DAILYREPORTFROM SITE S.No:43 Date 21.02.2013 Site: M/s Baldev alloys pvt. LTD. Vwta020,VWHA052,053,054 1 . Details of communications received on …(E-mail, Fax, Courier, Post, by hand etc.,) : Nil. 2 . Details of communications sent to HO on…… : Daily report. 3 . Details of consignments / materials received from HO / others : Nil. 4 . Details of payments received from HO / others : Nil. 5 . Attendance with details 5.1 Staff (VEESONS) : MR.M.E.MANIKANDAN(2141) Mr. DINESH KUMAR.S (1832) 5.2 Contract Workers (Contractor wise) : Utkal Engineers: Boiler: Supervisor:01 IBR Welder -00;Fitter- 04;Welder-05; Riger- 03;grinder-0 Helper- 07(Total=20) 6 . Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,) : 1.contractor man power shortage 2. Radiography film required from contractor. 3.customer side insert

Upload: manikandan-elumalai

Post on 06-Nov-2015

212 views

Category:

Documents


0 download

DESCRIPTION

DPR-21-02-13

TRANSCRIPT

DAILY REPORTFROM SITE

DAILYREPORTFROM SITE

S.No:43 Date 21.02.2013Site: M/s Baldev alloys pvt. LTD.Vwta020,VWHA052,053,054

1.Details of communications received on (E-mail, Fax, Courier, Post, by hand etc.,):Nil.

2.Details of communications sent to HO on:Daily report.

3.Details of consignments / materials received from HO / others:Nil.

4.Details of payments received from HO / others:Nil.

5.Attendance with details

5.1Staff (VEESONS):MR.M.E.MANIKANDAN(2141)Mr. DINESH KUMAR.S (1832)

5.2Contract Workers (Contractor wise):Utkal Engineers: Boiler: Supervisor:01 IBR Welder -00;Fitter-04;Welder-05; Riger-03;grinder-0 Helper-07(Total=20)

6.Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,):1.contractor man power shortage2. Radiography film required from contractor.3.customer side insert plates

7.Materials, documents, payments urgently required from HO with details:1. Utkal engg Contractor payment.

8.Any urgent / important site complaints: UTKAL Engineering Should be increasing his manpower. Utkal engineering tools & tackles Shortage.(welding machine & cutting set, Grinding machine)

Site status:VWTA020 BOILER:

Work started time: 08-00AM work end time: 8-00PM1) Bed material bunker monorail beam erection work U/P.2) Furnace seal plate welding work u/p.3) Dividing chute to mixing nozzle chute flange welding work completed.4) Feed water Common header to WHRB & FBC line Supports work U/P.5) Air Ducting outer stretch welding work U/P.

ESP; 1) Discharge electrode alignment third field completed.2) Roof beam Plat form Brackets & channel erection work Completed.

Prepared by (Name): M.E.MANIKANDANSignature:Staff No : 2141

Checked & Approved by (Name) :M.E.MANIKANDANSignature:Staff No. :2141