489

properly stored, installed, or maintained. Defective bearings should be replaced 2490

immediately to avoid damage to the shaft and other components 2491 2492 Adjust and balance equipment and systems so that final vibration tests are made on 2493

equipment as it will actually be operating. 2494 2495

2496 i. Power measurement: Voltage, Current, Frequency, kW 2497 2498

Using the field test measurements of amps, input, volts, the typical motor-2499 performance data values of power factor (pf), and the motor-efficiency 2500

corresponding to the measured amps input, the motor power output is calculated as 2501 follows 2502

2503 bhp = (amps × volts × pf × motor efficiency)/746- for single-phase motors, 2504 bhp = (1.73 × amps × volts × pf × motor efficiency)/746- for three-phase motors 2505

2506 In both equations, amps and volts are the field-test measurement values and, in the 2507

case of three-phase motors, are the averages of the measured phase values. 2508 2509

The specific manufacturer’s motor performance data for the particular motor being 2510 tested may be used to estimate actual running horsepower at load. Most motor 2511 manufacturers publish performance curves for each style and size of motor they 2512

manufacture. These curves show the relationship between actual running hp, motor 2513 speed (rpm), motor efficiency at load, and motor-power factor at load. 2514

2515

Page 61: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

From field measurements of motor electrical input kilowatts, voltage, and 2516

amperage, the following relationship can be used to determine motor power factor: 2517 2518

kW = (1.73205 × V × A × pf)/1000 2519 2520

Rearranging terms, 2521 2522 pf = (kW × 1000)/(1.73205 × V × A) 2523 2524 where: 2525

kW = three-phase kilowatts 2526 V = three-phase voltage 2527 A = average amperage across all three-phases 2528

2529 Note: For single-phase motors, the factor 1.73205 becomes 1.0. 2530

2531 Using the calculated power factor and/or the measured motor rpm, determine the 2532

estimated motor efficiency and the Percent of full-load horsepower from the 2533 manufacturer’s motor performance curves. 2534

2535 The frequency of operation of the motor shall be considered as 50Hz as per Indian 2536

power regulations and in case VFD provided for fans, actual frequency readings 2537 from the field VFD to be measured. 2538

2539

7.0 Test Procedures 2540

2541 Air volumetric measurement 2542

2543

7.1 General 2544 The requirements of Section 5 and Section-6, “Air Measurement,” shall apply as a 2545

minimum to system air face velocity measurement at the Air handlers 2546 2547 7.1.1. System Preparation 2548

2549 Prior to the air volumetric measurement obtain and verify the following: 2550

2551

a) Obtain updated construction drawings, specifications, approved shop drawings 2552

and submittals, addenda, bulletins, and change orders related to the air systems 2553

b) Obtain /refer field-data forms for equipment delivery, Pre-commissioning & 2554

start up checklist .(refer Section-9 for AHU Checklist) 2555

c) Conduct the Pre-commissioning & Start up checks as per the section-9 checklist 2556

of Air handlers 2557

d) Verify that fans are installed, rotating correctly with proper rpm, and controlled 2558

to supply the required airflow rate, and that all installation, start-up, lubrication, 2559

and safety requirements have been met. 2560

e) Check that filters are clean and properly mounted and sealed. 2561

f) Verify that fire, smoke, automatic, and volume-control dampers are operable 2562

and accessible and are in an open or normal position. 2563

Page 62: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

g) Verify that controls are installed, operable, and calibrated 2564

h) Verify that boxes are installed, operable, and accessible 2565

i) Verify that terminal devices are installed and accessible. 2566

j) Verify that access doors are installed and secured. 2567

2568 Perform the following in accordance with design documents before beginning Air 2569 volumetric measurement 2570

2571

Verify that all dampers are in an open position and all boxes or automatic 2572 air-volume control devices are in an acceptable mode. 2573

Verify that all air terminal deflectors are in the position indicated by the 2574

manufacturer when using Ak ( effective area) factors to determine airflow 2575 rate and obtain correction factors for all velocity-measuring instruments 2576

Record the nameplate data on the fan, motor, and air handling cabinet. 2577 2578

Air volumetric measurement procedure 2579 2580

a) Operate the associated Air handler fan to full capacity. 2581

b) Set the system in the minimum outdoor-air mode . 2582

c) Refer section -5 and section-6 test method of Air volumetric measurement “for 2583

methods of measurement. 2584

d) Calculate the area of the filters/ grills/louvers and apply the diversity factor for 2585

grills and louvers as per manufacturer data. 2586

e) Perform the air balancing as per the section “air balancing “of this standard. 2587

f) Perform a Pitot-tube velocity traverse of the main ducts and record the average 2588

velocity at the main duct. 2589

g) Calculate the supply air volume as per the below equation 2590

2591

Q = VA 2592 where 2593 Q = flow rate in cfm (m3/s) 2594

A = cross sectional area at the traverse plane in ft2 (m2) /filter 2595 2596

h) Measure the return airflow rates across the filters/louvers/grills using the Vane 2597

anemometer /matrix velocity meter and record the average face velocity. 2598

i) Calculate the return air volume as per the STEP 7. 2599

j) The total design flow must include the estimated duct leakage (Refer the ducting 2600

section of this standard) plus 10% of system total to allow for balancing effects. 2601

Minimum outdoor air quantities must be maintained during all system modes 2602

established by Pitot-tube velocity traverse or Matrix velocity meter. 2603

k) Record the above data in operational data collection sheet provided in the 2604

section-9 2605

l) Follow the above step 3 to 10 of this procedure for DOA exhaust and supply fan 2606

air volumetric measurement. 2607

Page 63: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2608

2609 7.2 Water flow measurement 2610 2611

General 2612

2613 The requirements of Section 5, and Section 6, “Water flow measurement,” shall 2614 apply as a minimum to system at the Air handlers 2615

2616 7.2.1 System Preparation 2617

2618

a. Obtain updated construction drawings, specifications, approved shop drawings 2619

and submittals, addenda, bulletins, and change orders related to the air systems 2620

b. Obtain /refer field-data forms for equipment delivery, Pre commissioning & 2621

start up checklist .(refer section-9 AHU Checklist) 2622

c. Conduct the Precommissioning & Start up checks as per the section-9 for 2623

checklist of Air handlers. 2624

d. Verify that coils, valves, strainers, insulation pipes and associated controls are 2625

installed and controlled to supply the designed water rate, and that all 2626

installation, start-up, lubrication, and safety requirements have been met. 2627

e. Perform the water balancing as per the section water balancing described else 2628

where in this standard 2629

f. Open all manual valves for maximum flow 2630

g. Check the strainers and see that they are clean and have the correct mesh for the 2631

system fluid. 2632

h. Verify the commissioning of the associated chillers, pumps & Cooling tower 2633

systems and associated controls as specified in this standard, refer section-9 for 2634

checklist. 2635

2636 7.2.2 Water flow measurement 2637

2638

a. Operate the associated chilled water system i.e Chillers, Pumps & Cooling 2639

towers to design /full capacity. 2640

b. Verify that butterfly valves are open fully, balancing valves are adjusted to 2641

design water flow. 2642

c. Refer section-5 and section-6 test method of water flow measurement “for 2643

methods of measurement. 2644

d. Install the water flow meter on the desired location of the air handler pipes. 2645

e. Record the above data in operational data collection sheet provided in the 2646

section-9 “ 2647

2648

2649 2650

2651 2652

Page 64: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2653

7.3 Temperature Measurement: Air side & Water side 2654 2655 7.3.1 General 2656 2657

The requirements of Section 5 and Section 6, “Air volumetric measurement & 2658 Water flow measurement,” shall apply as a minimum to system at the Air handlers 2659

2660 7.3.2 System preparation 2661 2662

a) Obtain updated construction drawings, specifications, approved shop drawings 2663

and submittals, addenda, bulletins, and change orders related to the air systems 2664

b) Obtain /refer field-data forms for equipment delivery, Pre commissioning & 2665

start up checklist .(refer Section-9 for AHU Checklist) 2666

c) Conduct the Pre commissioning & Start up checks as per the Section-9 checklist 2667

of Air handlers. 2668

d) Verify that coils, valves, strainers, insulation pipes and associated controls are 2669

installed and controlled to supply the designed water rate, and that all 2670

installation, start-up, lubrication, and safety requirements have been met. 2671

e) Verify that fans are installed, rotating correctly with proper rpm, and controlled 2672

to supply the required airflow rate, and that all installation, start-up, lubrication, 2673

and safety requirements have been met. 2674

f) Check that filters are clean and properly mounted and sealed. 2675

g) Verify that fire, smoke, automatic, and volume-control dampers are operable 2676

and accessible and are in an open or normal position. 2677

h) Verify that controls & gauges are installed, operable, and calibrated 2678

i) Verify that boxes are installed, operable, and accessible 2679

j) Verify that terminal devices are installed and accessible. 2680

k) Verify that access doors are installed and secured. 2681

l) Verify that all dampers are in an open position and all boxes or automatic air-2682

volume control devices are in an acceptable mode. 2683

m) Verify that all air terminal deflectors are in the position indicated by the 2684

manufacturer when using Ak (effective area) factors to determine airflow rate 2685

and obtain correction factors for all velocity-measuring instruments 2686

n) Record the nameplate data on the fan, motor, and air handling cabinet. 2687

o) Prior to recording the temperature, system shall be in equilibrium and 2688

operational from 30 Minutes. 2689

2690 7.3.3. Temperature Measurement: Air side & Water side procedure 2691 2692

a. Operate the associated chilled water system i.e Chillers, Pumps & Cooling 2693

towers to design /full capacity. 2694

b. Operate the associated Air handler fan to full capacity. 2695

c. Set the system in the minimum outdoor-air mode . 2696

Page 65: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

d. Refer section-5 and section-6 test method of Temperature measurement “for 2697

methods of measurement. 2698

e. Verify that butterfly valves are open fully, balancing valves are adjusted to 2699

design water flow. 2700

f. With the system at equilibrium, measure the coil temperatures by setting the 2701

coil to its design water flow and airflow. Measure the entering and leaving water 2702

temperatures, entering and leaving coil temperatures and supply and return air 2703

temperatures (dry-bulb and wet-bulb for cooling coils and drybulb only for 2704

heating coils). 2705

g. Record the above data in operational data collection sheet provided in the 2706

Section-9” 2707

2708 7.4. Pressure Measurement: Air side & Water side 2709

2710 7.4.1. General 2711 2712

The requirements of Section 5 and Section 6 shall apply as a minimum to system at 2713

the Air handlers 2714 2715

7.4.2 System preparation 2716 2717

Repeat the system preparation methods for the Temperature Measurement: Air side 2718

& Water side 2719 2720

7.4.3 Pressure Measurement: Air side & Water side procedure 2721 2722

a. Operate the associated chilled water system i.e Chillers, Pumps & Cooling 2723

towers to design /full capacity. 2724

b. Operate the associated Air handler fan to full capacity. 2725

c. Set the system in the minimum outdoor-air mode . 2726

d. Refer section-5 and section-6 test method of Temperature measurement “for 2727

methods of measurement. 2728

e. Verify that butterfly valves are open fully, balancing valves are adjusted to 2729

design water flow. With the system at equilibrium, measure the coil 2730

temperatures by setting the coil to its design water flow and airflow. Measure 2731

the air side pressure across the all filters, coils and fan using the instrument as 2732

specified in the section-5 2733

f. Measure the water pressure with calibrated pressure gauges installed at the Air 2734

handlers pipe section. 2735

g. Record the above data in operational data collection sheet provided in the 2736

section-9 2737

2738 2739

2740 2741

Page 66: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2742

2743 7.5 Rotational Speed Measurement 2744 2745 7.5.1 System Preparation 2746

2747

a. Obtain updated construction drawings, specifications, approved shop drawings 2748

and submittals, addenda, bulletins, and change orders related to the air systems 2749

b. Obtain /refer field-data forms for equipment delivery, Pre-commissioning & 2750

start up checklist .(refer Section 9 for AHU Checklist) 2751

c. Conduct the Pre-commissioning & Start up checks as per the section-9 for 2752

checklist of Air handlers. 2753

d. Verify that fans are installed, rotating correctly with proper rpm, and controlled 2754

to supply the required airflow rate, and that all installation, start-up, lubrication, 2755

and safety requirements have been met. 2756

e. Check that filters are clean and properly mounted and sealed. 2757

f. Verify that fire, smoke, automatic, and volume-control dampers are operable 2758

and accessible and are in an open or normal position. 2759

g. Verify that controls are installed, operable, and calibrated 2760

h. Verify that boxes are installed, operable, and accessible 2761

i. Verify that terminal devices are installed and accessible. 2762

2763

7.5.2 Test Procedure 2764

2765

a. Open all air inlets and doors fully. 2766

b. If fan blades are plastic a reflective sticker will need to be placed approximately 2767

5 – 7 cm (2 – 3 in) from the tip of the blade. 2768

c. Turn on the fan to be tested. All fans should be tested individually and at full 2769

speed. 2770

d. Holding the meter still 0.6 - 1.0 m (2 - 3 ft) away from the fan and at a slight 2771

angle point the laser at the sticker or directly at one blade if blades are reflective 2772

/ metal, until the reading on the tachometer becomes constant. 2773

e. Compare fan RPM with manufacturers specifications 2774

f. If the fan has reflective / metal blades the recording on the tachometer must be 2775

divided by the number of blades the fan has. The RPM should be within 2776

manufacturer’s guidelines or the guidelines set by an independent testing 2777

facility. 2778

g. Record the above data in operational data collection sheet provided in the 2779

section-9 2780

2781 2782 2783 2784

2785

Page 67: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2786

7.6 Vibration analysis 2787 2788 7.6.1 Testing Vibration Isolation 2789 2790

Ensure that equipment is free-floating by applying an unbalanced load, which 2791 should cause the equipment to move freely and easily. On floor-mounted 2792 equipment, check that there are no obstructions between the base or foundation and 2793 the building structure that would cause transmission while still permitting 2794 equipment to rock relatively free because of the application of an unbalanced force 2795

(Figure 13). On suspended equipment, check that hanger rods are not touching the 2796 hanger. Rigid connections such as pipes and ducts can prohibit mounts from 2797 functioning properly and from providing a transmission path. Note that the fact that 2798

the equipment is free floating does not mean that the isolators are functioning 2799 properly. For example, a 500 rpm fan on isolators with a natural frequency of 500 2800 cpm (8.33 Hz) could be free-floating but would actually be in resonance, resulting 2801 in transmission to the building and excessive movement. 2802

2803 Determine whether isolators are adjusted properly and providing desired isolation 2804

efficiency. All isolators supporting a piece of equipment should have approximately 2805 the same deflection (i.e., they should be compressed the same under the equipment). 2806

If not, they have been improperly adjusted, installed, or selected; this should be 2807 corrected immediately. Note that isolation efficiency cannot be checked by 2808 comparing vibration amplitude on equipment to amplitude on the structure (Figure 2809

14). 2810

The only accurate check of isolation efficiencies is to compare vibration 2811 measurements of equipment operating with isolators to measurements of equipment 2812 operating without isolators. Because this is usually impractical, it is better to check 2813

whether the isolator’s deflection is as specified and whether the specified or desired 2814 isolation efficiency is being provided. 2815

2816

2817 2818

2819

Page 68: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2820

Although it is easy to determine the deflection of spring mounts by measuring the 2821 difference between the free heights with a ruler (information as shown on submittal 2822 drawings or available from a manufacturer), these measurements are difficult with 2823 most vibration pads or rubber mounts. Further, most pads and rubber mounts do not 2824

lend themselves to accurate determination of natural frequency as a function of 2825 deflection. For these mounts, the most practical approach is to check that there is 2826 no excessive vibration of the base and no noticeable or objectionable vibration 2827 transmission to the building structure. 2828

2829

If isolators are in the 90% efficiency range and there is transmission to the building 2830 structure, either the equipment is operating roughly or there is a flanking path of 2831 transmission, such as connecting piping or obstruction, under the base. 2832

2833 2834 7.6.2 Procedure for Testing Equipment Vibration. 2835 2836

a. Determine operating speeds of equipment from nameplates, drawings, 2837 or a speed-measuring device such as a tachometer or strobe, and indicate 2838

them on the test form. For any equipment where the driving speed 2839 (motor) is different from the driven speed (fan wheel, rotor, impeller) 2840

because of belt drive or gear reducers, indicate both driving and driven 2841 speeds. 2842

