dpw business review board overview. 2 1.overview of dpw’s new and existing review processes...

10
DPW Business Review Board Overview

Upload: bruno-gordon

Post on 19-Dec-2015

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

DPW Business Review BoardOverview

Page 2: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

2

1. Overview of DPW’s new and existing review processes

2. Business Review Board details• Purpose• Processes• Participants• Outcomes

Contents

Page 3: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

3

Overview of DPW’s new and existing review processes

Business Review Board

Architecture Review Board

Executive Information

Systems Governance Board

Primary Questions

What are the project details?

What is the business and technical approach?

What resources are required?

What will the project accomplish with respect to DPW’s goals?

Outcome

Project is approved or not approved

Priority of project is discussed and determined

Primary Questions

How will the business and program requirements be met?

How can DPW use existing business functionality to support these requirements?

Outcome

Existing solutions and functions are utilized when possible

All impacted stakeholders agree to the business approach

Primary Questions

How will solution be implemented?

How well is the project complying with DPW’s technical standards?

Outcomes

Project is scored according to compliance with technical standards

Existing technical components and functions are utilized when possible

(GB)

(BRB)

(ARB)

Page 4: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

4

Business Review Board (BRB)Mission Statement

“The mission of the Business Review Board is to review the business and program requirements in order to verify that the business value of a proposed initiative is understood and that existing business solutions are leveraged.”

Page 5: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

5

How can a Business Review help DPW address business issues?

Projects start because a business need has been identified. Business decisions impact DPW’s resources. A business review process would…

Create a forum for decision-makers to truly understand the stakeholders, business value, and program needs associated with a proposed project

Provide initiative sponsors with the opportunity to map their business needs against existing business solutions to see if DPW can reuse the approved solutions already in place

Decrease design, development, and testing time and costs by using pre-existing solutions that have been designed and approved

Help initiative sponsors to understand the business value of integration with existing enterprise applications (e.g. monitoring clients/providers across programs, improving customer service by using a single point of contact, reducing redundant processes)

Provide a business function resource for initiative sponsors who are beginning the DPW Review Process (informal information session and Q/A session)

Page 6: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

6

BRB: What?

• How will this help DPW to achieve its goals?• Who are the stakeholders? Have they been or will they be included throughout

the requirements process?• What are the program and business needs?• What is the best way to meet these business needs?• Do we have processes and systems in place that perform the functions

needed?• Will this impact other systems, processes, or data in other program areas?• Does the business need dictate the need to integrate or utilize enterprise

applications or tools (e.g. MCI, MPI, Data Warehouse, GIS)?

Project sponsors will be expected to address the following questions in their BRB presentation. Each presenting team is responsible for preparation and gathering as much information as possible to address these questions. The BRB Guidelines as well as the BRB Coordinator will provide resources to assist in this preparation. The team may engage the Board for input on unknowns, but should be prepared to speak to each question.

Page 7: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

7

BRB: When?

The Business Review Board is a required step for proposed projects and major releases for existing projects. This will help the project sponsor to prepare for the Governance Board, which will be responsible for approving projects. Once approved, the team will have the option of returning to the BRB or moving straight to the ARB process.

Planning Requirements

Definition

General System

Design

Detailed System

Design

Develop-ment

Systems Integration and Testing

Business Review

Architecture Review

Project Lifecycle View

. . .

New Projects and

Major Releases

The BRB will also serve as a review forum for changes in business functionality at the discretion of project teams.

BRB GB

BRB

ARB

BRB

ARB

Both the BRB and the ARB can be utilized as a resource for program offices/project sponsors for assistance in preparing their business or technical approach.

The ARB will continue to provide a review forum for a project’s technical solution.

Page 8: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

8

BRB How?

In general, the BRB will operate in a similar manner to the existing Architecture Review Board.

• BRB meetings will occur on a consistent day and time, the second and fourth Mondays of every month at 2:30 in Room 59, as needed

• Project sponsors will be responsible for contacting the BRB coordinator to present at a BRB meeting

• Multiple projects can present at one BRB meeting

• Guidelines and tools to help project sponsors presenting will be provided in FileNet and posted on the BIS Intranet (e.g. what to include in the presentation, how to fill in the matrix, what other resources are available to help them prepare)

• Project sponsors will provide all presentation materials, including the required

– BRB Presentation– Business Function Matrix

Page 9: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

9

Chair Teresa Shuchart

Coordinator Sandy Moore

Individual(s) Program Office

Dennis Brown Laura Chopp Arlene DiMarco Dave Ehrhart Lynnette Hassinger Todd Klunk Varada Krishnamurthy Mike Light Cheryl Martin Bill Miller Candace Orr Ray Packer Curt Pegg Suzanne Puzak Gary Rossman Jeff Rowe Barb Rupp Carla Solomon Bob Stranko Jim Swoyer Ed Zogby

OIMOA-BISOA-BISOMAPOCYFOCDOA-LicensingOA-BISOCYFComptroller OperationsOMHSASOIMOA-BISOA-PeopleStatOMROIMOMAPOA-BISOMAPOA-BISOIM

BRB: Who? The BRB participants volunteered or were recommended based on experience with the given business function area(s) and across program areas. General business function areas represented include client management, provider management, information management, and financial management. In addition, representation from PeopleStat and BIS will also provide coordination across review processes.

Page 10: DPW Business Review Board Overview. 2 1.Overview of DPW’s new and existing review processes 2.Business Review Board details Purpose Processes Participants

10

BRB Outcomes

Outcomes of a BRB review include:

• Validated and approved business approach for the new program initiative

– Completed checklist/business map of business function requirements to existing functions

– Informed decision (or action items assigned) on design approach for system to meet the business needs (e.g. build, reuse existing system, transfer new system)

• Action Items – Additional documentation or meetings – Follow up reviews (Governance, Architecture)