dp conference mts symposium - dynamic...
TRANSCRIPT
DP Conference MTS Symposium
Flow Assurance
Elijah KemptonTommy Golczynski
Marine Technology SocietySeptember 30, 2004
Session Outline
•Flow Assurance Overview•Key Flow Assurance Issues
•Wax•Hydrates•Slugging
•Deepwater Impacts on Flow Assurance•Emerging Technologies
•Design Considerations•Black Oil Systems•Gas Condensate Systems
Flow Assurance Overview
What is Flow Assurance?• Analysis of the entire production system to ensure that
the produced fluids continue to flow throughout the life of the field.
• Optimization of the design and operating procedures to cost effectively prevent or mitigate slugging, surge volumes, wax deposition, gelling, hydrates, asphaltenes, etc.
Key Flow Assurance Issues
•Wax (Paraffin) – What is it?•A solid hydrocarbon which precipitates from a produced fluid•Forms when the fluid temperature drops below the Wax Appearance Temperature (WAT)•Melts at elevated temperatures (20°F+ above the WAT)•Rate of deposition can be predicted for pigging frequency
Key Flow Assurance Issues
•Wax•Since 1996, there have been 51 major occurrences that the MMS had to be involved in
•All were paraffin-related•Means of remediation
•Pigging•Continuous inhibition (150-250 ppm for Gulf of Mexico)
Reduced wax deposition rate by 60-90%
•Industry Technology•Modeling is overly-conservative (6X pigging frequency)
Key Flow Assurance Issues
Above WAT Wax Crystals (WAT)
Seabed Temp. (40°F)
Example WAT Measurement
Key Flow Assurance Issues
•Factors effecting wax deposition rate
•Wax Appearance Temperature, WAT
•Production Fluid Temperature
•Flowline U-value
•Fluid PropertiesViscosity
N-Paraffin Content
Key Flow Assurance Issues
•Wax Deposition – Insulation Impact
Key Flow Assurance Issues
•Hydrate – What is it?•An Ice-like solid that forms when:
•Sufficient water is present•Hydrate former (i.e., methane) is present•Right combination of Pressure and Temperature (High Pressure / Low Temperature
Molecular Structure of
Hydrate Crystal
Key Flow Assurance Issues
•Hydrates•Primary cause for insulated flowlines•Deepwater operations
•Increased operating pressure•Cold ambient temperatures
•Means of remediation•Crude oil displacement (looped flowlines)•Depressurization•Coiled tubing•Continuous Inhibition (Prevention Only)
Methanol/MEGLDHI
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
40 45 50 55 60 65 70 75 80 85
Temperature, °F
Pres
sure
, psi
a
Pure Water
Sea Water
Produced Water
Key Flow Assurance Issues
•Hydrates – Base Information
Hydrates NoHydrates
0.300
0.325
0.350
0.375
0.400
0.425
0.450
0.475
0.500
0.525
0.550
0.575
0.600
50 75 100 125 150 175 200 225 250 275 300
Shut-in Pressure, bara
Met
hano
l Dos
age,
BB
L M
eOH
/BBL
Wat
er
761 GOR 1100 GOR
1700 GOR 2500 GOR
0
5
10
15
20
25
30
35
40
45
50
1000 2000 3000 4000 5000 6000 7000 8000 9000 10000
Flowrate, B/d
Met
hano
l Rat
e, g
pm
5% Water Cut
10% Water Cut
20% Water Cut
25% Water Cut
30% Water Cut
40% Water Cut
50% Water Cut
25 GPM
Key Flow Assurance Issues
•Hydrates – Base Information
Key Flow Assurance Issues
•Slugging – What is it?•Periods of Low Flow Followed by Periods of High Flow•Occurs in Multiphase Flowlines at Low Gas Velocities
Key Flow Assurance Issues
•Slugging•Causes
•Low fluid velocityBigger ≠ Better
•Seabed bathymetry (downsloping)•Riser type
“Lazy-S” is a slug generator
•Means of prevention•Increase flowrate•Separator pressure•Gas lift Difficult with
Catenary Risers
Lower Temperatures