2843

b. Determine acceptance criteria from specifications, and indicate them on 2844

the test form 2845 2846

c. Ensure that the vibration isolation system is functioning properly 2847

2848 d. Operate equipment and make visual and aural checks for any apparent 2849

rough operation. Any defective bearings, misalignment, or obvious 2850 rough operation should be corrected before proceeding further. If not 2851 corrected, equipment should be considered unacceptable. 2852

2853 e. Measure and record vibration at bearings of driving and driven 2854

components in horizontal, vertical, and, if possible, axial directions. At 2855 least one axial measurement should be made for each rotating 2856

component (fan motor, pump motor). 2857 2858

f. Evaluate measurements 2859 2860 7.7. Power measurement: Voltage, Current, kW 2861

2862 7.7.1 System Preparation 2863 2864

a. Obtain updated construction drawings, specifications, approved shop drawings 2865

and submittals, addenda, bulletins, and change orders related to the air systems 2866

b. Obtain /refer field-data forms for equipment delivery, Pre-commissioning & 2867

start up checklist. (refer section-9 for AHU Checklist) 2868

Page 69: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

c. Conduct the Pre-commissioning & Start up checks as per the section-9 for 2869

checklist of Air handlers. 2870

2871

7.7.2 Test Procedure 2872 2873

a. Operate the associated Air handler fan to full capacity. 2874

b. Set the system in the minimum outdoor-air mode. 2875

c. Refer section-5 and section-6 test method of Air volumetric measurement “for 2876

methods of measurement. 2877

d. With the system at equilibrium, measure the voltage & current. 2878

e. Calculate the kW ratings as per the equation specified in the section 6: Power 2879

measurement. 2880

f. Record the above data in operational data collection sheet provided in the 2881

section-9. 2882

2883

7.8 Sound pressure Measurement wrt AHU operation. 2884

2885 Sound Testing. Ideally, a building should be completed and ready for occupancy 2886 before sound level tests are taken. All spaces in which readings will be taken should 2887

be furnished with whatever drapes, carpeting, and furniture are typical because 2888 these affect the room absorption, which can affect sound levels and the subjective 2889

quality of the sound. In actual practice, because most tests must be conducted before 2890 the space is completely finished and furnished for final occupancy, the testing 2891

engineer must make some allowances. Because furnishings increase the absorption 2892 coefficient and reduce by about 4 dB the sound pressure level that can be expected 2893

between most live and dead spaces, the following guidelines should suffice for 2894 measurements made in unfurnished spaces. If the sound pressure level is 5 dB or 2895 more over the specified or desired criterion, it can be assumed that the criterion will 2896

not be met, even with the increased absorption provided by furnishings. If the sound 2897 pressure level is 0 to 4 dB greater than the specified or desired criterion, recheck 2898 when the room is furnished to determine compliance 2899

2900 Follow this general procedure 2901

2902

Obtain a complete set of accurate, as-built drawings and specifications, including 2903

duct and piping details. Review specifications to determine sound and vibration 2904 criteria and any special instructions for testing. 2905 Visually check for noncompliance with plans and specifications, obvious errors, 2906

and poor workmanship. Turn system on for aural check. Listen for noise and 2907 vibration, especially duct leaks and loose fittings 2908

2909 Adjust and balance equipment, as described in other sections, so that final acoustical 2910 tests are made with the HVAC as it will be operating. It is desirable to perform 2911 acoustical tests for both summer and winter operation, but where this is not 2912

practical, make tests for the summer operating mode, as it usually has the potential 2913 for higher sound levels. Tests must be made for all mechanical equipment and 2914

systems, including standby. 2915

Page 70: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Check calibration of instruments 2916

2917 a) Measure sound levels in all areas as required, combining measurements as 2918

indicated in step 3 if equipment or systems must be operated separately. 2919 Before final measurements are made in any particular area, survey the area 2920

using an A-weighted scale reading (dBA) to determine the location of the 2921 highest sound pressure level. Indicate this location on a testing form, and 2922 use it for test measurements. Restrict the preliminary survey to determine 2923 location of test measurements to areas that can be occupied by standing or 2924 sitting personnel. 2925

b) Determine whether background noise measurements must be made. 2926 c) If specification requires determining sound level from HVAC equipment 2927

only, background noise readings must be taken with HVAC equipment 2928

turned off. 2929 d) If specification requires compliance with a specific noise level or criterion 2930

(e.g., sound levels in office areas not to exceed 35 dBA), ambient noise 2931 measurements must be made only if the noise level in any area exceeds the 2932

specified value. 2933 e) For residential locations and areas requiring very low noise, such as sound 2934

recording studios and locations used during the normally quieter evening 2935 hours, it is usually desirable to take sound measurements in the evening 2936

and/or take ambient noise measurements. 2937 2938 8.0 Data collection Frequency. 2939

2940

8.1 Air volumetric measurement – Matrix/Pitot tube traverse. 2941 2942

The output shall be measured in equilibrium condition. The recording of data shall 2943

continue for time period of atleast 30 Minutes during which tolerance specified in 2944 section 10 shall be met and atleast 6 set of readings on each cross sectional area on 2945

the measurement plane shall be taken at every 15 minutes interval and recoded. 2946 Data shall be sampled at equal intervals than span 60 sec or less. 2947

2948

8.2. Digital Vane Anemometer 2949 2950

The output shall be measured in equilibrium condition. The recording of data shall 2951 continue for time period of atleast 30 Minutes during which tolerance specified in 2952

section 10 shall be met and The total rectangular opening or core area is to be 2953 divided into squares or rectangles 3 in. (7.5 cm) to 5 in. (12.5 cm) on a side, and the 2954 average velocity for the instrument will be the arithmetical average of the readings 2955 in these squares. Totalizing instruments may be moved from one square to another; 2956 for these instruments, a reading time of at least 10 seconds in each square is 2957

recommended. 2958 2959 8.3 Water flow measurement 2960 2961

The output shall be measured in equilibrium condition. The recording of data shall 2962

continue for time period of atleast 30 Minutes during which tolerance specified in 2963 section 10 shall be met and atleast 3 set of readings shall be taken at every 10 2964

Page 71: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

minutes interval and recoded. Data shall be sampled at equal intervals than span 60 2965

sec or less. 2966 2967 9.0 Test Report Formats – Refer attachment for formats. 2968 2969

10.0 Measurement equipment- accuracy, Tolerances 2970 2971 2972

Table: Variation allowed during steady state conditions

Readings

Variations of Arithmetical

mean valves from the

specified test conditions

Maximum variation of individual

readings from the specified test

condition

Temperature of air

dry bulb +/- 0.3 Deg C +/- 0.5 Deg C

wet bulb +/- 0.2 Deg C +/- 0.3 Deg C

Temperature of water +/- 0.3 Deg C +/- 0.5 Deg C

Air flow +/- 5% +/- 10%

Water flow +/- 3% +/- 5%

Water pressure

less than 1/2 scale of the scale

division mark

1/2 scale of the scale division

mark

Air pressure +/- 5% +/- 10%

Sound pressure +/- 3 dB +/- 5 dB

Vibration levels-rms

Velocity, mm/s +/- 2.0 +/- 2.3

2973 2974

2975 2976

2977 2978 2979 2980 2981

2982 2983 2984 2985 2986

2987 2988

2989

Page 72: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

2990

2991

Annexure HA.1(Informative) 2992 Unitary and Packaged AC Systems 2993

2994

2995

1.0 A unitary system typically combines the cooling, air distribution and controls in one 2996

unit called IDU ( Indoor Unit ) and the compressor , air cooled condenser , 2997

condenser fan and controls in another unit called ODU ( Out door Unit ). 2998

2999

2.0 The packaged air conditioning system can either be air cooled or water cooled . The 3000

air cooled system will be similar to the Unitary system while the water cooled 3001

system will have compressor, water cooled condenser, evaporator and evaporator 3002

fan combined in one package. 3003

3004

3.0 The IDU and ODU of unitary and packaged air conditioning system are factory 3005

made and tested and accepted before it reaches site. 3006

3007

4.0 Site work usually involves the refrigeration pipe work, electrical and condensate 3008

water removal connections and commissioning. 3009

3010

5.0 Sample check lists are given in attachments for Delivery (HA-1D), for Installation 3011

(HA-1C) and Operation ( HA-1S.) . 3012

3013 3014

3015 3016

3017 3018 3019 3020

3021

3022

3023 3024 3025 3026 3027

3028 3029 3030 3031 3032

3033

3034

3035

Page 73: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA - 1 D Unitary Systems - Split AC Unit For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No- Evaporator

A4 Air Flow - Evaporator l/sec

A5 Evap fan motor power Kw

A6 Evap fanmotor V/Ph/Freqency

A7 Total cooling/ Heating capacity KW

A8 Airflow- Condenser l/sec

A9 Ambient Temp O C

A10 Cond fan motor power kw

A11 Cond fan motor V/Ph/Frequency

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 Copper pipes sealed at Y/N

both ends

B4 Unit tags present Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

2 HA - 1 C Unitary Systems - Split AC Unit For all "NO" responses, A Evaporator sectionSample Checklist - Installation please fill in details A1 Unit adequately supported Y/N

and Start up in Remarks column A2 Adequate service clearences Y/N

available for maintenance and unit removal

A3 Condensate drain properly installed with slope Y/N

A4 Unit label visible Y/N

B Condenser SectionB1 Unit adequately supported Y/N

B2 Adequate service clearences Y/N

available for maintenance and unit removal

B3 Unit label visible Y/N

C Refrigerant pipingC1 Piping correctly installed Y/N

as per drawing and specifications

C2 Disconnection for unit Y/N

removal is easy

C3 Pipe pressure tested and Y/N

found OK

C4 Pipe insulated as per Y/N

specifications

C5 Valves and test ports are Y/N

accessible

C7 Unit charged with refrigerant Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Motor rotation correct Y/N

D3 Terminations checked Y/N

D4 Earthing is proper Y/N

E ControlsE1 Thermostat installed Y/N

E2 Thermostat calibrated Y/N

E3 Control wiring correct Y/N

E4 Control sequence verified Y/N

E5 No abnormal noice or Y/N

vibration

E6 Manufacturers checklist Y/N

completed

E7 Filters installed and are Y/N

clean

APPENDICES TO COMMISSIONING STANDARD - HA1

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Unitary and Packaged AC Units

Final Annexure. SPLIT-HA11 of 2

Page 74: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

Actual Design

3 HA - 1 O Unitary Systems - Split AC Unit For all "NO" responses, A1 Room Temperature DB/WB OC

Sample Checklist - Operation please fill in details A2 Grill temperature OC

in Remarks column A3 Voltage V

A4 Starting current Amps

A5 Full load current Amps

A6 High pressure cutout setting psi

A7 Low pressure cutout setting psi

A8 Suction pressure psi

A9 Discharge pressure psi

A10 Evaporator entering DB/WB OC

A11 Evaporator leaving DB/WB OC

A12 Cond entering DB/WB OC

A13 Cond leaving DB/WB OC

A14 Air flow Evaporator l/sec

A15 Air flow Cond l/sec

A16 Noise at 1 m from Evap d B a

A17 Noise at 1 m from Cond d B a

Final Annexure. SPLIT-HA12 of 2

Page 75: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.2 (Informative)

VRF Systems

1. The VRF (Variable Refrigerant Flow) System will have multiple indoor units connected

with a single outdoor or multiple out door units .These are factory made and tested and

accepted before it reaches site.

2. Site work involves the refrigeration pipe work from Indoor units to our door units ,

pressure testing , vacuuming the entire refrigerant piping system , charging the

refrigerant to the system , mechanical , electrical and condensate water removal

connections and control system and BMS connectivity and finally testing and

commissioning the system.

3. Sample check lists are given in attachments for Delivery ( HA -2D ) , Installation

( HA-2C ) , Start Up ( HA – 2S ) and operation ( HA-2O)

Page 76: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA -02 VRF For all "NO" responses, A Model verification

Sample Checklist -

Delivery

please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 No of Units

A4 Unit Serial No

A5 Compressor type

A6 Cooling Capacity TR

A7 Condensor type Water/Air

A8 Condenser flow rate

( water cooled )

LPM

A9 Condenser fan air quantity ( Air cooled ) CMH

A10 Refrigerant type

A11 Compressor motor power KW

A12 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Copper piping and fittings are free from

damage

Y/N

B4 Incomer MCB of correct size and capacity Y/N

B5 Motor bearings sealed/lubricated Y/N

B6 Refrigerant piping insulation intact Y/N

B7 Condensate drain properly installed with

slope

Y/N

B8 Foundation for ODU installed properly Y/N

B9 Testing & Commssioning instruments availabe Y/N

B10 Vibration isolators OK Y/N

B11 Unit label visible Y/N

B12 Installation manual provided Y/N

B13 Test/warranty certificate provided Y/N

B14 Unit tags affixed Y/N

2 HA-02 VRF For all "NO" responses, A VRF

Installation Checklists please fill in details Indoor Units

in Remarks column A1 Low side ( Cassette /High Wall / AHU)

A2 Unit adequately supported Y/N

A3 Refrigerant piping laid as per design / layout Y/N

A4 Central Remote controller Connected to IDUs Y/N

A5 Adequate service clearences available for

maintenance and unit removal

Y/N

A6 Condensate drain properly installed with

slope

Y/N

A7 Refrigerant piping connection to IDU properly Y/N

A8 Unit label visible Y/N

B Ducting ( In case of AHU )

B1 Grill /Diffuser properly connected Y/N

B2 Sufficient duct length available upstream Y/N

B3 Ductwork is adequately supported Y/N

B4 Flexible connector installed at duct input Y/N

B5 Ducting internally Clean Y/N

B6 Testing locations available Y/N

C ControlsC1 Dampers/sensors accessible Y/N

C2 Airflow sensor calibration Y/N

C3 BMS Connectivity correcly established

C4 Control wiring correct Y/N

C5 Control sequence verified Y/N

APPENDICES TO COMMISSIONING STANDARD - HA -02

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - VRF

Final Annexure. VRF HA-21 of 3

Page 77: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

D Refrigerant PipingD1 Piping correctly installed as pee drawing and

adequately supported

Y/N

D2 Piping arranged for easy unit removal Y/N

D3 Flare tool , cutter , nuts available for

maintenance

Y/N

D4 Piping is clean and no external visible damage Y/N

D5 All valves as per design drawings Y/N

D6 Pipe insulation correct as applicable Y/N

D7 Valve tags installed Y/N

E ElectricalE1 Safety disconnect in accessible location Y/N

E2 Central Remote Controller with PC

Connected

Y/N

E3 Cable lugs correct size Y/N

E4 Electrical connections are tight Y/N

E5 Earthing adequate Y/N

E6 Main Incomer installed correct Y/N

E7 Control voltage provided correct Y/N

E8 Withstand ratings exeed fault levels Y/N

F InstrumentationF1 Control panel accessible Y/N

F2 Sensors correctly installed Y/N

F3 Safety controls installed correct Y/N

F4 Electrical protections correctly installed Y/N

3 HA-02 VRF For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details A1 Manufacturers checklist Completed Y/N

in Remarks column A2 Safety controls verified Y/N

A3 Leak test Procedure followed properly Y/N

A4 Refrigerant ( system) pressure as per design Y/N

A5 Low oil flow protection Y/N

A6 Set of required tools available Y/N

A7 Low design cond water flow( for water cooled

)

Y/N

A8 Loss of refrigerant / Less refrigerant Charge Y/N

A9 Motor overload Y/N

A10 Phase imbalance/ reversal Y/N

A11 Over/ under voltage Y/N

A12 Water temp sensor operating correct( water

cooled )

Y/N

A13 No unusual noise or vibration Y/N

B Controls StartupB1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 Central Remote Controller with PC verified Y/N

