downtown seattle transit capacity white paper final draft

Upload: the-urbanist

Post on 04-Feb-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    1/19

    HIGH CAPACITY TRANSIT STUDY

    SOUTH KING COUNTY CORRIDORS

    2014 FINAL DRAFT DOWNTOWN SEATTLE TRANSIT CAPACITY WHITE PAPER

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    2/19

    2

    (This page intentionally blank)

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    3/19

    3

    INTRODUCTION

    ANALYSIS FRAMEWORK

    This White Paper presents an analysis of the

    possible future of transit demand and

    capacity in downtown Seattle. This is a

    component of the South King County High

    Capacity Transit (HCT) Study.

    The central question is whether or notthere will be enough capacity on

    downtown Seattle surface streets andin

    the existing Downtown Seattle Transit

    Tunnel (DSTT) to accommodate potential

    additional HCT connections. The HCT

    connections under consideration in the

    paper are those between downtown and

    Ballard, and between downtown and

    West Seattle, Burien (and potentially

    Renton). If there is not sufficient capacity

    on downtown Seattle surface streets

    combined with the DSTT, then

    consideration of additional capacity willbe required as part of future High Capacity

    Transit planning.

    REGIONAL BUSES

    ST LINK LRT

    KC METRO BUSES

    SEATTLE STREETCAR

    FIG. 1 Principal existing & potential transit corridors in

    Downtown Seattle

    To address that question, 2035 travel demand and capacity in existing and planned HCT corridors

    connecting to downtown Seattle was analyzed. The intent is to explore how HCT service evaluated in

    the South King County HCT study could be connected to serve a variety of origins and destinations.

    Connectivity and transfer demand were also analyzed using origin and destination information from

    Sound Transits ridership model for 2035. This analysis identifies where travel could potentially be

    constrained and how future HCT might serve to address those constraints.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    4/19

    4

    CONTEXT

    DOWNTOWN SEATTLE TRANSPORTATION

    Seattles Commercial Core and the surrounding neighborhoods comprising the Center City continue to

    grow (Figure 2). Significant new private and public investments, as well as growing demand for transit,

    are transforming this part of the city. This change is being brought about by substantial private

    investment in jobs and housing paired with strong public investment in light rail, streetcars, bike

    facilities and the new waterfront resulting from the Alaskan Way Viaduct replacement project. Figure 3

    illustrates the new private development and transportation infrastructure projects planned or under

    construction as of early 2014.

    FIG. 2 Neighborhoods included in Seattles Center City (City of Seattle, Department of Planning and Development)

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    5/19

    5

    I.D . CHI NAT O WN S TATION

    FIG. 3 The future transportation network serving downtown Seattle, showing growing public investment in

    transportationchoices. (DSA/SDOT Downtown Access Study, VIA Architecture, 2013)

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    6/19

    6

    A RING OF CONSTRAINTS

    In 2003 the City of Seattle issued the Center City Circulation Report which presented a comprehensive

    conceptual approach for maximizing access to downtown Seattle by improving and integrating public

    transit, bicycle and pedestrian networks. This is a macro-scale effort to integrate existing light rail, bus,

    monorail, streetcar, ferry terminal, Alaskan Way Viaduct and Seawall (AWVS), and bicycle and pedestrian

    projects, all independent transportation projects that will affect future circulation in downtown Seattle.

    The Center City report emphasizes that access to downtown Seattle is limited by a ring of physical

    constraints. An outer ring limits points of regional access and consists of the Ship Canal and Lake Union,

    Lake Washington, the Duwamish Waterway, and Elliott Bay (Figure 4). An inner ring limits access to the

    Downtown Core of the Center City. There are few points of accessto and from I-5, Spokane Street and

    the Alaskan Way Viaduct (Figure 5).

    To Ballard

    To West

    Seattle

    North Link

    SR 520

    East Link

    Central Link

    Map Key:

    Seattle Center City

    Ring of constraintslimitingaccess

    Existing and plannedSR 520 Bus Service

    Existing and plannedLink light rail service

    Existing Sounderservice

    Potential Ballardto Downtown and

    Downtown toWest Seattle HCTconnections

    FIG. 4 The outer ring of constraints (Center City

    Circulation Report, SDOT & Nelson/Nygaard, 2003)

    FIG. 5 The inner ring and travel through the

    Downtown Seattle: existing and planned corridors

    However, there are several trends that will improve regional connections in coming decades despite

    the mobility challenges posed by geography. A substantial portion of the regions residentialand

    commercial growth is occurring within Seattle, particularly in and around downtown, meaning that

    more people will be living and working there. Growth in downtown Seattle will provide moreopportunities for work and home locations to be within walking distance of one another, which will

    help to alleviate the constraints described above.