Relative Inexpensive
Erosion Concerns
Proven Technology
DisadvantagesAdvantages
Gas LiftOverview
Key Flow Assurance Issues
•Slugging – Gas Lift Impacts
0
10000
20000
30000
40000
50000
60000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
Liq
uid
Out
let F
low
rate
(B/d
)
0 MMSCFD Gas Lift
0
5000
10000
15000
20000
25000
30000
35000
40000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
Liq
uid
Out
let F
low
rate
(B/d
)
5 MMSCFD Gas Lift
0
5000
10000
15000
20000
25000
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
Liq
uid
Out
let F
low
rate
(B/d
)
10 MMSCFD Gas Lift
-150
-100
-50
0
50
100
150
3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Time (hours)
Liq
uid
Acc
umul
atio
n A
bove
Nor
mal
(bbl
)0 MMSCFD Gas Lift
5 MMSCFD Gas Lift
10 MMSCFD Gas LiftSurge Volume
Key Flow Assurance Issues
•Other IssuesAsphaltenes
ScaleCorrosion
Emulsions
Pour Point
Liquids Management
Cooldown Times
Flare Capacity
C-Factors
ErosionDepressurization
Surge Volume
Pigging
Chemical Inventory
Sand
Deepwater Impacts on Flow Assurance
•Hydrate Formation/Wax Deposition•Leads to:
•Insulation / dual flowlines•Dry oil flushing•Active heating•Chemicals•Revamped operating strategies
•Lack of pressure / need for boosting•Deepwater + high water cut + long tiebacks
•Riser base gas lift•Multiphase pumping•Subsea separation
• Potential Energy Losses
• Gas does “work” in moving fluids
• Function of water depth
• Expansion Cooling (Joule-Thomson Effect)
• Exacerbated at large pressure differentials
• RISER DOMINATES DEEPWATER SYSTEMS
• Insulation may not be the answer!
Deepwater: Temperature Losses
95
100
105
110
115
120
125
0 1 2 3 4 5 6 7 8
FLOWLINE
RISER BASE
TOPSIDES
RISER
WELLHEAD
Distance (miles)
Tem
pera
ture
(°F)
Deepwater: Temperature Losses
Joule-ThomsonCooling
46%
Surroundings(U-Value)
6%
Potential Energy(Work)
48%
16.59.215
16.62.96
16.61.23
RiserFlowline
Temperature Drop (°F)Flowline Length(miles)
Deepwater: Temperature Losses
• Heat transfer coefficient (U-value) dictates steady state temperatures• Q (heat loss) = U•A•∆T
• U-Value ↓, Q ↓ …T ↑
• Thermal mass (ρ, Cp) impacts transient performance• Measure of heat storage
• Prolongs cooldown times
• Prolongs warm-up times
Deepwater: Temperature Losses
Tem
pera
ture
(°F)
Time(hours)
40
50
60
70
80
90
100
110
0 5 10 15 20 25 30 35 40
HIGH (Gelled Fluid #2 – Water Base)
MEDIUM (Gelled Fluid #1 – Oil Base)
LOW (Nitrogen)
Transient Temperature Loss
Pres
sure
(psi
a)
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6 7 8
Distance (miles)
FLOWLINERISER BASE
RISER
WELLHEAD
TOPSIDES
Deepwater: Pressure Losses
176440515
17912386
18121433
RiserFlowline
Pressure Drop (psia)Flowline Length(miles)
Deepwater: Pressure Losses
• Dry trees preferred for accessibility
• Dry trees more difficult for flow assurance
• Typically cannot depressurize
• Short cooldown times (2-8 hours)
• Fewer insulation/heating options than subsea
• Limited chemical (MeOH/MEG) deliverability
• Wax deposition more difficult to remediate
Deepwater:Dry Trees vs. Subsea Tieback
Dry Tree Analysis: Cooldown ComparisonProduction Fluid Temperature
40
45
50
55
60
65
70
75
80
85
90
95
100
0 1 2 3 4 5 6 7 8 9 10 11 12
Time (Hours)
Tem
pera
ture
(°F)
Solid - Conduction
Liquid - Conduction+Convection
Gas - Conduction+Convection+Radiation
HYDRATE FORMATION TEMPERATURE
Dry Tree:Conduction / Convection / Radiation
Concentric Non-Concentric
• Heat Transfer: Q = k·A·∆T / L(Conduction Only)
• Accommodate Auxiliary Lines?