B4 BMS control system tested Y/N

B5 Unit voltage/amps verified Y/N

B6 Remote start/stop signal verified Y/N

B7 Sequence of compresor operation verified Y/N

B8 Demand limiting signal verified Y/N

B9 Unit " run " sequence verified Y/N

B10 Unit "alarm " sequence verified Y/N

C Start up/ TAB

C1 Precommissioning checks complete Y/N

C2 Refrigerant charge as per design Y/N

C3 No unusual noise or vibration Y/N

C4 Calibrated insruments used Y/N

C5 Motor full load current in limits Y/N

C6 Motor voltage/amps verified Y/N

C7 Check and confirm proper function Y/N

of control algorithms in BMS

C8 Check Operation sequence Y/N

Final Annexure. VRF HA-22 of 3

Page 78: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

4 HA -02 VRF VRF

Start Up - Operation Please fill in details A1 Room Temperature Deg C

in Remarks column A2 Grille temperature Deg C

A3 Voltage Volt

A4 Starting current - ODU Amps

A5 Full load current - ODU Amps

A6 High pressure cutout setting psi

A7 Low pressure cutout setting psi

A8 Suction pressure psi

A9 Discharge pressure psi

A10 Room Temperature DB/ WB Deg C

A11 Cond entering DB/WB Deg C

A12 Cond leaving DB/WB Deg C

A13 Air flow - Evaporator l/sec

A14 Air flow - Condenser l/sec

A15 Noise at 1 m from Evap d B a

A16 Noise at 1 m from Cond d B a

A17 Ambient Temperature DB/WB Deg C

Final Annexure. VRF HA-23 of 3

Page 79: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.3 (Informative)

Chillers – Vapour Compression

1. The chillers comprise of compressor ( Reciprocating , Scroll, Screw or Centrifugal ) ,

condenser( air cooled or water cooled ) , chiller ( DX or Flooded ) and expansion devise

all connected in series through refrigerant piping. The compressors may be

hermetically sealed, semi hermetic, directly coupled or belt driven depending on the

capacity and the type of manufacture, mounted on a steel frame work. These chillers

will work on given type of refrigerant as specified by the manufacturer. Chillers are

factory made and tested at the factory and accepted before it reaches site

2. The chillers are classified as a) water cooled and b) air cooled chillers. The chillers

are installed either in a plant room or on building roof single or in multiple numbers

based on the capacity and usage pattern.

a) Water cooled Chillers: The water cooled chillers will have cooling tower and

condenser water pumps connected to the chillers through water piping for its proper

functioning. The water cooled chillers will have single / multiple chillers connected to

single or multiple condenser pumps single or multiple cooling towers and single or

multiple chilled water pumps.

b) Air Cooled Chillers: The air cooled chillers will have air cooled condensers and

connected directly to the evaporator and then compressor through refrigerant piping.

The air cooled chillers will have single or multiple chillers, single or multiple air cooled

condensers connected in parallel ,single or multiple chilled water pump.

3. Site Work : Site work involves the proper foundation for the chillers , pump sets,

condenser water piping (in case of water cooled system) , refrigerant piping in case of

air cooled system , mechanical , power and control wiring , electrical panel and control

system including BMS connectivity .

4. Sample check lists are given in attachments for delivery( HA- 3D) , for installation

(HA-3C , and for Start up ( HA-3S) .

Page 80: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA -03 Chiller For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Compressor type

A5 Cooling Capacity TR

A6 Condensor type Water/Air

A7 Condenser flow rate lpm

A8 Chiller flow rate lpm

A9 Refrigerant type

A10 Compressor motor powe k W

A11 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Water openings plugged Y/N

B4 Motor bearings sealed/lubricated Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

B7 Unit tags affixed Y/N

2 HA-03 Chiller For all "NO" responses, A ChillerInstallation Checklists please fill in details A1 Unit adequately supported and secured Y/N

in Remarks column A2 Adequate service clearences Y/N

available

A3 All components accessible Y/N

for maintenance

A6 Vibration isolators OK Y/N

A7 Unit label visible Y/N

B PipingB1 Piping correctly installed Y/N

B2 Piping arranged for easy unit removal Y/N

B3 Piping adequately supported Y/N

B4 All components accessible Y/N

for maintenance

B5 Piping is clean Y/N

B6 All valves as per design drawings Y/N

B7 Pipe insulation correct as applicable Y/N

B8 Valve tags installed Y/N

D ElectricalD1 Safety disconnect in accessible location Y/N

D2 Cable lugs correct size Y/N

D3 Electrical connections are tight Y/N

D4 Eearthing adequate Y/N

D5 VFD / Starter installed correct Y/N

D6 Control voltage provided correct

D7 Withstand ratings exeed fault levels

E InstrumentationE1 Control panel accessible Y/N

E2 Sensors correctly installed Y/N

E3 Calibrations verified Y/N

E4 Safety controls installed correct Y/N

E5 Electrical protections correctly installed Y/N

2 HA-03 Chiller For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Safety controls verified Y/N

A3 Low chilled water temp

A4 High refrigerant pressure Y/N

A5 Low oil flow protection Y/N

A6 Low chilled water flow Y/N

A7 Low cond water flow

A8 Loss of refrigerant

APPENDICES TO COMMISSIONING STANDARD - HA3

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Chiller - Vapour Compression

Final Annexure. CHILLER-HA31 of 2

Page 81: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

A9 Motor overload

A10 Phase imbalance/ reversal

A11 Over/ under voltage

A12 Water temp sensor operating correct

A13 No unusual noise or vibration

B Controls startupB1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

B4 Unit voltage/amps verified

B5 Remote start/stop signal verified

B6 Chilled water reset signal verified

B7 Demand limiting signal verified

B8 Unit " run " sequence verified

B9 Unit "alarm " sequence verified

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Flow rate measured Y/N

C3 No unusual noise or vibration Y/N

C4 Calibrated insruments used Y/N

C5 Motor full load current in limits Y/N

C6 Motor voltage/amps verified Y/N

C7 Strainers removed and cleaned Y/N

C8 Check and confirm proper function

of control algorithms in BMS Y/N

C9 Check Operation sequence Y/N

C10 Chilled water temp in/out ---/---

C11 Evap pressure drop OK Y/N

C12 Chilled water flow rate OK Y/N

C13 Cond water temp in/out ----/----

C14 Cond water pressure drop OK Y/N

C15 Ambient DB Temp -----

C16 Chiller noise level at 1 m OK Y/N

Final Annexure. CHILLER-HA32 of 2

Page 82: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.4 (Informative)

Cooling Towers

1. The cooling tower is a device which rejects heat from the system to the atmosphere.

It can be Natural draft atmospheric type , induced draft counter -flow, or induced draft

cross- flow and are installed out side the building or on the terrace of building . The

cooling towers will be in single or multiple units depending on the plant capacity

and plant design parameters . Induced draft cooling tower fans are driven by single or

multiple motors with or with out VFD .

2. The cooling towers are factory made as per manufacturers design parameters and

shifted to site in assembled or dismantled condition. These cooling towers are

mounted on foundation outside the building or on the terrace .

3. Site work involves usually assembly of components if sent to site in dismantled

condition , condenser water connection with valves , strainers , make up water piping,

electrical cabling and mechanical work.

4. Sample check lists are given in attachments for delivery ( HA-4D), for installation

(HA-4C) and start up ( HA-4S)

Page 83: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S

NoAppendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA -04 Cooling Tower For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Capacity

A5 Fan speed/power rpm/KW

A6 Motor power/speed KW/rpm

A7 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Water openings plugged Y/N

B4 Access doors are operable Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

B7 Unit tags affixed Y/N

2 HA-04 Cooling Tower For all "NO" responses, A Cooling TowerInstallation Checklists please fill in details A1 Unit adequately supported and secured Y/N

in Remarks column A2 Adequate service clearences Y/N

available

A3 Ladder provided is adequate

A4 Vibration isolators OK Y/N

A5 Unit label visible Y/N

B PipingB1 Piping correctly installed and adequately supported Y/N

B2 All components accessible for maintenance Y/N

B3 Piping is clean Y/N

B4 All valves as per design drawings Y/N

B5 Make up water supply provided Y/N

B6 Pipe insulation correct as applicable Y/N

B7 Valve tags installed Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Direction of motor rotation correct Y/N

D3 Electrical connections are tight Y/N

D4 Eearthing adequate Y/N

D5 VFD / Starter installed correct Y/N

E InstrumentationE1 Control panel accessible Y/N

E2 Sensors correctly installed Y/N

E4 Valve actuators installed Y/N

E5 Calibrations verified Y/N

E6 Safety controls installed correct Y/N

E5 Electrical protections correctly installed Y/N

2 HA-04 Cooling Tower For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details in

Remarks column

A1 Manufacturers checklist completed Y/N

A2 Tower basin filled Y/N

A3 Sump nozzles and strainers are clean

A4 Motor/gear box lubricated Y/N

A5 Fan pitch adjusted Y/N

A6 No unusual noise or vibration Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

B4 High/Law water alarms operational

B5 VFD Operational ( if applicable )

B6 Float switch, make up water operational

C Start up/ TAB

APPENDICES TO COMMISSIONING STANDARD - HA4

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Cooling Towers

Final Annexure. CT-HA41 of 2

Page 84: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S

NoAppendix No Appendix Title Notes Item No Description Unit Response Remarks

C1 Precommissioning checks complete Y/N

C2 Flow rate measured Y/N

C3 Motor rotating in correct direction. Y/N

C4 No unusual noise or vibration Y/N

C5 Calibrated insruments used Y/N

C6 Motor full load current in limits Y/N

C7 Motor voltage/amps verified Y/N

C8 Strainer removed and cleaned Y/N

C9 Check and confirm proper function

of control algorithms in BMS Y/N

C10 Check Operation sequence Y/N

C11 Water distributed evenly even at Y/N

50% flow

C12 Make up water quality OK Y/N

C13 Blow down control verified Y/N

C14 Make up flow meter signal Y/N

C15 Water temp at inlet/outlet ----/-----

C16 Ambient wet bulb temp ------

C16 Determine range / approach -----/-----

Final Annexure. CT-HA42 of 2

Page 85: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.5 (Informative)

Pumps

1. In HVAC System, or pumps are used for circulation of condenser water between

condenser and cooling tower , chilled water and or brine circulation between chiller

and coils in AHUs and FCUs, room cooling units etc.. The pumps used in air

conditioning system are either mono block or split casing type .These pumps installed

will be single or multiple pumps as per the design requirements and can be connected

in parallel or in series with the chiller / condenser . The pumps are installed in primary

, secondary or tertiary circuit depending on the system design .The pump motors are

operated directly or through VFDs .

2. The pumps are factory made and tested and accepted before it reaches site .

3. Site work involves installation on the foundation, levelling , pipe connection , electrical

and control system. The chilled water pumps will be insulated as per the design

mentioned in the specification / data sheet .

4. Sample check lists are given in attachments for Delivery ( HA -5D ) , Installation (

HA-5C ) , Start Up ( HA – 5S ) .

Page 86: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HA -05 Pumps For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Pump type cfm/mm WG

A5 Impeller size mm

A6 Inlet/outlet Dia mm

A7 Capacity Flow/Head lpm/m WG

A8 Motor power/speed KW/rpm

A9 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Water openings plugged Y/N

B4 Installation manual provided Y/N

B5 Test/warranty certificate provided Y/N

B6 Unit tags affixed Y/N

2 HA-05 Pumps For all "NO" responses, A PumpInstallation Checklists please fill in details A1 Unit adequately supported and secured Y/N

in Remarks column A2 Adequate service clearences available for

manitenance and removal

Y/N

A3 Vibration isolators OK Y/N

A4 Unit label visible Y/N

B PipingB1 Piping correctly installed and adequately

supported

Y/N

B2 All components accessible for maintenance Y/N

B3 Piping is clean Y/N

B4 Shut off valves at inlet and outlet, Strainer at

Inlet

Y/N

B5 Pressure gauges at inlet and outlet Y/N

B6 Pipe insulation correct as applicable Y/N

B7 Valve tags installed Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Direction of motor rotation correct Y/N

D3 Electrical connections are tight Y/N

D4 Eearthing adequate Y/N

E InstrumentationE1 Control panel accessible Y/N

E2 Sensors correctly installed Y/N

E4 Valve actuators installed Y/N

E5 Electrical protections correctly installed Y/N

2 HA-05 Pumps For all "NO" responses, A Mechanical Startup

Start up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Unit and motor lubricated Y/N

A3 Pump shaft rotates freely

A4 Sensors correctly installed Y/N

A5 Valve on supply header is open Y/N

A6 No unusual noise or vibration Y/N

B Controls startup

B1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Flow rate measured Y/N

C3 Inlet/Outlet pressure noted Y/N

APPENDICES TO COMMISSIONING STANDARD - HA5

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Pumps

Final Annexure. PUMP-HA51 of 2

Page 87: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

C4 Motor rotating in correct direction. Y/N

C5 No unusual noise or vibration Y/N

C6 Calibrated insruments used Y/N

C7 Motor full load current in limits Y/N

C8 Motor voltage/amps verified Y/N

C9 Strainer removed and cleaned Y/N

C10 Check and confirm proper function

of control algorithms in BMS Y/N

C11 Check Operation sequence Y/N

Final Annexure. PUMP-HA52 of 2

Page 88: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.6 (Informative)

Air Handling Units

1. Air handling units are of two types .a) DX system where refrigerant is supplied to the

cooling coil through expansion devise b) Chilled water system ( Indirect cooling

system ) where chilled water is supplied to the Cooling coils through water piping .

In both the cases cold air is delivered to the air conditioned space through ducting.

2. Air handling units may be floor mounted or ceiling mounted .

3. The air conditioning system will have single or multiple AHUs . These are factory

assembled or assembled at site as per manufacturer’s recommendations.

4. Site work involves mounting the AHUs on prefixed foundation , assembling the

cooling / heating coils , damper connection , Canvas and duct connection , pipe

connection , fixing the motor and drive assembly , filter section , control valves ,

mechanical , electrical and control system and BMS connectivity where applicable.

5. Sample check lists are given in attachments for Delivery ( HA -6D ) , Installation (

HA-6C ) , Start Up ( HA – 6S )

Page 89: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HA -06 Air Handling Unit For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A 3 Unit Serial No

A 4 Cooling / Heating Capacity

A 5 Supply air Flow cfm

A 6 Supply fan motor power/speed KW/rpm

A 7 Return Fan motor power/speed KW/rpm

A 8 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Coil surface free of damage Y/N

B4 Air openings sealed Y/N

B5 Water openings plugged Y/N

B6 Access doors operable Y/N

B7 Installation manual provided Y/N

B8 Test/warranty certificate provided Y/N

B9 Unit tags affixed Y/N

2 HA - 1 C Air Handling Unit For all "NO" responses, A Air Handling Unit

Installation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearences Y/N

available for maintenance

A3 Condensate drain properly installed Y/N

A4 Vibration isolators OK Y/N

A5 Unit label visible Y/N

B Water pipingB1 Piping correctly installed and adequately supported Y/N

B2 Unit/coil removal possible Y/N

B3 Piping is clean Y/N

B4 Pipe insulation correctly installed Y/N

B5 Valve tags installed Y/N

C Ducting

C1 Dampers/sensors accessibleC2 Mixing of outdoor/return air possible Y/N

C3 Ductwork is adequately supported Y/N

C4 Dampers open/close properly Y/N

C5 Ducting internally clean Y/N

C6 Testing locations available Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Direction of motor rotation correct Y/N

D3 Electrical connections are tight Y/N

D4 Eearthing adequate Y/N

D5 Stater/VFD installed Y/N

E InstrumentationE1 Control panel accessible Y/N

E2 Sensors correctly installed Y/N

E3 Damper actuators installed Y/N

E4 Control valve actuators installed Y/N

E5 Electrical protections correctly installed Y/N

F ControlsF1 Thermostat installed Y/N

F2 Thermostat calibrated Y/N

F3 Control wiring correct Y/N

F4 Control sequence verified Y/N

2 HA - 1 C Air Handling Unit For all "NO" responses, A Mechanical Startup

Start up Checklists please fill in details in

Remarks column

A1 Manufacturers checklist complted Y/N

A2 Filters installed and are clean Y/N

Equipment/ System - Air Handling Units

Delivery, Installation, Start up and Operation Check Lists.