    Link light rail will provide new points of regional access, allowing travelers to bypass surface

    constraints as the network expands north, east and south. However, on-street congestion in

    downtown Seattle is projected to increase with additional development, and future HCT planning

    may benefit from partnerships between transit agencies and the City of Seattle to ensure reliable

    transit travel times.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    7/19

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    8/19

    8

    CURRENT TRANSIT CAPACITY

    King County Metro buses are currently overloaded at peak travel times, both on downtown Seattles

    surface streets and in the DSTT. There is a lack of both surface street throughput and available bus

    stop curb space on north-south streets at peak travel times, which results in speed and reliabilityissues for bus routes serving downtown Seattle.

    FIG. 7 2012 AM Peak Period Downtown Passenger

    Load (TMP Briefing Book, Figure 4-18. Data from

    King County and City of Seattle)

    To understand the nature of these limitations, King County Metro studied bottlenecks in Seattles

    Central Business District transit network and published a report identifying the maximum number of

    buses per hour that can be accommodated by each Commercial Core street.1 In most cases, the

    capacity of a street is constrained by bus stop capacity, or the amount of curb space available for

    arriving buses. This King County Metro analysis, performed in anticipation of the end of the Ride Free

    Area and pay-on-entry boardings, reveals that stops on 2nd, 3rd and 4th Avenues at Pike Street are at or

    over capacity. The DSTT, currently used for both light rail and bus service, is currently operating at its

    maximum mixed-mode vehicle capacity, serving approximately 50 buses and 16 light rail vehicles per

    hour at peak periods.

    Demand in these corridors will continue to grow. To address that growth, Sound Transit and King

    County Metro are currently reevaluating their near- and long-term assumptions about the capacity of

    the DSTT and the downtown street network for buses and light rail. Because the results of that

    evaluation are not yet available, this analysis utilizes assumptions from King County Metro s 2001

    Tunnel Capacity Study as well as King County Metros analysis of expected Commercial Core bus stop

    capacity after implementation of its pay-on-entry policy in 2012.

    As Sound Transit expands Link light rail to reach more travel markets, an increasing number ofregional transit trips will shift to light rail, meaning fewer regional buses will travel on downtown

    streets. At the same time, increased Link service will result in headways incompatible with mixed

    operations in the DSTT, requiring relocation of buses to surface streets. Link service will intercept

    riders outside of downtown Seattle, reducing some bus trips on downtown streets. Although there

    will be fewer regional bus routes entering downtown Seattle, any remaining transit capacity on

    surface streets could be taken up by growing demand for local bus routes within downtown.

    1 Simulation Testing of No Ride Free Area at Selected Critical Bus Stops in the Sea ttle CBDKing County Metro, 2011, pp. 25.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    9/19

    9

    FUTURE DEMAND AND CAPACITY

    GROWTH IN PERSON TRIPS

    Between 2011 and 2012, Seattles population grew

    at a rate 25% faster than that of surrounding King

    County. Citywide, Seattle gained more than 23,000

    residents between 2010 and 2012.

    More apartments were developed in the Seattle area

    in 2013 than in any of the previous 20 years. This will

    occur again in 2014 and in 2015.2

    The Puget Sound Regional Council has projected

    35,000 additional residents and 129,000 additional

    jobs will be accommodated in SeattlesCenter City

    232,100

    2008

    361,100

    2030

    47,500

    2008

    83,200

    2030

    22,600

    2011

    52,500

    2035

    between 2008 and 2030. Conservative estimates

    are that between 3,000 and 5,000 apartments

    will be added per year over the next three years.

    Center CityJobs

    Center CityResidents

    Peak Hour TransitTrips Through TheCommercial Core

    Approximately three-quarters of those new

    apartments will be built in Seattle, most of them

    concentrated in the Center City and close-in

    FIG. 8 Growth in Center City Jobs, Residents, & Transit Trips

    neighborhoods. The supply of office space is also increasingfor example, Amazon, Inc. alone is

    adding space for approximately 17,000 new workers between 2014 and 2015.3

    As a result of those additional jobs and residents, the number of transit trips taken in and arounddowntown Seattle is expected to grow as well. According to Sound Transits EMME model, the

    number of peak-hour transit trips in and around the Center City will more than double by 2035,

    increasing by nearly 30,000 trips over 2011 levels in the Commercial Core.