Dry Tree:Concentric vs. Non-Concentric
Dry Tree:Concentric vs. Non-Concentric
Tem
pera
ture
(°F)
Time (Hours)
40
50
60
70
80
90
100
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
15 psia N230 psia N259 psia N2102 psia N2
Dry Tree:Gas Properties
• Transient issues drive deepwater design
• Cooldown / restart - Hydrates• Typical deepwater practice
• Dual flowlines / crude oil displacement
• Typically cannot depressurize (oil systems)
• Consider potential for future expansion• Insulation• Topsides facilities
Design for Expansion
22.5 km
10 km8 km
8 km
Design for Expansion
Total Time to Displace Existing System = 22 Hours (Sequential)
Total Time to Displace Integrated System = 45 Hours (Sequential)High Level Insulation, or Additional Topsides Facilities Required!
Emerging Technologies
• Passive Insulation Solutions
• Microporous Insulation
• Phase Change Materials
• Artificial Lift
• Subsea Separation (-)
• Multiphase Pumping (+)
• Gas Lift (+ / -)
Emerging Technologies
• Active Heating
• Hot Water Circulation
• Electrically Heated
• “Electrically-heated ready”
• Chemicals
• Low Dosage Hydrate Inhibitors
• “Cold Flow”
Design Considerations:Black Oil and
Gas Condensate Systems
Black Oil System:Steady State Design Checklist• Hydraulics
• Line sizing• Dry tree vs. subsea tieback• Single vs. dual flowlines• Dual flowlines becoming “standard” for deepwater
• Pressure drop• Velocity / erosion (minimum / maximum)• Slugging
• Thermal• Insulation requirements
• Hydrate formation• Wax deposition• Gel formation
• Shutdown• Planned• Unplanned
• Depressurization• Restart
• Warm• Cold
• Fluid displacement / pigging• Flowline preheating
Black Oil System:Transient Design Checklist
Black Oil Systems:Steady State Design Considerations
Black Oil System:Steady State Hydraulics
• Pressure drop effects• Physical
• Line size• Tieback distance• Water depth
Multiphase flow:Head losses <> head gains
• Pipe roughness (typical values)Steel: 0.0018”Tubing: 0.0006”Flexible pipe: ID/250
• Fluid properties• Gas/oil ratio (GOR)• Density• Viscosity
May require insulation to limit viscosity
Pres
sure
(psi
a)
0
500
1000
1500
2000
2500
0 1 2 3 4 5 6 7 8
Distance (miles)
Black Oil System: Slugging• Hydrodynamic
• High frequency• Minimal facilities impact
• Terrain • High liquid / gas flowrates• Topsides concern• Riser fatigue concern• Utilize gas lift
Hydrodynamic SluggingGas Outlet Flow
0
1
2
3
4
5
6
7
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Time (hours)
Terrain SluggingLiquid Outlet Flow
0
10000
20000
30000
40000
50000
60000
70000
80000
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Time (hours)
Black Oil System: Slugging• Slugging issues
• Sensitivity to Fluid GOR / water cut
7500 / 7512500 / 10015000 / 1500
5000 / 40017500 / 25020000 / 12517500 / 100
1300 GOR 1800 GOR760 GOR
10000 / 20026000 / 3256015000 / 13024000 / 1754015000 / 12520000 / 16020
DNF
Terrain Slugging Regime (BPD) / Surge Volume (BBL)
5000 / 30080
Water Cut (%)
Black Oil System: Slugging• Slugging issues
• Sensitivity to Trajectory: up vs. downslope
-8600
-8500
-8400
-8300
-8200
-8100
-8000
-7900
-7800
-7700
-7600
-7500
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
Distance, miles
Wat
er D
epth
, ft
Original Route - 40 miles total length
Alternate Route #1 - 36 miles total length
Alternate Route #2 - 45 miles total length
WELLHEAD RISER BASE
0
50
100
150
200
250
300
350
400
0 1 2 3 4 5 6 7 8
Time (hours)
Liqu
id A
ccum
ulat
ion
Abo
ve N
orm
al* (
bbl)
Original RouteAlternate Route #1Alternate Route #2
50 bbl Slug Catcher Capacity
>24 hour Ramp-up Required
10 hour Ramp-up Required
• Hydrates• Maintain steady state temperature
above hydrate formation region, down to “reasonable” flowrate
• Looped flowline ~ 25% of field production (50% per flowline)
• For low water-cut systems, continuous hydrate inhibition is possible
• Future: continuous LDHI inhibition
Black Oil System:Steady State Thermal Design
• Wax• Maintain temperature above WAT (stock
tank), down to “reasonable” flowrate• Looped flowline ~ 25% of field production
(50% per flowline)
• Maintain viscosity at acceptable levels to reduce pressure drop