APPENDICES TO COMMISSIONING STANDARD - HA6

Final Annexure. AHU-HA61 of 2

Page 90: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

A3 Fans/motors lubricated/aligned Y/N

A4 Fan belts correct and in good condition Y/N

A5 Unit pressure tested and correct Y/N

A6 Belt guards in place Y/N

A7 Canvas connection proper Y/N

A8 Sensors correctly installed Y/N

A8 Unit dampers fully open Y/N

A9 No unusual noise or vibration Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Lighting within unit installed Y/N

B3 Power available for commissioning Y/N

B4 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Duct work balancing done Y/N

C3 Air flow/pressure measured Y/N

C4 Fan operating point marked in fan curve Y/N

C5 Water side measurements done Y/N

C6 Supply air quantity correctas per design Y/N

C7 No unusual noise or vibration Y/N

C8 Calibrated insruments used Y/N

C9 VCD Positions marked Y/N

C10 Fan motor full load current in limits Y/N

C11 Flow rates in ducts within allowable tolerances Y/N

C12 Compare fan air flow in front of filter Y/N

section with air flow in main ducts

C13 Measure fan speed and compare with design Y/N

C14 Check and confirm proper function Y/N

of control algorithms in BMS

C15 Check AHU Operation sequence Y/N

C16 Entering and leaving air temp at coil Y/N

C17 Entering and leaving air temp at heating coil Y/N

C18 Entering and leaving chilled water temp Y/N

C19 Entering and leaving hot water temp Y/N

C20 Coil flow and air/water pressure drops at each coil Y/N

Final Annexure. AHU-HA62 of 2

Page 91: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.7 (Informative)

Ducting Systems

1. Ducting is used to distribute air to single or multiple zones and collect it back to the

fan room as per layout drawing .The ducting for air conditioning / ventilation system

categorized as Supply air , Return air , Fresh air , Exhaust air ducts and are made of

metallic sheets ( GS / SS / Al) . The ducts running exposed are made air tight and

insulated where ever required as per design parameters. In addition ducting is also

made of non metallic ( fiber glass duct pre-insulated ) , or of fabric .

2. The ducts are provided with canvass connection at the fan outlet , dampers to adjust the

volume of air flow to various parts /zones of the system.

3. The ducts are factory made and delivered to site and / or made at site. The ducts

running inside the building are suspended from the ceiling or run along the wall

mounted on fixed brackets .

4. The ducts are made of rectangular circular or oval cross section based on the design

requirements . For selecting the thickness of the sheet and type of transverse joint for

duct construction rigidity , leakage and sealing , BIS Standard IS 655 and or SMACNA

standard will be followed.

6. Sample check lists are given in the attachments for Delivery ( HA -7D ) , Operation

( HA-7C ) , Start Up ( HA – 7S )

Page 92: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HB -06 Ducting For all "NO" responses, A System Checks

System Check please fill in details A 1 Pre commissioning checks completed Y/N

in Remarks column A2 Ductwork correctly installed as per drg Y/N

A3 Duct work properly tagged Y/N

A 4 Joints are leak tight Y/N

A 5 Ductwork clean and free of damage Y/N

A 6 Duct construction standard is followed Y/N

A 7 Access doors installed as per drawing Y/N

A 8 Insulation done correctly ( if applicable ) Y/N

A 9 Gaskets are installed correct Y/N

A 10 Ductwork structurally sound/no sagging Y/N

A 11 All transverse and longitudinal joints area sealed Y/N

A 12 Ductwork meets leakage class specified Y/N

A 13 All ductwork leak tested as specified Y/N

A 14 Elbows have adequate inside radius Y/N

A 15 Elbows larger than 450 mm have turning vanes Y/N

A 16 All civil penetrations are sealed and made fire proof Y/N

A 17 Volume control dampers installed as per drawing Y/N

A 18 All maintenance points are accessible Y/N

A 19 Updated as- built drawings are made available Y/N

2 HB-06 Ducting For all "NO" responses, B Start upStart up

Checklists

please fill in details in

Remarks column

B1 All precommissioning checks are completed Y/N

B2 Leakage test reports are available Y/N

B3 Duct internals are clean Y/N

B4 All VCD/VAV dampers are open Y/N

B5 AHU/ TFA airflow exeeds/ meets the design flow before balancing Y/N

B6 Adjust zone air diffusion Y/N

B7 Measure air flow at each outlet and match with design flow Y/N

B8 Carryout balancing of flows in each Y/N

branch and finally adjust fan speed.

B9 Verify for excess noise in any segment Y/N

3 HB-06 Ducting For all "NO" responses, C Operation.Operation

Review

please fill in details in

Remarks column

C1 All pre commissioning and start up procedures are completed Y/N

C3 Airflow balancing records are verified Y/N

C4 Check airflow at each VAV box at maximum and minimum positions Y/N

C5 Correct and calibrated instruments are used for all

measurements

Y/N

C6 All ductwork components operate as Y/N

per specifications and correct airflow

rates are achieved in each space

C7 There is no draught or excess air noise Y/N

in occupied zone.

APPENDICES TO COMMISSIONING STANDARD-HA7

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Air Distribution - Ducting Systems

Final Annexure. Ducting-HA71 of 1

Page 93: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.8 (Informative)

Variable Air Volume Systems

1. Variable Air Volume (VAV) units are installed in the supply air path. The air

conditioning system will have single or multiple VAV units connected with a single

duct or multiple ducting branches.

2. These are factory made and tested and accepted before it reaches site. Site work

involves mounting the VAVs in duct line, canvass connection, sensors, mechanical,

electrical , control system and BMS connectivity where applicable .

3. Sample check lists are given in attachments for Delivery (HA -8D ) , for Installation

(HA-8C) and for Start Up (HA -8S)

Page 94: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HA -08 Variable Air Volume Unit For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A 3 Unit Serial No

A 4 Cooling/ Heating Capacity

A 5 Supply air Flow. Max cfm

A 6 Supply Air Flow Min cfm

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Air flow sensing tube connected Y/N

B5 Enclosure for control panel OK Y/N

B6 Installation manual provided Y/N

B7 Test/warranty certificate provided Y/N

B8 Unit tags affixed Y/N

2 Variable Air Volume Unit For all "NO" responses, A Variable Air Volume unitInstallation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearences Y/N

available for maintenance and unit removal

A3 Unit label visible Y/N

B Ducting

B1 Dampers/sensors accessibleB2 Sufficient duct length available upstream Y/N

B3 Ductwork is adequately supported Y/N

B4 Flexible connector installed at duct inlet Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ControlsC1 Temp sensor calibration Y/N

C2 Airflow sensor calibration Y/N

C3 Control wiring correct Y/N

C4 Control sequence verified Y/N

3 Variable Air Volume Unit For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Canvas connection proper Y/N

A3 Sensors correctly installed Y/N

A4 Unit dampers fully open Y/N

A5 No unusual noise or vibration Y/N

B Controls startupB1 Control sequence verified Y/N

B2 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Duct work balancing done Y/N

C3 Air flow/pressure measured Y/N

C4 Supply air quantity correctas per design Y/N

C5 No unusual noise or vibration Y/N

C6 Calibrated insruments used Y/N

C7 VCD Positions marked Y/N

C8 Flow rates in ducts within allowable tolerances Y/N

C9 Check and confirm proper function Y/N

of control algorithms in BMS

C10 Minimum air flow design vs measured Y/N

C11 Max air flow design vs measured Y/N

C12 Space temperature desin vs measured Y/N

APPENDICES TO COMMISSIONING STANDARD - HA8

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Variable Air Volume Systems

Final Annexure. VAV-HA81 of 1

Page 95: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.9 (Informative)

Fans

1. The fans used in HVAC system are for supply air, return air , exhaust air and any

other types of ventilation requirements .

2. The ventilation system will have single or multiple supply , return or exhaust air fans

connected with or with out ducting .These are factory made and tested and accepted

before it reaches site.

3. Site work involves installation of fans , motor on the floor on foundation or wall with

properly designed mounting bracket , ducting with canvas connection, mechanical ,

electrical , structural and control system.

4. Sample check lists are given in attachments for Delivery ( HA -9D ) , Installation (

HA-9C ) , Start Up ( HA – 9S ) .

Page 96: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HA -09 Fans For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Fan Type

A5 Capacity cfm

A6 Static Pressure mm of WG

A7 Motor power/speed KW/rpm

A8 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Installation manual provided Y/N

B5 Test/warranty certificate provided Y/N

B6 Unit tags affixed Y/N

2 HA -09 Fans For all "NO" responses, A Exhaust Fan

Installation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearences Y/N

available for maintenace and unit removal

A3 Vibration isolators OK Y/N

A4 Fan belts are in order and tight

A5 Back draft damper installed and correct

A6 Drive guard in place

A7 Unit label visible Y/N

B Ducting

B1 Dampers/sensors accessibleB3 Ductwork is adequately supported Y/N

B4 Dampers open/close properly Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Direction of motor rotation correct Y/N

C3 Electrical connections are tight Y/N

C4 Eearthing adequate Y/N

C5 Stater/VFD installed Y/N

D InstrumentationD1 Control panel accessible Y/N

D2 Sensors correctly installed Y/N

D3 Damper actuators installed Y/N

D4 Electrical protections correctly installed Y/N

2 HA -09 Fans For all "NO" responses, A Mechanical Startup

Start up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Fans/motors lubricated/aligned Y/N

A3 Fan belts correct and in good condition Y/N

A4 Belt guards in place Y/N

A5 Canvas connection proper Y/N

A6 Sensors correctly installed Y/N

A7 Dampers fully open Y/N

A8 No unusual noise or vibration Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Duct work balancing done Y/N

APPENDICES TO COMMISSIONING STANDARD - HA9

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Fans

Final Annexure. EX FAN-HA91 of 2

Page 97: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

C3 Air flow/pressure measured Y/N

C4 Fan operating point marked in fan curve Y/N

C5 Supply air quantity correct as per design Y/N

C6 No unusual noise or vibration Y/N

C7 Calibrated insruments used Y/N

C8 VCD Positions marked Y/N

C9 Fan motor full load current in limits Y/N

C10 Flow rates in ducts within allowable tolerance Y/N

C11 Measure fan speed and compare with design Y/N

C12 Check and confirm proper function Y/N

of control algorithms in BMS

Final Annexure. EX FAN-HA92 of 2

Page 98: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.10 (Informative)

Boilers / Hot Water Generators

1.0 A packaged boiler is a steam or hot water generator, manufactured and supplied or

a unit ready for installation.

1.1 Heat input is the heat value of the fuel used by the unit during test based on the

gross or net calorific value (as agreed) plus the sensible heat in the fuel above

ambient temperature and any heat supplied to the unit from a separate source.

1.2 Heat output is the heat absorbed by the working fluid, steam or water.

1.3 Thermal efficiency is the heat output divided by the heat input expressed as a

percentage.

1.4 Instrument requirements will typically include, but not limited to the following:

- Thermocouple

- Infrared thermometer

- Differential pressure measurement devices

- Flow meter

- Data logger

1.5 Sample checklists for Delivery.HA-10-D and for Construction. HA-10-C are

attached. Sample checklists for data collection is attached as HA-10-S.

Page 99: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

4 HA- 10 -D Boiler - Delivery For all "NO" responses, A Model verificationplease fill in details A1 Manufacturer

in Remarks column A2 Model Number

A3 Serial Number

A4 System type

A5 Output capacity K Cal/Hr

A6 Input required K Cal/Hr

A7 Stage/ Modulating

A8 Fuel type

A9 Entering Fuel Pressure Pa

A 10 Entering Fuel Temp OC

A11 Combustion Efficiency %

A12 Working pressure Pa

A 13 Power connection V/Ph/Fre/Full Load Current

A14 Entering water temp OC

A 15 Leaving temp Water/Steam OC

B Physical ChecksB1 Unit free from External damage Y/N

B2 Water openings are sealed Y/N

B3 All components are present Y/N

B4 Installation/start up manual provided Y/N

B5 Unit tags fixed Y/N

B6 Access door space is adequate Y/N

B7 Restraints are in place Y/N

5 HA -10 - C Boiler -

Installation/Start up

For all "NO" responses, A BOILER

please fill in details A1 Unit secured as per specifications Y/N

in Remarks column A2 Adequate clearance for maintenance Y/N

A4 All accessories installed Y/N

A5 No visible water leaks Y/N

A6 Instruments installed as per design Y/N

A7 Siesmic restraints in place Y/N

A8 Flue/ Chimney correctly installed Y/N

A9 Combustion air supply Y/N

B PIPINGB1 Water/ Steam piping correctly installed Y/N

B2 Fuel supply piping correctly installed Y/N

B3 Blow down system correctly installed Y/N

B4 Make up water connection Y/N

B5 Safety relief valves installed Y/N

B6 Pipes insulated as required to specs Y/N

B7 Check valves correctly installed Y/N

B8 Flow switches correctly installed Y/N

B9 System flushed to specs Y/N

B10 Stainers cleaned Y/N

B11 Isolation valves correctly installed Y/N

B12 Balancing valves correctly installed Y/N

B13 Expansion tank with air seperator installed as per

design

Y/N

B14 Air vents and bleeds installed and functional Y/N

B15 Steam traps installed and functional Y/N

B16 Hot water and condensate pumps Y/N

installed correctly and operational

B 17 Instruments installed on supply/return Y/N

B18 All valves/ test ports accessible Y/N

B19 Valve tags attached Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Terminations checked Y/N

C3 Earthing is proper Y/N

APPENDICES TO COMMISSIONING STANDARD - HA10

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Boilers & Hot Water Generators

Final Annexure. BOILER-HA101 of 2

Page 100: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

D ControlsD1 Control panel accessible Y/N

D2 Control panel labelled Y/N

D3 Remote start/stop verified Y/N

D4 Test ports available close to all sensors Y/N

D5 Actuators installed Y/N

D6 Actuator calibration checked Y/N

D7 All control devices,pneumatic tubing Y/N

and control wiring completed/checked

E Start upE1 System flushed Y/N

E2 System filled and air purged Y/N

E3 Cheked for unusal noise/ vibration OK/Not OK

E4 Manufacturer's start up check list completed Y/N

E5 Boiler safeties energized/tested Y/N

E6 CO and CO2 values from burner adjustment Y/N

E7 Start up reports include optimal and Y/N

actual percentages of Oxygen, Carbon

Dioxide and Carbon Monoxide

E8 Primary heating water set point Y/N

6 HA -10 -O Boiler. For all "NO" responses, A1 Space temperature set point OC

Sample Checklist -

Operation

please fill in details A2 Outdoor air temperature OC

in Remarks column A3 Fire damper opening %

A4 Firing rate set point Low limit

A5 Firing rate set point High limit

A6 Rate of fuel firing Kg/sec

A7 Operating Control set point OC

A8 Inlet water temperature OC

A9 Hot water supply temperature OC

A10 Hot water return temperature OC

A11 Hot water/steam temperature reset OC

A12 Hot water/steam pressure reset Pa

A13 Pressure at water inlet Pa

A14 Presssure at water/steam outlet Pa

A15 Inlet water flow rate Kg/sec

A16 Outlet water/steam flow rate Kg/sec

A17 Blow down rate Kg/sec

A18 Fuel consumption Kcal/Hr

A19 Power consumption KWh

A20 Drain water temperature OC

A21 Flue gas temperature OC

A22 Carbon Dioxide ( % by volume ) %

A23 Carbon Monoxide ( % by volume ) %

A24 Nitrogen (% by volume ) %

A25 Excess air ( % by volume ) %

Final Annexure. BOILER-HA102 of 2

Page 101: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.11 (Informative)

Fan Coil Units

1. The fan coil units ( FCU ) are mounted directly on the wall of air conditioned rooms

with or with out ducting & canvas connection and with supply air grill . The FCUs can

be single or multiple units in a chilled water air conditioning system .These are factory

made and tested and accepted before it reaches site.

2. Site work involves mounting the FCU on pre-decided location , connecting the

temperature controller , cabling , treated fresh air connection if required , mechanical ,

electrical , chilled water pipe connection and condensate water removal connections ,

control system and BMS connectivity if applicable .

3. Sample check lists are given in attachments for Delivery ( HA -11D ) , Installation (

Ha-11C ) , Start Up ( HA – 11S ) .

