DPW Outreach Presentation on
Date July 12, 2018
DPW Highway Department 2nd Floor
Ajayan Bridge Replacement on Route 4
Project No. GU-ER-0004(114)
and Upcoming DPW Bridge Projects
• Introduction
• Ajayan Bridge Project Briefing • Location of Ajayan Bridge Project • Overview of Project • Project Features
• Bridge Type • Bridge Layout • Environment • Other Project Features
• Construction Staging • Project Schedule
• Upcoming DPW Bridge Projects
• Questions/Answers
Agenda
Upcoming DPW Bridge Projects
• Ajayan Bridge Bid Summer 2018
• In 2019 Aplacho Bridge will be Bid
• In 2021 An Additional 5 Bridges will be IFB
Ajayan Bridge Replacement
Project Location
• Route 4 near east village boundary of Merizo
• Near west village boundary of Inarajan
• Over Ajayan River at Ajayan Bay
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Project Overview
• Existing bridge constructed in 1968
• Existing is a single span CIP concrete bridge
• 2004 Inspection showed substructure and channel rated in serious condition
• Need to replace structural deficient bridge over Ajayan River
• New bridge will be longer and wider
• Channel will be armored for scour and erosion resistance
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement
Key Project Features • New 105’ single span Pre-stressed AASHTO Girder Bridge • New pre-stressed concrete pile foundations for improved
scour vulnerability • Armored channel banks • Wider bridge which includes 2-12’ travel lanes and 8’
shoulders • New concrete bridge railings and approach slabs • Approx. 350 ft of new pavement • New striping, signs and guardrail for improved safety and
access • Relocation and accommodation of existing utilities on the
new bridge
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement
Plan View
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Pile Foundation
Ajayan Bridge Replacement
• Environmental Mitigation • Within coastal tidal area • Nearby wetlands need to be protected (Section 401 &
404 permits acquired, permit conditions to be implemented.)
• Archeological monitoring • Biological monitoring prior to start of work • Turbidity monitors will be used during construction • Construction BMPs will be included
• Catchment platforms • Protective netting • Silt screen fences • Turbidity curtains
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
• Construction Staging • The existing bridge structure will be removed
• The existing piles will be removed and capped at mudline
• Existing guardrails will be replaced
• Pavement will be removed and replaced
• Heavy construction equipment needs to be assessed before it can cross the existing bridge
• Traffic will be maintained during construction
• Existing bridge will be removed in TWO phases
• New bridge will be constructed in TWO phases
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Construction Staging
Ajayan Bridge Replacement
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement Construction Staging
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Ajayan Bridge Replacement
Ajayan Bridge Replacement
Estimated Cost $3M
Design Completion January 2018
Begin Contractor Outreach July 2018
Advertise for Bids Summer 2018
Start Construction Spring 2019
Ajayan Bridge Replacement Project No. GU-NH-0004(118)
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
Aplacho Bridge Replacement 2019
Aplacho Bridge
Aplacho Bridge Location
• Aplacho Bridge Replacement
• On Route 17 (Cross Island Road) in Santa Rita
• IFB 2nd Quarter 2019
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
Aplacho Bridge Replacement 2019
• The new Aplacho bridge will be wider and longer (approximately 79’ span).
• Superstructure Type: Pre-stressed AASHTO Girders
• Substructure Type: Reinforced Concrete Spread footing
• Reconstruct road approaches: 400’ north and 700’
• DPW considering redesign of the abutments to be Geosynthetic Reinforced Soil-Integrated Bridge System (GRS)
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
Aplacho Bridge Replacement 2019
Key Project Features
• Bridge Replacement
• Reconstruction of approach roadway
• Utility Relocations and drainage improvements
Aplacho Bridge Replacement 2019
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
• Construction of paved shoulder
• New striping and signing
• Construction of new drainage improvements
• Relocation of existing water, sewer, communication lines and powerline relocation.
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
Aplacho Bridge Replacement 2019
• Building Permit and appurtenant permits
• Protection of existing nearby wetlands
• Temporary and Permanent Erosion and Sediment Control
• Listed species was discovered: Currently working on the Biological Opinion with USFWS
Environmental Permits and Protection
Aplacho Bridge Replacement Project No. GU-NH-0017 (106)
Aplacho Bridge Replacement 2019
Route 1 Reconstruction of Multiple Bridges 2021
Project Location
• Located in the Villages of: Hagatna, Asan, and Piti
• Along Route 1,between Route 2A and Route 4
• Total of 5 Bridges
• Approx. 270 miles of existing Bridge
Route 1 Reconstruction of Multiple Bridges (Hagatna to Piti) No. GU-DAR-0001 (131)
Route 1 Reconstruction of Multiple Bridges
Route 1 Reconstruction of Multiple Bridges (Hagatna to Piti) No. GU-DAR-0001 (131)
Purpose & Need
• Purpose: Allow usage of heavy military vehicles along Route 1
• Need: Replace existing Route 1 bridges to be able to carry heavy military vehicles
Route 1 Reconstruction of Multiple Bridges 2021
BR-01-Atantano Bridge BR-04-Fonte Bridge
Route 1 Reconstruction of Multiple Bridges (Hagatna to Piti) No. GU-DAR-0001 (131)
BR-27-Asan 1 Bridge
BR-35-Laguas Bridge BR-36-Sasa Bridge
Route 1 Reconstruction of Multiple Bridges 2021
Route 1 Reconstruction of Multiple Bridges (Hagatna to Piti) No. GU-DAR-0001 (131)
Start End
Planning Early 2017 Late 2018
Design Early 2019 Early 2021
Construction Mid 2021 2023
Note: Dates are preliminary and are subject to change
Project Schedule
Questions/Comments