• Insulate to minimize pigging frequency• Pigging frequency > residence time
• Continuous paraffin inhibition (if necessary)
Black Oil System:Steady State Thermal Design
Black Oil System:Steady State Thermal Design
•Limited insulating capacity0.75 – 1.50Flexible
•Riser installation difficulties0.20 – 0.25Pipe-in-pipe
•Dependant on soil properties•Combined with insulation
0.50 – 1.00Burial
•Buoyancy issues0.50 – 0.75Wet (Syntactic)
0.08 – 0.10
Achievable U-value(BTU/hr-ft²-°F)
•Industry acceptanceMicro-porous
Issue / ConcernInsulation Option
Black Oil System:Steady State Thermal Design
Arrival TemperatureWater Cut = 0%
20.0
22.0
24.0
26.0
28.0
30.0
32.0
34.0
36.0
38.0
40.0
42.0
44.0
46.0
48.0
50.0
7500 10000 12500 15000 17500 20000 22500 25000 27500 30000 32500 35000 37500 40000Liquid Flowrate (blpd)
Arr
ival
tem
pera
ture
(°C
)
0.5 W/m².K1.0 W/m².K2 W/m².K3.0 W/m².Kno heat loss
0.50 BTU/ft² hr ºF
0.30 BTU/ft² hr ºF
0.20 BTU/ft² hr ºF
0.09 BTU/ft² hr ºF
Adiabatic (0 BTU/ft² hr ºF)
Black Oil Systems:Cooldown Design Considerations
• Shutdown statistics• Typical shutdown durations
• 89% shutdowns < 10 hours• 94% shutdowns < 12 hours• 99.9% shutdowns < 24 hours
• Typical shutdown causes
Black Oil System: Cooldown
PumpsScaleCorrosionSandParaffinHydratesAsphaltenesSeparationOther
• Planned shutdown Procedure• Inject hydrate inhibitor for one residence time
(minimum)• At high water cuts, may need to reduce flowrate to
effectively treat system
• Inject hydrate inhibitor into subsea equipment• Particular attention to horizontal components• Self-draining manifold / jumpers• Treat upper portion of wellbore
• SCSSV vs. top ~50 ft
• Shut-in system
Black Oil System: Cooldown
• Unplanned shutdown Procedure• Determine minimum cooldown times
• “No-Touch Time”~2-4 hours / no action taken subsea
• “Light Touch Time”~2-4 hours / treat critical componentsTime is a function of chemical injection philosophy / number of wells
• “Preservation Time”Time required to depressurize or displace flowlines with non-hydrate forming fluid
Black Oil System: Cooldown
Time=0 Time=8Time=4
“No-Touch” “Light Touch” “Preservation”
• Insulation selection• Cooldown time determined
by:• U-Value• Thermal mass (ρ, Cp)
Measure of heat storageLine size impacts
Bigger = More Thermal Mass
• Gas / liquid interface typically controlling point
• Gas = low thermal mass• Highest pressure• Coldest temperature
Black Oil System: Cooldown
40
50
60
70
80
90
100
110
120
130
140
150
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36
Time (hours)
Tem
pera
ture
(F)
Pipe-in-Pipe (0.20 BTU/hr-ft²-F)
Wet Insulation (0.75 BTU/hr-ft²-F)
Flexible Pipe (1.00 BTU/hr-ft²-F)
HYDRATE FORMATION (PURE WATER)
Black Oil System: Cooldown
30
40
50
60
70
80
90
100
110
120
130
140
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
Tem
pera
ture
(F)
0 hours (Steady State)
1 hours
2 hours
4 hours
6 hours
8 hours
10 hours
12 hours
18 hours
24 hours
RESERVOIRWELLHEAD
FLOWLINE
RISER
Black Oil System: Cooldown
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
6000
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
Pres
sure
(psi
a)0 hours (Steady State)
24 hours
RESERVOIR
WELLHEAD
FLOWLINE
RISER
Black Oil System: Cooldown
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
Liq
uid
Hol
dup
(-)
0 hours (Steady State)
24 hours
RESERVOIRWELLHEAD
FLOWLINE
RISER
Black Oil System: Cooldown
-30
-20
-10
0
10
20
30
40
50
60
0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
Distance (miles)
Hyd
rate
Pro
pens
ity, T
-Thy
d (F
)
0 hours (Steady State)
1 hours
2 hours
4 hours
6 hours
8 hours
10 hours
12 hours
18 hours
24 hours
RESERVOIR
WELLHEAD
FLOWLINE
RISER
• Is there adequate chemical injection to treat subsea components within cooldown time?• Wellbore• Trees• Jumpers• Manifolds
• What is the subsea valve closure philosophy?• Packed: More liquid / higher pressures• Un-packed: Less liquid / lower pressures
• Does insulation provide sufficient cooldown time?• No-touch• Light-touch• Preservation
• Is gel formation a possibility?• If yes, system design philosophy changes
• Is SCSSV set deep enough to avoid hydrates?