Page 102: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HA -12 Fan Coil Unit For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A 3 Unit Serial No

A 4 Air flow/ Static Pressure cfm/mm

WG

A 5 Cooling/ Heating capacity

A 6 Supply fan motor power/speed KW/rpm

A 7 Chilled water flow/ Pr drop lpm/mm

A 8 Hot water flow/Pr drop lpm /mm

A 9 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Coil surface free of damage Y/N

B4 Water openings plugged Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

B7 Unit tags affixed Y/N

2 HA -12 Fan Coil Unit For all "NO" responses, A Fan Coil UnitInstallation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearences Y/N

available for maintenance and unit removal

A3 Condensate drain properly Y/N

installed with adequate slope

A4 Vibration isolators OK Y/N

A5 Unit label visible Y/N

B Water pipingB1 Piping correctly installed and adequately supported Y/N

B2 Piping is clean Y/N

B3 Pipe insulation correctly installed Y/N

B4 Valve tags installed Y/N

C Ducting

C1 Dampers/sensors accessibleC2 Ductwork is adequately supported Y/N

C3 Dampers open/close properly Y/N

C4 Filters correctly installed and clean

C5 Ducting internally clean Y/N

C6 Testing locations available Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Direction of motor rotation correct Y/N

D3 Electrical connections are tight Y/N

D4 Eearthing adequate Y/N

E InstrumentationE1 Control panel accessible Y/N

E2 Sensors correctly installed Y/N

E3 Control valve actuators installed Y/N

E4 Electrical protections correctly installed Y/N

F ControlsF1 Thermostat installed Y/N

F2 Thermostat calibrated Y/N

F3 Control wiring correct Y/N

F4 Control sequence verified Y/N

2 HA -12 Fan Coil Unit For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Fans/motors lubricated/aligned Y/N

A3 Unit pressure tested and correct Y/N

APPENDICES TO COMMISSIONING STANDARD-HA11

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Fan Coil Units

Final Annexure. FCU-HA111 of 2

Page 103: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

A4 Canvas connection proper Y/N

A5 Sensors correctly installed Y/N

A6 Unit dampers fully open Y/N

A7 No unusual noise or vibration Y/N

B Controls startupB1 Power available for commissioning Y/N

B2 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Air flow/pressure measured Y/N

C3 Water side measurements done Y/N

C4 Supply air quantity correct as per design Y/N

C5 No unusual noise or vibration Y/N

C6 Calibrated insruments used Y/N

C7 Fan motor full load current in limits Y/N

C8 Flow rates in ducts within allowable tolerance Y/N

C9 Measure fan speed and compare with design

C10 Check and confirm proper function

of control algorithms in BMS Y/N

C11 Check Operation sequence Y/N

C12 Entering and leaving air temp at coil --/--

C13 Entering and leaving air temp at heating coil --/--

Final Annexure. FCU-HA112 of 2

Page 104: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HA.12 (Informative)

Meters and Gauges

1. Meters and Gauges are primarily used in the air conditioning system during

installation, commissioning , testing , operation and system balancing of the air as

well as water.

2. Meters are normally used to measure the pressure / velocity / quantity , temperature of

air , water, refrigerant or any other gas and or fluid flowing through the pipeline /

chiller, condenser, fan etc of HVAC system . Meters are also used to measure the

electrical parameters such as voltage , continuity , KWh , KVA , current and or any

variations in flow of current

3. The gauges are used to measure the pressure of air , water , refrigerant and any other

liquid , gas used in the air conditioning system.

4. The Meters and Gauges are calibrated and certified by the NABL accredited testing

laboratory and recalibrated regularly as per guidelines specified by the test lab /

manufacturers.

5. The details of various meters and gauges is mentioned under Appendix H-12 – Test

Measurements and Testing Instruments .

Page 105: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA-12D Meters and Gauges For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details Meters and Gauges

A. Meters in Remarks column A1 Manufacturer

a. Mechanical - Water side A2 Model No

b. Mechanical - Air side A3 Capacity / Range

c. Electrical / Electronics A4 Serial No / Identification No

B. Gauges A5 Type

B Physical ChecksB1 Meters & Gauges free from Physical damage Y/N

B2 Calibration done Y/N

B3 Accuracy - Acceptable Y/N

B4 Connecting socket / port provided Y/N

B5 Installation manual provided Y/N

Test/warranty certificate provided Y/N

B6 Unit tags affixed Y/N

HA-12C Meters and Gauges For all "NO" responses, A Meters and Gauges

Installation Checklists please fill in details A1 All items fitted properly Y/N

in Remarks column A2 Able to read the parameters properly Y/N

A3 Easy access for maintenance Y/N

A4 Removal of unit possible Y/N

A5 Unit label visible Y/N

A6 All fitting joints are not leaking Y/N

A7 All Meters & Gauges tested for its functioning Y/N

B Controls startup

B1 Temp sensor calibration Y/N

B2 Airflow sensor calibration Y/N

B3 Control wiring correct Y/N

B4 All items calibration period valid Y/N

B5 Control sequence verified

B6 BMS Connectivity correcly established

HA-12S Meters and Gauges A Mechanical Start up Checklists For all "NO" responses, A1 Manufacturers checklist completed Y/N

please fill in details A2 Commissioning format ready Y/N

in Remarks column A3 Sensors correctly installed Y/N

A4 Permissible parameter chart available Y/N

A5 Readings verified of actual performance Y/N

B Start up/ TAB Y/N

B1 Precommissioning checks complete Y/N

B2 Air distribution balancing done

B3 Air flow/pressure measured Y/N

B4 Supply air quantity correct as per design Y/N

B5 Water distribution balancing done Y/N

B6 Water flow / pressure measured Y/N

B7 DP sensors installed at specified locations Y/N

B8 Check and confirm proper function of control Y/N

algorithms in BMS

APPENDICES TO COMMISSIONING STANDARD-HA12

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Meters and Gauges

Final Annexure. Meters & Gauges-HA121 of 1

Page 106: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.1 (Informative)

Refrigerant Piping

1. In a vapor compression type refrigeration system the major components like

compressor , condenser evaporator and the expansion devise and control valves are

connected through metal pipes ( seamless Copper or Steel pipe) . The performance of

above components and the system depends on correctness installed the piping. The

factors to be considered while installing the refrigerant piping are:

a) Design and selection of right size of pipe and laying them for suction, hot gas and

liquid line as prescribed in / OEMs installation manual .

b) Carry out pressure testing after completing the to ensure the system will with

stand pressure while in operation

c) Carry out Vacuum test to ensure there is no moisture and non condensable gas

inside the pipe line .

d) Charging the system with correct quantity of refrigerant after breaking the vacuum

2. The pipes used for the refrigeration system should be seamless copper or steel pipe to

withstand the burst pressure of refrigerant used in the system .

3. The tube manufacturers specify the grade and the standard followed by them in

manufacturing the tubes meant for refrigeration system.

4. Sample check lists are given in attachments for Delivery ( HB -1D ) , Start up ( HB-

1B) and operation ( HB-1C)

Page 107: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 Refrigernt Piping For all "NO" responses, A System ChecksSample Check List - Delivery please fill in details A 1 ODUs have been levelled and installed properly Y/N

in Remarks column A2 Vibration isolation pads of correct size have been provided

below ODUs

Y/N

A 3 IDUs have been installed as per design layout Y/N

A 4 Drain piping of IDUs properly laid with required slope and

connected to main drain

Y/N

A 5 Grade of copper piping selected is as recommended for

specific installation

Y/N

A 6 Routing of copper piping from ODU to IDU is as per

detailed & approved layout

Y/N

A 7 Refrigerant piping has been laid properly as shown in

Drawing

Y/N

A 8 There is no visble dents / damages in piping and fittings Y/N

A 9 Connecting piping between ODU & IDU have been

supported properly

Y/N

A 10 Refrigerant piping running out side the building are

properly covered to protect from any damages

Y/N

A 11 Selection of refrigerant piping material as per IS Standard IS

10773

Y/N

A 12 Selection of various pipe fittings such as T joint, Y /

branching joint and multiple branching

Y/N

A 13 Brazing material shall confirm to IS 2927

A 14 Selection of insulation material - size thickness and grade

as defined in BOQ / Specification

Y/N

A 15 Proper tools used for cutting , flaring , bending etc Y/N

A 16 Nitrogen gas used for pressure testing the system Y/N

A 17 Valves and fittings provided in refrigarnat line are of

standard make / as recommended by the Commissioning

agent

Y/N

A 18 Suction piping has been insulated properly from IDU to

ODU

A 19 Test ports for BMS as per PID provided Y/N

A 20 Main incoming with MCB and earthing is terminated at the

ODU .

Y/N

A 21 All compressors and other motors and electrically

operated controls are connected with proper cable size ,

earthing and terminated as per electrical rules

Y/N

A 22 All cables used are as specified in BOQ with out any

deviation

Y/N

A 23 Final as built drawings are available Y/N

A 24 All equipment and component details are avaiilable and

recorded

Y/N

A 25 Gas cylinders are identified with proper marking such as

Nitrogem , CO2 , Oxygen and Acetiline

Y/N

A 26 The refrigerant cylinders also have identification mark on

the cylinder such as R 22 , R 32, R 407C , R 410A etc

Y/N

A 27 Pressure regulator in working condition is used for brazing

and pressure tesing purpose

Y/N

A 28 There is sufficient space around the ODUs for

maintenance purpose with a proper access

Y/N

A 29 Isolatation switch is porvided near the condensing unit in

case the the condensers are located far away from the

compressor

Y/N

A 30 While carrying out copper pipe brazing , the brazing

procedure has been followed as per IS 2927

Y/N

APPENDICES TO COMMISSIONING STANDARD-HB1

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Refrigerant Piping

Final Annexure. Ref Piping-HB11 of 2

Page 108: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

2 Refrigerant Piping For all "NO" responses, B Start Up

Start up Check please fill in details in

Remarks Column

B1 Pressure testing of the refrigarant lines is complete and

system having no leak.Readings recorded

Y/N

B2 Vacuum test has been carried out for the entire system

and readings recorded

Y/N

B3 All Service valves are in open position before startimg

the machines

Y/N

B4 After the vacuum testing , vacuum was broken by charging

minimum quantity of refrigerant to maintain positive

pressure

Y/N

B5 All the electrical work including the laying cable ,

termination of power wiring at the motor are done as per

the local electrical guidelines

Y/N

B6 Electrical safety items / alarm bells / indicating lamps etc

are in place

Y/N

B7 Electrical incoming supply is having proper balanced

voltage

Y/N

B8 Megger testing has been done for the cabling and

readings are OK

Y/N

B9 Refrigerant charging line with calbrated pressure gauge

and connecting tube is vailable at site

Y/N

B10 LOG book having required columns to record all the

readings as per the guidelines is available

Y/N

B11 First Aid Kit is available at the location in case of multi unit

/ large installations

Y/N

B12 Water connection / provision for water is available at site

near the plant room

Y/N

B13 Trained operating staff present during commissioning Y/N

3 Refrigerant Piping For all "NO" responses, C OperationOperation Review please fill in details in

Remark column

C1 All the controls and the control wiring are checked for its

opeartion on no load condition

Y/N

C2 All pre commissioning and start up procedures are

completed

Y/N

C3 Measuring instruments are calibrated and in working

condition

Y/N

C4 Refrigerant charged to the system and pressure readings

recorded

Y/N

C5 Individual indoor units are run and checked for any

vibration / noise

Y/N

C6 Air flow of IDUs measured for individual units and

achieved as specified

Y/N

C7 All low side equipment / AHU parameters are as per design Y/N

C8 Current drawn is measured and recorded for individual

units

Y/N

C9 Condenser in and out pressure and temperature readings

are inline with the design and recorded

Y/N

C10 Inside conditions are recorded Y/N

C11 Compressor in and out temperature / pressure readings are

recorded

Y/N

C12 All operating parameters are recorded and as per design Y/N

C13 Noise level of ODUs are measured and does not exceed

desired limits

Y/N

C14 Operation / Instruction Mannual including technical

leteratures of all equipment / controls are available at site

Y/N

C15 Any deviation in parameters recorded and corrective

action taken to resolve

Y/N

Final Annexure. Ref Piping-HB12 of 2

Page 109: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.2 (Informative)

Water Piping

1. Water piping consists of Condenser water, chilled water, make up water and,

condensate / drain water. The condenser and chilled water piping design is very

important for the system to function efficiently.

2. The piping can be laid above the ground level, or on the ground or in a trench below

the ground level. The condenser / chilled water piping is laid to connect the condenser

/ chiller and the respective pumps installed in the plant room or out side the plant room.

3. The site work involves laying the pipes on the ground with proper support and above

the ground with proper suspension method using vibration isolation where required

after the equipment are properly levelled and grouted.

4. The condenser and chillers are connected by using necessary valves / strainers and

vibration isolation as per design / layout drawing.

5. Pressure testing the lines as per the standard practice using hydraulic pump and

flushing the system in order to remove dirt and solid particles from the line

6. Sample check lists are given in attachments for Delivery ( HB -2D ) , Start Up ( HB

– 2B ) and operation ( HB-2C)

Page 110: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HB -02 Water piping For all "NO" responses, A System Checks

Sample Checklist - Delivery please fill in detailsin

Remarks column

A 1 Pre commissioning checks completed Y/N

A2 Piping correctly laid as per drawing with Y/N

A 3 Piping properly tagged with flow directions Y/N

A 4 Pipes are adequately flushed Y/N

A 5 Strainers removed and cleaned Y/N

A 6 Pipes pressure tested Y/N

A 7 Insulation done correctly ( if applicable ) Y/N

A 8 All valves as per design drawings Y/N

A 9 Piping clean and free of damage Y/N

A 10 Drainage/Venting possible Y/N

A 11 All fittings are as per specifications Y/N

A 12 Valves are accessible for operation and

maintenance

Y/N

A 13 Pipes do not block access to equipment Y/N

A 14 All openings sealed till ready for use Y/N

A 15 As built drawings available Y/N

A 16 Flexible connections installed where

specified

Y/N

A 17 Test ports installed near all sensors Y/N

A 18 Motorised valves are ready to operate Y/N

2 HB -02 Water piping For all "NO" responses, B Start up

Start up Checklists please fill in details B1 All manual shut off valves are open Y/N

in Remarks column B2 All by pass valves are closed Y/N

B3 Balancing of water flow rates done Y/N

where manual balancing valvesare provided

B4 Where PIBCVs provided , manual Y/N

balancing valves set to operating point before

PIBCV operation is verified

B5 No unusal noise or vibration when valves are

opened or closed

Y/N

B6 Pressure and flow measurements to be recorded

at each control valve

Y/N

3 HB -03 Water piping For all "NO" responses, C Operation.

Operation Review please fill in details C1 All pre commissioning and start up Y/N

in Remarks column procedures are completed

C2 Pipes pressure tested before insulation Y/N

C3 Pressure testing records available Y/N

and verified

C4 Pipe flows balanced and all balancing records

verified

Y/N

C5 Water flow measurements carried out Y/N

at each valve a) Fully open

b) 10 % open

C6 No unusual hydraulic noise Y/N

C7 If any additives are used same is Y/N

correctly authorised

C8 Calibrated instruments are used Y/N

C9 All components operate as specified Y/N

C10 All flow rates are achieved as specified Y/N

APPENDICES TO COMMISSIONING STANDARD - HB2

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Water Piping

Final Annexure. Water Piping-HB21 of 1

Page 111: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.3 (Informative)

Chilled Water System

1. Chilled water system comprises of single or multiple chillers , chilled water pumps

single or multiple mounted on a RCC or metallic frame foundation having isolation pad

/ material below it , complete chilled water piping from the chillers to ( AHUs, FCUs)

air distribution system , isolation / modulating valves , check valves , strainers ,

controls etc.

2. The chilled water system will have primary circuit , secondary circuit or tertiary

circuit depending upon the type of system chosen , number of floors etc. Each circuit

will have different sets of Pumps with flow /capacity control mechanism. .

3. The chilled water system will have isolation valves at branches, modulating valves ,

check valves and strainers wherever required.

4. There will be single of multiple AHUs , FCUs, all connected through chilled water

piping from the plant room to various spaces to be conditioned.

5. The AHUs and FCUs will be installed with Control valves operated with pressure /

temperature sensors which will control flow of water through each AHU and FCU

thereby controlling the flow through each pump set.