    2 Rental market & development trendsDupre+Scott, September 2013

    3 http://seattletimes.com/html/businesstechnology/2020775791_apartmentboomxml.html

    http://seattletimes.com/html/businesstechnology/2020775791_apartmentboomxml.htmlhttp://seattletimes.com/html/businesstechnology/2020775791_apartmentboomxml.htmlhttp://seattletimes.com/html/businesstechnology/2020775791_apartmentboomxml.html
  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    10/19

    10

    ACCOMMODATING BUS, BIKE, AND RAIL

    To determine the amount of transit capacity that will be available to meet future travel demand, this

    analysis draws upon existing studies from King County Metro4, the City of Seattle5, and input from Sound

    Transit, with the following assumptions about the state of the Center City transit network in 2035:

    In 2035, Link Light Rail will operate through

    the DSTT at three-minute headways using

    four-car trains and a load factor of 2.0

    (twice as many passengers as there are

    seats)

    King County Metro buses will continue to

    operate at their current load factor (1.05)

    Bus volumes on 2nd, 3rd, and 4th Avenues

    will remain the same as today, constrained

    by curb space and stop capacity

    The Center City Connector is planned to connect

    the First Hill and SLU Streetcars via 1st Avenue,

    running at five- minute headways

    Modifications to surface streets, including cycle

    tracks and transit lanes, will be implemented when

    funding is available as outlined in Seattles Transit

    and Bicycle master plans

    Based on these assumptions, the capacity of the transit system in the Commercial Core was

    calculated. The results are shown in Table 2 summarized for the DSTT and all surface transit

    (streetcar, surface bus).

    The surface capacity values shown in Table 2 are based on the bus stop constraints and assumed

    vehicle load factors. Key to this capacity being delivered is that the transit vehicles can travel through

    the Commercial Core without excessive delay caused by other vehicles. An analysis ofthe 2035 Puget

    Sound Regional Council travel demand model (which forecasts future vehicle trafficvolumes and

    speeds) indicates that the average peak hour speeds on the north/south streets to be approximately 6-

    10 MPH. The additional transit lanes proposed in the Seattle Transit Master Plan on 2nd and 4th

    Avenues will help to improve transit speeds through the Commercial Core; however, cross street traffic

    and turning vehicles could still result in delays to surface transit that could ultimately impact the ability

    of surface transit to travel reliably through downtown.

    TABLE 2: Funded Peak Hour Transit Capacity

    through the Center City In 2035

    Facility Corridor Effective Seats6

    Link Light Rail DSTT 23-24K

    Surface Transit 1st, 2nd, 3rd

    4th & 5th

    21-23K

    Total Capacity 44-47K

    4 Center City Connector Transit Study, Tier 2 SDOT & Nelson Nygaard, October 2013

    5 King County Metro; Center City Connector Alternatives Analysis

    6 Note: Effective Seatsis a measure of capacity and includes stop capacity and load factor. It does not assume all transit

    riders have a seat, but rather is used to describe the carrying capacity of a transit vehicle. In this analysis, capacity is

    estimated for buses using a load factor similar to what KC Metro experiences today (1.05); for Link Light Rail, capacity is

    estimated using the same load factor as is used in Sound Transits long range operating assumptions (2.0)

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    11/19

    11

    FUTURE DEMAND

    Future transit demand was evaluated using a transit trip origin-destination (OD) matrix extracted

    from the 2035 ST EMME model which includes implementation of ST2 projects. This OD method was

    selected because it is difficult to accurately predict which transit routes will serve downtown Seattle

    in 2035 with the information currently available7. OD trips are not assigned to individual transit lines,but rather to specific transit modes such as Link Light Rail, surface transit (bus/streetcar). Potential

    demand stemming from the Ballard and SKC HCT projects was also identified. Key assumptions used

    to estimate demand include:

    The geographic boundaries of the different OD areas evaluated define the available transit mode

    (see Figure 9). For example, transit trips beginning or ending in First Hill or the Central District

    will be accommodated by surface transit, while trips to/from North King County and Snohomish

    County will occur on Link Light Rail.

    Transfers are assumed to occur within the Commercial Core according to the rates shown in

    Table 3. The transfer rates are based on the project team s best judgment based on

    observations of existing travel patternsfor example transfers from Sounder to 4th Avenue andDSTT transit. The transfer assumption is a key element of this analysis since transfer trips can

    appear to be counted twice, for example on Link and on a surface bus.

