WP 3 : Technological innovationWP 3 : Technological innovation
« MEditerranean Development of Innovative Technologies for
integrAted waTer managEment »
Kick-off meeting [7th-8th May 2004]
WP3 Technological innovation
Action B. Monitoring and capture prototypes for submarine springs
Suggestion of reallocation of tasks responsibility + budget
• Task B.1 Preliminary studies : springs location, discharge of springs, morphology of the submarine environment (results of WP 1 and WP3 A) => CREEN-ESIB + GDHER (Lebanon)
• Task B.2. Environment impact : environmental study => CREEN-ESIB (Lebanon)
• Task B.3. Construction of the prototype : design for one submarine spring in Cheka Bay in Lebanon => hydraulic calculation : CNRS - HSC + CREEN-ESIB; technical drawing : subcontracting from ESIB; submarine capture construction : subcontracting from ESIB; low cost prototype of micro-capture for Syria and Turkey : CNRS-HSC (co-ordination) + AECS + HUKHAM
• Task B.4. Installation of the prototypes : feasibility study in Turkey and Syria : AECS + HUKHAM + CNRS-HSC; installation in Lebanon (authorisation : GDHER), subcontracting for divers and boats.
• Task B.5. Monitoring of the springs : CREEN-ESIB+ CNRS-HSC
• Task B.6. Feasibility study : CNRS - HSC
WP3 Technological innovation
• Responsibility of Tasks of Action B : CREEN-ESIB or CNRS-HSC ?
• Budget reallocation - Man months:– NYMPHEA budget:
• Personnel : 147400€ => Post-doc CNRS/HSC about 38 400€/year => two years ?
• Durable equipment : 15000 € => to CREEN-ESIB• Sub contracting : 45 000 € => to CREEN-ESIB• Travel and subsistence : 30 000 € => reduce, post doc HSC• Consumables : 6000€ => CREEN - or HSC• Protection of knowledge: 8000 € => CREEN ? HSC CNRS ?• Financial audit : 24 000 € => not necessary • Other specific cots: 1000 € => CREEN or HSC (scientific
experts…)
WP3 Technological innovation
WP3 Technological innovation
• Other WP : WP5: transfer technology: Who ? CNRS-HSC or LIRMM with contribution of CREEN-ESIB ?
• Prepare a technical proposal explaining the possibility and feasibility of reallocating tasks and budget on other partners, under responsibility of CREEN-ESIB ?
• Who ? Delay ? : ………………………………...• Electronically submitting => CPF modification and
WP description (ND)• CPF forms to be signed; Technical proposal to be
signed, sent to the EC