6. The control system comprises of flow control and temperature control at various points

in smaller plants while the larger system will have automatic control mechanism using

BMS connectivity.

7. The site work will involve laying the piping as per layout drawing, fabricating and

welding using proper bends , Tees, reducers and installation of valves , fittings and

controls , mechanical , electrical and control system.

8. The pressure testing carried out and system is flushed and fresh water is filled in to

the system.

9. All the piping , valves fittings from chiller , to pump and to AHU, FCU are insulated

as per the specification .

10. Sample check lists are given in attachments for Delivery ( HB-3D ) , Start Up ( HB

– 3C ) and operation ( HB-3S)

Page 112: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HB -02 Chilled Water System For all "NO" responses, A System Checks

Sample Checklist please fill in details A 1 Chiller/s Installed as per Approved drawing Y/N

in Remarks column A2 Foundation for chiller/s are proper, Enough access provided for

maintenance

Y/N

A3 Vibration Isolator of chillers installed as per approved specs Y/N

A 5 Chilled Water Pumps Installed as per Approved drawing Y/N

A7 Foundation and inertia blcoks ( if any)for pumps are proper,

Enough access provided for maintenance

Y/N

A8 Vibration Isolator of pumps installed as per approved specs Y/N

A9 Pipes are connected to chillers and pumps with required valves

as per PID

Y/N

A10 Tagging of equipments and valve is done Y/N

A11 Supports for chilled water piping is checked, Necessary supports

near diversion , near equipments are provided

Y/N

A12 Chilled water piping & drain piping is laid as per approved shop

drawing and PID including for AHUs, FCUs etc

Y/N

A13 Insulation is checked properly Y/N

A14 Piping clean and free of damage Y/N

A15 Equipment clean and free of damage Y/N

A16 Drainage/Venting is provided at proper location Y/N

A17 All Piping fittings are as per specifications Y/N

A18 Flow directions marked on pipes Y/N

A19 Flexible connections installed where specified Y/N

A20 Test ports installed near all sensors Y/N

A21 Motorised valves are ready to operate Y/N

A22 Piping is tested with hydrotested and reports signed off Y/N

A23 The blank off are provided at equipment end to avoid water flow

( Chillers, Pumps, AHUS etc)

Y/N

A24 Flushing and passivation activity is done and reports are signed

off

Y/N

A25 All test ports including for BMS as per PID are provided.

Pressure and temperature Guages Provided

Y/N

A26 All duct works are checked, the installation cheklist is signed Y/N

A27 Equipments are electrically connected with proper cable size

and earthing

Y/N

A28 Meggar test of cabling is done Y/N

A29 All openings sealed with proper sealant till ready for use Y/N

A30 As built drawings available Y/N

A31 All installation check list are approved with snags Y/N

A32 Allequipments details are taken and recorded Y/N

2 HB -02 Chilled Water System For all "NO" responses, B Start upStart up Checklists please fill in details B1 All manual shut off valves are open Y/N

in Remarks column B2 All by pass valves are closed Y/N

B3 Water Balancing of water flow done where manual balancing

valves are provided

Y/N

B4 Where PIBCVs provided , manual balancing valves set to

operating point Before PIBCV operation is verified

Y/N

B5 No unusal noise or vibration when valves are opened or closed (

Pumps, Chillers, Piping Supports)

Y/N

B6 Pressure and flow measurements to be recorded at each control

valve. Valves are adjusted accordingly

Y/N

B7 Electrical mains are charged and checked Y/N

B8 Electrical Paramaters are checked for all equipments Y/N

B9 OLR settings done as per limit Y/N

B10 Checking of VCD and FD Operation Y/N

3 HB -03 Chilled Water System For all "NO" responses, C Operation.

Operation Review please fill in details C1 All pre commissioning and start up Y/N

APPENDICES TO COMMISSIONING STANDARD - HB3

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Chilled Water System

Final Annexure. CHW System-HB31 of 2

Page 113: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

in Remarks column procedures are completed

C2 Calibrated instruments are used Y/N

C3 All water and air flow rates are achieved as specified Y/N

Pipe flows balanced and all balancing records verified Y/N

C4 Chiller Paramters ( Electrical/Mechanical) are noted and

recorded.

Y/N

C5 Chiller parameters are as per design Y/N

Pumps Paramters ( Electrical/Mechanical) are noted and

recorded.

Y/N

C6 Pumps parameters are as per design Y/N

C7 All Low side equipments parameters are checked Y/N

All Low side equipments parameters ( Electrical/Mechanical) are

as per design

Y/N

C8 Inside Conditions / Process parameters are recorded Y/N

C9 Any deviation in parameters recorded and resolved Y/N

Final Annexure. CHW System-HB32 of 2

Page 114: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.4 (Informative)

Condenser Water System

1. Condenser water system comprises of single or multiple chillers , Cooling towers

single or multiple , condenser water pump sets single or multiple mounted on a RCC

or metallic frame foundation having isolation pad / material below it, isolation /

modulating valves , check valves , strainers and controls etc.

2. Condenser water system will have isolation valves at condenser inlet and out let , pump

in and out and cooling tower in and out , check valves and strainers wherever required

3. The site work will involve laying the piping as per layout drawing, fabricating and

welding using proper bends , Tees, reducers and installation of valves , fittings and

controls , mechanical , electrical and control system.

4. The pressure testing carried out and system is flushed and soft and uncontaminated

fresh water is filled in to the system.

5. Sample check lists are given in attachments for Delivery ( HB -4D ) ,Start Up ( HB –

4C ) and operation ( HB-4S)

Page 115: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

1 HB -02 Condenser Water System For all "NO" responses, A System Checks

Sample Checklist please fill in details A 1 Cooling towers Installed as per Approved drawing Y/N

in Remarks column A2 Foundation for cooling tower r/s are proper, Enough access

provided for maintenance

Y/N

A 3 Enough area is provided for air circulation Y/N

A 4 Condenser Water Pumps Installed as per Approved drawing Y/N

A 5 Foundation and inertia blcoks ( if any)for pumps are proper,

Enough access provided for maintenance

Y/N

A 6 Vibration Isolator of pumps installed as per approved specs Y/N

A 7 Pipes are connected to equipements with required valves as per

PID

Y/N

A 8 Tagging of equipments and valve is done Y/N

A 9 Supports for condenserd water piping is checked, Necessary

supports near diversion , near equipments are provided

Y/N

A 10 Piping clean and free of damage Y/N

A 11 Equipment clean and free of damage Y/N

A 12 Drainage/Venting/ Over flow is provided at proper location Y/N

A 13 All Piping fittings are as per specifications Y/N

A 14 Flow directions marked on pipes Y/N

A 15 Flexible connections installed where specified Y/N

A 16 Test ports installed near all sensors Y/N

A 17 Motorised valves are ready to operate Y/N

A 18 Piping is tested with hydrotested and reports signed off Y/N

A 19 The blank off are provided at equipment end to avoid water flow Y/N

A 20 Flushing and passivation activity is done and reports are signed

off

Y/N

A 21 All test ports including for BMS as per PID are provided. Pressure

and temperature Guages Provided

Y/N

A 22 Equipments are electrically connected with proper cable size and

earthing

Y/N

A 23 Meggar test of cabling is done Y/N

A 24 As built drawings available Y/N

A 25 Allequipments details are taken and recorded Y/N

2 HB -02 Condenser Water System For all "NO" responses, B Start up

Start up Checklists please fill in details B1 All manual shut off valves are open Y/N

in Remarks column B2 All by pass valves are closed Y/N

B3 Water Balancing of water flow done where manual balancing

valves are provided

Y/N

B4 No unusal noise or vibration when valves are opened or closed (

Pumps, Towers, Piping Supports)

Y/N

B5 Pressure and flow measurements to be recorded at each control

valve. Valves are adjusted accordingly

Y/N

B6 Electrical mains are charged and checked Y/N

B7 Electrical Paramaters are checked for all equipments Y/N

B8 OLR settings done as per limit Y/N

3 HB -03 Condenser Water System For all "NO" responses, C Operation.

Operation Review please fill in details C1 All pre commissioning and start up procedures are completed Y/N

C2 Calibrated instruments are used Y/N

C3 All water and air flow rates are achieved as specified Y/N

C4 Pipe flows balanced and all balancing records verified Y/N

C5 Cooling Tower Paramters ( Electrical/Mechanical) are noted and

recorded.

Y/N

C6 Cooling Tower parameters are as per design Y/N

APPENDICES TO COMMISSIONING STANDARD-HB4

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Condenser Water System

Final Annexure. Cond W Systsem-HB41 of 2

Page 116: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix

No

Appendix Title Notes Item No Description Unit Response Remarks

C7 Pumps Paramters ( Electrical/Mechanical) are noted and

recorded.

Y/N

C8 Pumps parameters are as per design Y/N

C9 Any deviation in parameters recorded and resolved Y/N

Final Annexure. Cond W Systsem-HB42 of 2

Page 117: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.5 (Informative)

Direct Expansion System

1.0 Direct Expansion system ( DX) comprises of Indoor Unit single or multiple connected to

Out Door Unit single or multiple through refrigerant piping . The DX system may have

air cooled condensers or water cooled condensers with cooling tower and pumps

connected through water piping.

2.0 The out door unit comprises of compressor, motor , condenser , all in a enclosed casing

either factory made or site assembled . These are factory made and tested and accepted

before it reaches site.

3.0 Site work involves a) installation of Indoor unit and out door unit on prefixed foundation

refrigerant piping between indoor unit and out door unit including fixing valves , pressure

testing the entire refrigerant piping , vacuuming . b) Installation of controls, electrical

power and control wiring , c) mechanical works like providing supports for piping d)

duct with canvas connection from the indoor unit to the air conditioned space d) insulation

of suction piping and e) commissioning and balancing the system.

4.0 Sample check lists are given in attachments for Delivery ( HB -5D ) , Start Up ( HB –5C)

and operation ( HB-5S )

Page 118: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA - 1 D Dx Systems - VRV/Packaged Units For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No- Indoor Units

A4 Air Flow - Indoor Units l/sec

A5 Indoor Unit fan motor power Kw

A6 Indoor Unitsfanmotor V/Ph/Frequency

A7 Total cooling / Heating capacity KW

A9 Airflow- Outdoor Unit l/sec

A10 Ambient Temp O C

A11 Cond fan motor power kw

A12 Cond fan motor V/Ph/Frequency

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Copper pipes sealed at Y/N

both ends

B4 Unit tags present Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

2 HA - 1 C Dx Systems - VRV/Packaged Units For all "NO" responses, A Evaporator sectionSample Checklist - Installation please fill in details A1 Unit adequately supported Y/N

and Start up in Remarks column A2 Adequate service clearances Y/N

available for maintenance

A3 Condensate drain properly Y/N

installed

A4 Unit label visible Y/N

B Condenser SectionB1 Unit adequately supported Y/N

B2 Adequate service clearances Y/N

available for maintenance

B3 Unit label visible Y/N

C Refrigerant pipingC1 Piping correctly installed Y/N

as per drawing

C2 Disconnection for unit Y/N

removal is easy

C3 Pipe supports are as per Y/N

specifications

C4 Pipe pressure tested and Y/N

found OK

C5 Pipe insulated as per Y/N

specifications

C6 Valves and test ports are Y/N

accessible

C7 Valves are tagged Y/N

C8 Unit charged with refrigerant Y/N

D ElectricalD1 Isolator in accessible location Y/N

D2 Motor rotation correct Y/N

D3 Terminations checked Y/N

D4 Earthing is proper Y/N

E ControlsE1 Thermostat installed Y/N

E2 Thermostat calibrated Y/N

E3 Control wiring correct Y/N

E4 Control sequence verified Y/N

E5 No abnormal notice or Y/N

vibration

E6 Manufacturers checklist Y/N

completed

APPENDICES TO COMMISSIONING STANDARD - HB5

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - DX Systems

Final Annexure. DX System-HB51 of 2

Page 119: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

E7 Filters installed and are Y/N

clean

Actual Design

3 HA - 1 O Dx Systems - VRV/Packaged Units For all "NO" responses, A1 Room Temperature OC

Sample Checklist - Operation please fill in details A2 Grill temperature OC

in Remarks column A3 Voltage V

A4 Starting current Amps

A5 Full load current Amps

A6 High pressure cutout setting psi

A7 Low pressure cutout setting psi

A8 Suction pressure psi

A9 Discharge pressure psi

A10 Evaporator entering DB/ WB OC

A11 Evaporator leaving DB/ WB OC

A12 Cond entering DB/ WB OC

A13 Cond leaving DB/ WB OC

A14 Air flow Evaporator l/sec

A15 Air flow Cond l/sec

A16 Noise at 1 m from Evap d B a

A17 Noise at 1 m from Cond d B a

Final Annexure. DX System-HB52 of 2

Page 120: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.6 (Informative)

Air Distribution System

1. The HVAC systems use air ducts installed in a building to supply conditioned air to

various spaces through supply air duct with terminal outlets , vents such as diffusers

grilles , cassettes registers etc . The air from the conditioned space is received through

return air ducts with terminal such as grilles , diffusers .

2. Based on the heat load and air quantity requirement, layout of the space to be air

conditioned with the supply air duct routing and return air path to the air handling

unit room is prepared .Sizing of the supply air duct has a bearing on the pressure drop

and outlet velocities.

3. Air distribution of HVAC system comprises of single or multiple AHUs / Fans from

where the cooled / treated / dehumidified air is circulated and collected back from

the conditioned areas though supply and return air ducting.

4. The material used for ducting shall have properties which are user friendly such as

rust resistance ,least friction for flow of air , easily malleable and giving air tight seal

when installed. The recommended materials for the ducting are galvanized steel ,

aluminium or stainless steel sheets .The ducts can be either rectangular or circular as

preferred by the designer and will have insulation where required as per design

5. The duct fabrication , joinery , installation and flanges are carried out in line with BIS

IS 655 , SMACNA standard.

6. The site work will involve laying the installation of main ducts ,connecting and

terminating the branches as per layout drawing, fixing dampers , grilles and diffusers ,

canvas connections , joining all joints and making them air tight .

7. Sample check lists are given in attachments for Delivery ( HB -6D ) , Installation (

HB-6C ) , Start Up ( HB – 6B ) and operation ( HB-6S)

Page 121: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 Air Distribution System For all "NO" responses, A Model verification As Applicable

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Cooling /Heating Capacity

A6 Supply air Flow cfm

A7 Supply fan motor power/speed KW/rpm

A8 Return Air Flow cfm

A9 Return Fan motor power/speed KW/rpm

A10 Voltage/Phase/Frequency V/-/Hz

A11 Filters rating MERV

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Access doors operable Y/N

B6 Installation manual provided Y/N

B7 Test/warranty certificate provided Y/N

B8 Unit tags affixed Y/N

2 Air Distribution System For all "NO" responses, A Air Distribution SystemInstallation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearances Y/N

available for maintenance

A3 Clear acess available Y/N

for Dampers/Duct/VAV/CAV/filters removal

A5 Fan / Chamber / Air Handling Unit /

Ductwork system internally clean

Y/N

A6 Air filters installed and clean

A7 Air leakage tests completed with all test

blanks removed

Y/N

A7 Fan / AHU / Coil drains and traps complete

A8 Unit label visible Y/N

B DuctingB1 Mixing of outdoor/return air possible Y/N

B3 Ductwork is adequately supported Y/N

B4 Dampers open/close properly Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Direction of motor rotation correct Y/N

C3 Electrical connections are tight Y/N

C4 Earthing adequate Y/N

C5 Starter/VFD installed Y/N

D InstrumentationD1 Control panel accessible Y/N

D2 Sensors correctly installed Y/N

D3 Damper actuators installed Y/N

D4 Control valve actuators installed Y/N

D5 Electrical protections correctly installed Y/N

E ControlsE1 Control wiring for distribution control

complete and tested (ie. Motorised

dampers, VAV’s/CAV’setc.)