    The transfer rate varies by types of trips that enter or traverse the Center City. Five trip types

    were identified, as shown in Figure 10.

    Demand was calculated at three hypothetical screenlineswithin the Center City OD zone. The

    north screenline is roughly at Valley Street, the middle screenline is in the Commercial Core,

    roughly between Pine and James Street, the south screenline is roughly at Dearborn Street. The

    screenlines are not absolute (e.g., at Union Street) because of the OD method being used8. The

    goal is to identify the point at which the transit routes are at their fullest as they travel through

    the study area. The maximum demand across the each of the screenlines was identified and

    summed to estimate total demand.

    The results of the demand analysis are shown in Table 4.

    7 The Sound Transit EMME model assumes that many routes from the north will be truncated as Link extends north of the

    University of Washington. There are also potential truncations for service as East Link is built. However, with fewer long-

    distance routes, King County Metro could re-deploy transit hours to serve Center City trips and other neighborhoods near the

    Center City with additional service, since transit demand is expected to be high. Considering that the Sound Transit model is

    not capacity constrained, it is likely that additional bus service not explicitly assumed in the model would be required to meet

    the high transit demands forecasted under 2035 conditions. This OD method, combined with a fixed bus load factor of 1.05assumes that additional bus service will be provided in the future.

    8 The OD method assigned 30% of intra-Center City trips and 75% of trips that transfer from Link/Sounder to surface transit

    to the cross the middle screenline. This method was chosen to simplify the assumptions about which specific stop within the

    Downtown Commercial Core people get on and off at.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    12/19

    12

    TABLE 3: Downtown Surface Transit between Origin and Destination Pairs 2035

    Origin/Destination PairsAssumed

    Transfer RateNotes

    Travel to Center City via Link Light

    Rail, Bus, or Ballard/SKC HCT

    30% This assumes that some trips will be made via a transfer

    to a bus in the Commercial Core. For example, travel from

    West Seattle to South Lake Union or from Ballard to theStadium District

    Travel to Center City via Sounder

    Commuter Rail

    75% Assumes many trips on Sounder will transfer to surface bus

    to reach the final destination within the Center City.

    Travel to First Hill/Central District

    via Markets Served by Light Rail, ST

    Regional Bus, Ballard/SKC HCT or

    Sounder

    100% Assumes that all long-distance regional trips will transfer

    to a bus in the Commercial Core to reach First

    Hill or the

    Central District. No transfers are assumed from Capitol

    Hill or the Center City.

    TABLE 4: Projected Peak Hour Demand

    for Center City Transit Facilities In 20359

    Facility Trip Demand

    Link Light Rail (DSTT) 18-20KSurface Transit 25-27K

    Potential West Seattle/

    Ballard HCT

    6-8K

    Total Demand 49-55K

    North Link

    Kirkland/Redmond

    (520)

    Ballard

    Center City

    (Area of Study)

    First

    Hill

    Capitol

    Hill

    Central

    District

    I-90 / East Link

    West Seattle /Burien

    Central Link /

    Sounder /

    ST Express

    Extents of Center City assumed inDemand analysis

    Trips occurring outside of Downtown

    FIG. 9 Trips On Downtown Transit Corridors Occurring Outside the Center City

    9 King County Metro; Center City Connector Alternatives Analysis

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    13/19

    14

    VARIABLES

    Understanding the capacity of a specific facility

    requires determining which origins and

    destinations travelers using that facility are likely

    to require, and how proposed and existing

    connections will facilitate those trips.

    Trip Types

    In the Center City, there are at least five different

    trip types possible given various origin

    destination pairs (see Figure 10). Each places a

    different demand on the capacity of the facilities

    it uses. For a specific trip, this distribution ofdemand can depend on several factors, such as:

    The number of riders requiring a trip through

    the Center City

    The number of riders using a facility for trips

    within the Center City

    Whether a rider arrives close enough to walk

    to their final destination, or whether their

    trip requires them to transfer to an

    intermediate mode or facility

    Trip Distribution

    Constraints inherent in Seattles current and proposed transit facilities also pose challenges for

    particular trips, including trips made by riders arriving at King Street Station via Sounder commuter

    rail who need to travel to destinations north through the Center City; trips made by riders arriving in

    the Center City via Ballard HCT who want to continue south; or trips made by the growing number of

    people living and working in the Center City who need to reach key Center City destinations such as

    the stadiums. It is also important to consider instances in which demand is so high at DSTT stations

    (such as the InternationalDistrict /Chinatown Station or at Westlake) that riders are not able to board

    trains because they are full.

