dpr-21-02-13
DESCRIPTION
DPR-21-02-13TRANSCRIPT
DAILY REPORTFROM SITE
DAILYREPORTFROM SITE
S.No:43 Date 21.02.2013Site: M/s Baldev alloys pvt. LTD.Vwta020,VWHA052,053,054
1.Details of communications received on (E-mail, Fax, Courier, Post, by hand etc.,):Nil.
2.Details of communications sent to HO on:Daily report.
3.Details of consignments / materials received from HO / others:Nil.
4.Details of payments received from HO / others:Nil.
5.Attendance with details
5.1Staff (VEESONS):MR.M.E.MANIKANDAN(2141)Mr. DINESH KUMAR.S (1832)
5.2Contract Workers (Contractor wise):Utkal Engineers: Boiler: Supervisor:01 IBR Welder -00;Fitter-04;Welder-05; Riger-03;grinder-0 Helper-07(Total=20)
6.Important brief feedback about Fabrication / Erection / Commissioning (delay with reference to schedule, major problems etc.,):1.contractor man power shortage2. Radiography film required from contractor.3.customer side insert plates
7.Materials, documents, payments urgently required from HO with details:1. Utkal engg Contractor payment.
8.Any urgent / important site complaints: UTKAL Engineering Should be increasing his manpower. Utkal engineering tools & tackles Shortage.(welding machine & cutting set, Grinding machine)
Site status:VWTA020 BOILER:
Work started time: 08-00AM work end time: 8-00PM1) Bed material bunker monorail beam erection work U/P.2) Furnace seal plate welding work u/p.3) Dividing chute to mixing nozzle chute flange welding work completed.4) Feed water Common header to WHRB & FBC line Supports work U/P.5) Air Ducting outer stretch welding work U/P.
ESP; 1) Discharge electrode alignment third field completed.2) Roof beam Plat form Brackets & channel erection work Completed.
Prepared by (Name): M.E.MANIKANDANSignature:Staff No : 2141
Checked & Approved by (Name) :M.E.MANIKANDANSignature:Staff No. :2141