Y/N

APPENDICES TO COMMISSIONING STANDARD - HB6

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Air Distribution System

Final Annexure. Air Distribution system-HB61 of 2

Page 122: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

E2 Controls point checked for distribution

controls (Motorised dampers, VAV’s / CAV’s

etc. can be driven to required positions

Y/N

E3 Control wiring correct Y/N

E4 Control sequence verified Y/N

3 Air Distribution System For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details in

Remarks column

A1 Manufacturers checklist completed Y/N

A2 Filters installed and are clean Y/N

A3 Fan belts correct and in good condition Y/N

A4 Unit pressure tested and correct Y/N

A5 Belt guards in place Y/N

A6 Canvas connection proper Y/N

A7 Sensors correctly installed Y/N

A8 Unit dampers fully open Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Lighting within unit installed Y/N

B3 Power available for commissioning Y/N

B4 BMS Connectivity correctly established Y/N

4 Air Distribution System For all "NO" responses, A Start up/ TABOperational please fill in details A1 Precommissioning checks complete Y/N

in Remarks column A2 Air flow/pressure measured Y/N

A3 Fan operating point marked in fan curve Y/N

A4 CAV/VAV Pre-Commissioning Checks

complete

Y/N

A5 Supply air quantity correct as per design Y/N

A6 No unusual noise or vibration Y/N

A7 Calibrated instruments used Y/N

A8 Fan motor full load current in limits Y/N

A9 Flow rates in ducts within allowable Y/N

tolerance.

A10 Compare fan air flow in front of filter Y/N

section with air flow in main ducts

A11 Check and confirm proper function Y/N

of control algorithms in BMS

A12 Check Fan Operation sequence Y/N

A13 Measure the air flow at the terminal

diffuser/grill to ensure that air is reaching to

the farthest terminal units

Y/N

A14 Adjust the dampers at each terminal unit to

match to the design flow as per the

approved ducting layout.

Y/N

A15 After adjusting the dampers for each

diffuser recheck for the air flow at each

diffuser to match the design flow

Y/N

A16 VCD Positions marked as per desired air

flow setting

Y/N

A17 Check for the air flow at the return air filter

side. If the air flow at the return air filter

side is excess of the deign total air flow

reduce the speed of the fan through supply

air dampers/VFD to achieve the design air

flow.

Y/N

Final Annexure. Air Distribution system-HB62 of 2

Page 123: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 Air Distribution System For all "NO" responses, A Model verification As Applicable

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Cooling /Heating Capacity

A6 Supply air Flow cfm

A7 Supply fan motor power/speed KW/rpm

A8 Return Air Flow cfm

A9 Return Fan motor power/speed KW/rpm

A10 Voltage/Phase/Frequency V/-/Hz

A11 Filters rating MERV

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Access doors operable Y/N

B6 Installation manual provided Y/N

B7 Test/warranty certificate provided Y/N

B8 Unit tags affixed Y/N

2 Air Distribution System For all "NO" responses, A Air Distribution SystemInstallation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearances Y/N

available for maintenance

A3 Clear acess available Y/N

for Dampers/Duct/VAV/CAV/filters removal

A5 Fan / Chamber / Air Handling Unit /

Ductwork system internally clean

Y/N

A6 Air filters installed and clean

A7 Air leakage tests completed with all test

blanks removed

Y/N

A7 Fan / AHU / Coil drains and traps complete

A8 Unit label visible Y/N

B DuctingB1 Mixing of outdoor/return air possible Y/N

B3 Ductwork is adequately supported Y/N

B4 Dampers open/close properly Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Direction of motor rotation correct Y/N

C3 Electrical connections are tight Y/N

C4 Earthing adequate Y/N

C5 Starter/VFD installed Y/N

D InstrumentationD1 Control panel accessible Y/N

D2 Sensors correctly installed Y/N

D3 Damper actuators installed Y/N

D4 Control valve actuators installed Y/N

D5 Electrical protections correctly installed Y/N

E ControlsE1 Control wiring for distribution control

complete and tested (ie. Motorised

dampers, VAV’s/CAV’setc.)

Y/N

APPENDICES TO COMMISSIONING STANDARD - HB6

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Air Distribution System

Final Annexure. Air Distribution system-HB61 of 2

Page 124: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

E2 Controls point checked for distribution

controls (Motorised dampers, VAV’s / CAV’s

etc. can be driven to required positions

Y/N

E3 Control wiring correct Y/N

E4 Control sequence verified Y/N

3 Air Distribution System For all "NO" responses, A Mechanical StartupStart up Checklists please fill in details in

Remarks column

A1 Manufacturers checklist completed Y/N

A2 Filters installed and are clean Y/N

A3 Fan belts correct and in good condition Y/N

A4 Unit pressure tested and correct Y/N

A5 Belt guards in place Y/N

A6 Canvas connection proper Y/N

A7 Sensors correctly installed Y/N

A8 Unit dampers fully open Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Lighting within unit installed Y/N

B3 Power available for commissioning Y/N

B4 BMS Connectivity correctly established Y/N

4 Air Distribution System For all "NO" responses, A Start up/ TABOperational please fill in details A1 Precommissioning checks complete Y/N

in Remarks column A2 Air flow/pressure measured Y/N

A3 Fan operating point marked in fan curve Y/N

A4 CAV/VAV Pre-Commissioning Checks

complete

Y/N

A5 Supply air quantity correct as per design Y/N

A6 No unusual noise or vibration Y/N

A7 Calibrated instruments used Y/N

A8 Fan motor full load current in limits Y/N

A9 Flow rates in ducts within allowable Y/N

tolerance.

A10 Compare fan air flow in front of filter Y/N

section with air flow in main ducts

A11 Check and confirm proper function Y/N

of control algorithms in BMS

A12 Check Fan Operation sequence Y/N

A13 Measure the air flow at the terminal

diffuser/grill to ensure that air is reaching to

the farthest terminal units

Y/N

A14 Adjust the dampers at each terminal unit to

match to the design flow as per the

approved ducting layout.

Y/N

A15 After adjusting the dampers for each

diffuser recheck for the air flow at each

diffuser to match the design flow

Y/N

A16 VCD Positions marked as per desired air

flow setting

Y/N

A17 Check for the air flow at the return air filter

side. If the air flow at the return air filter

side is excess of the deign total air flow

reduce the speed of the fan through supply

air dampers/VFD to achieve the design air

flow.

Y/N

Final Annexure. Air Distribution system-HB62 of 2

Page 125: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.7 (Informative)

Hot Water System

1. The hot water system is installed for heating of the space air conditioned. The hot

water system will have separate sets of Pumps with flow / capacity control

mechanism.

6. The hot water system will also have isolation valves at branches, modulating valves ,

check valves and strainers wherever required.

7. There will be single of multiple AHUs , FCUs, may have additional heating coils

connected through hot water piping from the plant room .

8. The control system comprises of flow control and temperature control at various points

in smaller plants while the larger system will have automatic BMS system with all

controls connected to it .

9. The site work will involve laying of piping as per layout drawing, fabricating and

welding joints, with proper bends , Tees, reducers and installation of dampers ,valves

, fittings and controls , mechanical work.

10. The pressure testing carried out and system is flushed and fresh water is filled in to

the system.

11. All the piping , valves fittings from condenser / hot water boiler to pump and AHU,

FCU are insulated as per the specification .

12 Sample check lists are given in attachments for Delivery ( HB -7D ) , Installation (

HB-7C ) , Start Up ( HB – 7M ) and operation ( HB-7S)

Page 126: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HB-7D Hot Water System For all "NO" responses, A System Checks

Sample Checklist please fill in details A 1 Hot water generators Installed as per

Approved drawing

Y/N

in Remarks column A2 Foundation for generators are proper,

Enough access provided for maintenance

Y/N

A3 Vibration Isolator of installed as per

approved specs

Y/N

A 4 Ventilation is provided in plant room Y/N

A 5 Hot Water Pumps Installed as per Approved

drawing

Y/N

A7 Foundation and inertia blcoks ( if any)for

pumps are proper, Enough access provided

for maintenance

Y/N

A8 Vibration Isolator of pumps installed as per

approved specs

Y/N

A9 Pipes are connected to Hot water generator

and pumps with required valves as per PID

Y/N

A10 Tagging of equipments and valve is done Y/N

A11 Supports for hot water piping is checked,

Necessary supports near diversion , near

equipments are provided

Y/N

A12 Hot water piping & drain piping is laid as

per approved shop drawing and PID

including for AHUs, FCUs etc

Y/N

A13 Insulation is checked properly Y/N

A14 Piping clean and free of damage Y/N

A15 Equipment clean and free of damage Y/N

A16 Drainage/Venting is provided at proper

location

Y/N

A17 All Piping fittings are as per specifications Y/N

A18 Flow directions marked on pipes Y/N

A19 Flexible connections installed where

specified

Y/N

A20 Test ports installed near all sensors Y/N

A21 Motorised valves are ready to operate Y/N

A22 Piping is tested with hydrotested and

reports signed off

Y/N

A23 The blank off are provided at equipment

end to avoid water flow ( Hot water

generator , Pumps, AHUS etc)

Y/N

A24 Flushing and passivation activity is done and

reports are signed off

Y/N

A25 All test ports including for BMS as per PID

are provided. Pressure and temperature

Guages Provided

Y/N

A26 All duct works are checked, the installation

cheklist is signed

Y/N

A27 Equipments are electrically connected with

proper cable size and earthing

Y/N

A28 Meggar test of cabling is done Y/N

A29 All openings sealed with proper sealant till

ready for use

Y/N

A30 As built drawings available Y/N

A31 All installation check list are approved with

snags

Y/N

A32 Allequipments details are taken and

recorded

Y/N

APPENDICES TO COMMISSIONING STANDARD - HB7

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Hot Water System

Final Annexure. Hot Water system-HB71 of 2

Page 127: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

2 HB -7C Hot Water Water System For all "NO" responses, B Start upStart up Checklists please fill in details B1 All manual shut off valves are open Y/N

in Remarks column B2 All by pass valves are closed Y/N

B3 Water Balancing of water flow done where

manual balancing valves are provided

Y/N

B4 Where PIBCVs provided , manual balancing

valves set to operating point Before PIBCV

operation is verified

Y/N

B5 No unusal noise or vibration when valves

are opened or closed ( Pumps, Hot water

generator , Piping Supports)

Y/N

B6 Pressure and flow measurements to be

recorded at each control valve. Valves are

adjusted accordingly

Y/N

B7 Electrical mains are charged and

checked

Y/N

B8 Electrical Paramaters are checked for all

equipments

Y/N

B9 OLR settings done as per limit Y/N

B10 Checking of VCD and FD Operation Y/N

B11 Water flow quality is checked

3 HB -7S Hot water Generator Water System For all "NO" responses, C Operation.Operation Review please fill in details in Remark columnC1 All pre commissioning and start up

procedures are completed

Y/N

C2 Calibrated instruments are used Y/N

C3 All water and air flow rates are achieved

as specified

Y/N

C4 Pipe flows balanced and all balancing

records verified

Y/N

C5 Hot water generator Paramters ( Electrical /

Mechanical) are noted and recorded.

Y/N

C6 Hot water generator parameters are as per

design

Y/N

C7 All the settings are done and recorded Y/N

C8 Pumps Paramters ( Electrical/Mechanical)

are noted and recorded.

Y/N

C9 Pumps parameters are as per design Y/N

C10 All the settings are done and recorded Y/N

C11 All Low side equipments parameters are

checked

Y/N

C12 All Low side equipments parameters (

Electrical/Mechanical) are as per design

Y/N

C13 All the settings are done and recorded Y/N

C14 Inside Conditions / Process parameters are

recorded

Y/N

C15 Any deviation in parameters recorded and

resolved

Y/N

Final Annexure. Hot Water system-HB72 of 2

Page 128: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.8 (Informative)

Basement Ventilation System

1. Basement Ventilation system comprises of Jet fans , supply and exhaust fans , controls

and control panel and BMS connectivity. The jet fans will be suspended from the ceiling

as per layout prepared. The operation of these fans is controlled by sensors installed

at various pre-decided locations based on CFD ( Computational Fluid Dynamics )

analysis.

2. The basement ventilation system will have multiple Jet fans directly suspended from

the ceiling . The supply and exhaust air fans are installed in the outer wall of the building

may or may not have duct connections based on the design of layout.

3. The ventilation fans are factory made and tested and accepted before it reaches site.

4. Site work involves usually installation of Jet fans , supply and exhaust fans , ducting

when required, mechanical, cabling, electrical and control system and BMS

connectivity.

5 Sample check lists are given in attachments for Delivery ( HB -8D ) , Start Up ( HB–

8C ) and operation ( HB-8S)

Page 129: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S NoAppendix

NoAppendix Title Notes Item No Description Unit Response Remarks

1 HB -08 Basement Ventilation System For all "NO" responses, A System Checks

Sample Checklist please fill in details A 1 Jet fans, Supply and exhaust fans Installed as per

Approved drawing

Y/N

in Remarks column A2 Enough access provided for maintenance for all fans Y/N

A 3 No clash of fans with other services, civil works, walls

etc

Y/N

A 4 PLC and starter panels installed as per approved

drawngs

Y/N

A 5 Cables, cables trays , termination done as per

approved SLD, shop drawings

Y/N

A 6 Ducts works are done with as per approved drawings

with fire coating

Y/N

A 7 Fire dampers if required are installed as per approved

drawings

Y/N

A 8 Vibration Isolator of jet fans, supply and exhaust fans

installed as per approved specs

Y/N

A 9 Co sensors are installed as per appropriate location as

per approved drawing

Y/N

A 10 Tagging of equipments is done Y/N

A 11 Equipment clean and free of damage Y/N

A 12 Equipments are electrically connected with proper

cable size and earthing

Y/N

A 13 Meggar test of cabling is done Y/N

A 14 Approved CFD anaylsis is available Y/N

A 15 Approved logic is available Y/N

A 16 As built drawings available Y/N

A 17 All equipments details are taken and recorded Y/N

2 HB -02 Basement Ventilation System For all "NO" responses, B Start up

Start up Checklists please fill in details B1 Electrical mains are charged and checked Y/N

in Remarks column B2 Electrical Paramaters are checked for all

equipments

Y/N

B3 OLR settings done as per limit Y/N

B4 No unusal noise or vibration noticed during startup of

fans

Y/N

B5 Air paths are clear and there is no blockage

B6 Interface with Fire Protection system is done and

checked

Y/N

3 HB -03 Basement Ventilation System For all "NO" responses, C Operation.

Operation Review please fill in details C1 All pre commissioning and start up procedures are

completed

Y/N

C2 Calibrated instruments are used Y/N

C3 All the settings are done and recorded Y/N

C4 All fans parameters ( Mechanical and Electrical)are

noted

Y/N

C5 Any deviation in parameters recorded and resolved Y/N

C6 PLC panels readings and checked and recorded Y/N

C7 Fir dampers oopeartion and its interface is checked

and recorded

Y/N

C8 Interface with fire protection is checked manually as

well as in AUTO mode

Y/N

C9 Scenarios as per approved logics are created and

verified

Y/N

C10 The readings are cross chekced with approved CFD

report and deviations are recorded

Y/N

APPENDICES TO COMMISSIONING STANDARD - HB8

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Basement Ventilation System

Final Annexure. Basement Vent-HB81 of 1

Page 130: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.9 (Informative)

Kitchen Ventilation System

1. Kitchen ventilation system comprises of exhaust fan and hood with filters , ducting

and necessary controls and sensors

2. The kitchen ventilation system will have single or multiple systems , return or exhaust

air fans connected with or with out ducting .These are factory made and tested and

accepted before it reaches site.

3. Site work involves installation of fans with proper isolation material , kitchen hood ,

ducting , mechanical , electrical work , sensors , controls and BMS connectivity

4. Sample check lists are given in attachments for Delivery ( HB -9D ) , Installation (

HB-9C ) , and operation ( HB-9S)

Page 131: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 Kitchen Ventilation System For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Fan Type

A5 Capacity cfm

A6 Static Pressure mm of WG

A7 Motor power/speed KW/rpm

A8 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Installation manual provided Y/N

B5 Test/warranty certificate provided Y/N

B6 Unit tags affixed Y/N

B7 Grease Filter installed and clean.