    Understanding the capacity of any corridor requires assumptions about trip distribution as transitvehicles move through the Center City. In an idealized scenario, the number of riders departing a

    vehicle at any given station would be equal to the number of riders boarding that same vehicle, such

    that seats would be available to all boarding riders. If this were the case, capacity of a given transit

    corridor could be designed simply as a factor of the number of transit trips into and out of the Center

    City made via that corridor.

    Fig. 10Possible Center City Trip Types

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    14/19

    15

    jobs andpeople.

    sandpeople.

    jobsand people.

    bsandpeople. bsandpeople.

    sandpeople.

    jobs andpe ople.

    jobs andpeople. sandpeople.

    jobsand people.

    bsandpeople.

    jobs andpeople.

    sandpeople.

    jobsand people.

    bsandpeople. bsandpeople.

    sandpeople.

    jobs andpe ople.

    jobs andpeople. sandpeople.

    jobsand people.

    bsandpeople.

    WESTLAKE

    WESTLAKE

    MADISON

    MADISON

    INTLD

    IST

    INTLD

    IST

    COMMERCIAL CORE

    PERFECT TRIP DISTRIBUTION

    DEMAND = CAPACITY

    BALLARD HCT

    job

    jo

    job jobjo

    jo

    WEST SEATTLE/

    BURIEN HCT

    MAXIMUM

    DEMAND

    ADDITIONAL TRIPS

    THROUGH AND WITHIN

    COMMERCIAL CORE

    EXCEED CAPACITY

    COMMERCIAL CORE

    IMPERFECT TRIP DISTRIBUTIONDEMAND > CAPACITY

    BALLARD HCT

    job

    jo

    job jobjo

    jo WEST SEATTLE/

    BURIEN HCTMAXIMUM

    DEMAND

    FIG. 11 Trip Distribution in Center City Transit Corridors

    In reality, trip demand along transit corridors is often distributed unevenly among various stations and

    asymmetrically between directions of travel, requiring additional capacity where theres a high potential

    for overlapping trips (see Figure 11). For example, if riders wishing to board a northbound train at a

    station in the Commercial Core are faced with a full train of riders headed to points north that have not

    yet left the train, twice the vehicular capacity is needed in order to accommodate both sets of riders.

    This analysis assumes that in reality, the trip distribution will be somewhere between the perfect case

    scenario (0% trip overlap) and the worst case scenario (100% trip overlap), and splits the difference

    between the two at the midpoint of trip distribution.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    15/19

    16

    OVERALL CAPACITY VS. DEMAND

    After accounting for trip growth and planned capacity, the

    analysis found that demand on transit routes traveling through

    the Commercial Core; including the potential HCT corridors

    evaluated between Ballard, West Seattle, Burien, and Renton;

    will exceed the capacity of existing and planned facilities in

    2035. While this aggregate finding is informative about general

    transit demand in Seattles Center City, it does not fully describe

    the value of specific facilities in accommodating likely travel

    origins and destinations. Tables 2 and 4 describe a discrepancy

    of approximately 5,000 - 8,000 effective seats9 between

    anticipated future peak hour demand and capacity on Center

    City transit facilities.

    Trip demand was calculated by breaking Center City trips down

    into origin and destination pairs, then assigning each trip to

    the Center City transit mode most likely to serve each origin

    and destination. Demand was assessed for each mode at the

    north and south edges of the Center City, as well as within the

    Commercial Core were highest trip volumes were expected to

    occur. Next, the point of highest demand was

    identified for each mode and assumed to be the controlling factor

    in the capacity needed to accommodate that mode.

    FIG. 12 Third Avenue Transit Corridor at peak

    hour

    9 Note: Effective Seatsis a measure of capacity and includes stop capacity and load factor. It does not assume all transit

    riders have a seat, but rather is used to describe the carrying capacity of a transit vehicle. In this analysis, capacity is

    estimated for buses using a load factor similar to what KC Metro experiences today (1.05); for Link Light Rail, capacity is

    estimated using the same load factor as is used in Sound Transits long range operating assumptions (2.0).

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    16/19

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    17/19

    18

    WHERE CAN ADDITIONAL HIGH CAPACITY TRANSIT BE

    ACCOMMODATED?