Black Oil System:Cooldown Checklist
Black Oil Systems:Depressurization Design
Considerations
• Hydrate remediation strategy• Reduce pressure below hydrate formation pressure at seabed
• Effectiveness based on:• Fluid properties
• GOR• Water cut
• Seabed bathymetry• Upslope• Downslope
• Deepwater issues• Reduce pressure to ~200 psia at seabed• Maintain pressure below hydrate conditions during restart
Black Oil System: Depressurization
Time=0 Time=8Time=4
“No-Touch” “Light Touch” “Preservation”:Depressurization
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
40 45 50 55 60 65 70 75 80 85
Temperature, °F
Pres
sure
, psi
a
Pure Water
Sea Water
Produced Water
Phyd ~ 200 psia
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 1 2 3 4 5 6 7 8 9
0.0 hours0.5 hours1.0 hours
Pres
sure
(psi
a)
Distance (miles)
FLOWLINE
MUDLINE
BOTTOM HOLE
RISER BASE
Depressurization:Subsea Tieback
0
500
1000
1500
2000
2500
3000
3500
4000
4500
0 2000 4000 6000 8000 10000 12000
0.0 hours
0.5 hours
1.0 hours
Distance (feet)
Pres
sure
(psi
a)
MUDLINE
BOTTOM HOLE
GAS/LIQUIDINTERFACE
SCSSV
Depressurization – Dry Tree
• Can you depressurize below hydrate formation conditions?• If YES, can you depressurize in late-life at high water cuts?
• If YES, can you maintain pressure below hydrate formation conditions during restart?
• Difficult for deepwater
• If YES, is there a pour point concern?• Depressurization increases restart pressure requirements
• If NO, consider the following for hydrate prevention:• Displacement (dual flowlines)
• Active heating
• Continuous chemical inhibition
Black Oil System:Depressurization Checklist
Black Oil Systems:Displacement Design
Considerations
• During “Prevention” time, displace produced fluids from flowline• Unable to get hydrate inhibitor to in-situ fluids
during shutdown• Dual flowlines required• Sufficient insulation / cooldown time• Function of flowline length
Black Oil System: DisplacementHydrate Prevention - Shutdown
Time=0 Time=8Time=4
“No-Touch” “Light Touch” “Preservation”:Displacement
Black Oil System: DisplacementDischarge Pressure Required
HOLD BACKPRESSURE AT OUTLET
Black Oil System: DisplacementHydrate Prevention - Shutdown
Dead Oil Flushing - Year 5FPSO Pump Discharge Pressure
FPSO Arrival Pressure Controlled at 1500 psia
0
200
400
600
800
1000
1200
1400
1600
1800
0 0.5 1 1.5 2 2.5 3 3.5
Time (H)
Pig reaches base of first riser
Produced fluids move up second riser
Gas breaks through
second riser
Pig moves up second riser
• During “Prevention” time, displace produced fluids from flowline• Topsides design considerations
• Available backpressure• Circulation rate
Limited by pig integrityTypically 3-5 ft/secMay be faster for “straight-pipe”
• Storage volume• Circulation passes
With pig: 1 residence timeWithout pig: 2-3 residence times for efficient water removal
Black Oil System: DisplacementHydrate Prevention - Shutdown
Black Oil System: DisplacementHydrate Prevention – Dry Tree
• During shutdown, how quickly will fluids fall below SCSSV?• Very little work done with L/D ratios >100 (deepwater riser
~10000)• Field data shows oil/water separation ~ 70-80 ft/hr
• Bullhead / displace with non-hydrate forming chemical to SCSSV• Methanol/MEG (volume concerns)• Heavy diesel (high density, by-pass produced fluids)• Dead oil
• Ability to bullhead a function of displacement rate
• Is there sufficient time to accomplish displacement operation?• Sufficient insulation / Cooldown time
• Is the topsides facility designed to accomplish displacement operation?• Pump capacity• Storage capacity
• Can system be restarted into crude-oil filled flowline?• Displace with gas?• High pour point fluids – what is the restart pressure required?