2 Kitchen Ventilation System For all "NO" responses, A Exhaust Fan

Installation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearances Y/N

available for maintenance

A3 Vibration isolators OK Y/N

A4 Shipping bolts removed Y/N

A5 Fan belts are in order and tight

A6 Back draft damper installed and correct

A7 Drive guard in place

A8 Unit label visible Y/N

B Ducting

B1 Dampers/sensors accessible

B2 Vibration isolators OKB3 Ductwork is adequately supported Y/N

B4 Dampers open/close properly Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Direction of motor rotation correct Y/N

C3 Electrical connections are tight Y/N

C4 Earthing adequate Y/N

C5 Starter/VFD installed Y/N

D InstrumentationD1 Control panel accessible Y/N

D2 Sensors correctly installed Y/N

D3 Damper actuators installed Y/N

D4 Electrical protections correctly installed Y/N

3 Kitchen Ventilation System For all "NO" responses, A Mechanical Startup

Start up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Fan belts correct and in good condition Y/N

A3 Canvas connection proper Y/N

A4 Sensors correctly installed Y/N

A5 Dampers fully open Y/N

B Controls startupB1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correctly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Duct work balancing done Y/N

APPENDICES TO COMMISSIONING STANDARD - HB9

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Kitchen Ventilation System

Final Annexure. KITCHEN Vent-HB91 of 2

Page 132: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

C3 Air flow/pressure measured Y/N

C4 Fan operating point marked in fan curve Y/N

C5 Supply air quantity correct as per design Y/N

C6 No unusual noise or vibration Y/N

C7 Calibrated instruments used Y/N

C8 VCD Positions marked Y/N

C9 Fan motor full load current in limits Y/N

C10 Flow rates in ducts within allowable Y/N

tolerance.

C11 Measure fan speed and compare with Y/N

design

C12 Check and confirm proper function Y/N

of control algorithms in BMS

Final Annexure. KITCHEN Vent-HB92 of 2

Page 133: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.10 (Informative)

Exhaust System

1. The Exhaust system comprises of, supply and exhaust fans, controls and control panel

and BMS connectivity. Exhaust fans may or may not have duct connections based on

the design of layout.

2. The fans factory made and tested and accepted before it reaches site.

3. Site work involves usually installation of fans with proper vibration isolation system

ducting and fire dampers where ever required, mechanical , cabling , electrical and

control system with BMS connectivity.

4. Sample check lists are given in attachments for Delivery ( HB -10D ) , Start up ( HB-

10C ) , and operation ( HB-10S)

Page 134: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HB -10 Exhaust Systems For all "NO" responses, A System Checks

Sample Checklist please fill in details A 1 Supply and exhaust fans Installed as per

Approved drawing

Y/N

in Remarks column A2 Enough access provided for maintenance for

all fans

Y/N

A 3 No clash of fans with other services, civil

works, walls etc

Y/N

A 4 Starter panels installed as per approved

drawngs

Y/N

A 5 Cables, cables trays , termination done as per

approved SLD, shop drawings

Y/N

A 6 Duct works are done as per approved shop

drawings

Y/N

A 7 Fire dampers if required are installed as per

approved drawings

Y/N

A 8 Access doors are provided in exhaust duc

work

Y/N

A 9 Vibration Isolator for supply and exhaust fans

installed as per approved specs

Y/N

A 10 Tagging of equipments is done Y/N

A 11 Supports for all fans are as per approved

drawings

Y/N

A 12 Equipment clean and free of damage Y/N

A 13 Equipments are electrically connected with

proper cable size and earthing

Y/N

A 14 As built drawings available Y/N

A 16 All equipments details are taken and

recorded

Y/N

2 HB -02 Exhaust Systems For all "NO" responses, B Start up

Start up Checklists please fill in details B1 Electrical mains are charged and checked Y/N

in Remarks column B2 Electrical Paramaters are checked for all

equipments

Y/N

B3 OLR settings done as per limit Y/N

B4 No unusal noise or vibration noticed during

startup of fans

Y/N

B5 Condition of fliters checked

B6 Air paths are clear and there is no blockage

3 HB -03 Exhaust Systems For all "NO" responses, C Operation.

Operation Review please fill in details C1 All pre commissioning and start up

procedures are completed

Y/N

C2 Calibrated instruments are used Y/N

C3 All the settings are done and recorded Y/N

C4 All fans parameters ( Mechanical and

Electrical)are noted

Y/N

C5 Fir dampers oopeartion and its interface is

checked and recorded

Y/N

C6 Any deviation in parameters recorded and

resolved

Y/N

APPENDICES TO COMMISSIONING STANDARD - HB10

Delivery, Installation, Start up and Operation Check Lists.

Equipment/ System - Exhaust Systems

Final Annexure. Exhaust System-HB101 of 1

Page 135: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.11 (Informative)

Pressurisation System

1. The pressurization system will have single or multiple fans ,connected with ducting

dampers & actuators , motors and controls . The fans are factory made and tested and

accepted before it reaches site.

2. Site work involves usually installation of fans with vibration isolation pads, ducting

with dampers & damper actuators , Starter / VFD , mechanical , electrical panel ,

cabling , control system and BMS connectivity

3. Sample check lists are given in attachments for Delivery ( HB -11D ) , Installation

(HB-11C) Start Up ( HB – 11S)

Page 136: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA -09 A Pressurisation Fans For all "NO" responses, A Model verification

Sample Checklist - Delivery please fill in details A 1 Manufacturer

in Remarks column A2 Model No

A3 Unit Serial No

A4 Fan Type

A5 Capacity cfm

A6 Static Pressure mm of

WG

A7 Motor power/speed KW/rpm

A8 Voltage/Phase/Frequency V/-/Hz

B Physical ChecksB1 Unit free from Physical damage Y/N

B2 All components present Y/N

B3 Air openings sealed Y/N

B4 Installation manual provided Y/N

B5 Test/warranty certificate provided Y/N

B6 Unit tags affixed Y/N

2 HA -09 A Pressurisation Fans For all "NO" responses, A Pressurisation Fan

Installation Checklists please fill in details A1 Unit adequately supported Y/N

in Remarks column A2 Adequate service clearences Y/N

available for maintenance

A3 Vibration isolators OK Y/N

A4 Shipping bolts removed Y/N

A5 Fan belts are in order and tight

A6 Dampers installed properly

A7 Drive guard in place

A8 Unit label visible Y/N

B Ducting (If provided )

B1 Dampers/sensors accessibleB3 Ductwork is adequately supported Y/N

B4 Dampers open/close properly Y/N

B5 Ducting internally clean Y/N

B6 Testing locations available Y/N

C ElectricalC1 Isolator in accessible location Y/N

C2 Direction of motor rotation correct Y/N

C3 Electrical connections are tight Y/N

C4 Eearthing adequate Y/N

C5 Stater/VFD installed Y/N

D InstrumentationD1 Control panel accessible Y/N

D2 Sensors correctly installed Y/N

D3 Damper actuators installed Y/N

D4 Electrical protections correctly installed Y/N

2 HA-09A Pressurisation Fans For all "NO" responses, A Mechanical Startup

Start up Checklists please fill in details A1 Manufacturers checklist Y/N

in Remarks column completed

A2 Fan belts correct and in good condition Y/N

A3 Canvas connection proper Y/N

A4 Sensors correctly installed Y/N

A5 Dampers fully open Y/N

B Controls startup

B1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

C Start up/ TABC1 Precommissioning checks complete Y/N

C2 Electrical tests complete and verified Y/N

C3 Air flow/pressure measured Y/N

APPENDICES TO COMMISSIONING STANDARD - HB11

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - Pressurisation System

Final Annexure. PR.FAN-HB111 of 2

Page 137: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

C4 Fan operating point marked in fan curve Y/N

C5 Supply air quantity correct as per design Y/N

C6 No unusual noise or vibration Y/N

C7 Calibrated insruments used Y/N

C8 VCD Positions marked Y/N

C9 Fan motor full load current in limits Y/N

C10 Measure and record pressure difference

across doors ( doors closed/ open as per

design

Y/N

C11 Measure fan speed and compare with Y/N

design

C12 Check and confirm proper function Y/N

of control algorithms in BMS

Final Annexure. PR.FAN-HB112 of 2

Page 138: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure HB.12 (Informative)

Control System (HVAC)

1. Functioning of HVAC equipment mainly depends on the control system that is

provided which regulates the operational parameters and controlling and maintaining

the desired output, energy consumed and health of various components / equipment

with the help of sensing devices .

2. Building automation is the centralized control of a building's heating, ventilation and

air conditioning, lighting and other systems through a building management system or

building automation system . Modern BAS can also control indoor and outdoor lighting

as well as security, fire alarms, and basically everything else that is electrical in the

building.

3. The building automation system helps to improve occupant comfort, efficient

operation of building systems, reduction in energy consumption and operating costs,

and improved life cycle of utilities often referred to as intelligent building or smart

building.

4. Central controllers and most terminal unit controllers are programmable. The program

features include time schedules, setpoints, controllers, logic, timers, trend logs, and

alarms. The unit controllers typically have analog and digital inputs that allow

measurement of the variable (temperature, humidity, or pressure)

and analog and digital outputs for control of the transport medium (hot/cold water

and/or steam).

5. Various types of control system are :

a) Chiller : Capacity modulation/ control , Temperature of chiller outlet , Chilled

water pump speed , condenser water pump speed, water quantity delivered by

individual pumps , cooling tower fan motor, and heat rejection by cooling tower ,

pump motor speed regulation , Compressor capacity modulation etc.

b) AHU :Chilled water flow though the coil, supply and return air temperature, S.Air

quantity delivered by the AHU and back to the AHU ,air quantity supplied to

various rooms ,

c) Mechanical : Noise, vibration, pressure readings, temperature readings, flow of

water / liquid and air ,

d) Electrical : High / low Voltage, current , continuity , power factor

Page 139: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

1 HA - 12 Control Systems Sample For all "NO" responses, A Sensors and Actuators Model Verification

Checklist - Delivery please fill in details A1 Manufacturer

check against drawing in Remarks column A2 Model No.

A3 Range if mentioned.

USE SEPARATE SHEET B Physical Checks

FOR EACH SYSTEM B1 Unit free from Physical damage Y/N

B2 All components present Y/N

B5 Installation manual provided Y/N

B6 Test/warranty certificate provided Y/N

B7 Unit tags affixed Y/N

2 HA - 12 CONTROL SYSTEMS For all "NO" responses, A Control Components

Installation Checklist please fill in details A1 SENSORS / ACT SECURED Y/N

in Remarks column A2 Adequate service clearances available Y/N

A3 All components accessible for maintenance Y/N

A7 Unit label visible Y/N

B Sensors and Actuators

B9 tags TO CONTRLR# & CHANNEL installed Y/N

D Electrical to Sensor / Actuator

D1 Supply (say 24V) is protected Y/N

D3 Electrical connections are tight Y/N

D4 Earthing IF APPLCBL adequate Y/N

3 HA - 12 Controls For all "NO" responses, A Inital Standalone Startup

Start up Checklists please fill in details A1 Manufacturers checklist completed Y/N

in Remarks column A2 Non Communication to Sensors checked Y/N

A3 All Actuators working with controller

A4 All External Relays operating Y/N

A6 No unusual error messages Y/N

B Controls startup

B1 Control sequence verified Y/N

B2 Power available for commissioning Y/N

B3 BMS Connectivity correcly established Y/N

B4 alarms operational

B5 VFD if attached Operational ( if applcbl)

C Start up / TAB

C1 Precommissioning checks complete

C2 Check and confirm proper function of

control algorithms in BMS

C10 note PB, IAT and AT for each P&I

1 HA-12 SYS BMS COMMISSIONING Sample For all "NO" responses, A PROGRAM AND Front-End HARDWARE

Checklist - Delivery check please fill in details A1 Manufacturer

against drawing in Remarks column A2 Model No.

A3 SOFTWARE LICENSE

B Physical Checks

B1 COMPUTER AND DISPLAY

B2 All componenets present

B5 SOFTWARE manual provided

B6 Test / warranty certificate provided

B7 Unit tags affixed

2 HA-12 BMS COMMISSIONING For all "NO" responses, A BMS AND Controllers Hardware

Installation Checklists please fill in details A1 Each Item tagged

in Remarks column A2 Adequate service clearances available

A3 All componenets accessible for

maintenance

A7 Unit label visible

B hand-auto-off switches

B1 functioning and set

APPENDICES TO COMMISSIONING STANDARD - HB12

Delivery, Installation, Start up and Operation Check Lists

Equipment/ System - CONTROLS and BMS

Final Annexure. Controls & BMS-HB121 of 2

Page 140: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

S No Appendix No Appendix Title Notes Item No Description Unit Response Remarks

D Controllers and Front End Electrical

D1 Supply (say 24V) is protected

D3 Emergency Supply if reqd working

D4 Earthing IF APPLCBL adequate

3 USE SEPARATE SHEET Alarm Settings on Digital Inputs

FOR THESE Alarm Settings on Analog Inputs

History Collection Points

History Intervals

RUNTIME POINTS AND ALARM

POWER ACCUMULATION POINTS

SETPOINTS

ADVISORY MESSAGES

PASSWORD LEVELS

BACKUPS

A) EACH CONTROLLER CONFIGURATION

B) TOP-END CONFIGURATION

C) ALL GRAPHIC DISPLAYS

D) CHARTS AND GRAPHS

E) DASHBOARD IF ANY

Final Annexure. Controls & BMS-HB122 of 2

Page 141: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure – I (Informative)

Resolution of concerns and non-conformance

1.0 Any concerns and non-conformance observed during the installation and inspection

phase shall be communicated to the project team for resolution.

2.0 The concerns and non-conformance shall be documented in a log format and shall

be updated periodically. These are best presented in a log format and the log needs

to be updated periodically.

3.0 The following items may be included as a table in the log book.

a) Serial number.

b) Date

c) Brief description of issue

d) Name of person raising the issue.

e) Probable cause of the issue.

f) Impact the issue may have on construction or operation.

g) Suggested resolution

h) Person to resolve the issue.

i) Brief description of action.

j) Issue closure date.

k) Issue closure authorised (Name).

Page 142: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure – J (Informative)

Systems Manual

1.0 Systems manual is the collection of the following:

a) Final OPR

b) Basis of Design

c) Commissioning Plan

d) Commissioning Process report

e) Equipment and System manuals

f) Operation and maintenance manuals

g) Schematic drawings

h) Information on training

i) Test – Results and commissioning report.

j) As built drawing

k) O&M manual

2.0 Systems manual shall be put together by the commissioning team.

3.0 Systems manual is meant to provide information to the operating and maintenance

staff of the building regarding design and construction and to provide

comprehensively and in one document all relevant information.

4.0 Systems manual will be helpful for ongoing commissioning and for system

performance improvement.

Page 143: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure – K (Informative)

Training

1.0 OPR shall address the training requirements such as training of operating staff,

services that may be outsourced, scope of work of the facility management team

etc. Warranty and service agreements for major equipment and system will have a

bearing on the training plans.

2.0 Training needs shall depend on the nature, type and complexity of systems installed

and the skill levels of the staff available to operate the systems.

3.0 Training requirements of own staff and any contractors workforce needs to be

separately identified and catered for

4.0 Training may include the following

- Purpose of the systems

- O & M Manuals

- Control drawings and schematics.

- Start up and operation of building.

- Interaction with other systems

- Optimization for energy conservation.

- Health and safety.

- Special maintenance and replacement.

- Occupant interaction.

- System response to different operating conditions.

- Emergency situations.

5.0 All training may be stored in audio video format for future reference and for

facilitating subsequent training services.

Page 144: Draft Commissioning Process for HVAC Systems · Starting the commissioning process right at project inception will achieve 127 maximum benefits. 128 129 Appendices are included to

Final Draft for public Comments - Comm Process for HVAC_19.02.2020

Annexure – L (Informative)

Commissioning Report

1.0 Commissioning report shall contain all relevant documentation relating to the

process of commissioning.

2.0 Any deviation from OPR which is accepted by the owner needs to be listed.

3.0 All construction checklists will form part of this.

4.0 The issue log and resolution details will be included.

5.0 Test procedure and data summarize.

6.0 Copies of all progress reports generated during commissioning process.

7.0 For any deferred tests, the required conditions and estimated schedule needs to be

mentioned.

8.0 A preliminary report may be submitted to the owner for review and final report may

include owner’s comments.

9.0 The report should include a warranty review and states.