    The central question addressed by this study is whether the capacity planned for Center City transit

    facilities will be adequate to accommodate potential additional HCT service along with expectedgrowth in Center City transit trips, or whether additional capacity will be required as part of a future

    HCT investment. The study evaluated Sound Transits ridership forecasts for HCT service connecting

    Ballard, West Seattle, Burien, and Renton to the Center City, and predicts demand for an additional

    6,000 to 8,000 trips through the Commercial Core. The study also found that the north-south

    avenues in the Commercial Core as well as the DSTT are both operating near their maximum

    capacities and will continue to do so until 2035, meaning new transit capacity through the Center

    City will be required. There are several options for how to accommodate new capacity, each with its

    own benefits and challenges. The following options discuss both how additional HCT service could

    be accommodated, while also addressing the finding that overall additional transit capacity will be

    needed through the Commercial Core.

    Bus Rapid Transit (BRT)

    To accommodate demand for Ballard/West Seattle/Burien/Renton BRT service

    and for buses serving other corridors, up to two bus-only lanes could be

    considered in each direction on 2nd and 4th Avenues through the Commercial

    Core (as proposed in the Seattle Transit Master Plan). This reconfiguration of

    existing street width could allow for buses to pass each other, similar to existing

    operations on 3rd Avenue.

    Benefits and Challenges

    Low capital cost but medium to high operations cost

    Bus operations in the Commercial Core are limited by a finite amount of curb

    space

    Will require transit-only lanes in existing right-of-way A surface alignment will face significant speed and reliability issues in the

    Commercial Core due to increased traffic volumes, cross street congestion,

    signal timing requirements, turning vehicles and pedestrian movements

    Grade Separated Rail-Only Facility

    Whether elevated or underground, an additional grade-separated alignment

    through the Center City would accommodateprojected demand for Ballard

    and West Seattle/Burien/Renton HCT, but would likely only accommodate

    someunmet surface transit demand.

    Benefits and challenges

    Grade-separation provides reliability. Without a transfer , a grade separated rail-only facility does not accommodate

    trips to and from neighborhoods served only by bus

    Structural supports required for an elevated alignment could potentially reduce

    surface street capacity.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    18/19

    19

    New Rail/Bus Tunnel(s)

    In addition to serving Ballard and West Seattle/Burien/Renton-bound riders,

    a tunnel or tunnels accommodating both rail and bus vehicles would have

    serve multiple travel markets, reliably accommodatingmost unmet demandfrom surface-routed corridors.

    Benefits and challenges

    Accommodates demand for rail and bus trips

    Provides reliable travel time

    Relieves demand for almost 60% of on-street capacity

    Requires integrated stations/hubs to transfer

    Requires multi-agency coordination and funding

    Requires rerouting of buses to access tunnel

    Peak Hour:

    Projected Demand For New HCT: 6-8K trips10

    60% of Unmet Surface Demand: 2-3K tripsTotal Demand for Rail/Bus Tunnel: 8-11K trips

    Transfers and Connections

    WESTLAKE

    HUB

    STADIUM

    STATION

    For the best return on investment, a new HCT line through downtown Seattle

    will simultaneously offer a reliable connection to the markets it serves directly

    as well as alleviate unmet transit demand. The amount of service that can be

    accommodated by a grade separated alternative depends greatly on station

    locations and the quality of transfers to and from connecting

    transit facilities.

    For example, a shared-use bus/rail tunnel would be most effective if portals

    were configured to provide reliable travel time for bus routes that will

    continue to use Aurora, Dexter/Westlake, Stewart/Olive, and the SODO Bus-way to access the Center City. A rail-only tunnel could also offer useful capacity

    for DSTT riders, but only if seamless transfer opportunities are provided at

    downtown transit hubs such as Westlake Station. Connections and transfers

    south of the Commercial Core that take into account the year-round calendar

    of stadium events will be very important.

    In all cases, improved connections and wayfinding at the Westlake Station

    transit hub will be necessary to connect any future HCT facility to Link Light

    Rail service in the DSTT, as well as to surface buses serving South Lake Union

    and origins east of the downtown. South of the Commercial Core, improved

    transfers and wayfinding between new HCT service, Link Light Rail, Sounder

    service, and bus routes will further expand each facilitys demand and capacity.

    10 Source: Sound Transit EMME Model, including Ballard to Downtown and South King County HCT studies.

  • 7/21/2019 Downtown Seattle Transit Capacity White Paper Final Draft

    19/19

    20

    (This page intentionally blank)