• For dry trees, is a proper fluid available for displacement?
Black Oil System:Displacement Checklist
Black Oil Systems:Restart Design Considerations
Black Oil System: Cold Restart• System pressure < hydrate formation conditions throughout
restart?• For deepwater, hydrostatic pressure in riser too high• Separator pressure: may need alternate start-up vessel
• Hydrate inhibition required until arrival temperature reaches “Safe Operating Temperature” (SOT)• Maintain hydrate inhibitor rate: Fluid completely inhibited• Reduce hydrate inhibitor rate: Fluid not completely inhibited to
shut-in conditions
• SOT is minimum topsides temperature that provides sufficient cooldown time, in the event of an interrupted restart
Black Oil System: Cold Restart
Shut-in Pressure, psia
Met
hano
l Dos
age,
BB
L M
eOH
/BB
L H
2O
0.30
0.35
0.40
0.45
0.50
0.55
0.60
1000 1200 1400 1600 1800 2000 2200 2400 2600 2800 3000
PRODUCEDWATER
SEA WATER
PURE WATER
Black Oil System: Cold Restart
Flowrate, BPD
Met
hano
l, gp
m
0
5
10
15
20
25
30
35
40
45
50
2000 3000 4000 5000 6000 7000 8000 9000 10000
5% WATER
50% WATER
25% WATER
75% WATER
Black Oil System: Cold Restart• Achievable restart rates determined by:
• Shut-in conditions• Fluid GOR• Water cut• Hydrate inhibitor
• “Rule of Thumb”: Greater inhibitor injection rates result in lower overall inhibitor volumes used during restart• Small tiebacks: 5-10 gpm / well• Large deepwater: 25+ gpm / well
• Warm-up trends:• Wellbore: Very quick (<30 minutes)• Flowline: Function of flowrate / water cut / length / insulation
Black Oil System: Cold Restart
Black Oil System: Cold Restart
1.12.95.8Micro-porous
1.58.4> 24Buried
1.13.210.6Flexible
1.23.59.2Conventional
1.13.06.1Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study3 Mile Tieback – Warm-up Time
7.013.0> 24Micro-porous
> 24> 24> 24Buried
12.3> 24> 24Flexible
10.9> 24> 24Conventional
7.214.0> 24Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study15 Mile Tieback – Warm-up Time
772798> 850Micro-porous
> 2300> 1700> 850Buried
1053> 1700> 850Flexible
1074> 1700> 850Conventional
781814> 850Pipe-in-pipe
Max Flowrate
10000STBPD
5000 STBPD
Insulation Type
Cold Restart: Case Study15 Mile Tieback – MeOH Volume
• Is there sufficient hydrate inhibitor available?• Delivery rates• Storage volumes
• How will multiple wells be restarted?• Single well at max. rate• Multiple wells at reduced rate• Single flowline vs. dual flowline
• What is the minimum temperature required to achieve safe conditions?• Safe Operating Temperature (SOT)
Black Oil System:Restart Checklist
• Hydraulics• Ensure Production Delivery Throughout Field Life• Minimize Slugging
• Wax Deposition• Minimize Wax Deposition (Insulation/Pigging/Chemicals)
• Hydrate Formation• Avoid Steady State Hydrate Formation• Optimize Cooldown Times (Insulation)• Prevent Transient Hydrate Formation
(Depressurization/Displacement/Chemicals)• Minimize Inhibitor Consumption
Black Oil System:Summary of Design Considerations